This document is a Statement of Work (SOW) for the construction of a dining facility, warehouse, and training sheds at the Zambia Peace Operations Training Center (POTC). The key requirements are:
Task A: Construct a multi-purpose dining facility at the POTC that can accommodate up to 400 soldiers, utilizing solar power, energy efficient materials, and green building techniques. The facility will include a kitchen, offices, storage, and latrines.
Task B (optional): Construct a solar-powered warehouse at the POTC with office space, an armory, and storage areas. The warehouse will feature a solar PV system, translucent roof panels, and energy efficient lighting and HVAC.
Task C (optional): Construct five covered, multi-purpose training sheds at the POTC, each with seating for 140 personnel, a metal roof and support structure, and rain water harvesting capabilities.
The period of performance is 12 months from date of award. Key deliverables include project schedules, progress reports, safety incident reports, as-built drawings, and maintenance manuals. The place of performance is the POTC in Lusaka, Zambia.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 7 - Past Performance Questionnaire (PPQ).docx | DOCX document | |
| Attachment 1 - Zambia POTC Construction SOW 0001 (Clean).pdf | ||
| 19AQMM24R0139 0001.pdf | ||
| 19AQMM24R0139-Zambia Dining Facility and Warehouse - B-M 0001.pdf | ||
| 19AQMM24R0139 Q and A Final.xlsx | XLSX spreadsheet | |
| 24R0139-Zambia Dining Facility and Warehouse-Pre-Proposal Conference.pdf | ||
| Attachment 4 - Appendix 2. Multipurpose Warehouse.pdf | ||
| Attachment 3 - Appendix 1. Dining Facility Drawings.pdf | ||
| Attachment 5 - Appendix 3. Training Shed.pdf | ||
| 19AQMM24R0139.pdf | ||
| 19AQMM24R0139-Zambia Dining Facility and Warehouse - B-M.pdf | ||
| Attachment 1 - Zambia POTC Construction SOW 4 June 2024.pdf | ||
| Attachment 6 - Appendix 4. Project Scheduling.pdf | ||
| Attachment 2 - Bid Chart Zambia Warehouse Dining Sheds.xlsx | XLSX spreadsheet |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Zambia Dining Facility and Warehouse Construction Projects
May 13August 1July 30, 2024June 4, 2024
REVISED, POST SITE SURVEY Q&A
1. GENERAL.
1.1. Background. The Global Peace Operations Initiative (GPOI) is a U.S. Department of State security assistance program focused on building international peacekeeping capacity worldwide in close collaboration with the U.S. Department of Defense (DOD). The GPOI program’s mission is to strengthen the effectiveness of the United Nations (UN) and regional peace operations by enhancing partner countries’ capacities to prepare, deploy, and sustain peacekeepers and reinforcing UN and regional organizations’ performance and accountability frameworks. Department of State’s Bureau of Political Military Affairs, Office of Global Programs and Initiatives, Peace Operations Capacity Building Division (PM/GPI/POCB) serves as the GPOI Program Office.
1.2. GPOI Program Objectives.
▪ Support partner countries’ development of critical mission capabilities.
▪ Enhance partner countries’ peace operations planning, training, and readiness competencies.
▪ Enable partner countries to conduct effective operations and sustainment.
▪ Reinforce UN and regional organizations’ performance and accountability frameworks.
1.3. Project Context. This Statement of Work (SOW) defines requirements for an environmentally friendly dining facility and warehouse construction project that will provide the Zambia Defense Force (ZDF) with operational and sustainable infrastructure to support ZDF peacekeeping training. The green aspect of this facility complies with the Government of Zambia’s (GOZ) desire to reduce its dependence on fossil fuels.
1.4. Project Purpose. The overarching purpose of this project is to build the ZDF’s capacity to prepare, deploy, and sustain effective peacekeeping forces in support of UN and AU mandated tasks. The activities in this SOW shall complement broader GPOI programming efforts and support U.S. Government (USG) peacekeeping policy priorities for Zambia and the region.
2. REQUIREMENTS.
2.1. Summary of Requirements. The Contractor shall: Plan, resource, design, supervise, and facilitate the construction of a dining facility, a multipurpose warehouse and training sheds at Zambia’s Peace Operations Training Center (POTC) in Lusaka, Zambia. These facilities will utilize solar power and energy storage and grid power as backup and use energy efficient materials when possible. The green aspect of these facilities complies with the GOZ’s desire to reduce its dependence on fossil fuels. Additionally, the camp suffers from power outages throughout the day which frequently disrupt training. The ZDF would like to use the national grid for their electrical needs as backup. The Contractor will also provide training on how to operate specialty equipment (Solar panels) and provide a recommended maintenance plan.
2.2 Required Tasks. Required tasks under this SOW are as follows, with additional detail provided under the Scope of Work section below.
REQUIRED TASKS
TASK A. Construct a Dining Facility at Zambia POTC (see APPENDIX 1)
TASK B.
(OPTIONAL)
Construct a Multipurpose Warehouse at Zambia POTC (see APPENDIX 2)
TASK C.
(OPTIONAL)
Construct Training Sheds at Zambia POTC (see APPENDIX 3)
2.2.1. Coordinate with Zambia officials and facilitate the procurement and delivery of equipment and supplies as required to complete all tasks and subtasks.
2.2.2. Minimize the use of wood in all construction projects due to the extreme termite problem.
The use of metal is preferred for the structural component of each building.
2.2.3. Constructed buildings under this task order shall have LED lighting consisting of fixtures with LED lamps that can be locally sourced (as specified by the site design), doors, door hardware, and finishes as indicated in the attached drawings. The building shall comply with the current standards of the country’s building codes and regulations. Exterior Doors shall be made of metal.
