J.1.1 SOW and Technical Requirements (V3).pdf

PDF 297 KB Posted

Attached to
Basement Water Leakage Abatement, U. S. Embassy London
Solicitation number
19GE5023Q0090
Issued by

About this file

This statement of work outlines the technical requirements for a water leakage abatement project at the basement level of the U.S. Embassy in London. The contractor will be required to conduct site visits and surveys to identify all locations of water ingress in the CHP plant room, boiler room, and pond equipment room. Repair work will include chemical grout injection at interfaces between walls and slabs, as well as cracks and joints. Where injection is not possible, the contractor must install edge containment channels. The contractor must submit documentation of past similar projects, safety plans, and warrant work for three years. The project is to be completed in three phases with defined deliverables within 90, 475, and 365 calendar days from notice to proceed.

View the file

Other files

File Type Posted
19GE5023Q0090 0002.pdf PDF
J.1.3 Boilers Room.pdf PDF
19GE5023Q0090 Questions and Answers.pdf PDF
J.1.6 Section drawing.pdf PDF
J.1.5 Pond Equipment Room.pdf PDF
J.1.1 SOW and Technical Requirements (revised).pdf PDF
19GE5023Q0090 0001.pdf PDF
J.1.4 CHP Room.pdf PDF
J.1.2 Repair drawings.pdf PDF
19GE5023Q0090.pdf PDF
J.1.1 SOW and Technical Requirements.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

AND

TECHNICAL REQUIREMENTS

FOR

WATER LEAKAGE ABATEMENT IN THE BASEMENT OF THE US EMBASSY, LONDON

United States Embassy at

33 Nine Elms Lane

SW11 7US

London-UK

US EMBASSY, LONDON – FACILITY MANAGEMENT

September 2023 – Rev 3

1. PURPOSE/ PROJECT INFORMATION

The US Embassy, London proposes to employ a specialist Contractor to repair the water ingress into the plant rooms and parking garage at the below grade basement floor of US Embassy, London. The work shall start in the Generators room, Pond Equipment room and Boilers room. If the repair work, that the Contractor has carried out in the aforementioned areas, is satisfactory, the work may be continued in the other areas of the basement as directed by the CO/COR.

The newly constructed U.S. Embassy, London has exhibited water ingress and seepage at various locations of the below ground construction of the building; there is evidence of water ingress to the diaphragm wall and mat slab since construction.

Water leakage into the basement has occurred since construction, primarily at the interface between the diaphragm wall and mat slab, pond wall and basement slab, as well as cracks in the mat slab.

The scope of work is defined by the Statement of Work and drawings. The work on the repair project generally includes the following:

a) Chemical grout injection at the following locations:

• The interface between the diaphragm wall and mat slab.

• The interface between the pond wall and basement floor.

• Cracks and construction joints in the mat slab and basement floor.

• Isolated cracks in the diaphragm wall and other locations with leaks.

b) Cutting and grinding to create water collection channels where conflicts or access constraints preclude grout injection. Forming collection chancels above slab is an option if the slab cutting is not possible.

The Contractor’s proposal shall include, but not be limited to, the following:

• All fees for transport and travel to and from site.

• All office based and site visit costs.

• Time for reviewing all historical information, drawings and data relating to water ingress.

• Any associated costs to conduct and complete the report works.

Upon project award, and subject to sensitivity, additional information may be provided to the Contractor for review, assistance, and understanding of the existing structure. This information will likely include:

• Pertinent drawings of below construction portion of the building

• Investigation of leakage in the basement/parking garage.

If any of the above-mentioned documents are Sensitive but Unclassified (SBU), then the

Contractor may only be able to review the SBU documents in the US Embassy office.

2. GENERAL PROJECT NOTES

2.1 Code Compliance:

All work performed shall be completed in accordance with the current International

Building Code and any other local standards rules and regulations.

2.2 Coordination:

The Contractor shall coordinate work between all trades and bring any conflicts to the

Contracting Officer’s Representative (COR) prior to the work being performed. The

Contractor is responsible for all costs for corrections associated with the Contractor’s failure to properly coordinate the work.

2.3 Familiarity with Conditions:

2.3.1 The Contractor shall visit the site of the proposed work and become fully acquainted with the existing conditions relating to the construction, labor, facilities involved, difficulties, restrictions, and the possible logical extensions of the scope attending the performance of the contract.

