This Scope of Work document is issued by the Utah Department of Transportation (UDOT) Region 4 for Solicitation #UDOT260139CN and outlines the requirements for a fencing contractor to provide and install 48,200 linear feet of Right-of-Way Fence, Type G (Metal Post) with Tortoise Fence, along with 110 brace posts, 8 right-of-way gates (10-foot opening), and 6 tortoise fence step-overs. The project encompasses all labor, equipment, and materials necessary for installation according to plans, standard drawings, special provisions, and standard specifications. The tortoise fence will be buried 12 inches under natural ground level where possible, with provisions for drilling in rock areas where bedrock is encountered. The contract start date is February 2, 2026, with a completion deadline of April 20, 2026. Major materials include metal line posts, fence fabric, tension wire, fence clamps, hog rings, tortoise fence, and cobble for bedrock areas. The project does not include grading or leveling prior to installation, and all existing roads and traffic lanes must remain open throughout construction.

Environmental compliance is a critical component of this project, requiring a presence/absence survey for Mojave Desert tortoises prior to construction, mandatory tortoise sensitivity training for all construction staff, and coordination with the Red Cliffs Desert Reserve at least one week before construction begins. Construction activities are confined to a 15-foot corridor within the UDOT right-of-way, with daily waste removal and compliance with Construction General Permit requirements including Storm Water Pollution Prevention Plan (SWPPP) implementation. A UDOT-provided monitor will be on-site to ensure compliance and conduct vehicle surveys, requiring contractors to coordinate their schedule with the monitor at least two weeks in advance. The contract includes liquidated damages of $500 per day from April 21–May 2, 2026, increasing to $2,500 per day from May 3, 2026, until project completion. The contract will be awarded to the lowest responsive and responsible bidder in accordance with the State of Utah Procurement Code.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B Scope of Work Fence Project

UDOT is requesting a fencing contractor to provide and install 48,200 linear feet of Right-of-Way Fence, Type G (Metal Post) with Tortoise Fence, 110 Brace Posts, 8 Right-of-Way Gates (10-foot opening), and 6 Tortoise Fence Step-Overs. This contract includes all labor, equipment, and materials necessary to install the fence as shown in the plans, standard drawing, special provisions, and standard specifications.

The Right-of-Way Fence, Type G (Metal Post) with Tortoise Fence will be installed by burying the tortoise fence 12” under the natural ground level where possible. If bedrock is encountered additional equipment to drill fence posts will be necessary. Pay item: “Fence Post (Drilling in Rock)” is in the contract for drilling in rock. The quantity for fence posts requiring drilling is an estimated quantity. Final payment for this item will be made based on actual field quantities encountered during installation. Whether the tortoise fence is buried or folded with cobble in bedrock areas, payment will be made under the same fence items.

Major items to be purchased for the Right-of-Way Fence, Type G (Metal Post) with Tortoise Fence include metal line posts, fence fabric, top and bottom tension wire, fence clamps, hog rings, tortoise fence, and cobble (in bedrock areas). Additional material requirements are shown in the plans, standard drawings, special provisions, and standard specifications. All work must include associated components and be performed according to the plans, special provisions, and specifications. Please note that this scope does not include grading or leveling the area prior to installation. Fence will be installed on natural ground.

All existing State, County, City roads and lanes of traffic will remain open at all times.

Environmental Requirements:

· All fencing activities will be conducted from inside the UDOT ROW and will be confined to a corridor within 15 feet of the fence alignment.

· A presence / absence survey for tortoises will be conducted prior to construction to search for new burrows and/or signs of current occupancy.

· All construction staff will be required to attend a Mojave Desert Tortoise Sensitivity Training prior to construction.

· Coordination of construction within and adjacent to the RCDR will be completed by contacting the Red Cliffs Desert Reserve (Cameron Rognan, 435-301-7430) at least one week prior to the beginning of construction.

· Construction staff will ensure that undersides of vehicles on the ROW are inspected for the presence of Mojave desert tortoise prior to the vehicle moving.

· If a tortoise is located at any time during construction, construction staff will follow guidance provided during the Mojave Desert Tortoise Sensitivity Training to ensure proper reporting and avoidance.

· Staging areas or construction borrow areas occurring outside the roadway prism, including all public or private land, require appropriate coordination and permitting. Refer to Standard Specification Section 01355, Article 1.12 for specific requirements.

· Clean up and remove waste daily.

· Comply with Construction General Permit (CGP), by finalizing the SWPPP before beginning any earth disturbing activities and submit Notice of Intent (NOI); implement and maintain the project SWPPP according to CGP requirements throughout project construction.

· The Contractor shall comply with Blue Stakes requirements where applicable.

· A UDOT-provided monitor will be on-site to ensure compliance. One of their tasks will include a survey ahead of moving vehicles, and the contractor must coordinate their schedule with the monitor at least two weeks in advance and keep this schedule.

Project Timeline:

The contractor's start date is February 2, 2026, and the completion deadline is April 20, 2026.

Failure to complete the contract by April 20, 2026, will result in Liquidated Damages (LD’s) as follows:

· $500 per day from April 21, 2026, through May 2, 2026.

· $2,500 per day starting May 3, 2026, until the contract is complete.