1. Statement of Work.pdf
PDF 520 KB Posted
- Solicitation number
- 127EAW24R0032
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Statement of Work for the Deer Mountain Snowmobile Park Parking Lot Repaving project. The project consists of a base bid that includes conditioning the existing base material and applying 2.5-inches of PG 64-28 Asphalt along with necessary shoulder backing. The project locations are within the Goosenest Ranger District of the Klamath National Forest. The applicable FHWA Standard Specifications 2014 and supplemental specifications are provided. Required submittals include a Hazardous Spill Plan, Fire Plan, Construction Schedule/Plan of Operation, Traffic Control Plan, and Job Hazard Analysis/Safety Plan, with 15 working days for government approval. Material certifications and testing reports for Asphalt Concrete PG 64-28 and Aggregate Base Class II are also required, with a 15-day approval time.
The related federal contract opportunity is Solicitation Number 127EAW24R0032 for the Deer Mountain Parking Area Repaving project, with an estimated project value between $100,000 and $250,000. It is a Total Small Business Set Aside. All requests for information must be submitted by 1300 hours PST on May 28th, 2024, and a pre-proposal site visit will not be held.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 6. Davis-Bacon Act WD # CA20240007.pdf | ||
| 3. Supplemental Specifications.pdf | ||
| 2. Schedule.docx | DOCX document | |
| 127EAW24R0032.pdf | ||
| 4. Project Drawings.pdf | ||
| 5. Fire Plan.pdf | ||
| 7. RFI Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C – STATEMENT OF WORK
C-1 PROJECT SCOPE
Deer Mountain Snowmobile Park Parking Lot Repaving
This solicitation is for contract work that includes a primary task that shall be carefully coordinated and scheduled. The project consists of a base bid. The base bid includes the conditioning of existing base material and the application of 2.5-inches of PG 64-28 Asphalt along with necessary shoulder backing.
C-2 PROJECT LOCATION
The project sites are located within the Goosenest Ranger District of the Klamath
National Forest. Refer to project location map below.
Deer Mountain Snowmobile Park
From Weed, head North on CA-97 for about 16 miles. Then turn right onto FS Road 19.
Continue for approximately 4 miles to arrive onto the project vicinity of Deer Mountain
Snowmobile Park.
Diagram (above): Project location map of Deer Mountain Snowmobile Park
C-3 SPECIFICATIONS APPLICABLE TO THIS INDIVIDUAL PROJECT
Deer Mountain
(41,570488,-122.131980)
CA-97
[X] FHWA Standard Specification 2014 applies
[_] FHWA Standard Specification 2014 Metric applies
The attached “List of Specifications” and “Supplemental Specifications” apply. All specifications not included in the specification listing, but referenced by listed specifications, are applicable.
# DESCRIPTION DATE
101 TERMS, FORMAT, AND DEFINITIONS 2014
102 BID, AWARD, AND EXECUTION OF CONTRACT 2014
103 SCOPE OF WORK 2014
104 CONTROL OF WORK 2014
105 CONTROL OF MATERIAL 2014
106 ACCEPTANCE OF WORK 2014
107 LEGAL RELATIONS AND RESPONSIBILITY TO
THE PUBLIC
108 PROSECUTION AND PROGRESS 2014
109 MEASUREMENT AND PAYMENT 2014
151 MOBILIZATION 2014
153 CONTRACTOR QUALITY CONTROL 2014
154 CONTRACTOR SAMPLING AND TESTING 2014
155 CONSTRUCTION SCHEDULE 2014
156 PUBLIC TRAFFIC 2014
403 ASPHALT CONCRETE 2014
412 ASPHALT TACK COAT 2014
635 TEMPORARY TRAFFIC CONTROL 2014
703 AGGREGATE 2014
C-4 PRODUCTS SAMPLES AND/OR SUBMITTALS
Title
Referenced by Contract clause or Specification
No.
Time of
Government
Approval After
Submittal
Hazardous Spill Plan 107.10 15 working days
Fire Plan Fire Protection and
Suppression
15 working days
Construction Schedule/
Plan of Operation
FAR 52.236-15 15 working days
Traffic Control Plan 156 & 635 15 working days
Job Hazard Analysis / Safety Plan FAR 52.236-13 15 working days
C-5 SHOP DRAWINGS
Found in attached document “Tri-Forest Snowmobile Park_1.5.2024.pdf”.
C-6 MATERIAL CERTIFICATIONS AND TESTING REPORTS
Title
Referenced by Contract clause or Specification No.
Time of
Government
Approval
After
Submittal
Asphalt Concrete PG 64-28 FP-14 403, 412 15 days
Aggregate Base Class II FP-14 703.05 15 days
File details come from the government source that posted it. Updated .