This document appears to be a set of Questions and Answers related to a federal contract opportunity. The key details are:
The contract opportunity is for Solicitation Number 12970224R0021, titled "Plums National Forest; Feather River Ranger District; 22N94 Replace Retaining Wall 3". The scope of work involves removing and replacing an existing wire-faced retaining wall with a government-furnished Hilfiker Wall material. The contractor is responsible for providing all required materials and personnel not furnished by the government to complete the project. The work includes removing and disposing of the existing asphalt and aggregate, excavating the existing structure, preparing the base, constructing the new retaining wall structure, backfilling, and paving the road. The contract value range is $100,000 to $250,000. Requests for Information are due by April 29, 2024. The document also provides clarification on the requirements for key personnel such as the Project Manager, Site Superintendent, and Erosion Control Manager.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions Received Answers Justin wanted to clarify one thing as I am running my numbers. Item 22501, Mechanically Stabilized Earth Wall, shows up twice in the schedule. My assumption is that you are saying that the Government will provide the earth wall and I will add the pay item to install. You know what they say about assuming, so I just wanted to make sure. The only thing we are bidding there is the installation of one MSE, that the Government provides. We don’t need to source a second one from Eureka, correct?
Correct, the Government will furnish Hilfiker Wall material. I’ve included the Statement of work below to ensure we are on the same page. Let me know if you have any additional questions.
C.1 Statement of Work The Contractor shall furnish all equipment and personnel necessary to remove and replace the existing Wire-Faced Retaining Wall with government furnished Hilfiker Wall material. The Contractor shall furnish all materials not provided by the government to complete the project. (See Section G) Work includes: Remove and dispose of the existing AC surface, remove and stockpile the aggregate base, excavate the existing MSE structure, dispose of all steel and fabric encasement materials, prepare the structure base, construct the new Government Furnished MSE structure with the retained rock facia including an upper and lower drain system, Backfill as needed to the sub-base level, replace the augmented road base, place a 3” course of hot asphalt, and install object markers.
Section H- special contract requirements refers to Key Personnel. Only the Erosion Control Manager is highlighted. Does this mean that the contractor need identify the Erosion Control Manager only ?
AGAR 452.237-74 Key Personnel (Feb 1988) A. Proposals shall identify the following Key Personnel and their qualifications/experience.
• Project Manager
• Site Superintendent. Shall have a minimum of five years working on similar projects in remote areas.
• Project Quality Control Manager. Shall have a minimum of three years’ experience as a CQC manager/supervisor.
• Health and Safety Manager.
• Erosion Control/SWPP Manager. Shall have a minimum of three years’ experience with erosion control/SWPP.
Except for the Project Manager and the CQC Manager, multiple positions listed above may be filled by the same person.