2.3.2 The Contractor shall thoroughly examine and become familiar with the requirements of the contract documents.

2.3.3 The Contractor shall in no way be relieved of any obligation under the contract because of the Contractor's failure to receive or examine any required forms and legal documents or visit the site and become fully informed of all conditions and requirements that may in any manner affect the work to be performed.

2.4 Existing Conditions:

2.4.1 Contractor shall field verify all existing dimensions and conditions. Dimensions shown on the plans are approximate, and field measurements and verification will be required to complete the work. Contractor shall obtain all field measurements as necessary to coordinate with and match new construction to existing conditions.

2.4.2 Contractor may need to move the existing equipment to provide the required access to perform the repair works. COR’s approval is required before relocating any equipment. Contractor shall reinstate the equipment to their original status.

The Contractor is responsible for ensuring the provision of all insurance required by local law to cover their employees in the performance of the above requirements.

3 REPAIR METHODS:

3.1 Chemical Injection Grouting.

3.1.1 The repair works shall include surface preparation, supply, and injection of chemical grout into cracks and joints as required to stop the groundwater ingress into the specified rooms.

3.1.2 Removed.

3.1.3 Removed

3.1.4 Previously injected cracks and joints which leak within the specified warranty period are to be re-injected per the terms of the warranty at no additional cost to the US Government.

3.1.5 Should any new water leaks (not to exceed 15% of the previously injected cracks in the specified room) that occur within one year after the completion of the work shall be injected per the specified method at no additional cost to the US

Government.

3.1.6 The warranty period in Section-9 shall commence after the completion of the Final

Work.

3.1.7 Reference Standards: ASTM International. C42/C42M: Standard Test Method of

Obtaining and Testing Drilled Cores and Sawed Beams of Concrete.

3.2 Edge Containment

Where injection repairs cannot be completed, primarily at areas where access is blocked by mechanical equipment, edge containment measures will be necessary. This will include the creation of channels or gutters in the floor slab and directed to the nearest drains.

4 ADMINISTRATIVE REQUIREMENTS:

4.1 Coordinate Work to ensure that adjacent areas are not adversely affected and that fumes due to injection work are not objectionable. Coordinate:

4.1.1 With COR.

4.1.2 With other trades:

• To ensure that Work done by other trades is complete and ready for injection

Work.

• To avoid or minimize Work on, or in immediate vicinity of, injection Work in progress.

4.2 Pre-installation Meeting:

4.2.1 Conduct meeting at Site.

4.2.2 Review requirements for injection Work, including:

• Construction schedule.

• Availability of materials, Injection Subcontractor’s personnel, equipment, and facilities needed to make progress and avoid delays.

• Site use, access, staging, and set-up location limitations.

• Forecast weather conditions.

• Cracks and joints to be injected, and condition of other construction that will affect injection Work.

• Surface preparation and substrate condition and pretreatment

• Injection procedures.

• Testing and inspection requirements.

• Site protection measures.

• Governing regulations.

4.3 Contractor’s Site superintendent, injection-material manufacturer’s technical representative, Injection Subcontractor’s foreman and COR shall attend the pre-installation meeting.

5 SUBMITTALS

5.1 Product Data:

Submit manufacturer’s product data for all products, including but not limited to:

a) Injection-material manufacturer’s literature, including written instructions for evaluating, preparing, and treating substrate; technical data including tested physical and performance properties; and mixing and injection instructions.

b) Include temperature ranges for storage and application of materials, and special cold weather application requirements or limitations.

c) Include recommended site protection measures.

d) Include Safety Data Sheets (SDS) for information only; safety restrictions are sole responsibility of Contractor.

5.2 Certificates:

5.2.1 Signed by injection-material manufacturer, certifying that products furnished comply with requirements and are recommended by manufacturer for uses indicated.

5.2.2 Signed by injection-material manufacturer, certifying that Subcontractor is approved to install its products.

5.3 Injection Subcontractor Qualifications:

Evidence that Subcontractor’s existing company has minimum five years of continuous experience in injection of specified materials; list of at least five representatives, successfully completed projects of similar scope and size, including:

a) Project name.

b) Owner’s name.

c) Project manger’s name, address, and telephone number.

d) Description of work.

e) Injection materials used.

f) Equipment used.

g) Project supervisor.

h) Total cost of injection work and total cost of project.

i) Completion date.

6 QUALITY ASSURANCE

6.1 Injection Subcontractor Qualifications: Experienced firm that is approved, authorized, or licensed by injection-material manufacturer to inject specified material and that is eligible to receive injection-material manufacturer’s warranty. Must have successful installations of specified materials in local area in use for minimum of five years.

