2. Statement of Work-Bldg 154, Air Compressor Replacement_7.22.22.pdf

PDF 565 KB Posted

Attached to
Building 154, Air Compressor Replacement, Ames, IA Federal contract opportunity
Solicitation number
12505B22R0025
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Midwest Area

About this file

This solicitation is for an air compressor replacement project located at a USDA facility in Ames, Iowa. The project requires removal of two existing air compressors and installation of two new water-cooled rotary screw air compressors rated at 125HP each. Additional specifications include installation of new automated valves, flow meters, temperature probes, pressure gauges, piping, and integration with the building automation system. The solicitation is a 100% small business set-aside with a magnitude of construction estimated between $500,000 to $1 million. The period of performance is 365 days after notice to proceed. Site visits are scheduled and questions regarding the solicitation are due by August 25th. The solicitation and any amendments will be available on SAM.gov and the contract will be a firm-fixed price awarded following evaluation of proposals received in response to the RFP.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Building 154, Air Compressor Replacement

USDA, Ames, IA

7/22/22

Project Requirements:

Background:

Building 154, the Central Utility Plant, currently has (2) two 100HP, TS-20 Sullair Air Compressors each with a rating of 575 CFM at 115PSI. Both air compressors were installed in 1999 and need to be replaced and upgraded with new units. These air compressors supply compressed air to various systems on campus and are critical to plant operations as well as maintenance and research. Both air compressors are no longer able to maintain required air pressure on campus and have become harder to maintain over the last few years thus resulting in unreliability issues as well as inefficiencies. Both existing air compressors utilize two (2) Sullair desiccant air dryers to maintain the -40 degrees F dew point needed in the compressed air system. Currently, both Sullair dryers operate constantly due to the fact that if one of the dryers is placed offline, moisture will accumulate in this “offline” dryer. For energy savings, efficiency, and the need to have N+1 redundancy, the new desiccant dryers shall be able to run on just one set of air dryers while still providing the 575 CFM compressed air at 115 psi pressure at -40 degrees F. The buildings supplied by these air compressors are Buildings 3, 4, 5, 7, 9, 20, 21, 22 and 24.

Scope:

Contractor shall be responsible for:

1. Verifying any and all dimensions and shall carefully examine the air compressor room and surrounding space and shall make all necessary investigations to become thoroughly aware of the existing conditions and all difficulties involved in the completion of the work in accordance with the contract documents prior to the submission of your bid and commencement of work.

2. Maintaining air pressure in Buildings 3, 4, 5, 7, 9, 20, 21, 22 and 24 throughout the project by use of two (2) temporary electrically powered air compressors supplied and maintained by the Contractor.

a. Liquid gasoline or diesel, or natural gas or propane air compressors will not be allowed.

b. The temporary electrically powered air compressors shall be rated at 125psi at approximately 600CFM each.

c. The temporary electrically powered air compressors shall be connected to the existing air dryers to maintain the appropriate dew point setting of -40 degrees F.

d. USDA requires two (2) electrical air compressors to maintain the N+1 requirement to continue air pressure on campus in case of a failure of one of them.

e. Contractor will need to schedule air outages at least two (2) weeks in advance due to the unpredictability of ongoing scientific projects and Select Agent requirements.

f. Contractors may keep one of the existing Sullair air compressors online and in operation in lieu of a 2nd temporary air compressor, if possible.

g. The Contractor-furnished, temporary air compressors shall be located on the north side of Building 154. There is a 2-inch copper line compressed air connection located on the outside of the building. These temporary air compressors can be connected here and piped in a configuration that will allow switching between the temporary air compressors if needed during normal plant operations.

h. There is an existing 200A disconnect on the north side of Building 154 that the contractor can utilize for one of the temporary air compressor electrical connections.

i. Contractor will need to install a 2nd electrical service for the other temporary electrical air compressor or use one of the existing air compressor’s service.

