2. Schedule.docx

DOCX document 15 KB Posted

Attached to
127EAW24R0032 - Deer Mountain Parking Area Repaving
Solicitation number
127EAW24R0032
Issued by

About this file

This document is a Schedule of Items for a base construction project for the Deer Mountain Snowmobile Park Paving. The project requires the contractor to provide mobilization, asphalt concrete pavement, crushed aggregate base and shoulder backing, tack coat, and temporary traffic control. The quantities provided are estimated, and the contractor is responsible for field verification to meet all requirements. The solicitation is a small business set-aside with an estimated value between $100,000 and $250,000. The solicitation number is 127EAW24R0032 and the contracting agency is the Department of Agriculture Forest Service. Requests for information must be submitted by May 28, 2024, and no pre-proposal site visit will be held. Offerors are expected to inspect the site independently.

View the file

Other files

File Type Posted
6. Davis-Bacon Act WD # CA20240007.pdf PDF
3. Supplemental Specifications.pdf PDF
127EAW24R0032.pdf PDF
4. Project Drawings.pdf PDF
5. Fire Plan.pdf PDF
7. RFI Form.docx DOCX document
1. Statement of Work.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART I—THE SCHEDULE

SECTION B-- SCHEDULE OF ITEMS

B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)

PROJECT: DEER MOUNTAIN SNOWMOBILE PARK PAVING

Item
Construction Items
Qty
UNIT
Unit Price
Total Price
15101-0000
MOBILIZATION
1
LPSM
$
$
40302-0301
ASPHALT CONCRETE PAVEMENT,

(TYPE PG 64-28)

250
TON
$
$
41106-0100
CRUSHED AGGREGATE (Class II) -

BASE & SHOULDER BACKING

160
CUYD
$
$
41202-0100
TACK COAT (Rapid Setting)
125
GAL
$
$
63501-0000
TEMPORARY TRAFFIC CONTROL
1
LPSM
$
$
BASE TOTAL:
$___________

B.2 SCHEDULE NOTES

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.

* One award will be made from this solicitation and contractors must submit pricing for all items.

NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

Company Name:
POC & Title:
Email:
Phone Number:
UEI Number:
Tax ID:

File details come from the government source that posted it. Updated .