This technical specification document outlines the requirements for replacing pedestrian roof floors at the Naples Consulate facility for the Department of State. The scope of work involves demolishing existing flooring and installing new flooring, insulation, waterproofing and screed across three roof areas totaling approximately 1,200 square meters. The specification provides material and installation requirements for photovoltaic floor tiles, extruded polystyrene insulation, multi-layer bitumen waterproofing membrane, metal profiles and slope screed. Contractors must submit samples and specifications for all materials prior to use. The work must be completed within 120 calendar days of notice to proceed. The contractor will be responsible for all necessary equipment, permits, and safety plans throughout the project duration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment no. 0001.pdf | ||
| Attachment 3. DRAWINGS -V1.pdf | ||
| Meeting Minutes.pdf | ||
| Attachment 2. BILL OF QUANTITIES - V1.pdf | ||
| Questions and Answers.pdf | ||
| Attachment 2. BILL OF QUANTITIES.pdf | ||
| Attachment 1. TECHNICAL SPECIFICATIONS.pdf | ||
| 191T7023R0002.doc | DOC document | |
| Attachment 3. DRAWING.pdf | ||
| Cover Letter.pdf | ||
| SF-1442.doc | DOC document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Embassy of the United States of America
Rome, Italy
NAPLES - Consulate
Replacement of pedestrian Floorings of the roofs Garage, Gym, and Post
Office
Facility Engineering Office
Summary
1.1. SUBJECT OF THE SCOPE OF WORK 3
2. DESCRIPTION OF THE WORKS 4
BRIEF DESCRIPTION OF CURRENT STATE – AREA “A” 6
BRIEF DESCRIPTION OF CURRENT STATE – AREA “B” 8
BRIEF DESCRIPTION OF CURRENT STATE – AREA “C” 9
WORKS FORESEEN IN THE PROJECT; 11
INTERFERENCES IN GENERAL 13
WORK IN GENERAL 13
CONSTRUCTION SITE SAFETY 13
3. PROCEDURE FOR EXECUTING THE WORKS 14
3.1. MATERIAL ACCEPTANCE RULES 14
3.2. GENERAL RULES 14
3.3. QUALITY OF MATERIALS 14
4. FLOORING 15
5. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF RENTALS AND TRANSPORT 18
5.1. PROVISIONAL WORKS 18
5.2. RENTALS 18
5.3. TRANSPORTATION 18
6. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF THE WORKS 19
6.1. LAYING OF THE MATERIALS 19
7. SITE ORGANIZATION AND SAFETY 19
7.1. DAMAGE 21
8. AFTER AWARD ACTIVITIES 22
8.1. CONTRACT PHASE 22
8.2. IMPLEMENTATION PHASE 22
8.3. CONCLUSION PHASE 23
8.4. PERFORMANCE TIME 23
8.5. SUBCONTRACTING AND PIECEWORK 23
8.6. MATERIAL EQUIVALENTS 24
8.7. WORK PROGRESS 24
8.8. PARKING 24
9. REGISTRY OF SUBMISSION 25
GENERALITY'
1.1. Subject of the scope of work
The object of this contract concerns the works relating to:
- the replacement of the pedestrian roof floors, including screeds, insulations and waterproofing, in areas “A”, “B” and “C” of the Garage, Gym and Post Office at the Consulate in
Naples.
The works object of the contract, described in this Scope of Work (hereinafter SOW), shall be complete in all their parts.
For a complete identification of the work, please refer to the technical specifications indicated in this SOW and drawings.
A complete maintenance booklet for each individual component shall be delivered.
2. DESCRIPTION OF THE WORKS
The design of the works has the purpose of replacing the old and damaged Roof flooring on the pedestrian Roof on the areas pointed out in picture nr. 2.
Picture 1 – Territorial Plan, in the red circle the Consulate
Picture 2 – Inside the red line the Pedestrian Roof in question
Picture 3 – Inside the red line the Pedestrian Roof in question
Brief description of current state – Area “A”
Currently, the areas in question are in a very poor condition with evident signs of deterioration and broken in many points. Furthermore, several old satellite dish, no longer in use, shall be removed.
The existing flooring was created by overlapping several layers in the time. In fact, as you can see in the photo no. 4 there is a first screed and first layer of tiles on which a second screed was made, with a new waterproofing layer and other tiles on top.
Picture 4 – Existing stratigraphy - area “A”
Picture 5 – Existing area “A”
Brief description of current state – Area “B”
Currently, the areas in subject are in a very poor condition with evident signs of deterioration and waterproof layer broken in many points. The area “B” is a technical joint for connecting the Building
“A” to the Consulate Building. It is made with a Steel slab.
Picture 6 – Existing area “B”
Brief description of current state – Area “C”
Currently, the areas in subject are in a very poor condition with evident signs of deterioration and the waterproof layer broken in many points. The old satellite dish shall be removed.