3. Training the Utility Plant staff on how to properly operate the Contractor-furnished, temporary air compressors in case of any issues that may come up since the facility is operated 24 hours a day, 7 days a week. Utility Plant staff will need to know how to start and stop these units and respond to any faults that may occur after hours.

Contractor shall provide the Utility Plant personnel a contact name and number to call if any issues come up with the temporary units after hours.

4. Removing the two (2) existing 100HP Sullair air compressors and disposing of them in accordance with federal, state, and local codes. This is to include all fluids contained within each air compressor.

5. Replacing both Cutler-Hammer 200A, 600V disconnect switches feeding each existing air compressor. Both switches failed a recent short circuit study performed in 2022. Both existing disconnect switches shall be replaced with new disconnect switches that are properly rated above the calculated kA rating according to the latest study. Short circuit study results shall be provided to the contractor for reference.

6. Installing (4) four new automated valves. Two (2) on each discharge of the existing Sullair air dryers and two (2) on the discharge of the new air compressors and connecting them to Metasys for monitoring and automation.

a. Johnson Controls will need to be involved in the setup and programming.

b. Contractor shall ensure new automated valves are compatible with Metasys.

c. Contractor shall install new automated valves on the discharge side of each air dryer to gain the ability to isolate each dryer to eliminate the need to run both sets of dryers at all times. Currently, both sets of air dryers run constantly to prevent the offline set from accumulating moisture. This is a loss of 90CFM just to keep the offline set dry. Contractor shall install valves to isolate the discharge on the offline set and keep the inlet open and then we should be able to prevent moisture from accumulating in the offline set. This will gain us 90CFM.

7. Installing two (2) new water-cooled, rotary screw air compressors. Detailed specifications are listed below. New air compressors must have:

a. 460V/3ph/60hz, NEMA 12, Variable Speed Drive, capable of 80% turndown of compressed air supply.

b. 125PSIG full load pressure

c. 125HP, Premium ‘E’ TEFC fan motor

d. 594 ACFM full load capacity

e. Heavy Duty intake filter (99.99% Efficiency per ISO 5011)

f. Sound Attenuating Enclosure (74 dBA)

g. Water cooled Oil Cooler and Aftercooler with moisture separator and timed condensate drain.

h. Oil Filled

i. Rotary Screw Compressor

j. Compatibility with our existing building automation system, Metasys.

k. Ability to connect with BACnet/IP

l. 1-year package warranty, 5-year warranty on drive motor, coolers, and air/oil separator vessel and 10-year warranty on the air end.

m. Start-up service and training after completion. Contractor shall provide 2 separate sessions of training to accommodate the night shift personnel.

n. Compressor manufacturer shall be able to provide a factory certified service technician to our site within 4 hours of an emergency call for service.

Weather and technician availability dependent.

8. Connecting the two (2) new air compressors to Metasys, our building automation system. Refer to drawing set for reference and details. Johnson Controls will need to be involved in the setup and programming.

9. Ensuring all new copper piping is properly sized for the new air compressors, existing air dryers, dry cooler and trim cooler. Contractor shall also ensure that all copper piping for the new glycol pumping system is sized in accordance with manufacturer’s recommendations and air compressor cooling specifications.

10. Remove old, refrigerated air dryer electrical disconnect and conduit from wall behind existing air dryers. Remove wiring back to nearest junction box.

11. Replacing the existing FlowMaster CFM meter located on the inlet side of the receiver tank and installing a new flow meter and adding an additional nine (9) flow meters to the compressed air system as shown on the project drawings.

a. New flow meters shall be ONICON F-5500 thermal mass flow meters or approved equivalents and have the ability to connect to the existing building automation system (Metasys).

b. Johnson Controls will need to be involved in the setup and programming for each new flow meter.

12. Installing new temperature probes in the existing glycol loop as shown on the project drawings.

a. The temperature sensors shall be Johnson Controls TE-6300 Series Temperature Sensors with TE-6300W Thermowells or approved equivalent.

b. Contractor shall be responsible for installing all probes and the drywells for each probe.

c. All temperature probes shall be connected to Metasys for trending and troubleshooting purposes.

d. Johnson Controls will need to be involved in the setup and programming for each new temperature probe.