2.2.4. Perform the clearing, grubbing, excavation, compacting and removal needed to carry out all works regarding the projects specified. During site preparation storm water during and after construction should be considered. The Contractor shall be responsible for any damage to the site during the execution of these activities. The excavation works shall include minor tools, machinery, dump truck transportation to authorized sites in the region, and labor.
2.2.5. Conduct tasks and subtasks concurrently and coordinate the sequencing of the enhancements with the PTC Commandant or the designated representative.
2.2.6. Utilize green and energy efficient concepts within the designs of the buildings. This should include but not limited to the idea of “cool roof” and “cool wall” as discussed by the Cool Roof Rating Council (CRRC) (https://coolroofs.org/), which looks at two concepts: 1) Solar Reflectance- The fraction of solar energy that is reflected by the roof. 2) Thermal Emittance- The relative ability of the roof surface to radiate heat. In addition to the cool roofs, use passive and low-energy cooling design principles, translucent roof panels and tubular skylights to allow in natural light, the use of energy efficient windows with a low solar heat gain coefficient (SHGC) and/or reflective film, the use of energy efficient lighting, and the application of solar panels for electricity. When possible, the contractor shall propose additional “green” concepts to be used in the designs of the buildings. Cost/benefit and maintenance should be in the forefront of these proposals.
2.2.7. The contractor is responsible for providing all construction water requirements for construction. However, the Contractor may coordinate with the designated representative to manually provide water to the construction site if there is not a reliable source nearby. This water requirement should be included in their technical proposal.
2.2.8. Provide recommended solutions for all tasks and subtasks in their technical proposal.
2.2.9. The Contractor should include all the costs of the materials, labor, transportation, and materials testing that will be needed to complete the project and comply with all the specifications stated in this document.
2.3. GENERAL SPECIFICATIONS. All work shall be carried out in strict compliance with all contract clauses and these technical specifications. In the event the Contractor discovers discrepancies contained in the various design/ technical documents, Contractor must immediately notify the Contracting Officer Representative (COR) before taking any other action.
2.3.1. Quantities. This contract is based on a lump sum priced solicitation. Any quantities indicated in the specifications and drawings are for reference only and the Contractor is responsible for providing quantities needed to complete the work, without any price adjustment after award.
2.3.2 Trials and Tests.
2.3.2.1. Materials, permanent equipment, its accessories and other elements destined to the work, shall be subject to trials and tests necessary to verify their compliance with specifications, properties and characteristics, in accordance with permitted requirements and tolerances, in line with the use for which they have been intended. Materials, equipment, accessories, or elements that have not been accepted by the COR, shall be withdrawn from the work site, or replaced, at the Contractor’s cost.
2.3.2.2. Laboratory tests can be carried out, according to the specific case, at the work site or in laboratories previously authorized by the COR. Materials that bear quality certificates issued by ISO or its equivalent do not need to be routinely tested. Costs of laboratory trials and tests shall be at the Contractor’s expense. The COR shall be able to carry out special trials and tests at any time if it is needed to clarify the quality of any item. The Contractor shall get authorization in advance of laboratory tests to use specific facilities for tests. The COR will also provide the time allowed to provide results of the test(s).
2.3.3 Work Execution.
2.3.3.1. The construction program shall be carried out in a planned and progressive manner.
Activities shall be sequentially planned by the Contractor, and that plan shall be approved by the COR prior to commencement of the project. No work shall be initiated that contradicts the project plan. No work shall be performed that creates a safety hazard or creates unnecessary risk of damage to other work elements. Any change to the work plan must be approved by the
COR.
2.3.3.2. Contractor shall be responsible for maintaining quality of work by following proper operational procedures in construction.
2.3.3.3. Throughout the different stages of construction work the Contractor shall obtain approval from the COR to continue with subsequent stages of construction. Before receiving approval to continue through various stages of work, as directed, samples of completed work shall be tested to verify the quality of the work. The COR will provide guidance regarding the type(s) of samples required for testing.
2.3.3.4. All work shall be detailed with the date of performance and delivery. The Contractor shall submit a baseline schedule for approval by the COR prior to the Notice to Proceed. Progress schedule updates shall be submitted monthly as part of the pay requisition by the contractor to the Government. All schedules will be subjected to review by the COR and by Government technical staff.
2.3.4. Cost Of the Project. The Contractor should include all costs of the materials, labor, transportation, and materials testing that will be needed to complete the project and comply with all the specifications stated in this document.
2.3.5. Industrial Safety, Occupational Health, and Environmental Management.
2.3.5.1. The Contractor shall maintain a safe and healthy work environment during all work shifts in all construction areas and in construction yard in accordance with the appropriate/applicable Zambian safety standards. In addition, the Contractor will observe all current local workforce safety laws and regulations as published by “Ministry of Labor” for the protection of employees and the general public on or in close proximity to the work site who could be affected by the execution of the job directly or indirectly. For any work executed on heights its mandatory to comply with the proper Zambian standard or regulation. All vertical construction platforms and scaffolds shall be constructed and maintained in accordance with OSHA standards with all required kick plates, safety rails and tie off points. All construction personnel working at elevations more than two (2) meters above the floor or ground shall be tied off to structural members and/or to properly anchored and rated safety lines. All solar/electrical equipment shall be locked and tagged in the off position prior to working in potentially energized enclosures and on potentially energized electrical transmission systems.
2.3.5.2. For all confined space entrances installed (e.g., sewer manholes, electrical manholes, etc.) the Contractor shall conduct services in accordance with OSHA 29 CFR Part 1926. The Contractor shall provide training for staff on confined space entrance/exit procedures along with all retrieval, ventilation and personal protective equipment required.
