2-2. REQUIRED Attachment A-Price Schedule - Hopkins RICE Emissions Control Catalyst MRM.docx
DOCX document 22 KB Posted
- Attached to
- Hopkins Rice SCR Catalyst Replacement
- Solicitation number
- IFB-026-26-RM
- Issued by
- Leon County, Florida
About this file
This is a required price schedule attachment for a City of Tallahassee, Florida procurement for Hopkins Rice SCR Catalyst Replacement. The city seeks replacement emissions control catalysts for seven Wartsila engines (five 50SG engines and two 34SG engines) currently operating within the city's facilities. The three catalyst types required are SCR catalysts (HUG RFV 1300.103.C5.00.S150.450.000 or equivalent) for nitrogen oxide reduction, ROM catalysts (HUG ROM 1300.103.C3.D1.S150.045.255 or equivalent) for nitrogen oxide reduction with ammonia suppression, and OXI catalysts (HUG OCT 1500.141.A7.00.S150.150.000 or equivalent) for CO, VOCs, and formaldehyde oxidation. The Hopkins Catalyst scope includes three items for EM400 housing (two SCR, one ROM, and one OXI layer), while the Sub12 Catalyst scope covers three items for EM196 housing with the same catalyst types. Bid evaluation will be based on the total price for two units of item one, one unit of item two, and one unit of item three, while items four through six will not be scored during evaluation but will be incorporated into the final contract.
All prices must be submitted as firm-fixed prices inclusive of materials, supplies, equipment, transportation, handling, assessments, fees, and applicable Florida Sales Tax unless listed separately. Delivery terms are F.O.B. Destination with all freight and handling costs included in the unit price unless specified otherwise. Each line item includes sealing material as a lump sum covering all materials required for catalyst installation and shipping costs encompassing packing materials and delivery. Bidders must certify independent price determination and may submit additional rate sheets for items beyond those specified, though such supplemental items will not be scored but may be considered for contract incorporation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 10-10. REQUIRED Representations Certifications.docx | DOCX document | |
| 6-6. REQUIRED Certification of a Drug Free Workplace (1).pdf | ||
| 9-9. REQUIRED Local Vendor Affidavit.docx | DOCX document | |
| 8-8. REQUIRED Vendor Conflict of Interest.docx | DOCX document | |
| 4-4. Attachment B-Sample Contract - Hopkins RICE Emissions Control Catalyst.docx | DOCX document | |
| 5-5.REQUIRED HUMAN TRAFFICKING AFFIDAVIT.pdf | ||
| 11-11. REQUIRED Responsible Vendor Review Form.docx | DOCX document | |
| 1-1. IFB 026-26-RM SEC 123 updated 2025-07-02 JHupdates.docx | DOCX document | |
| 3-3. Attachment C-Drawings.docx | DOCX document | |
| 7-7. REQUIRED Non Collusion Affidavit of Respondent.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUIRD PRICE SCHEDULE ATTACHMENT A UPLOAD ON BONFIRE
(This page must be submitted with the bid and shall become an integral part of the contract.)
Bidder Name:
THE CONTRACTOR AGREES --
To furnish the supplies and/or services, awarded in whole or in part by the City, at the price set for each item offered by the Contractor, in accordance with the terms and conditions of the contract.
PRICE RELATED FACTORS
1. The price set for each item is a "firm-fixed" price, and inclusive of all materials, supplies, equipment, transportation, handling, assessments, fees, and taxes, unless any of these factors are listed below as a separate line item.
2. Delivery shall be "F.O.B. Destination". Unless freight/handling fees are listed below as a separate line item, the price set for each item shall include all freight/handling fees, and
3. The Contractor is not exempt from the Florida Sales Tax on materials or services.
CERTIFICATION OF INDEPENDENT PRICE DETERMINATION
The Bidder certifies that—
1. The prices set forth in the price schedule have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other bidder or competitor.
2. The prices set forth in the price schedule will not be knowingly disclosed by the bidder, directly or indirectly, to any other Contractor or competitor before response opening.
3. No attempts have been made by the bidder to induce any other concern to submit or not to submit a response for the purpose of restricting competition.
4. Bidders must submit responses based on the bidding requirements/specifications in this solicitation. Unless specifically requested in this solicitation, alternate or optional responses will not be considered for award and may render the entire submitted response as non-responsive.
5. Bid evaluations will be based on the total price for two of item #1, one of item #2, and one of item #3. The prices of items 4, 5, and 6 will not be considered during the bid evaluation, but will be incorporated into the contract.
Hopkins Catalyst (EM400 Housing)
| Item |
| Catalyst |
| Material |
| Quantity |
| Unit Price |
| 1 |
| One layer of SCR |
HUG RFV 1300.103.C5.00.S150.450.000
or equivalent
| Catalyst |
| 410 |
| Sealing MaterialNote 1 |
| 1 |
| ShippingNote 2 |
| 1 |
| 2 |
| One layer of ROM |
HUG ROM 1300.103.C3.D1.S150.045.255
or equivalent
| Catalyst |
| 410 |
| Sealing MaterialNote 1 |
| 1 |
| ShippingNote 2 |
| 1 |
| 3 |
| One layer of OXI |
HUG OCT 1500.141.A7.00.S150.150.000
or equivalent
| Catalyst |
| 410 |
| Sealing MaterialNote 1 |
| 1 |
| ShippingNote 2 |
| 1 |
Sub12 Catalyst (EM196 Housing)
| Item |
| Catalyst |
| Material |
| Quantity |
| Unit Price |
| 4 |
| One layer of SCR |
HUG RFV 1300.103.C5.00.S150.450.000
or equivalent
| Catalyst |
| 200 |
| Sealing MaterialNote 1 |
| 1 |
| ShippingNote 2 |
| 1 |
| 5 |
| One layer of ROM |
HUG ROM 1300.103.C3.D1.S150.045.255
or equivalent
| Catalyst |
| 200 |
| Sealing MaterialNote 1 |
| 1 |
| ShippingNote 2 |
| 1 |
| 6 |
| One layer of OXI |
HUG OCT 1500.141.A7.00.S150.150.000
or equivalent
| Catalyst |
| 200 |
| Sealing MaterialNote 1 |
| 1 |
| ShippingNote 2 |
| 1 |
Note 1: Sealing material is a lump sum that shall include all sealing material required to install one layer of catalyst. This includes module sealing material and door sealing material.
Note 2: Shipping costs shall include the cost to ship, and any packing materials required for shipment.
*Bidders are welcome to submit a rate sheet for any additional items they wish to include. The rate sheet will not be scored, but it may be considered for incorporation into the contract.
Name of Company Representative
Signature of Company Representative
File details come from the government source that posted it. Updated .