This is a Bid Schedule file related to an Invitation for Bid (IFB) issued by the State of Utah Division of Purchasing, with the State of Utah Division of Oil, Gas and Mining serving as the conducting procurement unit. The project involves reclamation construction for the Sowbelly Gulch Project in Carbon County, Utah, which includes closure of one abandoned mine, maintenance of four previously closed abandoned mines, and revegetation of disturbed areas at abandoned coal mines. A mandatory pre-bid meeting and site visit is required at coordinates 39.699968, -110.921501, with vendors expected to visit additional project sites. Work must commence upon receipt of the Notice to Proceed and be completed within 14 calendar days or by August 31, 2026, whichever is earlier, with potential weather-related extensions at the discretion of the owner. The contract is anticipated to result in a single award to the lowest cost responsive and responsible vendor.

The engineers' estimate for this project is $35,000.00, and the vendor must guarantee its pricing through project completion. Contractors are subject to liquidated damages provisions under Article 12 of the contract terms. No specific set-asides, incumbent information, or detailed funding sources are identified in the bid schedule file itself. Vendors are required to submit bids in accordance with the specifications contained in the complete project specifications document (007959_specs_complete).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Summary Bid Schedule

Sowbelly Gulch Maintenance
AMR/007/959Bid No.
Construction Specifications: Chapter 5: Bid Documents
Name of Bidder:
Summary Bid Schedule
Bid ItemLump Sum Amount
MINE CLOSURE CONSTRUCTION SUBTOTAL
(carried over from Detailed Bid Schedule)$0.00
MOBILIZATION/DEMOBILIZATION
INSURANCE
BONDS (see note below)
TOTAL CONTRACT BID PRICE$0.00

Variation in Contract Bond Rate:

TOTAL CONTRACT BID PRICE WRITTEN:

By submitting a bid under this solicitation, I/we acknowledge that I/we have examined the site conditions and have made the measurements and evaluations necessary to plan and bid the WORK.
Summary Bid Schedule Notes:
The total contract bid price entered here MUST match the total bid price entered in the item section on SciQuest. If the amounts are different, the bid price entered in the item section of SciQuest will be considered the correct bid and will be considered the official bid to be evaluated with other bids received.
Award of CONTRACT will be based on the base "Bid Price." Contractors are cautioned to submit accurate unit prices for any variations in quantities. Verified quantities can go either up or down from the original estimated quantities. If a unit price appears high at the time of any change order, the OWNER reserves the right to negotiate that unit price down to a reasonable amount regardless of the unit prices quoted in this section.
The "Variation in Contract Bond Rate" will be used to adjust the Lump Sum Amount for bonds when the CONTRACT amount changes (see Section 0200, Part 5.01.D).

Detailed Bid Schedule

Sowbelly Gulch Maintenance
AMR/007/959Bid No.
Construction Specifications: Chapter 5: Bid Documents
Name of Bidder:0
Detailed Bid Schedule: MINE CLOSURE CONSTRUCTION
BidVariation in
ItemSite ID/Tag NumberEstimatedQuantity
No.(Tag Number)Specified ClosureQuantityBid Price AmountUnit Price
14130909HO011BLOCK WALL MAINTENANCE1 cf/cf
24130909HO016NATIVE STONE WALL8 sf/sf
34130909HO022BACKFILL (MACHINE)41 cy/cy
44130916HO002BLOCK WALL MAINTENANCE6.5 cf/cf
54131002VO002CONCRETE CUSTOM24 cy (foam)/cy
64131002VO002CONCRETE CUSTOM5.5 cy (concrete)/cy
MINE CLOSURE CONSTRUCTION SUBTOTAL$0.00
(carry over to Summary Bid Schedule)
Detailed Bid Schedule Notes:
If a unit price appears to be excessive based on the market, OWNER reserves the right to negotiate that unit price for any change order. Otherwise the unit prices will be as bid.
The "Variation in Quantity Unit Price" on the Bid Schedule will be used for adjustments to the CONTRACT amount where the actual WORK quantity varies by more than 15% from the estimated quantity listed in the Bid Schedule (see Supplemental General Condition No. 26: Variation in Estimated Quantities). The "Variation in Quantity Unit Price" will also be used as the basis for determining costs for tasks not currently specified in the WORK that may be added in the future by change order.
Sites are listed here in the same sequence as they are listed in the Mine Closure Schedule in Appendix A, that is, sorted by tag number.
Revegetation is required at mine closure locations, but is considered incidental to the mine closure task. Costs for revegetation of mine closure locations should be incorporated into the mine closure bid. No separate bidding or payment will be made for mine closure revegetation.