6.2 The contractor shall employ a foreman who is trained and certified by the injection-material manufacturer and who has a minimum of five years of experience as foreman on similar projects, is fluent in English and to be always on site during the Work. The foremen will not be changed during the Project except for reasons beyond the control of Subcontractor and the Architect/Engineer and COR will be informed in advance of any changes.

6.3 Trial Installation: The contractor shall perform trial installations to demonstrate grouting procedures and quality of grouting.

1. At locations to be selected by COR:

• The contractor shall inject 2m segment of the construction joint between the wall and slab per Detail 1/S3.0. The trial segment is to include a vertical joint between panels.

• The contractor shall inject 2m segment of crack in slab surface per Detail 4/S3.0.

2. The COR will observe grouting procedure and completed installation. COR to be notified seven days in advance of performing trial installation.

3. If the COR determines trial installation does not comply with requirements, the contractor shall modify mockup, or construct new mockup as required until mockup is approved.

4. Approved trial installation will be standard for judging completed Work.

5. Approved trial installation may become part of completed Work if undisturbed at time of Substantial Completion.

6. The approved working foreman shall not be removed from the project without prior approval from COR. If removal is for acceptable cause, Contractor shall submit justification in writing within 48 hours prior to the removal. A new foreman will be onsite prior to removal of existing foreman to ensure work will not cease.

7. Work is to be installed by skilled workers who have a minimum of three years of experience performing said work of similar scope and detail. Provide documentation of past experience acceptable to the COR.

8. Work is to be done in accordance with contract documents and drawings. Deviation from such will be at the discretion of the COR and will be authorized in writing only.

9. Exercise caution in performing the work so as not to damage adjacent structures, utilities, and areas not in the scope of work. Be responsible to protect the adjacent structures, utilities, and site work from damage due to work or excavation and equipment.

10. If adjacent elements are damaged during the execution of the work, replace or repair the damaged item(s) to original condition at no additional cost to the US Embassy.

7 DELIVERY, STORAGE, AND HANDLING

The contractor shall:

7.1 Deliver, store, and handle materials according to manufacturer’s recommendations and in such a manner as to prevent damage to materials or structure.

7.2 Deliver materials to Site in original containers with seals unbroken, labeled with manufacturer’s name; product brand name and type; date of manufacture; lot number; SPI hazardous rating and appropriate warnings for handling; and directions for storing and mixing.

7.3 Keep materials dry and do not allow materials to be exposed to moisture during transportation, storage, handling, or installation. Reject and remove from Site new materials which exhibit evidence of moisture during application or have been exposed to moisture.

7.4 Store materials in original, undamaged containers in clean, dry, protected location on raised.

7.5 The Contractor shall provide platforms with weather-protective coverings, within temperature range required by injection material manufacturer.

7.6 Limit stored materials on structures to safe loading capacity of structure at time materials are stored, to avoid permanent deck deflection.

7.7 Conspicuously mark damaged or opened containers or containers with contaminated materials shall be removed from Site as directed by the COR.

7.8 Remove materials that cannot be applied within stated shelf life from Site and replace with new materials.

8 PROJECT CONDITIONS

8.1 Verify existing dimensions and details prior to start of injection Work. Notify the COR of conditions found to be different than those indicated in the Contract Documents.

The COR will review situation and inform Contractor and Injection Subcontractor of changes.

8.2 Comply with the US Embassy’s limitations and restrictions for Site use and accessibility.

8.3 Exercise care to avoid injecting or otherwise damaging embedded items. Remove and replace or otherwise remedy damage to embedded items, at no additional cost to US

Embassy.

8.4 Environmental Limitations: Install injection material when existing and forecast weather conditions permit material to be installed and cured according to injection-material manufacturer’s written instructions and warranty requirements.

• Do not install when air or substrate temperature is outside limits permitted by injection material manufacturer.

• Verify moisture level in crack is compatible with injection material.

8.5 Handle and install materials in strict accordance with safety requirements required by injection material manufacturer; Safety Data Sheets (SDS); and federal rules and regulations.