2.3.5.3. Respective to all projects, the Contractor shall adhere to safe environmental protection operations in the performance of this contract. All Contractor and Subcontractor provided vehicles and equipment shall follow the safety requirements and shall be maintained in good working order and shall be used only in those construction activities for which they were designed in accordance with manufacturer recommendations.
2.3.6 Subcontractors.
2.3.6.1. Subcontractors shall be able to demonstrate proper training, experience and knowledge of the proper designs/drawings and building techniques to satisfy the United States Government or its representative. The Contractor is responsible for any substandard or improper construction done by a subcontractor task. It is incumbent on the Contractor to lay out specifications and job site rules and to properly supervise the Subcontractors and to make whatever arrangements for indemnification are suitable between the parties concerning faulty work. The contractor shall provide the following information.
2.3.6.1.1. The Contractor shall provide a list of the names, addresses, and telephone numbers of all Subcontractors and all principal materials suppliers to be used on the project, clearly indicating what portions of the work shall be performed by them shall be included in the technical proposal. This list shall be presented in sufficient detail to indicate which work shall be performed by the Contractor work force and equipment, and the work which shall be performed by subcontractor work force and equipment.
For the Sub-contractors identified, provide documentation that demonstrates their experience relevant to the works planned to be assigned to them under the respective subcontracts.
2.3.6.1.2. In accordance with DOSAR 652.242-73 AUTHORIZATION AND PERFORMANCE (AUG 1999), provide written certification that authorization to operate and do business in the country in which this contract shall be performed has been obtained.
2.3.7 Security.
2.3.7.1. The Contractor shall maintain continuous coordination and constant communication with the COR. The Contractor shall observe all rules and follow all directions given by the end user (Zambia Defense Force) pertaining to security. The Contractor shall protect and retain responsibility for all work, workers, and secure all materials until such work and/or materials have been accepted by the Government and handed over to the end user. Materials and equipment not needed for the current day’s work shall be safely stored in the Contractor's secured construction yard located inside the facility’s secured area. The Contractor shall ensure security and safety is maintained throughout the construction process, and that the end user’s operations continue with as little impact as possible.
2.3.7.2. The Contractor shall provide all required documentation and identification for all personnel, materials, tools, equipment, and vehicles entering or exiting the area to complete all work delineated herein. All construction personnel and vehicles/equipment shall be vetted and approved per the end user’s security requirements prior to entering or exiting the project facilities. All personnel shall wear readily visible identification and clothing that allows them to be readily distinguished as construction personnel. The Contractor shall coordinate with the end user to arrange access to all facilities by construction personnel prior to the construction period.
3 SCOPE OF WORK.
3.1. Task A. Construct Green Multi-Purpose Dining Facility.
3.1.1. The Contractor shall construct a Multi-Purpose Dining Facility at the training center capable of accommodating up to four hundred (400) soldiers at one time with adequate spacing between tables, chairs, offices, along with storage, a kitchen, administrative/office space, commanders mess and latrines (see APPENDIX 1). The construction shall include the use of quality, energy efficient materials that are capable of withstanding a tropical rainy climate.
Construction shall be located on designated Zambian property within the perimeter of the training center. The center of the dining facility shall be located at 15°33’58”S 28°36’59.05”E (see FIGURE 1). The exact location of roads and structures shall be based on the terrain and topographic analysis completed during the design survey.
3.1.2. The Contractor shall design and construct the building in accordance with the layout in APPENDIX 1. The building shall be a single-story structure with removable partitions that allow larger space to be broken into two rooms in the parlor.
3.1.3. Foundation. Building foundation, skirt, and floor will be per specifications described in APPENDIX 1 and the Space Schedule described in FIGURE 2. Foundation depth will be determined during the Site Survey.
3.1.4. Floors. The floors shall be per the Space Schedule described in FIGURE 2. The Contractor shall install a vapor barrier directly below the foundations slab.
3.1.5. Walls. Walls shall be constructed with solid CMU concrete blocks. Those sections designed as load bearing IAW the contractors final design shall be a minimum strength of 13.7 20 MPa (2,0900 PSI) and reinforced with rebar, as necessary. (reinforced with rebar, as necessary) with a minimum strength of 13.7 MPa (2,000 PSI) ). Walls shall otherwise be non-load bearing CMU blocks. and the eExterior shall be plastered, primed and painted with paint that has a high solar reflectance and a high thermal emittance, resulting in a high solar reflectance index (SRI). Interior surfaces shall be plastered, primed and painted with water-based acrylic paint unless other specified.
3.1.6. Latrine walls shall be tiled and sealed up to the ceiling.
3.1.7. Door and Window schedule is described in APPENDIX 1.
3.1.8. Roof Design. The roof shall be corrugated CI galvanized steel sheet metal and pre-painted with a paint that has a high solar reflectance and a high thermal emittance, resulting in a high solar reflectance index (SRI). It is preferred that the contractor use oven-baked factory-applied painted corrugated sheet metal. (Note: an oven-baked factory-applied paint is more durable and efficient than a field-applied paint) This sheet metal should be a minimum thickness of 28 gauge. The roof aslope should be approximately 20 percent. The contractor shall propose a roof support system designed to support a sloped roof and flat interior ceiling over the specified areas. Trusses and purlins shall be steel and welded with minimum strength and dimensions required to support the roof design depicted in APPENDIX 1. Details on truss strength and dimensions shall be included in Contractor’s technical proposal. The roof should also have translucent roof panels in non-drop ceiling areas and a translucent ridge cap to allow natural light into the building. These panels/ridge cap should not be clear but rather colored such as opal white or soft white or, preferably, reflective silver. The necessary number of tubular skylights or similar items shall be placed to illuminate the areas with flat interior ceilings with natural light. Metal rain gutters shall be installed along the long side of the roof with downspouts to channel water way from foundation. Install adequate number of turbine type ventilator in each roof section.
