2_ AE 50620 Building Information Model Execut.pdf

PDF 342 KB Posted

Attached to
AE50620 Final Design Services for the Campbellton Rapid Project
Solicitation number
PE-97100-NONST-2025-000000119
Issued by
Fulton County, Georgia

About this file

This document is a Building Information Model (BIM) Execution Guide developed by the Metropolitan Atlanta Rapid Transit Authority (MARTA), serving as a comprehensive template for planning and managing BIM projects. The guide outlines a detailed framework for implementing BIM technologies across various project phases, including preliminary planning, design documents, and construction documentation. The document provides a structured approach to BIM implementation, defining project goals, software requirements, collaboration procedures, and specific deliverables across multiple project stages.

The guide emphasizes a range of BIM application goals, including building maintenance scheduling, systems analysis, asset management, space management, disaster planning, and record modeling, with specific levels of detail (LOD) for each objective. It specifies technical requirements such as using Revit 2014 for architectural and structural modeling, Civil 3D 2014 for civil engineering, and AutoCAD 2014 for mechanical systems. The document includes quality control checklists, collaboration procedures, and project deliverable requirements, with specific submittal phases for 30%, 60%, and record model close-out, focusing on PDF and Revit model formats for coordination and documentation purposes.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B

BIM Execution Guide

Appendix A

Table of Contents

Contents 1 Overview

2 Project Information

3 Project Contacts

4 Software Used

5 BIM Project Schedule

6 Project BIM Goals

7 Project Deliverables

8 Collaboration Procedures

9 Quality Control Checklist

1 Overview

This template is to be a tool used in planning MARTA BIM projects. The BIM Project Manager is responsible for the issuing and maintain this document. The BIM PM will use this tool to collaborate with the Project PM. The project BIM goals and deliverables for different project milestones will be defined in this document. Every project should have a copy of this file in the project directory and should be completed early in the project planning stages. This is a template and may be modified or added to in order to fit a specific project needs or requirements.

2 Project Information

Project Information

Project Owner

Project Name

Project Number

Project Location and Address

Contract Type / Delivery Method

Brief Project Description

Additional Project Information Unique BIM Requirements?

3 Project Contacts

Role Organization Name E‐Mail Phone

MARTA Project Manager

MARTA BIM Manager

Project Manager

Lead Civil

Lead Arch

Lead Structural

Lead Mech

Lead Elec

Lead Plumbing

4 Software Used It is critical to identify the software used as Revit is not backward compatible.

Discipline Software Release

Architecture Revit 2014

Civil Civil 3D 2014

Mechanical AutoCAD 2014

Structural Revit 2014

5 BIM Project Schedule This schedule should be completed prior to the start of work on the model. If there is a deviation from the schedule the BIM Project Manager should include a report documenting the deviation.

Project Phase Estimated Start Date

Actual Start Date

Estimated Completion

Date

Actual Completion

Date

Preliminary Planning

Design Documents 60%

Design Documents 100%

Construction Documents 50%

Construction Documents 90%

Issue for Permit

Issue for Construction

6 Project BIM Goals

Table 4.0 to be utilized in the planning process. The BIM PM will lead a meeting including the stake holders and project team available describing the pros and cons of each goal. In the outcome of the meeting the project goals should be defined and the BIM Project Manager will have a clear understanding of the scope of work. The BIM PM will complete and maintain the BIM Execution Guide.

PROJECT PLANNING CHECKLIST

GOAL LOD DESIGNER YES/NO

Building Maintenance Scheduling 500 MARTA

Building Systems Analysis 500 Design Team

Asset Management 500 MARTA

Space Management & Tracking 400/500 MARTA

Disaster Planning 500 MARTA

Record Modeling 500 MARTA

Site Utilization Planning 200 Contractor

Construction Systems Design 200 Contractor

Digital Fabrication 200 Design Team / Contractor

3D Control Planning 200 Contractor

3D Coordination 200 Design Team

Design Authoring 350 Design Team

Engineering Analysis 350 Design Team

Sustainability 350 Design Team

Design Review 200 Design Team

Programming 200 Design Team

Phase Planning 200 Contractor

Cost Estimation 500 Contractor

Existing Conditions Modelling As required MARTA/Design Team

PROJECT GOAL DESCRIPTIONS AND RESPONSIBLE PARTIES

Responsibility Goal Description

ARCH/SE/MEP Example: Use clash detection between structural and MEP disciplines in order to better coordinate construction drawings.