8.6 Maintain Safety Data Sheets (SDS) with materials in storage area and available for ready reference on Site.

8.7 Maintain adequate ventilation during preparation and injection Work.

9 WARRANTY

Provide joint and Several Warranty by Manufacturer, Contractor, and Injection

Subcontractor:

9.1 Written warranty, signed by injection-material manufacturer, Contractor, and Injection

Subcontractor, including:

9.1.1 Additional injection of previously injected cracks and joints that do not comply with requirements; that do not remain watertight; that fail in adhesion, cohesion, or general durability; or that deteriorate in manner not clearly specified by submitted injection material manufacturer’s data as inherent quality of material for application indicated. Warranty does not include deterioration or failure of injection material due to failure of substrate prepared according to requirements.

9.1.2 Labor and materials to perform warranty work.

9.2 Warranty Period: 3 years from date of Substantial Completion.

10. MATERIALS

10.1 Source Limitations: The contractor shall obtain injection materials through one source from single manufacturer, or from sources approved by manufacturer of injection material, as follows:

10.2 Chemical Grout: Use one of the following or approved technical equivalent:

10.2.1 DE NEEF Flex LV PURe, manufactured by GCP Applied Technologies

10.2.2 Sika Injection-201 CE, manufactured by Sika Limited.

10.3 Auxiliary Materials:

10.3.1 Surface Sealer: Chemical Grout Manufacturer’s approved hydraulic cement or polymer surface sealer, used as required to control chemical grout and ensure filling of joint or crack.

10.3.2 Injection ports and packers as recommended by manufacturer.

10.3.3 Repair mortar for injection holes: Sika MonoTop-115GP, manufactured by Sika

Limited, or approved technical equivalent.

11. EXECUTION

11.1 EXAMINATION

The contractor shall examine substrates and conditions with representative of injection-material manufacturer for compliance with requirements and for other conditions affecting installation or performance of injection Work.

a) The contractor shall verify that areas and conditions under which injection Work are to be performed permit proper and timely completion of the Work.

b) The contractor shall notify COR in writing of conditions which may adversely affect installation or performance of injection Work and recommend corrections.

c) The contractor shall Do not proceed with injection Work until adverse conditions have been corrected, reviewed, and approved by COR.

d) The contractor’s commencement of injection Work constitutes acceptance of Work surfaces and conditions.

11.2 PROTECTION

a) Take precautions to ensure the safety of people, including building users, passers-by, and workers, and animals, and protection of property, including adjacent building elements, landscaping, and motor vehicles.

b) Prevent construction materials from meeting pedestrians, motor vehicles, landscaping, buildings, and other surfaces that could be harmed by such contact.

c) Protect paving and sidewalks, and adjacent building areas from mechanical damage due to scaffolding and other equipment.

d) Limit access to Work areas using barricades.

e) Assume responsibility for injury to persons or damage to property due to the Work, and remedy at no cost to US Government.

11.3 PRESSURE INJECTION EQUIPMENT

The contractor shall ensure:

Injection equipment shall be capable of continuously metering, mixing, and pumping injection material under pressure through crack injection ports; equipment shall be approved by injection material manufacturer.

a) Volumetric metering shall continuously dispense components in proportions specified by injection-material manufacturer, within tolerance of plus or minus 5 percent.

b) Delivery shall be at constant, preset pressure recommended by injection-material manufacturer. Pressure loss in either line in 3 minutes, when stalled at 80 percent or high of maximum possible discharge pressure, shall be less than 5 pound per square inch.

c) Pump shall be equipped with automatic shut-off device to prevent injection of unmixed components.

11.4 PREPARATION

a) Inspect concrete surfaces and temporarily mark with chalk or crayon the cracks and joints to be injected. COR may review injection Work prior to start of surface preparation work.

b) Locate embedded items to avoid conflicts or damage from drilling of injection holes.

• Review as-built drawings provided by the US Embassy showing the layout of piping, conduit, or other potential embedded items.

• Non-destructively locate reinforcement and other embedded items and position drilled holes for injection ports to avoid conflicts or damage.

c) Prepare cracks and joints as recommended by injection-material manufacturer.

d) Clean concrete surface along crack or joint to be injected. Surface shall be sufficiently dry and free of dirt, dust, oil, laitance, unsound concrete, and other foreign material which might impede bond of surface seal, if required.

e) Remove mud, laitance, and other loose or porous materials in and along surface of cracks and joints, that could impair bond of surface sealer.

f) Install injection ports or packers to achieve complete filling of crack or joint.

• Number, spacing, and location of injection ports or packers shall be approved by representative of injection-material manufacturer; spacing shall not exceed 600 mm.

• Drill holes for injection ports or packers at 45-degree angle to intersect crack or joint at approximately mid-depth of crack or concrete member, whichever is less.