3.1.9. Interior Ceiling. An interior ceiling shall only be placed above the storage room, the administrative/office space, the commanders mess, and the latrines and dining areas (the kitchen area will not have a ceiling). It should be a flat design and constructed to enable interior climate control. Contractor shall proposal a detailed ceiling plan that considers insulation as part of their technical proposal. Ceiling design shall include a proposed rafter screening and ventilation plan to ensure that birds, small critters, and rodents are kept out. The necessary number of tubular skylights or similar items shall be placed to illuminate these specified areas with natural light.Contractor shall provide and connect two industrial ceiling fans throughout the dining hall and two oscillating pedestal fans in the kitchen. See APPENDIX 1.
3.1.10. Doors. The building shall have both center feed and side fee entrances as depicted in APPENDIX 1. Each entrance shall have a large, grated floor mat and well, with the well having a side cleanout just outside the door in order to clean and collect mud prior to entry. Door schedule is described in Attachment 3 - Appendix 1. Dining Facility Drawings page Figure 3.
3.1.11. Septic System. The Contractor shall utilize the existing septic system located in the vicinity of the dining facility and propose a plan to connect the dining facility to the septic system.
Formatted: Font: (Default) +Body (Calibri)
3.1.12. The contractor shall provide three (3) ductless wall mounted heat pump air conditioner with a minimum of 20,000 BTUs each shall be installed throughout the facility as follows:
3.1.12.1. Two (2) in Commanders Mess
3.1.12.2. One (1) in Kitchen Office
3.1.13. Provide dry fire protection throughout the building which includes dry powder extinguishers, CO2 extinguishers, smoke detectors, and a fire alarm. The contractor must ensure that there is adequate space between the smoke detectors and the roof so that they do not get triggered by the heat radiated from the roof.
3.1.14. The Contractor shall provide and install all furniture items specified in ANNEX 1.
However, contractor shall note that Appendix 1 CAD drawing contains an additional detailed list of required equipment organic to the facility (pots, pans, ranges, sinks, etc) and are not included in the equipment list. Both lists of equipment are required.
3.1.15. Connect all waterlines into the facility to the camp water source.
3.1.17. The Contractor shall propose plan to connect dining facility to solar PV system. (details listed in warehouse section)
3.1.18. Provide plumbing pipes and ancillary equipment to support the facility. Interior pipes will be PE or PPRC minimum 7.62cm and exterior piping will be uPVC or PVC minimum 10.16cm.
Separate wastewater lines shall be provided for black (septic tank) and grey wastewater (sanitation field).
3.1.19. The Contractor shall ensure more mature, existing trees throughout the area are retained where possible and incorporated into the overall site plan when possible. Ground vegetation may be removed, as required, to efficiently complete construction and achieve site plan requirements.
3.1.20. Drainage. The Contractor shall ensure the site is well drained with final grading. Existing natural drainage should be incorporated into the overall site plan design when possible. The Contractor shall construct a drainage channel around the entire dining facility building. The channel shall be trapezoidal, with interior channel dimensions measuring approximately 300m at the top and 250mm at the base with depth of no less than 350 mm. Concrete shall be a minimum thickness of 100 mm at all points of the channel. The concrete channel shall be sealed on all surfaces with a high-quality water proofing material to prevent sun and rain deterioration over time. The total length of channel shall be approximately 400m. The channel shall drain to a discreet drywell near the building. Additional drainage fabrication requirements (dry wells, French drains, etc.) shall be assessed during the design survey and as required, incorporated into the final site plan.
3.1.21. Handbook. The Contractor shall provide a final hard copy “Building Maintenance Handbook” in English which includes all technical specifications on equipment warranties, sources of supply, spare parts, equipment operation/maintenance, and tips for partner-nation sustainment of the site over the long term.
3.1.22. Signage. The Contractor shall design and install a prominent entry/identification sign or signs which thoughtfully describes the site’s purpose, pays tribute to the ZDF, and explicitly recognizes the longstanding U.S.-Zambia peacekeeping partnership. The contractor shall work with the ZDF and COR for approval of the final location(s) and designs.
3.1.23. Solar Power. The Contractor shall supply and install solar PV system with power output of approximately 200 kW peak of roof mounted solar, consisting of a minimum of solar panels rated at a range of 400-590325W each, with 4 solar inverters. (SMA STP 50-40). Energy storage should be minimum of 400 kWh of energy storage, consisting of 22 wall mounted battery inverters (SMA SI 8.0) and batteries consisting of 84 Tesvolt lithium batteries, each with a capacity of 4.8 kW. The power solution must include Installing a Solar Panel Distribution Box.
Connect the building’s solar panels/solar array to the solar panel distribution box which will connect to the local grid. Install LED exterior and interior fixtures to provide adequate lighting throughout the facility complete with the necessary switches and provide the required quantity of power outlets. To the extent possible, stored solar power should also support power to the Kitchen equipment. The Contractor shall also provide a 200-kW prime rated generator capable of auto starting and running back-up electricity continuously to the building and the camp in the event no solar or energy storage is available due to power outage, the generator should also have the ability to openly export data. A means to connect it must be included into the design.
3.1.24 Windows. Windows shall be double-walled laminated glass with glazing or reflective film, and an insulated aluminum system to achieve a low solar heat gain coefficient (SHGC). This is a more efficient insulation requirement depicted in Appendix 1, which is provided for illustrative purposes only. There should be wire mesh or bars on the outside for security. Window schedule is described in Appendix 1.
3.2. Task B. Solar Warehouse (OPTIONAL).
3.2.1. The Contractor shall construct a solar warehouse at the KKPTC. Construction shall be located on designated Zambian government property within the perimeter of the KKPTC. The center of the warehouse shall be located at 15°33’59”S 28°35’59”E, on a large parcel of open land (see FIGURE 1).