LEVEL OF DETAIL EXPECTATIONS PER DISCIPLINE

LOD Expectations

ARCH 200 The Model Elements are graphically represented within the Model as a generic system, object, or assembly with approximate quantities, size, shape, location, and orientation. Non‐graphic information may also be attached to the Model Element

Building (Preventative) Maintenance Scheduling Description:

A process in which the functionality of the building structure (walls, floors, roof, etc.) and equipment serving the building (mechanical, electrical, plumbing, etc.) are maintained over the operational life of a facility. A successful maintenance program will improve building performance, reduce repairs and reduce overall maintenance costs.

Potential Value:

Plan maintenance activities proactively and appropriately allocate maintenance staff Track maintenance history Reduce corrective maintenance and emergency maintenance repairs Increase productivity of maintenance staff because the physical location of equipment/system is clearly understood Evaluate different maintenance approaches based on cost Allow facility managers to justify the need and cost of establishing a reliability-centered maintenance program

Resources Required:

Design review software to view record model and components Building automation system (BAS) linked to record model Computerized maintenance management system (CMMS) linked to record model User-friendly dashboard interface linked to record model to provide building performance information and/or other information to educate building users

Team Competencies Required:

Ability to understand and manipulate CMMS and building control systems with record model Ability to understand typical equipment operation and maintenance practices Ability to manipulate, navigate and review a 3D model

Selected Resources:

Campbell, D.A. (2007). BIM – Web Applications for AEC, Web 3D Symposium.

Fallon, K. (2008). “Interoperability: Critical to Achieving BIM Benefits”. AIA Edges Website: Singh, H.; W.H. Dunn (2008).

Integrating Facilities Stovepipes for Total Asset Management (TAM). Journal of Building Information Modeling, Spring 2008. http://www.aia.ord/nwsltr_tap.cfm?pagename=tap_a_0704_interop

ASHRAE (2003). HVAC design Manual for Hospitals and Clinics. Atlanta, GA. (2004). Federal energy Management Program. O&M Best Practices: A Guide to Achieving Operational Efficiency, Release 2.0. July 2004.

www1.eere.energy.gov/femp/pds.OM_5.pdf

Piotrowski, J. (2001). Pro-Active Maintenance for Pumps. Archives, February 2001, Pump-Zone.com

©2010 The Computer Integrated Construction Research Group The Pennsylvania State University

Maintenance Scheduling: Tracking and maintaining lifecycle information about the building structure (wall, floors, roof, etc.) as well as the equipment serving the building (mechanical, electrical, plumbing, etc.) to plan and schedule a program of maintenance activities that will improve building performance, reduce repairs and reduce overall maintenance costs

Building Systems Analysis Description:

A process that measures how a building's performance compares to the specified design. This includes how the mechanical system operates and how much energy a building uses. Other aspects of this analysis include, but are not limited to, ventilated facade studies, lighting analysis, internal and external computational fluid dynamics (CFD) airflow, and solar analysis.

Potential Value:

Ensure building is operating to specified design and sustainable standards Identify opportunities to modify system operations to improve performance Create a "what if" scenario and change different materials throughout the building to show better or worse performance conditions

Resources Required:

3D model manipulation Building systems analysis software (energy, lighting, mechanical, other)

Team Competencies Required:

Ability to manipulate, navigate and review a 3D model Ability to understand building systems and typical operations Ability to assess building systems using analysis software

Selected Resources:

Ayat E. Osman, Robert Ries. " Optimization For Cogeneration Systems in Buildings Based on Life Cycle Assessment" May 2006, http://itocn.org/2006/20/

"Building Performance Analysis Using Revit" 2007 Autodesk Inc., http://images.autodesk.com/adsk/files/building_performance_analysis_using_revit.pdf

Building Systems Analysis: Measuring how a building's actual performance compares to design model predictions

Asset Management Description:

A process in which an organized management system will efficiently aid in the maintenance and operation of a facility and its assets. These assets, consisting of the physical building, systems, surrounding environment and equipment, must be maintained, operated and upgraded at an efficiency which will satisfy both the owner and users at the lowest appropriate cost. It assists in financial decision-making, as well as short-term and long-term planning. Asset management uses the data contained in a record model to determine cost implications of changing or upgrading building assets, segregate costs of assets for financial tax purposes and maintain a current comprehensive database that can produce the value of a company's assets.

Potential Value:

Store operations, maintenance owner user manuals and equipment specifications.