For concrete members thicker than 300 mm, reduce drill angle to accommodate maximum 1 m-long drill bit.

• Alternate port or packer placement from side to side along length of crack or joint.

• Insert injection ports or packers into holes in such a manner that the crack or joint is not plugged and injection Work is not adversely affected.

g) As required by manufacturer, or to ensure complete joint filling, seal crack and joint surfaces and perimeters of injection ports or packers with ribbon of hydraulic cement or polymer surface sealer.

h) Flush the crack or joint with potable water to remove dirt or foreign objects from crack or joint.

• If necessary, flush cracks and joints with maximum 5 percent solution of muriatic acid to remove excessive lime deposits from efflorescence. Flush crack or joint with potable water to neutralize acid flush.

• In cold weather, use warm water as recommended by chemical grout manufacturer. Do not pump grout into cracks where ice is present.

11.5 GROUTING

a) Perform initial injection Work in the presence of a representative of injection-material manufacturer. At conclusion of initial Site visit, representative shall prepare and furnish a written letter to the COR, stating whether installation was completed in accordance with requirements, or any recommendations for changes to injection procedures. These services shall be provided at no additional cost to

US Embassy.

b) Commence injection only after any required surface sealers have developed sufficient strength to withstand injection pressure without debonding or rupture.

c) Continuously inject material into crack or joint, as recommended by injection-material manufacturer.

1. Use injection pressure of 1.40 to 20 MPa, depending on the crack or joint width, the thickness of the member, and the condition of the substrate.

2. Start injection at lowest packer and continue until injection material emerges from adjacent packer.

3. Remove injection nozzle and cap injection packer immediately after injection material emerges from adjacent packer. Alternately, cap adjacent packer and continue injection until injection material emerges from next higher packer;

alternate procedure may be used if injection pressure does not substantially increase, packer caps remain in place, and no leaks occur.

4. Continue injection process upward from port to port, waiting for emergence of injection material from adjacent packer and capping injection packer, until crack or joint is filled.

5. After injecting three or four packers, re-inject last three or four packers. If port-to-port travel does not occur, stop work and modify injection setup to achieve port to-port travel. Modifications may include resetting injection packers, installing injection packers at closer spacing, or drilling holes which intersect crack or joint at different angle. Modifications shall be approved in advance by representative of injection-material manufacturer and Architect/Engineer.

d) Contractor shall maintain detailed record drawings showing the locations and quantities of injection work performed.

11.6 FIELD QUALITY CONTROL

Sample Injection Material: Obtain one sample of the injection material prior to beginning injection Work each day, representing first 50 feet of injection, and one sample for every

30 feet of injection thereafter.

1. Place injection material in plastic cup or another container. Add small amount of water if necessary.

2. Allow samples to cure.

3. Do not begin injection Work each day until initial sample has satisfactorily cured.

4. Label samples with injection date and location of injected crack or joint represented by sample.

5. Give samples to COR.

11.7 CLEANING

a) Clean surfaces of excess grout, surface sealer, and injection packers.

b) Allow injection material sufficient time to cure before performing cleanup.

c) Clean surfaces by grinding or other means, so that face of repair crack is flush with adjacent surface, with no indentations or protrusions.

d) Patch holes at injection ports using approved repair mortar.

11.8 USE OF PREMISES

a) Prior to commencing work, the contractor shall coordinate hours of work with the

COR to minimize the impact to the building's daily operations.

b) Access to the existing water supply and electrical power will be provided by the US

Embassy. The contractor shall coordinate location and placement of field material storage, dumpsters, and any other facilities required for construction with the COR prior to Construction.

c) Contractor shall protect all existing building surfaces for the duration of the project.

Any damage to the existing structure or building contents that has been determined to be caused by the Contractor, or construction practices that occur following the notice to proceed, shall be corrected to pre-construction condition at no expense to the US Embassy.

d) Contractor shall perform site cleanup on a regular basis and maintain the site in a clean and orderly manner. Areas that are not directly under construction that are used as pathways to transport materials, or to remove trash, are to be always kept clean. This maintenance includes, but not limited to dusting, sweeping, mopping, and picking up trash as required to keep the areas free of waste materials, debris, and rubbish.

e) Contractor shall have limited use of premises for construction operations as indicated on Drawings and by the Contract limits.

f) Contractor shall limit use of premises to the project site and areas indicated by the

COR. Contractor shall not disturb portions of Project site beyond areas in which the

Work is indicated.

g) Contractor shall keep access ways serving the premises clear and available to residents, US Embassy employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

h) The contractor shall coordinate use of premises under direction of the COR. This includes hours of work, special security precautions, and on-site storage of materials and equipment. Limited on-site storage is available at the site and is subject to coordination with and authorization by the COR.

i) The contractor shall assume full responsibility for the protection and safekeeping of products stored on premises, and for their proper use.

j) Contractor is responsible for the cost of restoring all building elements affected by construction to original condition.

