2. Scope of Work.pdf
PDF 121 KB Posted
- Solicitation number
- 12970224R0021
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity issued by the Department of Agriculture Forest Service. The contract requires the removal and replacement of an existing wire-faced retaining wall with a government-furnished Hilfiker Wall material along Forest Service Road 22N94 in the Plumas National Forest, California. Key details include:
The contractor shall furnish all equipment and personnel necessary to complete the work, which includes removing and disposing of the existing asphalt and aggregate, excavating the existing MSE structure, preparing the base, constructing the new MSE structure with a retained rock facing, backfilling, replacing the road base and asphalt, and installing object markers. The estimated price range for the contract is $100,000 to $250,000. The contract performance period is 180 calendar days. Special conditions include required permits, no on-site camping or facilities, limited water access, and equipment cleaning/noxious weed requirements. Proposals are due by the RFI deadline of April 29, 2024.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
22N94 Retaining Structure Replacement #3
Section C - DESCRIPTION / SPECIFICATIONS / STATEMENT OF WORK
C.1 Statement of Work The Contractor shall furnish all equipment and personnel necessary to remove and replace the existing Wire-Faced Retaining Wall with government furnished Hilfiker Wall material. The Contractor shall furnish all materials not provided by the government to complete the project. (See Section G) Work includes: Remove and dispose of the existing AC surface, remove and stockpile the aggregate base, excavate the existing MSE structure, dispose of all steel and fabric encasement materials, prepare the structure base, construct the new Government Furnished MSE structure with the retained rock facia including an upper and lower drain system, Backfill as needed to the sub-base level, replace the augmented road base, place a 3” course of hot asphalt, and install object markers.
Specific Requirements for the Base Items are:
• All existing AC and/or chip seal pavement is to be removed and disposed of away from government land. (See Section H)
• Excavate the existing MSE structure. Remove the geo-fabric and metal WW cages and dispose of away from government land.
• Prepare a base for and construct the new Government Furnished MSE structure as shown on the drawings. Also include installation of contractor supplied lower and upper drain system.
• Place and compact suitable fill over the MSE structure to the appropriate level for reconstruction of the new paved road section. Place and compact a six-inch course of aggregate base. Clean base material previously removed from the excavation may be reused here up to 50%.
• Apply a prime coat to compacted aggregate base and a tack coat to cut surfaces of remaining AC pavement.
• Placing, shaping, and compacting hot-mix asphalt concrete to produce a single compacted 3” course.
• Traffic control for public access and administrative travel. (See C.6-H Traffic Control Plan below, C.2 Project Location The project is located on the Feather River Ranger District of the Plumas National Forest, California.
FSR 22N94 runs along the Hartman Bar Ridge south of the Middle Fork of the Feather River. The road intersects with FSR 22N27 7.2 miles east of the community of Feather Falls, CA. Access from the east (Quincy) is via PC 511 & 514 at Little Grass Valley Res. Near La Porte, CA The project location is:
Survey Location: T21N, R7E, Sec. 5, NE ¼ GPS location: 39° 42.460’, -121° 12.789’
C.3 Contract Time The Contractor shall complete all work, including final site clean-up, within 180 calendar days from the Notice to Proceed. Contract period shall not include time the Contractor is unable to safely access the work sits for reasons beyond the Contractor’s control including closure of access to the project area for fires, floods, other weather-related events or for the Government’s convenience.
C.4 Project Clean-up Project site cleanup includes the removal and disposal of all projects generated trash, debris, and residue off National Forest Land in accordance with all applicable local, state, and federal regulations and requirements. Additional requirements are described in Section H
C.5 Price Range The price range for this contract is: $100,000.00 to $250,000.00.
C.6 SPECIAL CONDITIONS AFFECTING THE WORK
A. Physical Conditions. Physical site conditions As Shown on the Drawings and in the specifications are the result of site investigations and surveys performed:
i. At the time of original construction and,
ii. During subsequent routine inspections.
The Government makes no representations related to site conditions except as specifically noted in the drawings or the specifications. No inferences shall be made by the offeror or contractor.
B. Work Hours. The approved work week is: five days (Monday-Friday), between 6:00 AM and 6:00 PM, Pacific Time. Any schedule for site work on federal holidays, Saturdays, Sundays, and outside the times stated above shall be submitted to, and approved by, the Contract Officer prior to such work being performed. The Contracting Officer shall be notified within 24 hours of any emergency work needed to be performed outside the approved work week.