13. Installing new mechanical temperature gauges in locations shown on project drawings. Contractor shall provide a bypass valve for servicing on each gauge.

14. Connecting both new air compressors to the two (2) existing Sullair desiccant air dryers according to manufacturer’s recommendations.

15. Installing all wiring and programming to allow air dryers to rotate from one set to the other either manually by the operator or at an adjustable interval, i.e., every Monday at 10AM.

16. Connecting air compressors/air dryers to building automation system (Metasys).

a. Plant operator shall have the ability to switch from one air compressor/air dryer to the other using building automation controls.

b. Johnson Controls will need to be involved in the setup and programming. Air compressors shall be connected to Metasys through an Ethernet connection, BACnet over IP.

c. A CAT6 cable shall be ran from each new air compressor up to the server room that is located above the break room in Building 154.

d. The air dryers shall be connected to Metasys to display alarm conditions, dew point, LEAD/LAG, run status and failure to switch.

17. Ensuring that in the event of a failure of one of the air compressors, that the other air compressor shall automatically start up and take the campus load to maintain pressure on campus and in the Utility Plant. The air compressor that faulted shall send all alarms to the building automation system.

18. Reinstalling all existing blowdowns to each new air compressor and reconnecting them to the existing Sullair oil separator in the shop area of the Utility Plant.

19. Isolating the main receiver tank and installing a bypass to have the ability to bypass the tank in case of an emergency or for serviceability.

a. In addition to adding a new flanged 4-inch manual ball valve for bypassing purposes, the contractor shall replace the other two (2) existing 4-inch manual valves that are located on or around the receiver tank with new.

b. The new 4-inch manual valves shall be of the proper rating and material for a compressed air system.

20. Removing the existing glycol pump skid and installing new glycol skid pumping system in its place.

a. New pump skid assembly shall fit in the same footprint as the existing skid assembly.

b. New pump skid shall be sized in accordance with the air compressor manufacturer’s recommended cooling for proper operation of the new air compressors.

c. Connect the new glycol pump skid control panel to Metasys to display which pump is running, pump run status, any alarm status, GPM and pressure.

21. Replacing all existing 1½ inch glycol copper piping with new 2-inch copper pipes to accommodate the flow requirements of the new system.

22. Replacing any piping insulation that is removed with same type that was removed.

See specification sheet included with drawings.

23. Replacing all existing 2-inch copper compressed air pipes with 3-inch copper pipe to accommodate the 3-inch discharge on the new air compressors.

a. Existing air dryers have a 2-inch discharge. Contractors shall use a 3-inch to 2-inch reducer to connect new 3-inch copper piping from the compressed air piping to the existing air dryers.

b. The common header and any bypasses connecting both discharge pipes coming from each air compressor shall be 3-inch.

c. The common header connecting the air dryer inlet piping and any bypasses shall be 3-inch. See specification sheet included with drawings.

24. Replacing all existing manual ball valves with Apollo (or approved equivalent) manual ball valves that are of the correct size and pressure rating.

a. All 2-inch ball valves shall be replaced with new 3-inch ball valves where needed.

b. All 1½ inch manual ball valves shall be replaced with new 2-inch ball valves where needed. See specification sheet included with drawings.

25. Removing existing dry cooler and installing a new dry cooler (Model number: PFC- 0446 Closed Circuit Cooler or approved equivalent) outside to replace the existing dry cooler. Dry cooler shall be sized in accordance with air compressor manufacturer’s recommended cooling requirements for proper operation of the new air compressors.

a. Each fan coil unit on the new dry cooler shall have a capacity to cool 41 GPM of 50% glycol from 118F to 98F dry bulb temperature.

b. New dry cooler shall have a CFM of 42060.

c. Each fan coil unit shall be individually fused and suitable for outdoor service on 460 volts, 60HZ and 3 phase.

d. Control panel shall be in a U.L. listed weather resistant enclosure.

e. Concrete pad that currently holds the existing dry cooler shall be altered to accommodate the new unit.

f. New outdoor dry cooler shall be sized so that if both air compressors are running, this new dry cooler shall provide enough cooling for both.

g. New dry cooler shall have the ability to isolate and lockout each fan for servicing and maintenance.