Picture 7 – Existing area “C”
Picture 8 – Existing area “C”
Works foreseen in the project.
The works will concern in:
• Fencing of construction site areas and preparation of storage area and temporary routes.
• Dismantling of the existing satellite dishes and old useless systems.
• Area A: demolition of the existing Flooring including all the screed until reach the structural slab floor.
• Area B: dismantling of the existing waterproofing and screeds.
• Area C: Removal all the existing stones and demolition of the existing waterproofing and screed.
• Area A, B, C: installation of flooring in accordance with the stratigraphy below.
• Painting of the internal surface of the ring beam.
All the existing systems and devices shall be respected and preserved.
Drawing 1 – stratigraphy for area “A” and “B”
Drawing 2 – stratigraphy for area “C”
INTERFERENCES IN GENERAL
On the top of the terrace, there are several channels, cables, devices and any kind of interferences (i.
e. electric, water, sewage and so on), each of which shall be respected, and/or replaced or moved.
The interference item includes all manufacturing, materials and/or services necessary for the perfect functionality of the interference found.
WORK IN GENERAL
Before start with the work scheduled, all works, civil, electrical, hydraulic, safety of the sites, shall be supported by plans and executive drawings for the construction site, which shall be approved by the
COR.
At the end of the work, the Contractor shall provide As-Builts files in original format (e.g., dwg, word, excel, etc.).
CONSTRUCTION SITE SAFETY
The safety of the construction site, including all charges foreseen by the current legislation, will be an important aspect for the planned works. The item includes the following:
- Fencing of the construction site area, temporary walkways, construction site bathroom.
- All types of scaffolding possibly necessary for carrying out the planned works.
3. PROCEDURE FOR EXECUTING THE WORKS
3.1. Material acceptance rules
The materials required for the construction of the works, whatever their origin, will be of the best quality, and will be considered accepted only when, at the unquestionable judgment of the
COR, they correspond to those designated below in terms of nature, quality, durability, suitability and application. Except for special materials, all the works shall come from quarries, factories, refineries, etc., deposits. chosen exclusively by the Contractor, which cannot make any exceptions.
3.2. General rules
The items below shall establish the execution rules for the various works contemplated in the
Contract, as well as the technical specifications of the materials used.
By rule of thumb, in the execution, the Contractor will have to comply with the best rules of the art as well as with the following works. For the categories of works that are not found in this
SOW, and for which no special rules have been prescribed, in particular for any work to be carried out economically, the Contractor shall follow the best procedures dictated by the technique and comply with the orders that for this purpose, the COR will issue.
Works which, for any reason, immediately or subsequently prove to be badly performed, shall be redone at the Contractor's expense, without the need for a formal request from the COR; the possible presence on site of an overseer of the Principal cannot be invoked by the Contractor in discharge of its liability.
For the works on the networks and for the construction of artifacts and works of art, the
Contractor, having received the delivery, referring to the project cornerstones, will first carry out the tracing of the work by affixing the stakes and modifiers for the axis, for the sections and for the works of art; at his care and expense the pickets will be maintained until completion.
3.3. Quality of materials
All the works envisaged by this SOW can be performed in perfect working order and with materials that meet the technical specifications indicated and/or referred to in this SOW.
The quality of the material used in the execution of these works shall meet, when not otherwise specified by Contractor rules or regulations, the requisites required by the laws in force and by the official standards of good construction techniques.
The Government during construction and at any time, may take material samples from the manufactured articles used to verify their perfect correspondence with the approved types.
In this case, the Contractor shall have to make an operating team available to the Government to carry out the activities necessary for the execution of these checks, carried out with the help of a specific specialized Contractor. These charges will be charged to the Contractor, including any demolition and reconstruction of the works found to be non-compliant.
The Contractor shall report any defect or anomaly found on the materials supplied directly by the COR.
