SCHEDULE OF ITEMS
Chilao Campground Complex - Water System Rehabilitation (GAOA) Angeles National Forest
Base Bid: Visitor Center to Station Tank
| ITEM NUMBER |
| SPEC # AND SOURCE |
| BID ITEM |
| PAY UNIT |
| EST QTY |
| PRICE |
| TOTAL |
| 0001 |
| 151.01 FP-14 |
| Mobilization |
| LS |
| 1 |
| 0002 |
| 02318 & 02511 |
| Visitor Center to Station Tank Pipeline Installation |
| LF |
| 9250 |
| 0003 |
| 304.05 FP-14 |
| Road 3N21 Pulverization |
| SY |
| 17775 |
| 0004 |
| 403.04 FP-14 |
| Road 3N21 Paving 2" (HMA Caltrans 1/2in TYPE A, PG (64-16) |
| Ton |
| 1956.814 |
| 0005 |
| 634.05 FP-14 |
| Repaint Existing Pavement Striping and Directional Arrows |
| LS |
| 1 |
| 0006 |
| 02511 |
| Existing Visitor Center Trail PRV Valve Box Replacement |
| EA |
| 1 |
| 0007 |
| 02511 |
| Existing Valve Box Replacement |
| EA |
| 3 |
| 0008 |
| 02511 |
| New Creek Crossing Valve Box Installation |
| EA |
| 1 |
| 0009 |
| 02511 |
| New Standpipe Installation |
| EA |
| 1 |
Option 1: Chilao Fire Station Connections
| ITEM NUMBER |
| SPEC # AND SOURCE |
| BID ITEM |
| PAY UNIT |
| EST QTY |
| PRICE |
| TOTAL |
| 1001 |
| 151.01 FP- 14 |
| Mobilization |
| LS |
| 1 |
| 1002 |
| 02318 & 02511 |
| Station Tank to Fire Station Pipeline Installation |
| LF |
| 1650 |
| 1003 |
| 304.05 FP- 14 |
| Road 3N14A1 Station Helispot Barracks Pulverization |
| SY |
| 6000 |
| 1004 |
| 403.04 FP- 14 |
| Road 3N14A2Station Helispot Barracks Asphalt 2" (HMA Caltrans 1/2in TYPE A, PG (64-16) |
| Ton |
| 660.528 |
| 1005 |
| 02511 |
| Existing Firebox/Standpipe Rehabilitation |
| EA |
| 4 |
Option 2: Creek Crossing to Manzanita Tanks
| ITEM NUMBER |
| SPEC # AND SOURCE |
| BID ITEM |
| PAY UNIT |
| EST QTY |
| PRICE |
| TOTAL |
| 2001 |
| 151.01 FP-14 |
| Mobilization |
| LS |
| 1 |
| 2002 |
| 02318 & 02511 |
| Creek Crossing to Manzanita Tanks Pipeline Installation |
| LF |
| 3975 |
| 2003 |
| 304.05 FP-14 |
| Road 3N21 Creek Crossing to Manzanita Loop Pulverization |
| SY |
| 4320 |
| 2004 |
| 403.04 FP-14 |
| Road 3N21 Creek Crossing to Manzanita Loop Asphalt 2" (HMA |
Caltrans 1/2in TYPE A, PG (64-16)
| 2005 |
| 02511 |
| Existing Valve Box Replacement |
| EA |
| 2 |
| 2006 |
| 02511 |
| New Standpipe Installation |
| EA |
| 1 |
Option 3: Station Tank Rehabilitation
| ITEM NUMBER |
| SPEC # AND SOURCE |
| BID ITEM |
| PAY UNIT |
| EST QTY |
| PRICE |
| TOTAL |
| 3001 |
| 01200 |
| Mobilization |
| LS |
| 1 |
| 3002 |
| 09960 |
| Station Tank Coating |
| EA |
| 1 |
| 3003 |
| 03400 |
| Station Tank Rehabilitation (Cracks) |
| EA |
| 1 |
| 3004 |
| 15010 |
| Station Tank Rehabilitation (Valve, Ladder) |
| EA |
| 1 |
Option 4: Manzanita Tanks Rehabilitation
| ITEM NUMBER |
| SPEC # AND SOURCE |
| BID ITEM |
| PAY UNIT |
| EST QTY |
| PRICE |
| TOTAL |
| 4001 |
| 01200 |
| Mobilization |
| LS |
| 1 |
| 4002 |
| 09960 |
| Manzanita Tanks Coating |
| EA |
| 2 |
| 4003 |
| 03400 |
| Manzanita Tanks Rehabilitation (Cracks) |
| EA |
| 2 |
Option 5: Alps Wells Rehabilitation
| ITEM NUMBER |
| SPEC # AND SOURCE |
| BID ITEM |
| PAY UNIT |
| EST QTY |
| PRICE |
| TOTAL |
| 5001 |
| 01200 |
| Mobilization |
| LS |
| 1 |
| 5002 |
| 02511 |
| Alps Well 001 Rehabilitation |
| EA |
| 1 |
| 5003 |
| 02511 |
| Alps Well 002 Rehabilitation |
| EA |
| 1 |
| 5004 |
| 02511 |
| Alps Well 004 Rehabilitation |
| EA |
| 1 |
| 5005 |
| 02511 |
| Alps Well 005 Rehabilitation |
| EA |
| 1 |
| Base Plus Options 1 Through 5 Total: |
| $ |
B.2 SCHEDULE NOTES
* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.
* One award will be made from this solicitation, contractors must submit pricing for all items.
* Items labeled as optional are not required to be exercised by the government. If exercised, the contractor will be required to perform the optional work in accordance with the terms and conditions of this contract.
* Bid Bond/Guarantee. REQUIRED for proposals exceeding $150,000 IAW FAR 52.228-1 Bid Guarantee.
NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.
The contractor shall complete the table below and include the information with their proposal.
| Company Name: |
| POC & Title: |