Perform and analyze facility and equipment condition assessments Maintain up-to-date facility and equipment data including, but not limited to, maintenance schedules, warranties, cost data, upgrades, replacements, damages/deterioration, maintenance records, manufacturer's data, equipment functionality and others required by owner Provide one comprehensive source for tracking the use, performance and maintenance of a building's assets for the owner, maintenance team and financial department Produce accurate quantity takeoffs of current company assets to aid in financial reporting, bidding and estimating the future cost implications of upgrades or replacements of specified assets Allow for future updates of the record model to show current building asset information after upgrades, replacements or maintenance by tracking changes Aid financial department in efficiently analyzing different types of assets through an increased level of visualization Increase the opportunity for measurement and verification of systems during building occupation

Resources Required:

3D model manipulation Asset management system

Team Competencies Required:

Ability to manipulate, navigate and review a 3D model Ability to manipulate an asset management system Knowledge of tax requirements and related financial software Knowledge of the assets requiring tracking, whether the building is dynamic or static, and the end needs of the building to satisfy the owner

Selected Resources:

GSA Energy Performance and Operations:

http://www.gsa.gov/Portal/gsa/ep/contentView.do?programId=12122&channelId=- 8161&ooid=20917&contentId=21770&pageTypeId=8195&contentType=GSA_BASIC&programPage=%2Fep%2 Fprogram%2FgsaBasic.jsp&P=PMBIM

GSA Commissioning Overview: http://www.gsa.gov/Portal/gsa/ep/channelView.do?pageTypeId=8195&channel Page=%2Fep%2Fchannel%2FgsaOverview.jsp&channelId=-15163

NIST General Buildings Information Handover Guide: Principles, Methodology and Case Studies http://www.fire.nist.gov/bfrlpubs/build07/PDF/b07015.pdf

Asset Management: Linking data in a BIM record model to a database of building assets to assist in efficiently maintaining and operating the facility

B B

Space Management and Tracking Description:

A process in which BIM is utilized to effectively allocate, manage and track assigned workspaces and related resources. A BIM model will allow the facility management team to analyze the existing use of the space and appropriately manage changes in clientele and use of space, as well as future changes throughout the facility's life. Space management and tracking is an application of the record model.

Potential Value:

Identify and allocate space for appropriate building use Track current use of space Insure optimum use of the facility's space resources Assist in planning future space needs for the facility

Resources Required:

3D model manipulation Content management application

Team Competencies Required:

Ability to manipulate, navigate and review record model Ability to assess current space and assets and manage appropriately for future needs Selected Resources:

Valcik, Nicolas A. and Patricia Huesca-Dorantes. “Building a GIS Database for Space and Facilities Management.” New Directions for Institutional Research, n120 p53-61 2003.

Management and Tracking: Allocating, managing and tracking spaces and related resources within a facility

Disaster Planning Description:

A process in which emergency responders would have access to critical building information in the form of a model and information system. The BIM would provide critical building information to the responders to improve the efficiency of the response and minimize safety risks. The dynamic building information would be provided by a BAS while the static building information, such as floor plans and equipment schematics, would reside in a BIM model. These two systems would be integrated via a wireless connection and emergency responders would be linked to an overall system. The BIM coupled with the BAS would be able to clearly display where the emergency was located within the building, possible routes to the area and any other harmful locations within the building.

Potential Value:

Provide police, fire, public safety officials and first responders access to critical building information in real time Improve the effectiveness of emergency response Minimize risks to responders

Resources Required:

3D model manipulation BAS knowledge Emergency response knowledge

Team Competencies Required:

Ability to manipulate, navigate and review BIM model for facility updates Ability to understand dynamic building information through BAS Ability to make appropriate decisions during an emergency Selected Resources:

Building Information for Emergency Responders. Systemics, Cybernetics and Informatics, 11th World Multi- Conference (WMSCI 2007). Proceedings. Volume 3. Jointly with the Information Systems Analysis and Synthesis: ISAS 2007, 13th International Conference. July 8-11, 2007, Orlando, FL, Callaos, N.; Lesso, W.; Zinn, C. D.; Yang, H., Editor(s) (s), 1-6 pp, 2007. Treado, S. J.; Vinh, A.; Holmberg, D. G.; Galler, M.

Disaster Planning and Response: Using a BIM model to give emergency responders access to critical building information to improve the efficiency and effectiveness of their response and minimize the safety risks.

Record Modeling Description:

A process in which a 3D model contains an accurate depiction of the physical conditions and environment of a facility and its assets. This has potential to contain information relating to the main architectural and mechanical/electrical/plumbing (MEP) elements and equipment and asset information. Furthermore, with the continuous updating and improvement of the record model and the capability to store more information, the model contains a true depiction of space with a link to information such as serial codes, warranties and maintenance history of all the components in the building. The record model also contains information linking pre-build specification to as-built specifications. This allows the owner to monitor the project relative to the specifications provided.