C. Highway Permits. Contractor is responsible for securing any overload and over-size/width limit permits required for the transport of materials or equipment to the project site. The Contractor is responsible for conducting a thorough reconnaissance of all routes leading to the site.
D. Toilets. There are no facilities at or near the project site. The Contractor shall provide all necessary sanitation facilities as required by Butte County and State of California regulations.
E. Camping. Camping is not permitted on Government land within the burn perimeter of the North Complex except as may be specifically allowed by the Contracting Officer. Camping is permitted in established Forest Service campgrounds with the permission of the concessioner.
Contractor shall comply with all terms and conditions of any camping permit issued to allow use of premises. Any non-compliance will result in suspension of work until compliance is achieved.
F. Water. Limited quantities of non-potable water for the project construction can be drafted from
South Branch of the Middle Fork. Use Best Management Practices and do not block public access. Suction hoses/pipes shall have a 3/8” or less screen. Specific Requirements apply to Xxxx Xxxx. Information can be obtained from the Feather River District Office
G. Security. Contractor is responsible for the Contractor’s equipment and materials owned or supplied to the site. Lost, damaged, or stolen equipment or materials shall be replaced at the contractor’s expense. All equipment not equipped with a key lock system shall be secured in such a manner as to make it inoperable to the average person at the end of each working day.
All hand tools and other equipment shall be secured at the end of each working day. The contractor shall be responsible for signing, limiting public access, and safety of the public and/or government employees at the site. All refuse shall be properly stored or removed from the site at the end of each day.
The Government will identify up an area for the contractor’s use as staging and storage areas.
H. Public Access and Traffic Control. See Section H
I. Burning Permits. Contractor is subject to all rules and regulations governing the onsite burning of slash and other debris. Contractor shall obtain a burning permit from the jurisdiction having control over burning. The Contractor shall comply with Project Fire Prevention Plans. There will be no general burning activity as part of this contract.
J. Protection of Resources. Contractor shall thoroughly clean all equipment prior to delivery to the project site to remove weeds, seeds, mud, grease, and oil buildup from all equipment surfaces.
Spills of petroleum products and other hazardous substances shall be reported, contained, and removed in accordance with the approved Storm Water/Pollution Prevention Plans. Such plans shall be submitted in accordance with requirements of Section G, Submittals.
The Contractor shall be responsible for protecting existing resources and improvements and replace those improvements if damaged during this project. The Contractor shall ensure all activities conform the Sub-section C.9 below.
Protection of heritage sites shall be in accordance with provisions of Section H
C.7 PRE-BID CONFERENCE OR TOURS
A Pre-Bid Tour for the project will be scheduled and announced by the Contracting Officer Prospective offerors ARE NOT required to attend however, the offeror acknowledges that they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the Government.
C.8 EQUIPMENT CLEANING & NOXIOUS WEED-FREE CERTIFICATION
The Contracting Officer will coordinate with the contractor for an inspection of equipment prior to delivery or travel on to Forest Service land. For the purposes of this contract, all “Off-road equipment” includes all vehicles and equipment operating off paved roadways. Contractor shall employ whatever cleaning methods are necessary to ensure that off-road equipment is free of noxious weeds. Equipment shall be considered free of soil, seeds, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools is not required. This requirement is not applied to passenger vehicles making intermittent or casual visits to the site.
If the project area is known to contain noxious weeds, the equipment shall be cleaned before moving to other Forest Service system lands which do not contain noxious weeds as determined by the local District Ranger.
C.9 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON
FEDERAL HIGHWAY PROJECTS
The Standard Specifications for this project are contained within the “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-14 U.S. Customary Units. Copies of this document are available at the Federal Highway Administration web site at https://flh.fhwa.dot.gov/resources/specs/ in either Microsoft Word (.doc) or Adobe Acrobat (.pdf) format.
https://flh.fhwa.dot.gov/resources/specs/
Supplemental Project Specifications are included in full text as an attachment in Section J of the contract, and are intended to amend, supplement, or replace the FP-14 Standard Specifications. All specifications not included in the specification listing, but referenced by listed specifications, are applicable.
NOTE: Offerors are cautioned to carefully review these Standard and Supplemental Project Specifications prior to submission of proposals. All specifications in the “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-14 U.S. Customary Units are binding on the parties signing the contract.
C.10 AGAR 452.211-73 ATTACHMENTS TO STATEMENT OF WORK / SPECIFICATIONS (FEB
1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
File details come from the government source that posted it. Updated .