ReadMe

Sowbelly Gulch Maintenance
AMR/007/959

ReadMe/Spreadsheet Metadata/Instructions

File Name:007959_BidSchedule.xlsx
Last Updated:July 1, 2026
Created by:Chris Rohrer, UAMRP

Contact: Morgan Faulkner Abandoned Mine Reclamation Program Utah Division of Oil, Gas & Mining 1594 West North Temple, Suite 1210 P.O. Box 145801 Salt Lake City, UT 84114-5801

(801) 953-2391 mjfaulkner@utah.gov

Content: This spreadsheet lists provides tabular information from the the Bid Schedule of the construction specifications in spreadsheet format for the use and convenience of the bidders. This file allows the user to perform spreadsheet functions such as summing values that cannot be done with the plain text PDF format version of the bid schedule.

Bid No. TBD This file shall be used for the submission of the Detailed Bid Schedule.

This version revised April 5, 2018.

Instructions:Note that this spreadsheet has two worksheet tabs, one with the Detailed Bid Schedule and one with the Summary Bid Schedule.
Enter the intended bid price and unit price information into the cells with red borders on both worksheet tabs.
Cells with black borders have formulas that will calculate subtotals and totals. Do not write in them. They are write-protected (read only), so it should not be possible to overwrite the formulas.
Save and upload the XLSX spreadsheet file as instructed.
Transfer the entries from the Summary Bid Schedule tab of this XLSX spreadsheet file to the corresponding fields on the Summary Bid Schedule of the PDF format version of the Chapter 2 Bid Documents.
It is not necessary to transfer the entries from the Detailed Bid Schedule of this XLSX format spreadsheet to the Detailed Bid Schedule of the PDF format version of the Chapter 2 Bid Documents. The uploaded XLSX spreadsheet file will provide the detailed itemized breakdown of prices.
Complete the other pages of the PDF format version of the Chapter 2 Bid Documents (licensing, subcontractor and supplier lists, required submittals, etc.).
Upload the completed PDF format version of Chapter 2 as instructed.
Both the completed Summary Bid Schedule and the Detailed Bid Schedule, along with the completed PDF format Chapter 2 are required for a complete and responsive bid.
Worksheet Tabs:Summary Bid Schedule= Summary Bid Schedule from Chapter 2
Detailed Bid Schedule= Detailed Bid Schedule from Chapter 2
ReadMe= metadata about the spreadsheet and instructions
Comments:DOGM= Utah Division of Oil, Gas & Mining
AMRP= Utah Abandoned Mine Reclamation Program

Tag Number: The 12-character site ID number is derived from the township, range, and section, the opening type code, and a sequential number. The initial "3" indicates that the township and range are south and west of the SLBM. Thus site 3271314HO002 is the second adit inventoried in T27S R13W Sec 14.

Opening Types:
HO= horizontal opening (adit)
IO= inclined opening
VO= vertical opening (shaft)
HC= horizontal closed (caved or sealed adit)
VC= vertical closed (capped or filled shaft)
HP= horizontal prospect (short adit)
VP= vertical prospect (shallow shaft or pit)
ES= equipment and structures

Closed features (HC, VC, HP, VP) are not considered for closure and do not have inventory data.