Potential Value:

Aid in future modeling and 3D design coordination for renovation Provide documentation of environment for future uses, e.g., renovation or historical documentation Aid in the permitting process (e.g. continuous change versus specified code) Dispute elimination (e.g. link to contract with historical data highlights expectations and comparisons drawn to final product) Solid understanding of project sequencing by stakeholders leads to reduced project delivery times, risk, cost and lawsuits

Resources Required:

3D model manipulation

Team Competencies Required:

Ability to manipulate, navigate and review 3D model Ability to use BIM modeling application for facility updates Ability to thoroughly understand site processes to ensure correct input

Selected Resources:

http://www.bimforum.org/index.php?option=com_content&task=view&id=19#Q6 http://bentleybim.wordpress.com/2007/11/13/bentleys-bim-preferred-58-to-revit-38-executive-briefing/ http://continuingeducation.construction.com/article.php?L=19&C=213&P=1 http://www.aecbytes.com/buildingthefuture/2006/Expotitions_meeting.html

Record Modeling: Creating an accurate depiction of the physical conditions, environment and assets of a facility

Site Utilization Planning Description:

A process in which a 4D model is used to graphically represent both permanent and temporary facilities on site along with the construction activity schedule. Additional information incorporated into the model can include labor resources, materials and associated deliveries, and equipment location. Because the 3D model components are directly linked to the schedule, site management functions such as visualized planning, short-term re-planning and resources can be analyzed over different spatial and temporal data.

Potential Value:

Generate site usage layout for temporary facilities, assembly areas and material deliveries for all phases of construction Identify potential and critical space and time conflicts Select a feasible construction scheme Update site organization and space usage as construction progresses

Resources Required:

3D model manipulation Design authoring software Scheduling software

Team Competencies Required:

Ability to manipulate, navigate and review 3D model Ability to manipulate and asses construction schedule with 3D model Ability to understand typical construction methods Selected Resources:

Chau, K.W.; M. Anson, and J.P. Zhang. “Four-Dimensional Visualization of Construction Scheduling and Site Utilization.” Journal of Construction Engineering and Management. (July/August 2004): 598-606. ASCE. 5 September 2008. http://cedb.asce.org/cgi/WWWdisplay.cgi?0410956.

Dawood, Nashwam et al. “The Virtual Construction Site (VIRCON) Tools: An Industrial Evaluation.” ITcon. Vol. 10 (2005): 43-54. 8 September 2008. http://www.itcon.org/cgi-bin/works/Show?2005_5.

Heesom, David and Lamine Mahdjoubi. “Trends of 4D CAD Applications for Construction Planning.”

Construction Management and Economics. (February 2004). 22 171-182. 8 September 2008.

http://www.tamu.edu/classes/choudhury/articles/1.pdf.

Construction System Design (Virtual Mockup) Description:

A process in which 3D system design software is used to design and analyze the construction of a complex building system (e.g. form work, glazing, tie-backs, etc.) in order to increase planning.

Potential Value:

Increase constructability of a complex building system Increase construction productivity Increase safety awareness of a complex building system Decrease language barriers

Resources Required:

3D system design software

Team Competencies Required:

Ability to manipulate, navigate and review 3D model Ability to make appropriate construction decisions using a 3D system design software Knowledge of typical and appropriate construction practices for each component Selected Resources:

Leventhal, Lauren.” Delivering Instruction for Inherently-3D Construction Tasks: Lessons and Questions for Universal Accessibility”. Workshop on Universal Accessibility of Ubiquitous Computing: Providing for the elderly.

Khemlano (2007). AECbytes: Building the Future (October 18, 2007).

Digital Fabrication

A process that utilizes machine technology to prefabricate objects directly from a 3D model. The 3D model is spooled into appropriate sections and input into fabrication equipment for production of system assemblies.

Potential Value:

Automate building component fabrication Minimize tolerances through machine fabrication Maximize fabrication productivity

Resources Required:

3D model manipulation Fabrication equipment Fabrication methods

Team Competencies Required:

Ability to manipulate, navigate and review a 3D model Ability to manufacture building components using digital information Ability to understand typical fabrication methods Selected Resources:

Rundell, Rick. “BIM and Digital Fabrication (1-2-3 Revit Tutorial).” http://www.cadalyst.com/aec/bim-and-digital-fabrication-1-2-3-revit-tutorial-3707. 8 February 2008.