The exact location of roads and structures shall be based on the terrain and topographic analysis completed during the design survey. Warehouse will be powered by solar panels referenced in the Task A. and intermittently spaced translucent roof panels and tubular skylights to maximize natural light.
3.2.2. The Contractor shall design and construct the building in accordance with the layout in APPENDIX 2. The building shall be a single-story structure with office area, armory and latrines.
3.2.3. Foundation. Building foundation, skirt, and floor will be per specifications described in APPENDIX 2 and the Space Schedule described in FIGURE 2. Foundation depth will be determined during the Site Survey. Additionally, Floors need to be of a high quality that will withstand vehicles /semi-trucks being driven (international standards for flooring).
3.2.4. Floors. The floors shall be per the Space Schedule described in FIGURE 2.
3.2.5. Vapor Barrier. The contractor shall install a vapor barrier directly below the foundation slab.
3.2.6. Walls. Walls shall be constructed with solid CMU concrete blocks (reinforced with rebar, as necessary) with a minimum strength of 13.7 20 MPa (2,0900 PSI) and the exterior surfaces shall be plastered, primed, and painted with paint that has a high solar reflectance and a high thermal emittance, resulting in a high solar reflectance index (SRI). Interior surfaces shall be plastered, primed, and painted with water-based acrylic paint unless other specified. Walls in armory will need to be reinforced. The contractor will propose technical solution to reinforce armory walls which should include a combination of steel rebar, welded mesh, or still wiring. Armory walls have a different reinforcement requirement for safety purposes.
3.2.7. Door and Window schedule is described in APPENDIX 2.
3.2.8. Roof Design. The roof shall be corrugated CI galvanized steel sheet metal and pre-painted with paint that has a high solar reflectance and a high thermal emittance, resulting in a high solar reflectance index (SRI). It is preferred that the contractor use oven-baked factory-applied painted corrugated sheet metal. The sheet metal should be a minimum thickness of 0.8 mmgauge. The roof slope should be as depicted. The contractor shall propose a roof support system like a King Post Truss or Fink Truss system designed to support a sloped roof. Trusses and purlins shall be steel and welded with minimum strength and dimensions required to support the roof design depicted.
Details on truss strength and dimensions shall be included in Contractors technical proposal. The roof should also have translucent roof panels intermittently spaced amongst the metal sheeting and/or a translucent ridge cap to allow natural light into the building. These panels/ridge cap should not be clear but rather colored like opal white or soft white or, preferably, reflective silver.
The necessary number of tubular skylights or similar items shall be placed to illuminate the office area, which has a flat interior ceiling, with natural light. Metal rain gutters shall be installed along the long side of the roof with downspouts leading to open containers (provided by the Contractor) to collect rainwater. Install at least one (1) turbine type ventilator in each roof section. See
APPENDIX 2.
3.2.9. Interior Ceiling. Interior ceiling above the office area should be a flat design and constructed to enable interior climate control. Contractor shall proposal a detailed ceiling plan that includes insulation as part of their technical proposal. Ceiling design shall include a proposed rafter screening and ventilation plan to ensure that birds, small critters, and rodents are kept out. The necessary number of tubular skylights or similar items shall be placed in order to illuminate the office area with natural light. Armory ceiling will consist of heavy grade steel mesh.
3.2.10. Main Warehouse Ceiling. The ceiling throughout the main warehouse will be open.
Contractor shall propose a rafter screening and ventilation plan to ensure keep birds, small critters and rodents are kept out. Contractor shall provide and connect two heavy duty, industrial ceiling fans throughout the main warehouse. See APPENDIX 2.
3.2.11. Doors. The building shall have steel, metal and wood doors in the receiving and dispatch bays. Each entrance shall have a large, grated floor mat and well just outside the door to clean and collect mud prior to entry. Door in armory should be blast resistant. Door schedule is described in
APPENDIX 2.
3.2.12. Roll-Up Doors (RUD). As depicted in APPENDIX 2, the contractor shall install galvanized steel roll up doors throughout the facility. The main exterior RUD shall be no less than 2.753m wide and no less 4m in height. RUDs shall be both manually and power operated.
3.2.13. Lighting. The Contractor shall install interior and exterior LED lights. Contractor shall procure the lights locally so that bulbs (or bulb assemblies) can be easily repaired or replaced locally. The Contractor shall provide LED floodlights in the vicinity of the building’s exterior.
3.2.14. Windows. The windows shall be double-walled laminated glass with glazing or reflective film, and an insulated aluminum system in order to achieve and have a low solar heat gain coefficient (SHGC) and/or reflective film. This is a more efficient insulation requirement depicted in Appendix 2, which is provided for illustrative purposes only. There should be wire mesh or bars on the outside for security. Window schedule is described in FIGURE 4.5.Appendix 2.
3.2.15. Shelving. The Contractor shall provide heavy duty steel shelving throughout the main warehouse area. The main warehouse area will have approximately 300 ft of shelving. Shelves shall be fully assembled as appropriate and installed. The Contractors may fabricate shelves on site provided they meet all technical requirements. See ANNEX 2 for additional shelving requirements.
3.2.16. Work Benches. The Contractor shall provide 4 heavy duty work benches. Workbenches shall be fully assembled (as appropriate) and installed.
3.2.17. Fire Mitigation Equipment. The contractor shall provide dry fire protection throughout the building which includes dry powder extinguishers, CO2 extinguishers, smoke detectors, and a fire alarm. The contractor must ensure that there is adequate space between the smoke detectors and the roof so that they do not get triggered by the heat radiated from the roof.
