Attachment 2 - Bid Chart.xlsx

XLSX spreadsheet 106 KB Posted

Attached to
Forensic Laboratories Construction - Belize
Solicitation number
19AQMM24R0054
Issued by

About this file

This document contains an attachment with a bid chart for the construction of a new forensics laboratory in Dangriga, Belize. The bid chart lists 19 line items for the construction project with descriptions of the general scope of work, site preparation, foundation, earthwork, slab, masonry walls, beams and lintels, concrete stairway, roof, ceiling, plastering, painting, plumbing, electrical, doors and windows, handrails, floor finish, cabinets, and totals for subtotal, overhead, profit, tax, and total project cost of $10,000.

The related federal contract opportunity is a solicitation from the Department of State Office of Acquisition Management to provide forensic laboratories construction services in Belize. The solicitation documents contain additional details on the requirements and terms for the construction of the new forensics laboratory in Dangriga, Belize.

View the file

Other files

File Type Posted
19AQMM24R0054 00003.pdf PDF
19AQMM24R0054 002.pdf PDF
19AQMM24R0054 QA.xlsx XLSX spreadsheet
Attachment 3 Drawings 0001.zip ZIP file
Attachment 3a PUC Submission 0001.zip ZIP file
19AQMM24R0054 0001.pdf PDF
Attachment 1 - SOW 0001 (Track Changes).pdf PDF
19AQMM24R0054 B-M 0001.pdf PDF
Attachment 1 - SOW 0001 (Clean).pdf PDF
23R0054-Belize-Forensic Lab-Pre-Proposal Conference.pdf PDF
Attachment 1 - SOW.pdf PDF
Attachment 5 - Past Performance Questionnaire (PPQ).docx DOCX document
Attachment 3a PUC Submission.zip ZIP file
19AQMM24R0054 B-M.pdf PDF
Attachment 4 - Firm and Project Information.pdf PDF
19AQMM24R0054.pdf PDF
Attachment 3 Drawings.zip ZIP file
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY

NEW FORENSICS LAB
DANGRIGA, BELIZE

BID CHART

ITEMDESCRIPTIONUNITQTY.UNITTOTAL
COST
1.0General1.00Global- 0
2.0Site Preparation1.00Global- 0
3.0Service Entrance1.00Global- 0
4.0Foundation System1.00Global- 0
5.0Earthwork1.00Global- 0
6.0Slab on Grade1.00Global- 0
7.0Masonry Walls1.00Global- 0
8.0Ring Beam, Lintels, & Sills1.00Global- 0
9.0Concrete Stairway1.00Global- 0
10.0Roof1.00Global- 0
11.0Ceiling1.00Global- 0
12.0Plastering1.00Global- 0
13.0Painting1.00Global- 0
14.0Plumbing1.00Global- 0
15.0Electrical1.00Global- 0
16.0Doors, Windows, Security Bars1.00Global- 0
17.0Handrails1.00Global- 0
18.0Floor Finish1.00Global- 0
19.0Cabinets1.00Global- 0
SUBTOTALSUBTOTAL- 0
OVERHEAD
PROFIT
TOTAL WITHOUT IVA- 0
IVA Tax (12.5%)- 0
DBA10,000.00
TOTAL PROJECT COST10,000.00