3D Control and Planning (Digital Layout) Description:

A process that utilizes a model to lay out the building assemblies and produce lift drawings. Lift drawings are 2D/3D component drawings used by foremen during on-site construction.

Potential Value:

Decrease layout error by producing control directly from the 3D construction model Increase communication between office and field personal Decrease/eliminate language barriers

Resources Required:

3D model manipulation

Team Competencies Required:

Ability to manipulate, navigate and review a 3D model Ability to understand and interpret lift drawings Selected Resources:

http://www.construction-planning-and-control.com/

3D Coordination Description:

A process in which clash detection software is used during the coordination process to determine field conflicts by comparing 3D models of building systems. The goal of clash detection is to eliminate the major system conflicts prior to installation.

Potential Value:

Coordinate building project through a model Reduce and eliminate field conflicts, thus reducing requests for information (RFIs) significantly compared to other methods Visualize construction Increase productivity Reduced construction cost for potentially less-cost growth (i.e. fewer change orders) Decrease construction time Increase productivity on site More accurate as built drawings

Resources Required:

3D model manipulation Model review application

Team Competencies Required:

Ability to deal with people and project challenges Ability to manipulate, navigate and review a 3D model Knowledge of BIM model applications for facility updates Knowledge of building systems

Selected References:

Staub-French S and Khanzode A (2007) **3D and 4D Modeling for design and construction coordination:

issues and lessons learned** ITcon Vol. 12, pg. 381-407, http://www.itcon.org/2007/26 Khanzode A, Fischer M, Reed D (2008) **Benefits and lessons learned of implementing building virtual design and construction (VDC) technologies for coordination of mechanical, electrical, and plumbing (MEP) systems on a large healthcare project**, ITcon Vol. 13, Special Issue Case studies of BIM use , pg. 324-342, http://www.itcon.org/2008/22 AECbytes.com – venderhub

Design Authoring Description:

A process in which 3D software is used to develop a BIM based on criteria that is important to the translation of the building’s design. Two groups of applications are at the core of BIM-based design process: design authoring tools and audit and analysis tools.

Authoring tools create models while audit and analysis tools study or add to the richness of information in a model. Most of audit and analysis tools can be used for design review and engineering analysis BIM uses.

Design authoring tools are a first step towards BIM; a key step is connecting the 3D model with a powerful database of properties, quantities, means and methods, costs, and schedules.

Potential Value:

Transparency of design for all stakeholders Better control and quality control of design, cost and schedule Powerful design visualization True collaboration between project stakeholders and BIM users Improved quality control and assurance

Resources Required:

3D model manipulation

Team Competencies Required:

Ability to manipulate, navigate and review a 3D model Knowledge of construction means and methods Design and construction experience

Selected References:

Tardif, M. (2008). BIM: Reaching Forward, Reaching Back. AIArchitect This Week. Face of the AIA.

AIArchitect

Engineering Analysis (Structural, Lighting, Energy, Mechanical, Other) Description:

A process in which intelligent modeling software uses the BIM model to determine the most effective engineering method based on design specifications. Development of this information is the basis for what will be passed on to the owner and/or operator for use in the building's systems (i.e. energy analysis, structural analysis, emergency evacuation planning, etc.). These analysis tools and performance simulations can significantly improve the design of the facility and its energy consumption during its lifecycle.

Potential Value:

Automating analysis and saving time and cost Analysis tools are less costly than BIM authoring tools, easier to learn and implement, and less disruptive to established workflows Improve specialized expertise and services offered by the design firm Achieve optimum, energy-efficient design solution by applying various rigorous analyses Faster return on investment with applying audit and analysis tools for engineering analyses Improve the quality and reduce the cycle time of the design analyses

Resources Required:

3D model manipulation Engineering analysis tools and software

Team Competencies Required:

Ability to manipulate, navigate and review a 3D model Ability to assess a model through engineering analysis tools Knowledge of construction means and methods Design and construction experience

Selected References:

Malin, N. (2008). BIM Companies Acquiring Energy Modeling Capabilities.

http://greensource.construction.com/news/080403BIMModeling.asp Marsh, A. (2006). Ecotect as a Teaching Tool. http://naturalfrequency.com/articles/ecotectasteacher Marsh, A. (2006). Building Analysis: Work Smart, Not Hard. http://naturalfrequency.com/articles/smartmodelling Novitzki, B. (2008). Energy Modeling for Sustainability.

http://continuingeducation.construction.com/article.php?L=5&C=399 Stumpf, A., Brucker, B. (2008). BIM Enables Early Design Energy Analysis.

http://www.cecer.army.mil/td/tips/docs/BIM-EnergyAnalysis.pdf PIER Building Program (2008). Estimating Energy Use Early and Often.

www.esource.com/esource/getpub/public/pdf/cec/CEC-TB-13_EstEnergyUse.pdf Ecotect - Building Analysis for Designers. http://www.cabs-cad.com/ecotect.htm Khemlani (2007). AECbytes: Building the Future (October 18, 2007).