26. Removing the existing heat recovery unit in the shop area. This includes removing the copper lines back into the compressor room and securing them as needed.

a. Remove electrical wiring and existing disconnect switch.

b. Once heat recovery unit is removed, Contractor shall reconnect piping back to glycol system ensuring that the system is in a loop.

27. Removing the existing trim cooler above the air compressor room on the mezzanine.

a. Disconnect all copper water lines from existing trim cooler

28. Installing new trim cooler above the air compressor room on the mezzanine. New trim cooler shall be sized in accordance with the air compressor manufacturer’s recommended cooling for proper operation of the new air compressors.

a. The new trim cooler shall be able to support both air compressors running at the same time.

b. New trim cooler shall be complete with water regulating valve and temperature gauge.

c. Contractor shall reconnect existing chilled water supply and return lines to new trim cooler.

d. Connect temperature and pressure gauges to Metasys to display info.

29. Installing new mechanical pressure gauges as shown on the drawings. Provide bypass valving for maintenance and servicing.

30. Applying appropriate labels to the new and existing air lines per ANSI / ASME A13.1

2020. See specification sheet included with drawings. This includes the pneumatic copper lines, and the glycol cooling lines.

a. Compressed Air lines shall be labeled “Compressed Air”

b. Glycol cooling lines shall be labeled “Glycol Supply” and “Glycol Return”.

c. Any water lines shall be labeled “Industrial Water”.

d. Chilled water lines shall be labeled “Chilled Water Supply” and “Chilled Water

Return”.

e. Labels shall indicate direction of flow of air and any liquids in their respective piping.

f. See specification sheet included with the drawings.

31. Verifying any and all dimensions and carefully examining the entire project site and building and shall make all necessary investigations to become thoroughly aware of the existing conditions and all difficulties involved in the completion of the work in accordance with the contract documents prior to commencement of work. Difficulties identified and items that are unclear in this Statement of Work shall be brought to the attention of the COR, EPM and PPM/Owner immediately.

32. Replacing any existing piping insulation that is currently in use that needs to be removed with the same type. See specification sheet included with drawings.

33. Performing a complete compressed air system start-up and operations check once the project is complete. This procedure shall follow manufacturer’s start-up and operating recommendations. Contractor shall ensure that COR and air compressor manufacturer’s representative is present when the start-up and operations check is performed. This will be separate from the formal training.

34. Providing (2) training sessions to accommodate the night shift plant staff.

a. Each training session shall include operating the new air compressors, starting, and stopping each one, how to respond in the event of an issue, reading the display, etc.

b. Training manuals shall be included in close out submittals.

General Requirements

1.01 Work Restrictions & Conditions

A. Site Security Access

1. Access to the construction site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor/sub-contractor employees shall sign in and out at the main site entrance gate and wear a contractor/visitor identification badge at all times while on the site. The ID badges will be turned in at the end of the workday. A current government-issued identification with a picture ID is required for entry. Vehicle badges shall be displayed at all times while the contractor is on site.

2. Access to each individual site shall be arranged by the Contracting Officer's Representative (COR) according to the schedule submitted by the contractor and approved by the COR. The contractor shall coordinate and schedule his/her work under this contract to cause the least interference with the normal flow of visitor and employee traffic.

3. Construction vehicles will be allowed access adjacent to the work; contractor employee’s personal vehicles shall be parked in the facility parking lots.

4. The Contractor shall use only the service roads and access routes approved by the Contracting Officer’s Representative.

5. Work shall be confined to the areas identified on the Drawings. Unless accompanied by a NCAH/USDA employee, the Contractor, sub-contractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons included, but are not limited to, disease control and health requirements.

6. Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided if the situation occurs.

7. Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/sub-contractor employees from the site and barring further site access to individuals.

B. Work Hours: Regular work hours for the site are 7:00AM to 3:30PM, Monday through Friday, excluding Government holidays. Requests for exceptions to this schedule shall be made in writing forty-eight (48) hours in advance and approved by the Contracting Officer's Representative.

C. Work Outside Regular Work Hours: Work scheduled outside regular work hours including late hours, Saturdays, Sundays, and Government holidays requires the Contracting Officer’s Representative’s (COR) approval in advance. Make application to the COR at least 5 calendar days prior to such work to allow arrangements to be made by the Government for access to the work area and inspection & monitoring arrangements. Requests shall include the exact dates, hours, location, and purpose of the exception. If approved, the COR will coordinate access with the site security office.

D. Construct Work in stages to accommodate Owner’s use of premises during construction period. Coordinate construction schedule and operations with Contracting Officer’s Representative (COR).

E. Contractor shall coordinate use of premises under direction of the COR. Contractor shall confine construction equipment, storage of materials and equipment and operations of workers to areas permitted by law, ordinances, permits, or requirements of Contract Documents, and shall not unreasonably encumber premises with construction equipment or other material or equipment. Contractor shall:

1. Assume full responsibility for protection and safekeeping of items under this

Agreement, stored on site.

2. Move any stored items, under Contractor’s control, which interfere with operations of Owner or separate contractor.

3. Obtain and pay for use of additional storage or Work areas needed for operations.

4. Ensure that any materials that are delivered by FedEx, UPS, etc. are delivered to the jobsite and NOT to the USDA warehouse dock at Building 24 or to the north warehouse, Building 11. The USDA and/or the COR will not be responsible for receiving any materials destined for the project. USDA reserves the right to refuse any unscheduled deliveries that arrive at either warehouse or at the main gate. Special considerations shall be made with the COR in advance of the delivery.

5. Notify the COR of any scheduled deliveries. The COR will add the carrier or company to the visitor’s schedule. Contractor will meet the delivery and escort them to the jobsite.

F. Owner will occupy premises during the entire period of construction for its normal operations. Coordinate with Contracting Officer’s Representative (COR) in all construction operations to minimize conflict, and to facilitate Owner usage.

Contractor shall at all times conduct its operations as to ensure the least inconvenience to the Owner.

1.02 Security Clearance Requirements

A. Use of Premises

1. Limit of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the work is approved.

2. Keep driveways, entrances, walkways, and doorways serving premises clear and available to the Government, employees, visitors and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

3. Limited parking may be available on the site away from each facility.

4. The contractor shall provide a list of all staff employees that will be working on the project to the Contracting Officer’s Representative (COR) a minimum of three days in advance. The contractors that will be onsite will be required to provide a valid driver’s license and be a valid United States Citizen to be able to access campus.

5. Once onsite, contractors will be escorted by a USDA employee to the location of the work and will be escorted at all times while onsite.

B. Adherence to Security Policies and Procedures

1. The Contractor shall adhere to all Site, APHIS and USDA security policies and procedures including Code of Federal Regulations Requirements, Standard Operating Procedures, Security Directives, Security Procedures, General Orders, Post Orders and any applicable Government Policies and Procedures.

a. Failure to adhere to or violation of any above listed requirements, procedures, directives, orders and/or policies may result in criminal prosecution or contractor representative or contractor employee (violator) removal.

1.03 Intent of Contract Drawings

A. Government provided drawings, henceforth referred to as “Contract Drawings”, do not attempt to show complete details of building construction that may affect installation. Government provided diagrams of proposed systems are for reference only and do not necessarily show physical arrangement of all equipment and/or maximum number of devices. Minimum system requirements are shown.

B. Devices are shown diagrammatically only. System layout does not necessarily show maximum number of system components and should not be used for obtaining quantities for linear runs of conduits and wires. The contractor shall provide all conduits and wire wherever needed to complete installation of specific equipment required and provided by the Contractor.

