This document is a Schedule of Items for a base construction project for the Deer Mountain Snowmobile Park Paving. The project requires the contractor to provide mobilization, asphalt concrete pavement, crushed aggregate base and shoulder backing, tack coat, and temporary traffic control. The quantities provided are estimated, and the contractor is responsible for field verification to meet all requirements. The solicitation is a small business set-aside with an estimated value between $100,000 and $250,000. The solicitation number is 127EAW24R0032 and the contracting agency is the Department of Agriculture Forest Service. Requests for information must be submitted by May 28, 2024, and no pre-proposal site visit will be held. Offerors are expected to inspect the site independently.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 6. Davis-Bacon Act WD # CA20240007.pdf | ||
| 3. Supplemental Specifications.pdf | ||
| 127EAW24R0032.pdf | ||
| 4. Project Drawings.pdf | ||
| 5. Fire Plan.pdf | ||
| 7. RFI Form.docx | DOCX document | |
| 1. Statement of Work.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART I—THE SCHEDULE
SECTION B-- SCHEDULE OF ITEMS
B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)
PROJECT: DEER MOUNTAIN SNOWMOBILE PARK PAVING
| Item |
| Construction Items |
| Qty |
| UNIT |
| Unit Price |
| Total Price |
| 15101-0000 |
| MOBILIZATION |
| 1 |
| LPSM |
| $ |
| $ |
| 40302-0301 |
| ASPHALT CONCRETE PAVEMENT, |
(TYPE PG 64-28)
| 250 |
| TON |
| $ |
| $ |
| 41106-0100 |
| CRUSHED AGGREGATE (Class II) - |
BASE & SHOULDER BACKING
| 160 |
| CUYD |
| $ |
| $ |
| 41202-0100 |
| TACK COAT (Rapid Setting) |
| 125 |
| GAL |
| $ |
| $ |
| 63501-0000 |
| TEMPORARY TRAFFIC CONTROL |
| 1 |
| LPSM |
| $ |
| $ |
| BASE TOTAL: |
| $___________ |
B.2 SCHEDULE NOTES
* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.
* One award will be made from this solicitation and contractors must submit pricing for all items.
NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.
| Company Name: |
| POC & Title: |
| Email: |
| Phone Number: |
| UEI Number: |
| Tax ID: |
File details come from the government source that posted it. Updated .