Sustainability (LEED®) Evaluation Description:

A process in which a project is evaluated based on LEED® or other sustainable criteria. This can refer to materials, performance or a process. Sustainability evaluations can be applied across all four phases of a construction project: planning, design, construction and operation. Sustainability evaluation is most effective when it is done in planning and design stages and then applied in the construction and operations phases.

Model all sustainable aspects of a project throughout its lifecycle to obtain the desired LEED certification in the most efficient manner by condensing design analyses into a single database.

Potential Value:

Accelerate design review and LEED certification process with efficient use of a single database with all the sustainable features present and archived Improved communication between project participants to achieve LEED certification and decreased redesign efforts as a result Align scheduling and material quantities tracking for more efficient material use and better cash flow analysis Optimize building performance by tracking energy use, indoor air quality and space planning for the adherence to LEED standards leading to integrated facility management

Resources Required:

3D model manipulation LEED certification knowledge

Team Competencies Required:

Ability to manipulate, navigate, and review a 3D model Knowledge of current LEED certification information Selected Resources:

Building Information Modeling for Sustainable Design: http://goliath.ecnext.com/coms2/gi_0199- 7985352/Building-information-modeling-for-sustainable.html Sustainable Perspectives: Building Information Modeling for Sustainable Design:

http://www.edcmag.com/Articles/Featured_Special_Sections/BNP_GUID_9-5-2006_A_10000000000000214529 Building Information for Sustainable Design (Revit White Paper) Building Information Modeling and the Adoption of Green Technologies:

http://www.triplepundit.com/2008/05/building-information-modeling-and-the-adoption-of-green-technologies/ Krygiel, E., and Brad N. (2008). Green BIM: Successful Sustainable Design with Building Information Modeling. San Francisco: Sybex, 2008.

Design Reviews Description:

A process in which a 3D model is used to showcase the design to the stakeholders and evaluate meeting program and set criteria, such as layout, sightlines, lighting, security, ergonomics, acoustics, textures and colors. Virtual mock-ups can be done in high detail even on building components like façades to quickly analyze design alternatives and solve design and constructability issues. If properly executed, these reviews can resolve design issues with different options to cut costs and time investments. Modifications can also be made after reviews and final demolition and removal expenses are calculated.

Evaluation of the designed space can be facilitated by a high degree of interactivity to get positive feedback from end users and owners. Some of the top evaluation criteria are sightlines, lighting, ADA compliance, safety, security, acoustics, HVAC, ergonomics, aesthetics and millwork tolerances. Real-time modifications of design are enabled based on end user feedback. Therefore, decision-making time is cut in half since the attention focus is on one issue at a time until consensus is reached.

Potential Value:

Eliminate costly and timely traditional construction mock-ups Different design options and alternatives are easy to model and change in real-time during design review with end users and/or owners Create shorter and more efficient design reviews Resolve the conflicts that would arise in a mock-up and model the potential fixes in real-time along with revised tolerances and answered RFIs Preview space aesthetics and layout during design review in a virtual environment Evaluate effectiveness of design in meeting building program criteria and owner needs Create efficiencies in design process Easily communicate the design to the owner, construction team and end users. Get instant feedback on meeting program requirements, owner needs and building or space aesthetics

Resources Required:

3D model manipulation Design review software Interactive review space

Team Competencies Required:

Ability to manipulate, navigate and review a 3D model Ability to model photos realistically, to include textures, colors and finishes, and make easily navigable with different software or plug-ins

Selected Resources:

Dunston, Phillip S., Arns, Laura L., and McGlothin, James D. (2007). "An Immersive Virtual Reality Mock-up for Design Review of Hospital Patient Rooms," 7th International Conference on Construction Applications of Virtual Reality, University Park, Pennsylvania, October 22-23, 9 pages Majumdar, Tulika, Fischer, Martin A., and Schwegler, Benedict R. (2006). "Conceptual Design Review with a Virtual Reality Mock-Up Model," Building on IT: Joint International Conference on Computing and Decision Making in Civil and Building Engineering, Hugues Rivard, Edmond Miresco, and Hani Melham, editors, Montreal, Canada, June 14-16, 2902- 2911.