C. Locations of existing and Government concept devices are approximate and may be distorted for clarity in representation.

D. Anything mentioned in this Scope of Work and not shown on the drawings or shown on the drawings and not mentioned in the Scope of Work, shall be of like effect as if shown or mentioned in both.

1.04 Regulatory Requirements

A. The equipment materials, installation, workmanship, and operation shall conform to the most stringent applicable requirements of the most recent editions of the associated publications, in the below section and in the attached specifications unless otherwise noted:

1. National Fire Protection Association (NFPA)

a. NFPA 101 – Safety to Life from Fire in Buildings and Structures.

b. NFPA 1 – Uniform Fire Code

c. NFPA 5000 – Building Construction and Safety Code

2. Underwriters Laboratories, Inc. (U.L.)

a. Appropriate U.L. Standards

3. State and Local Building Codes as adopted by the Authority Having Jurisdiction

(AHJ).

4. The Uniform Federal Accessibility Standards (UFAS)

5. Occupational Safety and Health Administration (OSHA)

6. Architectural Barriers Act (ABA)

7. Equipment Manufacturer Printed Instructions

8. NFPA 70 -- National Electric Code (NEC)

1.05 Coordination

A. The contractor shall coordinate all work with the Contracting Officer's

Representative. In general, Owner will need a minimum of four (4) weeks’ notice to prepare spaces and remove existing cabinetry, equipment and furniture located on floor in preparation for contractor to come in and complete work.

B. The contractor shall submit an installation schedule for review and approval by the

Contracting Officer's Representative within ten (10) days of task order award.

C. The contractor shall be solely responsible for coordinating work with all sub-contractors and ensuring that all items of joint use in conjunction with installations are completed.

1.06 Special Provisions

A. The Contractor shall confine all operations to within the work limits of the project and exercise special care to maintain natural surroundings undamaged. All surfaces that have been altered for the installation of the new air compressors shall be refinished to match original condition by skilled personnel of the trades involved at no additional expense to the Government.

B. Finished surfaces of existing facilities that are affected, marred, scratched, or damaged by the contractor shall be refinished to match original condition.

1. Patching material shall be of the same type, style, and thickness, and shall be finished to match existing adjacent surface construction in color and texture.

2. Patching material, paint color, paint material and paint application methods shall be approved in advance by the Contracting Officer’s Representative.

C. No building structural members shall be cut or altered without prior approval of the

Contracting Officer's Representative.

D. Any damage resulting from contractor's operation shall be brought to the attention of the Contracting Officer's Representative immediately.

E. The contractor shall take all necessary and reasonable measures to keep the work site clean of trash and debris. Work areas shall be cleaned immediately as work in that area is completed, and before moving to a new work site. Place all trash and debris in OSHA approved containers, remove, and dispose of trash off site daily.

F. The contractor shall move all materials, and equipment, including ladders and scaffolding from the site at the completion of each day's operation unless otherwise approved by the Contracting Officer's Representative.

G. The contractor shall provide proper safety equipment to workmen and ensure a safe environment for employees and the general public at all times. The contractor shall work to ensure free, unobstructed, and safe access to and about the work area.

1.07 Temporary Facilities

A. Utilities: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The Contractor shall be responsible for making and removing any utility connections.

B. Telephones: The Contractor shall equip all his foremen and work leaders with cell phones as necessary to coordinate the work effort. The Government will not provide any phone service to the project.

C. Construction Material Storage Trailer: The Contractor may locate a construction material storage trailer to the site. Location shall be coordinated with the COR prior to delivery of any materials and/or construction beginning on site.

D. Toilet Facilities: The Contractor will be permitted to use the toilet facilities located inside the Utility Plant, Building 154.

E. Dumpster/Roll-off: The Contractor may locate a dumpster/roll-off to the site. Location of the dumpster shall be coordinated with the COR. Dumpster services shall be the contractor’s responsibility.