12. US EMBASSY OCCUPANCY REQUIREMENTS

a) US Embassy Occupancy: The US Embassy’s employees will continue to use and access the garage and site. The contractor shall perform the Work so as not to interfere with employee’s and the US Embassy’s day-to-day operations. Provide not less than seventy-two (72) hours’ notice to COR of activities that will affect US Embassy’s operations.

b) Existing Utility Interruptions: The contractor shall not interrupt utilities without written authorization from the COR.

13. JOB CONDITIONS

a) Contractor shall confine operations at site to areas permitted by laws, permits, contract, and the US Embassy.

b) Contractor shall confine access during the work at locations designated by the COR.

c) Contractor shall provide Access for the COR for random observation of work in progress.

14. FIELD VERIFICATION

a) Information on existing structures, utilities, and piping shown on the Drawings is taken from the original construction drawings. Verify the locations and elevations of all existing construction within the area of the Work.

b) Verify the accuracy of drawings, dimensions, locations, and site conditions relating to existing or other work. Errors due to failure to verify such information shall be promptly rectified without additional cost to the US Embassy.

15. SITE CLEANUP

a) Execute cleanup to ensure that the buildings, grounds, and adjacent sites are maintained free of waste, debris, and rubbish.

b) Provide a dumpster or other appropriate container for debris, and rubbish, with regularly scheduled pickup as required.

c) Handle materials in a controlled and responsible manner.

16. Unit Price and estimated quantity

16.1 The Contractor shall provide the cost of the repair works for the following rooms

• CHP (Generators) Room.

• Boilers Room.

• Pond Equipment Room

16.2 Removed

16.3 Removed

17. TASKS

17.1 Task 1 – Site visit, verification, surveying, and measurement works:

Contractor shall visit the site and shall accurately document where water is manifesting in the CHP plant room, Boilers room, and the Pond equipment room. The surveying of wall and floor ingress includes the following:

• Identify the locations of the water ingress, where accessible and noticeable.

• Identify the leaking areas that cannot be injected due access restrictions, and if there is a viable way to access them.

• Identify any other associated work required to compete the repair works, for example: removing existing equipment and replacing them in their original place. The Government is responsible for moving the existing equipment, as required and approved by the COR. Any fixed equipment shall remain in place.

• Identify the area that needs to be injected and the areas that needs Edge Containment/collector slot to the nearest drains.

• Verify the estimated quantity of work in section 16.3.

17.2 Task 2 – Commence the Repair Works:

Upon agreement of the Contractor’s finding in Task-1, the Contactor shall commence the repair works as per the SOW and the repair details in attached drawings.

17.3 Task 3 – Closing Report

Contractor shall provide a closing report which summarizes the repairs made and issues encountered. The Contractor shall indicate the location of the repairs on the site plan for records.

18. Schedule of Deliverables:

The contractor shall complete all work within time specified below. The start date of the project shall be agreed with the COR. The work schedule shall be as described in Phase-1 and Phase-2 below. After award the Contractor shall submit a site-specific risk assessment, a method statement and all other documents as required in the contract. After this and if satisfactory, the US Embassy will issue an NTP (Notice to Proceed).

The period of performance from the NTP’s date to the completion date shall be:

18.1 Phase -1: Repair Works

• 90 calendar days after notice to proceed.

18.2 Phase -2: Additional repair works described in section 3.1.5.

• As required within one (1) year after completing the repair works.

• Final work: 475 calendar days after notice to proceed.

19. Administration

The Contractor shall maintain all contact with the US Government through the Contracting

Officer’s Representative (COR).