Maldovan, Kurt D., Messner, John I., and Faddoul, Mera (2006). "Framework for Reviewing Mockups in an Immersive Environment," CONVR 2006: 6th International Conference on Construction Applications of Virtual Reality, R. Raymond Issa, editor, Orlando, Florida, August 3-4, on CD, 6 pages

Programming Description:

A process in which a spatial program is used to efficiently and accurately assess design performance in regard to spatial requirements. The developed BIM model allows the project team to analyze space and understand the complexity of space standards and regulations. Critical decisions are made in this phase of design and bring the most value to the project when needs and options are discussed with the client and the best approach is analyzed.

Potential Value:

Efficient and accurate assessment of design performance in regard to spatial requirements by the owner

Resources Required:

Design authoring software

Team Competencies Required:

Ability to manipulate, navigate and review a 3D model

Selected Resources:

GSA BIM Guide

Programming: Using a spatial program to efficiently and accurately assess a design’s performance and effectiveness relative to the spatial requirements

Site Analysis Description:

A process in which BIM/GIS tools are used to evaluate properties in a given area to determine the most optimal site location for a future project. The site data collected is used to first select the site and then position the building based on other criteria.

Potential Value:

Use calculated decision making to determine if potential sites meet the required criteria according to project requirements, technical factors and financial factors Decrease costs of utility demand and demolition Increase energy efficiency Minimize risk of hazardous material Maximize return on investment

Resources Required:

GIS software 3D model manipulation

Team Competencies Required:

Ability to manipulate, navigate and review a 3D model Knowledge and understanding of local authority’s system (GIS, database information)

Selected Resources:

The Site Selection Guide. US General Services Administration (GSA) Public Building Service.

Optimal Site Selection for Military Land Management, R.M. Wallace, ASCE Conf. Proc. 138, 159 (2004). DOI: 10.

1061/40737(2004)159.

Farnsworth, Stephen J. “Site Selection Perspective.” Prospecting Sites. June 1995, 29-31.

WPBG Sustainable Committee. Optimizing Site Potential.

Suermann P.C. Leveraging GIS Tools in Defense and Response at the U.S. Air Force Academy. ASCE Conf. Proc.

179, 82 (2005) DOI: 10. 1061/40794(179)82.

GIS – Based Engineering Management Service Functions: Taking GIS Beyond Mapping for Municipal Governments.

Phase Planning (4D Modeling) Description:

A process in which a 4D model (3D models with the added dimension of time) is utilized to effectively plan the phased occupancy in a renovation, retrofit or addition, or to show the construction sequence and space requirements of a building site. 4D modeling is a powerful visualization and communication tool that can give a project team, including the owner, a better understanding of project milestones and construction plans.

Potential Value:

Better understanding of the phasing schedule by the owner and project participants and showing the critical path of the project Dynamic phasing plans of occupancy offering multiple options and solutions to space conflicts Integrate planning of human, equipment and material resources with the BIM model to better schedule and cost estimate the project Space and workspace conflicts identified and resolved ahead of the construction process Marketing purposes and publicity Identification of schedule, sequencing or phasing issues More readily constructible, operable and maintainable project Monitor procurement status of project materials Increased productivity and decreased waste on job sites Conveying the spatial complexities and planning information of the project and supporting conducting additional analyses

Resources Required:

3D model manipulation Scheduling software 4D modeling software

Team Competencies Required:

Knowledge of construction scheduling and general construction process. A 4D model is connected to a schedule, and therefore, is only as good as the schedule to which it is linked.

Ability to manipulate, navigate and review a 3D model.

Knowledge of 4D software: import geometry, manage links to schedules, produce and control animations, etc.

Selected Resources:

Dawood, N., and Mallasi, Z. (2006). Construction Workplace Planning: Assignment and Analysis Utilizing 4D Visualization Technologies. Computer-aided Civil and Infrastructure Engineering, Pgs. 498-513.

Jongeling, R., Kim, J., Fischer, M., Morgeous, C., and Olofsson, T. (2008). Quantitative analysis of workflow, temporary structure usage, and productivity using 4D models. Automation in Construction, Pgs. 780-791.

Kang, J. H., Anderson, S. D., and Clayton, M. J. (2007). Empirical Study on the Merit of Web-based 4D Visualization in Collaborative Construction Planning and Scheduling. Journal of Construction Engineering and Management, Pgs.

447-461.