3.2.18. Furniture. The Contractor shall provide and install all furniture and equipment specified in
ANNEX 2.
3.2.19. Area Clearance. The Contractor shall clear the areas where the new building is to be sited and shall conduct all building foundation preparation required to support the new structure.
3.2.20. Drainage. The Contractor shall ensure the site is well drained with final grading. Existing natural drainage should be incorporated into the overall site plan design when possible. The Contractor shall construct a drainage channel around the entire warehouse perimeter. The channel shall be trapezoidal, with interior channel dimensions measuring approximately 300m at the top and 250mm at the base with depth of no less than 350 mm. Concrete shall be a minimum thickness of 100 mm at all points of the channel. The concrete channel shall be sealed on all surfaces with a high-quality water proofing material to prevent sun and rain deterioration over time. The total length of channel shall be approximately 400m. The channel shall drain to a discreet drywell near the building. Additional drainage fabrication requirements (dry wells, French drains, etc.) shall be assessed during the design survey and as required, incorporated into the final site plan.
3.2.21. Site Planning Considerations. The Contractor shall ensure more mature, existing trees throughout the area are retained where possible and incorporated into the overall site plan when possible. Ground vegetation may be removed, as required, to efficiently complete construction and achieve site plan requirements.
3.2.22. Warehouse Binder. The Contractor shall provide a “Warehouse Binder”. The 3-ring binder will include color-coded tabs for each section, a table of content, technical specifications for the building as outlined in SOW, facility maintenance, listing of all equipment and parts purchased to support the warehouse, listing of contact information all equipment manufacturers, listing of manufacturer warranties on equipment, systems, and/or parts and expiration dates, sources of supply, operator manual, maintenance manual, service schedule, and, where appropriate, operation and maintenance manual.
3.2.23. Signage. The Contractor shall design and install a prominent entry/identification sign or signs which thoughtfully describes the site’s purpose, pays tribute to the ZDF, and explicitly recognizes the longstanding U.S.-Zambia peacekeeping partnership. The contractor shall work with the ZDF and COR for approval of the final location(s) and designs.
3.2.24. Access Road. The Contractor shall construct an access road in the vicinity warehouse using reinforced gravel at the location depicted in FIGURE 1. The access road would be used by ZDF to bring in equipment to be stored in the warehouse and to facilitate access. Unfinished road repairs shall be reinforced with a gravel base, compacted, and surfaced with a material that will withstand severe weather conditions and not deteriorate. Compacted gravel should be a minimum of 100mm base gravel and 100mm surface gravel, finished with a 4% crown. Surface gravel should have a minimum 8% passing (no. 200 sieve) and a maximum liquid limit of 35. Road repairs shall be made to a minimum width of 4 meters. The estimated length of the road is 200M, but final length shall be determined during the site visit and included in the Contractor’s technical proposal.
3.2.25. The contractor shall provide six (6) ductless wall mounted heat pump air conditioners with a minimum of 20,000 BTUs each shall be installed throughout the facility in the offices and armory.
3.2.26. Solar requirements. Upon activation of this task the warehouse will be hooked up to the dining facility solar PV system. The Contractor shall also provide a 200-kW prime rated generator capable of auto starting and running back-up electricity continuously to the warehouse and the camp in the event no solar or energy storage is available due to power outage, the generator should also have the ability to openly export data. A means to connect it must be included into the design.
3.2.27. Lighting. Install fluorescent exterior and interior fixtures to provide adequate lighting throughout the facility complete with the necessary switches and provide the required quantity of power outlets.
3.3. Task C. Training Sheds (OPTIONAL).
3.3.1. This project entails the construction of five (5) covered, multi-purpose training sheds accommodating up to one hundred forty twenty (140) personnel in bleacher seating, with additional capacity in non-bleacher areas. The construction shall include the use of quality materials that can withstand a tropical rainy climate. See location and design requirements in FIGURE 1 and APPENDIX 3.
3.3.2. Roof, Support Structure, and Floors. Inverted Box Rib with interlocking beam support system or an appropriately engineered metal fabricated roof structure in place of an interlocking beam support system. The support structure shall be mild steel columns fitted on base plates and bolted to suitable anchor bolts embedded in the concrete footings. The floor shall be a 10cm thick 25MPa concrete floor, reinforced with BRC mesh on DPM on well compacted fill. Each floor shall be sealed a high quality non-porous sealer. Behind the middle set of bleachers will be a platform with bleacher seating to allow for viewing. Prime, and paint with water-based acrylic paint. Additional roof, support, and floor requirements are described in See APPENDIX 3.
3.3.3. Electrical. Contractor shall propose an electrical solution including the location of lights, light switches, electrical outlets in the proposal. Install nine (9) high wattage LED lights and three (3) electrical outlets to provide adequate lighting throughout each shed complete with necessary switches. Provide a main distribution panel per building with adequate circuit breakers. Equipment required includes direct burial electrical cable 500 meters rated 60 Amps, 3 phase.
3.3.4. Gutter system. Gutter system (metal) on the two (2) long sides of the roof with a minimum of two (2) fifty (50) gallon barrels for rainwater harvesting.
3.3.5. Bleachers/Seating. Two (2) stand metal bleachers to seat a company of one hundred forty twenty (140) soldiers around three sides of the perimeter of the concrete pad. The bleachers shall have an all-metal support structure. The training shed bleacher support structure shall be appropriately finished to prevent rust. The bleachers will not shall be secured to the floor so they can be configured for specific training events.not be removed from the facility. Behind the middle set of bleachers will be an elevated platform with additional space for bleacher seating to allow for viewing. See APPENDIX 3.
3.3.6. Solar requirements. Upon activation of this task the training sheds will be hooked up to the dining facility solar PV system.-
4. EQUIPMENT AND SUPPLIES.
4.1. The Contractor shall procure and deliver all required equipment and supplies to accomplish the work as specified in each task. See ANNEX 1 and ANNEX 2 for required end items.