20. SECURITY REQUIREMENTS

a) The US Department of State operates strict security procedures for entry into its properties. All personnel likely to be involved on site at any time during the contract period shall complete and return the security clearance questionnaire.

b) This form shall be completed and submitted to the Embassy immediately after award along with a photocopy of the employee’s current passport or driver’s license.

c) Depending on the type of works and the period spent on site, the Contractor may be requested to attend a security interview before commencement of works, costs to be deemed by the Contractor.

d) The right is reserved to refuse entry to the building at any time. Any decision on this matter shall be final and conclusive and at no additional cost to the US Embassy.

e) When necessary, Contractor employees shall be escorted by security personnel during the performance of their work.

f) When escorted, a maximum number of 5 Contractor employees are allowed per escort. If the Contractor estimates that more than 5 employees are required or if the work needs to be done simultaneously in separate areas of the building, this needs to be notified to the Embassy at least 7 days in advance, so adequate escort resources can be mobilized.

g) The US Department of State reserves the right to require additional information in certain cases.

h) The Contractor’s employees must work only within areas relevant to the equipment they are responsible to maintain. No Contractor’s personnel shall wander outside these areas without prior approval.

i) The Contractor shall ensure that all doors remain always closed/locked and ensure the rooms are left secure at the end of each working day.

j) Keys shall be signed out by Contractor’s personnel, and it shall be their responsibility that they are returned at the completion of the project. If the keys are lost or mislaid it will be the Contractor’s responsibility to arrange and pay for replacement of all locks and cylinders to ensure the site is always safe and secure.

21. ACCESS AND PARKING

a) The Contractor is responsible for and shall include within their quotation all costs and fees for congestion charges, transportation, deliveries, and parking costs.

b) The Contractor is responsible to provide the COR with operatives’ names, vehicle registration number, make, model and color, a minimum of 24 hours prior to visit.

c) If the Contractor is working within the Chancery, they are advised that a maximum of one parking space is available. However, the Embassy may not be able to provide parking on certain occasions so the Contractor should still therefore allow for parking within their quotation.

22. WORKING HOURS

a) All work shall be completed during normal business hours between 8:00 hours and 17:00 hours Monday to Friday.

b) For emergencies and call outs outside working hours see the specifics requirements section within this scope of work.

c) No planned work shall be carried on local and American holidays unless by prior agreement with the COR and at no additional costs to the US Department of State.

Please refer to the following website for the US Embassy public holidays https://uk.usembassy.gov/holidays/

23. HEALTH AND SAFETY, WELFARE AND ENVIRONMENTAL PROCEDURES

a) All work shall comply with all appropriate and relevant UK Health and Safety law and embracing the following:

• Health and Safety at Work Act 1974

• The Management of Health and Safety at Work Regulations 1999

• The Provision and Use of Work Equipment Regulations 1998 (PUWER)

• The Manual Handling Operations Regulations 1992

• The Workplace (Health and Safety and Welfare) Regulations 1992

• The Personal Protective Equipment at Work Regulations 1992

• The Control of Substances Hazardous to Health Regulations 2002 (COSHH)

• The Construction (Health, Safety & Welfare) Regulations 1996

• The Lifting Operations and Lifting Equipment Regulations 1998 (LOLER)

• The Control of Pollution Act 1974

• The Electricity at Work Regulations 1989

• The Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013(RIDDOR) The Health and Safety (First Aid) Regulations 1981

• The Noise at Work Regulations 2005

• The Health and Safety (Consultation with Employees) Regulations 1996

• The Health and Safety (Safety Signs and Signals) Regulations 1996

• Control of Lead at Work Regulations 2002 (CLAW)

• Control of Asbestos at Work Regulations 2012

• The Special Waste Regulations 1996

• Construction (Design and Management) Regulations 2015.

https://uk.usembassy.gov/holidays/

b) The Contractor shall provide the Contracting Officer Representative (COR) with site-specific work Risk Assessments and Method Statements (RAMS) prior to commencement of work.

c) After surveying the facility and the relevant equipment prior to commencement of the work, the Contractor shall inform the COR of any health and safety concerns or special requirements so their work can be carried out safely.

d) The Contractor must provide all necessary protection to the occupants of the building and public including safety barriers, screens, notices and portable firefighting equipment and any other safety provisions required by the work.

e) The Contractor shall maintain all routes of escape or provide temporary protected routes for public/building occupants. The Contractor shall be responsible for maintaining security/ emergency/fire detection alarm systems which may be affected by the work.

f) If connections to live services in the building demand temporary disconnection or switching off, this must only be carried out by prior arrangement with the COR.

g) A Permit to work system is in place for hot works (including soldering/welding/brazing), electrical isolations and access to LV and HV rooms, Confined Space Access. The Contractor and any sub-Contractors must familiarize themselves with the embassy process of working and request a permit before commencing any of this work.

