1. Statement of Work.pdf

PDF 520 KB Posted

Attached to
127EAW24R0032 - Deer Mountain Parking Area Repaving
Solicitation number
127EAW24R0032
Issued by

About this file

This document is a Statement of Work for the Deer Mountain Snowmobile Park Parking Lot Repaving project. The project consists of a base bid that includes conditioning the existing base material and applying 2.5-inches of PG 64-28 Asphalt along with necessary shoulder backing. The project locations are within the Goosenest Ranger District of the Klamath National Forest. The applicable FHWA Standard Specifications 2014 and supplemental specifications are provided. Required submittals include a Hazardous Spill Plan, Fire Plan, Construction Schedule/Plan of Operation, Traffic Control Plan, and Job Hazard Analysis/Safety Plan, with 15 working days for government approval. Material certifications and testing reports for Asphalt Concrete PG 64-28 and Aggregate Base Class II are also required, with a 15-day approval time.

The related federal contract opportunity is Solicitation Number 127EAW24R0032 for the Deer Mountain Parking Area Repaving project, with an estimated project value between $100,000 and $250,000. It is a Total Small Business Set Aside. All requests for information must be submitted by 1300 hours PST on May 28th, 2024, and a pre-proposal site visit will not be held.

View the file

Other files

File Type Posted
6. Davis-Bacon Act WD # CA20240007.pdf PDF
3. Supplemental Specifications.pdf PDF
2. Schedule.docx DOCX document
127EAW24R0032.pdf PDF
4. Project Drawings.pdf PDF
5. Fire Plan.pdf PDF
7. RFI Form.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C – STATEMENT OF WORK

C-1 PROJECT SCOPE

Deer Mountain Snowmobile Park Parking Lot Repaving

This solicitation is for contract work that includes a primary task that shall be carefully coordinated and scheduled. The project consists of a base bid. The base bid includes the conditioning of existing base material and the application of 2.5-inches of PG 64-28 Asphalt along with necessary shoulder backing.

C-2 PROJECT LOCATION

The project sites are located within the Goosenest Ranger District of the Klamath

National Forest. Refer to project location map below.

Deer Mountain Snowmobile Park

From Weed, head North on CA-97 for about 16 miles. Then turn right onto FS Road 19.

Continue for approximately 4 miles to arrive onto the project vicinity of Deer Mountain

Snowmobile Park.

Diagram (above): Project location map of Deer Mountain Snowmobile Park

C-3 SPECIFICATIONS APPLICABLE TO THIS INDIVIDUAL PROJECT

Deer Mountain

(41,570488,-122.131980)

CA-97

[X] FHWA Standard Specification 2014 applies

[_] FHWA Standard Specification 2014 Metric applies

The attached “List of Specifications” and “Supplemental Specifications” apply. All specifications not included in the specification listing, but referenced by listed specifications, are applicable.

# DESCRIPTION DATE

101 TERMS, FORMAT, AND DEFINITIONS 2014

102 BID, AWARD, AND EXECUTION OF CONTRACT 2014

103 SCOPE OF WORK 2014

104 CONTROL OF WORK 2014

105 CONTROL OF MATERIAL 2014

106 ACCEPTANCE OF WORK 2014

107 LEGAL RELATIONS AND RESPONSIBILITY TO

THE PUBLIC

108 PROSECUTION AND PROGRESS 2014

109 MEASUREMENT AND PAYMENT 2014

151 MOBILIZATION 2014

153 CONTRACTOR QUALITY CONTROL 2014

154 CONTRACTOR SAMPLING AND TESTING 2014

155 CONSTRUCTION SCHEDULE 2014

156 PUBLIC TRAFFIC 2014

403 ASPHALT CONCRETE 2014

412 ASPHALT TACK COAT 2014

635 TEMPORARY TRAFFIC CONTROL 2014

703 AGGREGATE 2014

C-4 PRODUCTS SAMPLES AND/OR SUBMITTALS

Title

Referenced by Contract clause or Specification

No.

Time of

Government

Approval After

Submittal

Hazardous Spill Plan 107.10 15 working days

Fire Plan Fire Protection and

Suppression

15 working days

Construction Schedule/

Plan of Operation

FAR 52.236-15 15 working days

Traffic Control Plan 156 & 635 15 working days

Job Hazard Analysis / Safety Plan FAR 52.236-13 15 working days

C-5 SHOP DRAWINGS

Found in attached document “Tri-Forest Snowmobile Park_1.5.2024.pdf”.

C-6 MATERIAL CERTIFICATIONS AND TESTING REPORTS

Title

Referenced by Contract clause or Specification No.

Time of

Government

Approval

After

Submittal

Asphalt Concrete PG 64-28 FP-14 403, 412 15 days

Aggregate Base Class II FP-14 703.05 15 days

File details come from the government source that posted it. Updated .