4.2. The Contractor shall obtain all required licenses to acquire, ship and deliver the supplies and equipment in each task.
5. PERIOD OF PERFORMANCE. The period of performance shall be 12 months from date of award.
5.1. Pre-Construction Survey: 30 calendar days from the Task Order Award.
5.2. Actual Construction: 11 months from the issuance of the Notice to Proceed (NTP).
6. PLACE OF PERFORMANCE. The place of performance for Task A, B and C shall be Zambia’s Peace Operations Training Center (POTC), located at the Kenneth Kaunda Peacekeeping training center (KKPTC), approximately fifteen (15) kilometers east of the town of Lusaka, Zambia.
7. DELIVERABLES. The contractor shall provide records and reports as stated below.
7.1. Tentative Project Schedule: The contractor shall provide a tentative project schedule indicating the number of days work for each sub-task and the cumulative total days of work for projects in the Technical Proposal. This shall be submitted in a graphic or matrix format which clearly delineates the sequencing and simultaneous execution of the sub-tasks within each country.
7.2. Final Project Schedule: The contractor shall provide the COR and the GPOI Country Manager a Final Project Schedule stating the number of days work for each sub-task, the start and completion dates of each sub-task, and the cumulative total days of work for projects within twenty-one (21) days of completing the coordination visit/ site survey. See Appendix 4. Project Scheduling, for scheduling and payment details, including sections 7.1, 7.2, 7.4, and 7.6
7.3 Required Documents Prior to Issuing Notice to Proceed.
7.3.1. COR/AQM
7.4. Revised Project Execution Schedule. The contractor shall provide any revisions to the project execution schedule on the last day of the preceding month for the next month’s work.
7.5 Recovery Schedule. The contractor shall provide the COR with a recovery schedule if the contractor is behind more than 10% on the Final Project Schedule.
7.6. Receiving and Inspection Report: The Contractor shall submit a complete Receiving and Inspection Report (DS-127) for equipment and materials upon receipt. The DS-127 shall be submitted along with the invoice in which the items are billed.
7.7. Weekly Construction Progress Report: The contractor shall provide a written Construction Progress Report to the COR and GPOI Country Manager regarding the status of each Subtask each week. Construction Progress Reports shall be submitted electronically no later than 1200 Eastern Standard Time on the last business day of each week.
7.8. Serious Incident Reports (SIRs): The contractor shall submit an SIR to the COR within twenty-four (24) hours of the incident’s occurrence. The criteria for SIRs shall include; injury or death of any member of the labor force, injury or death of any individual due to work associated with this SOW, unscheduled or unexpected work stoppages, issues with the host nation military or law enforcement agencies, and loss or damage to equipment, materials, or supplies associated with the work of this SOW.
7.9. Property Book Report: The contractor shall submit a property inventory report to AQM, the COR, the GPOI Country Manager each month following the award of the contract. The report shall be submitted on the last business day of each month.
7.10 Site Manager Maintenance Manual. The contractor shall provide a final hard copy, Maintenance and Warehouse Binder, as part of the request for a Certificate of Completion.
Additional requirements on the content of the handbook are included in the Statement of Work.
7.11. The contractor shall submit a request to the COR for a Certificate of Completion upon completion of all work. Upon receipt of the request, the contractor and COR shall schedule a date/ time for the work to be inspected. If the work has been completed in accordance with the requirements of the Statement of Work, the Department shall provide a Certificate of Completion.
7.12 Deliverables Schedule.
Description Due Date Submitted To
Contractor Inspection System/Construction Quality Management (CQM)
No later than 21 days from award. CO & COR
Initial Project Schedule Within 15 days of award CO & COR
Final Project Schedule with DFOWs coordinated with Schedule of Values
Within 15 days from approval of Initial Schedule of Values
CO & COR
Schedule of Values on Government supplied form
Within 15 days of award CO & COR
Issued for Construction (IFC) Drawings and Specification
Prior to NTP CO & COR
DS-127 Receiving and Inspection Report
Upon equipment delivery and with invoicing
CO & COR
Weekly construction Progress Report Weekly (during construction) CO & COR
3-Week Look Ahead Schedule Weekly (during construction) CO & COR
Description Due Date Submitted To
Revised Project Execution Schedule(s) On the last day of the preceding month for the next months’ work
CO & COR
Recovery Schedule Weekly, when contractor is behind schedule more than 10% of an approved schedule.
CO & COR
Notice of delay Within 10 days of delay CO & COR
Subcontractors Prior to issuance of NTP, and prior to performance of any subcontractor
CO
AQM NTP Documents Prior to issuance of NTP
Written Notification of Differing Site Conditions
Promptly, before conditions are disturbed.
CO & COR
Certification of Boundary Markers Before starting construction on a site COR
Staffing and Supervision Plan Thirty (30) days after contract award COR
Payment Tables No later than the 7th day of each month
COR
Quotations Within 90 days of award COR
Surplus declaration Before final acceptance COR
Hazardous Material notification 5 days before delivery COR
Special Warranties Not later than with request for inspection for Substantial Completion
COR
Trafficking in Persons Compliance Plan Certification
Annually CO & COR
Serious Incident report As incidents occur. No more than 24 hours from the time of the event.
CO & COR
As-Built Drawings (1 soft copy of PDF and 1 soft copy of AutoCAD)
No later than 10 days from substantial completion of construction
CO & COR
Description Due Date Submitted To
Contractor Inspection System No later than 21 days from award. CO & COR
Final Project Schedule No later than 21 days from completing coordination/design site survey after contract award
CO & COR
DS-127 Receiving and Inspection Report
Upon equipment delivery and with invoicing
Weekly construction Progress Report
Weekly (during construction) CO & COR
Revised Project Execution Schedule(s)
On the last day of the preceding month for the next months’ work
CO & COR
Recovery Schedule Weekly, when contractor is behind schedule more than 10% of an approved schedule.