h) Any welding or work activities of a similar nature must be carried out with proper and suitable protective screening and temporary firefighting equipment placed in or immediately adjacent the working area. COR or Safety Program Coordinator to issue “Permit to Work” prior to starting.

i) The Contractor is to provide the required first aid for their on-site staff.

j) Contractor shall ensure that the staff keep a copy of this Statement of Work and the contract documentation on hand on-site for reference at any time. The daily visitor log and any necessary Health & Safety logs shall be updated regularly as appropriate, ready for inspection at any time by the COR.

k) It is the Contractor’s responsibility to ensure that all their employees are equipped with certified access equipment, and personal protection equipment (PPE) to complete the tasks as requested within this document and provided attachments, and in accordance with the Contractor’s method statements and health & safety plan.

l) The COR shall inform the Contractor of the Embassy Health & Safety procedures to include but not be limited to egress routes, exits and assembly point in the event of an emergency.

m) Restrooms and welfare facilities are available for the use by the Contractor; however, they must be kept clean after use them.

n) All rubbish and superfluous material must be removed at the end of each site visit. The Contractor shall be responsible for the safe and environmentally friendly disposal of all redundant materials, parts, and consumables. Safe disposal records copies shall be provided to the COR after each visit.

o) If the Contractor considers or suspects that the execution of any work will, or is likely to, involve any interference or disturbance to gas piping or storage, pipes conveying steam and or any other hazardous substances or installations, he shall immediately stop work and forthwith notify the COR who will give the Contractor further instructions.

p) It is the responsibility of the Contractor to ensure that all current UK Government

Coronavirus guidelines and recommendations are adhered too, always providing a safe working environment for all employees, sub-Contractors and suppliers that are working or attending the site. The Contractor shall include for all costs associated for following the UK Government Coronavirus guidelines: for example, additional PPE and hand wash/sanitizer. The Contractor shall be responsible for the additional measures from site organization & conditions, starting work and progressing through to project completion/handover.

q) The Contractor shall ensure that their Risk Assessments and Method Statements are continually updated to adhere to the current HSE Coronavirus guidelines and recommendations.

24. STANDARDS OF CONDUCT IN THE PREMISES

a) The Contractor’s employees shall maintain satisfactory standards of competency, conduct and cleanliness when working within US Government properties and boundaries. These standards are especially strict when working within office environments or when working in or accessing adjacent areas.

b) The US Government reserves the right to ask any or all the Contractor’s employees to leave the premises if any employee is deemed disruptive. The Contractor shall immediately replace such an employee to maintain continuity of services at no additional cost for the Government.

c) The Contractor's employees shall wear clean, tidy uniforms and clear means of

Contractor identification when on site.

d) Contractor shall have limited use of premises for construction operations as indicated on Drawings and by the Contract limits.

e) Limit use of premises to the project site and areas indicated by the Owner.

f) Do not disturb portions of Project site beyond areas in which the Work is indicated.

g) Confine construction operations to areas designated on the Drawings and by the

Owner.

h) Keep access ways serving the premises clear and available to residents, Owner, Owner’s employees, and emergency vehicles at all times.

i) Do not use these areas for parking or storage of materials.

j) Coordinate use of premises under direction of the Owner. This includes hours of work, special.

k) security precautions, and on-site storage of materials and equipment. Limited on-site storage is

l) available at the site and is subject to coordination with and authorization by the

Owner.

m) The Contractor’s employees must only smoke in designated outdoor smoking areas.

n) Playing music in any part of the premises or use abusive, foul, or loud language at any time within the US Embassy boundaries is strictly forbidden.

o) Assume full responsibility for the protection and safekeeping of products stored on premises, and for their proper use.

p) The cost of restoring all landscaping, including soft and hard landscape elements, irrigation systems, etc., affected by construction to original condition shall be included in the Base Bid.

25. DEFINITIONS AND ACRONYMS USED

• Contractor: Name used to refer to the organization with whom the US Government wish to enter a contract.

• CO: Contracting Officer. A person in the US DOS with the authority to enter, administer and/or terminate contracts and make related determinations and findings.

• COR: Contracting Officer Representative. A person in the US DOS who is responsible for the technical direction and evaluation of the Contractor performance.

• SOW: Statement of Work

• DOS: Department of State

• US: Unites States of America.

• SBU: Sensitive but Unclassified

END OF STATEMENT OF WORK