Cost Estimating Description:

A process in which a BIM model can be used to generate an accurate quantity take-off and cost estimate early in the design process and provide cost effects of additions and modifications with potential to save time and money and avoid budget overruns. This process also allows designers to see the cost effects of their changes in a timely manner to help curb excessive budget overruns due to project modifications.

Potential Value:

Precisely estimate material quantities and generate quick revisions Stay within budget constraints with frequent preliminary cost estimates while the design progresses Better visual representation of project and construction elements that need to be estimated, taken off and priced Provide cost information to the owner during the early-decision making phase of design Focus on more value-adding activities in estimating, such as identifying construction assemblies, generating pricing and factoring risks, which are essential for high-quality estimates Exploring different design options and concepts within the owner’s budget Saving estimator time and allowing them to focus on more important issues in an estimate since take-offs can be automatically provided Quickly determine costs of specific objects

Resources Required:

Model-based estimating software Design authoring software Cost data

Team Competencies Required:

Ability to define specific design modeling procedures which yield accurate quantity take-off information Ability to identify quantities for the appropriate estimating level (e.g. ROM, SF, etc.) upfront

Selected Resources:

Lee, H., Lee, Kim, J. (2008). A cost-based interior design decision support system for large-scale housing projects, ITcon Vol. 13, Pg. 20-38, http://www.itcon.org/2008/2

Autodesk Revit. "BIM and Cost Estimating.” Press release. Jan. 2007. Autodesk. 11 Sept. 2008.

http://images.autodesk.com/adsk/files/bim_cost_estimating_jan07_1_.pdf Dean, R. P., and McClendon, S. (2007). "Specifying and Cost Estimating with BIM.” ARCHI TECH. Apr. 2007. ARCHI TECH. 13 Sept. 2008. http://www.architechmag.com/articles/detail.aspx?contentid=3624.

Khemlani, L. (2006). "Visual Estimating: Extending BIM to Construction.” AEC Bytes. 21 Mar. 2006. 13 Sept. 2008.

http://www.aecbytes.com/buildingthefuture/2006/visualestimating.html Buckley, B. (2008). "BIM Cost Management.” California Construction. June 2008. 13 Sept. 2008.

Manning, R.; Messner, J. (2008). Case studies in BIM implementation for programming of healthcare facilities, ITcon Vol. 13, Special Issue Case studies of BIM use, Pg. 246-257, http://www.itcon.org/2008/18

Existing Conditions Modeling

A process in which a project team develops a 3D model of the existing conditions for a site, facilities on a site, or a specific area within a facility. This model can be developed in multiple ways depending on what is desired and what is most efficient. Once the model is constructed, it can be queried for information, whether it is for new construction or a modernization project.

Potential Value:

Document existing building for historical use Provide documentation of environment for future uses Enhance efficiency and accuracy of existing conditions documentation Provide location information Aids in future modeling and 3D design coordination Use for visualization purposes

Resources Required:

3D model manipulation 3D laser scanning 3D laser scanning point cloud translation into objects

Team Competencies Required:

Ability to manipulate, navigate and review a 3D model Knowledge of BIM authoring tools Knowledge of 3D laser scanning tools

Selected Resources:

GSA BIM Guide Series 3. 3D Laser Scanning.

7 Project Deliverables

Submittal Phase Due Date Format Notes

PDF 30% Design PDF

Clash Detection Model

60% Design Revit / Navisworks

Model Construction Revit 2014

Record Model Close Out Revit 2014

8 Collaboration Procedures

Meeting Procedures A list of meetings to be held to maintain the schedule should be issued early in the project. A summary, or meeting minutes should be attached to this document after each meeting.

Meeting Type Date Meeting Minutes Completed

Project Planning Meeting BIM Manager to complete meeting summary and attach to this document.

BIM Requirements Kick‐Off

Model Coordination

Model Coordination

Electronic Communication This table will be customized based on how the project is managed i.e. FTP Site, B360, Local Network, or VDI.

File Location File Type File Maintainer Updated

Internal Folder John Doe Daily

FTP site Folder John Doe Weekly

A360 File Share Cloud Collaboration

John Doe Continuously

9 Quality Control Checklist

Checks Definition Responsible Party

Check Date

Report Attached

Visual Check Ensure there are no unintended model components and the design intent has been followed.

BIM Manager This date is to be identified in the planning stages Xx/xx/xx

The reviewer will be required to submit a report to the BIM

Manager to be attached to this document.

Interference Check

Detect problems in the model where two building components are clashing.

Standards Check Ensure that the BIM and MARTA Design Criteria have been followed (fonts, dimensions, line styles)

Close Out Documents

Ensure all procedures and documentation required for proper close out of a project are complied with.