CO & COR
Notice of delay Within 10 days of delay CO & COR
Subcontractors Prior to issuance of NTP, and prior to performance of any subcontractor
CO
AQM NTP Documents Prior to issuance of NTP
Written Notification of Differing Site Conditions
Promptly, before conditions are disturbed.
CO & COR
Certification of Boundary Markers
Before starting construction on a site
COR
Staffing and Supervision Plan Thirty (30) days after contract award
COR
Payment Tables No later than the 7th day of each month
COR
Quotations Within 90 days of award COR
Surplus declaration Before final acceptance COR
Hazardous Material notification 5 days before delivery COR
Special Warranties Not later than with request for inspection for Substantial Completion
COR
Trafficking in Persons Compliance Plan Certification
Annually CO & COR
Serious Incident report As incidents occur. No more than 24 hours from the time of the event.
CO & COR
As-Built Drawings (1 soft copy of PDF and 1 soft copy of AutoCAD)
No later than 10 days from substantial completion of construction
CO & COR
8. TRAVEL. Travel by contractor personnel in performance of work described in this SOW shall be in accordance with Joint Travel Regulation.
9. LIST OF FIGURES. The following figure referenced in this SOW is included below. All other figures are included as an attachment to this SOW.
FIGURE 1: GREEN DINING FACILITY, SOLAR WAREHOUSE, TRAINING SHEDS, TRANSFORMER PROJECT
LOCATIONS
FIGURE 2: SPACE SCHEDULE
S/No Task Area/Description Required Finish
Floor Requirements
1 A Main Dining Area Epoxy Terazzo
2 A,B Admin/Offices/Separate Rooms Epoxy Terazzo
3 A,B Latrine Rooms Tiles
4 A Kitchen Storage Tiles
5 B Main Area Warehouse Epoxy Terazzo
6 A Corridors Tiles
7 A Kitchen Tiles
Wall Requirements
8 A,B Latrine Rooms Tiles
9 A Corridors Smooth finish w/ paint
10 A Kitchen Storage Tiles
11 A Main Dining Area Smooth finish w/paint
12 B Main Warehouse Area Smooth finish w/paint
13 A Kitchen Tiles
14 A,B Admin/Offices Smooth finish w/paint
Other
15 A,B Ceiling Per SOW
16 A,B Exterior Walls Weather Guard Stucco
17 A,B Exterior Entry Way and Stoop areas Terazzo
ANNEX 1. TASK A (DINING FACILITY) FURNISHINGS AND END ITEMS.
LINE Dining facility Items UNIT QUANTITY
1. Office desk with 3 drawers 1
2. Office Chair (to go with desk) Adjustable Swivel Rolling Each 1
3. Refrigerator for the Commanders Mess 25 5/8 Swing glass door Each 1
4. Office Chairs Heavy Duty Black Dot Fabric Stack Chair with Arms Each 2
5. Smart Board 65" all on one interactive whiteboard/ 4K UHD touchscreen; flat panel digital electronic whiteboard. Built in Dual System and Camera for commander’s mess
Each 1
6. Underbar coolers for the commander’s mess 60” W 15.8 cu ft. glass doors, stainless steel
Each 2
7. Air Conditioner -ductless wall mounted heat pump with a minimum of 25,000 BTUs; Office -1, Commanders Mess-2. Note. Air Conditioners in CAD drawings will be located in dining room
Each 3
8. Juice dispenser machines steel 27.25” L x 15” W x 17.5” H Double5 gallon capacity with durable drip trays
Each 4
9. Electric bakery Scale 16lb capacity, 32 ounces x ½ ounces stainless steel material, 9-inch platform diameter
Each 1
10. Industrial Ceiling Fans https://www.industrialfansdirect.com/products Big Ass Fans 14 foot HVLS Ceiling Fan w/ Controller 4900 sq. ft. Coverage F-
PF62-1402S34X2
Each 2
11. 30 inch Oscillating pedestal fan for kitchen Each 2
ANNEX 2. TASK B (WAREHOUSE) FURNISHINGS AND END ITEMS
Line Warehousing Items Unit Quantity
1.
Heavy-Duty, Reinforced Steel Shelving Units, 72”-84” Height, 36”-42” Depth, 48”- 96” width; 1500-2600lbs capacity per shelf; adjustable shelves; hand-loading.
Similar to U-Line industrial shelving: https://www.uline.com/Product/Detail/H- 10488/Industrial-Steel-Shelving/Heavy-Duty-Steel-Shelving
Each Per SOW
2.
Heavy-duty wire storage cages, 48-60” Width, 24-36” Depth, 60-72” Height; 2-3 adjustable shelves (~600-800lbs capacity), full-sided doors. 2 per room:
https://www.uline.com/BL_2840/Wire-Security-Cages?keywords=Heavy-duty+wire+storage+cages
Each 12
3.
Heavy duty steel work bench with lower shelf; 72” L x 48” W, 2000 lbs. capacity, adjustable height, folding; 2 per room:
https://www.uline.com/Product/Detail/H-2484-SS/Industrial-Packing-Tables/
Each 12
4.
Hand Truck Dolly, Rubber Wheels, adjustable, with 500-pound capacity, similar to U-Line 3-in-1 Hand Truck: https://www.uline.com/BL_1847/Uline-3-In-1- Hand-Trucks
Each 1
5.
Portable Hydraulic Floor Crane with adjustable boom arm and hook; up to 2-ton capacity…