1.08 Lock-out/Tag-out Program:

A. The Contractor and/or sub-contractor employees who will be working on the job will apply a lockout/tagout (LOTO) process to control dangerous energy sources. The Contractor/sub-contractor shall have a LOTO program established and use Contractor LOTO locks, tags, and procedures.

B. The Contractor/sub-contractor shall review their LOTO program with NCAH F.E.U.

personnel to coordinate LOTO programs before implementing LOTO.

1.09 Hot Work Plan:

A. The Contractor/sub-contractor shall have a written plan in place to manage the safety and fire hazards associated with hot work. The Plan shall include fire watch and all other requirements in accordance with OSHA. The Contractor/sub-contractor shall maintain written records of hot work until final acceptance of the project and shall provide copies to the Owner’s Representatives at any time requested.

1.10 Submittal & Shop Drawings Procedures

A. Submittal Register: At the beginning of the project, the Contractor shall provide a Submittal Register identifying all the items called out in the Specifications for submittal to the COR for approval. The Contractor shall update and maintain the Submittal Register to show the current status of all required submittals.

B. Submittal Requirements

1. Format: There is no formal submittal transmittal or format for this project other than the documents shall be submitted as PDF files, scanned or created in documents that can be easily read when printed on 11x17 sheets. Exceptions for larger sheet sizes will be considered by the COR. Failure of the Contractor to provide legible submittals will be adequate grounds for rejection.

2. Identification: Submittals shall be labeled and marked for this project. The identification shall include: Contractor/sub-contractor’s name, date of submittal, description of item, specification section, and details on product data that are marked clearly for this project.

C. Submittal Procedures: All submittals will be posted in PDF by the Contractor and sent to the USDA for review. This same submittal process will be used for RFIs, Change Bulletins, etc.

D. Approved Submittals: The approval/acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist.

E. Submittal items for this project :

1. Air Compressors

2. Piping

3. Valves (Ball, Gate, Automated)

4. Pumps and pump skid

5. Air cooled condensing unit (dry cooler)

6. Trim Cooler

7. Pressure Gauges

8. Hangers and Supports

9. Flow meters w/totalizer

10. Temperature Probes

11. Mechanical gauges

12. Labeling for piping

13. Air compressor controls (BAS and compressor provided) including a points list, sequence of operations and ladder diagram.

1.11 Close-out Submittals

A. Warranty Documentation

1. Warranty List: Provide a warranty summary sheet in spreadsheet format with all the warranties listed by section, description, supplier, warranty contact, start date, end date. Provide electronic copy to the COR and place printed copy in the front of the Warranty Binder.

2. Warranty Copies in Binder: Provide one signed & dated copy of all warranties for the air compressor system installed on the project. The Warranty binder shall be divided by Specification Section and shall be provided to the COR. An electronic (scanned) copy of the Warranty Binder in a PDF file shall be submitted with the final close-out documentation.

3. Warranty Items:

a. New air compressors

b. New trim cooler

c. New glycol cooling system

d. New outdoor dry cooler.

e. New automated valves

B. Operation & Maintenance Manuals: Contractor shall provide a printed copy of all

Operation & Maintenance documentation provided with the air compressor systems installed in the project and place the manuals in an organized binder. The O&M Manuals shall be organized by specification section and shall have an index at the front of the binder. The Contractor shall also provide a PDF version of the Manuals to be submitted with the close-out documentation. Contractor shall provide a Sequence of Operations as well.

C. Record Drawings

1. Redline Specifications: During the construction period the Contractor shall keep an updated & marked-up or “redline” copy of the project specifications on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes. At the end of the project the Contractor shall electronically scan the redline specifications and provide an electronic copy in PDF to the Owner along with the close-out documentation.

2. Redline Drawings: During the construction period the Contractor shall keep an updated “redline” or “conformed” copy of the project drawings on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes.

At the end of the project the Contractor shall electronically scan the redline drawings at full-size and in color and provide an electronic copy in PDF to the Owner along with the close-out documentation.

END OF SECTION