4. FLOORING
The new flooring shall have the following stratigraphy and features, from top to bottom:
FLOORING "A" and "B"
The new flooring include:
• FLOORING in self-locking slabs such as LASTRA® 50x50 in a light color like white or
Botticino or similar, 3 cm thick, CE marked in accordance with UNI 1339 in double-layer vibro-compressed concrete, with ECOTOP "PHOTOCATALYTIC" (TX Active ®) finish, produced only with natural aggregates from Contractor with UNI EN ISO 9001 Quality
Certification and UNI EN ISO 14001 Environmental Certification. The flooring shall respond to environmental performance in accordance with point 2.4.1.2 of the Ministerial Decree
11/10/2017 (CAM), with a recycled material content ≥5%, this specification shall be accompanied by a product certification issued by a conformity assessment body which certifies the recycled content through the explanation of the balance of mass which consists in the verification of a self-declared environmental declaration, compliant with the ISO 14021 standard. With reference to point 2.2.6 of the D.M. 11/10/2017, the flooring shall have an SRI index ≥29. The flooring shall consist of two layers, of which the surface layer with a thickness of ≥ 4 mm and made with a mixture of quartz with a maximum particle size of 2 mm and with a minimum dosage of white photocatalytic cement type TX ACTIVE® of 400 Kg/m3. The product, with this finish and this colour, shall have a certificate of reduction of NOx values in 60 minutes of more than 60%. The flooring is made up of elements measuring 50x50 cm. The elements shall be equipped with suitable interlocking spacers which facilitate installation and ensure that it is blocked. The indirect tensile strength shall be ≥ 3.5 MPa. Resistance to climatic agents shall be at least Class 2, marking B (water absorption % by mass <6%). The freeze/thaw resistance shall be at least equal to Class 3 marking D (mass loss after freeze/ thaw test ≤1.0 kg/m2). The resistance to abrasion shall be at least equal to Class 4
(Li≤20mm), Marking I. To overcome architectural barriers, the flooring shall have a BCRA friction coefficient (DM 236 of 164/06/89) equal to or higher to 0.70 and a value of the USRV coefficient > 60. With reference to the measurement of the slip limit angle, conducted according to DIN 51097, this angle shall be ≥25°, i.e. Class C-Excellent. The density shall not be less than 2200 kg/m3; The supports are included according to the height that COR will decide.
• INSULATION. Single-layer extruded expanded polystyrene sheet with smooth surface skin and perimeter rebate on four sides, CFC, HCFC, HFC free (such as Styrodur® 5000 CS) and subjected to ITT tests by the FIW of Munich, equipped with Environmental Product
Declaration (EPD ), produced with flame retardant PolyFR, with a compressive strength value at 10% crushing according to EN 826 equal to 700 kPa; compressive strength for permanent loads after 50 years with compression ≤ 2% according to UNI EN 1606 equal to
250 kPa; water absorption according to UNI EN 12087 equal to 0.2% by volume; moisture absorption by diffusion and condensation according to UNI EN 12088 < 3% by volume; water absorption following the freeze-thaw test according to UNI EN 12091 ≤ 1% by volume;
resistance factor to the passage of water vapor μ (dimensionless) according to UNI EN
12086, 100 (for thicknesses of 60, 80 and 100 mm); average of closed cells according to UNI
EN ISO 4590 equal to or greater than 98%; reaction to fire European Class E according to
UNI EN 13501-1, declared thermal conductivity at 10°C according to UNI EN 12667, 0.034
W/mK for 60 mm thickness, ; with DIBt approvals (Z-23.34-1325*) for applications under load and under foundation slabs. THICKNESS 6cm;
• BITUME MEMBRANE. Preparation of the laying surface of waterproof coverings with a coat of solvent-based bituminous PRIMER in quantities of no less than 300g/m;
• Two layers of bituminous waterproofing membrane modified with elastomeric resins for surfaces confined or under heavy protection in areas with high temperature ranges, reinforced with continuous thread non-woven polyester fabric, torch-applied with 10 cm overlapping in the longitudinal direction and 15 cm at the ends of the sheets, laid out on the laying surface after treatment with a bituminous primer on flat, curved and inclined surfaces.
Thickness 4+4mm. The fixed price item also includes the waterproofing of the perimeter curbs, as per the attached drawings for a height of no less than 30 cm.
• METALLIC PROFILES in Zinc and Titanium to protect the perimeter curbs, with geometry indicated by the COR and including all the necessary anchors;
• PRIMER for special screeds, applied according to the methods indicated in the GROVE
PRIMER ECO technical sheet.
• SCREED ready for GROVE slope for heights between 4 cm and 10 cm.
The fixed price item includes all types of work to carry out the flooring, for example, transport, raising, lowering, stacking, protection of materials, finishes and so on.
The item also includes the profiling of the rainwater downspouts, using both new metal cages and cement mortar and anything else necessary to give the finished work in a workmanlike manner.
5. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF RENTALS AND
TRANSPORT
5.1. Provisional works
The main regulations concerning scaffolding, fixed metal scaffolding, mobile scaffolding, etc., are contained in the U.S. and Italian Law.
5.2. Rentals
The machines and tools given for hire shall be in perfect working order and be equipped with all the accessories necessary for their operation. The maintenance of tools and machines is the exclusive responsibility of the Contractor so that they are in constant efficiency.
The fixed price contract includes transport from the place of origin to the construction site and vice versa, assembly and disassembly, labor, fuel, lubricants, consumables, electricity, scrap and everything for the necessary functioning of the means. They also include general expenses and the entrepreneur's profit in the freight rates.
5.3. Transportation
If the size of the material to be transported is less or more than the payload of the vehicle requested for hire, no price reductions or increasing are envisaged.
The supply of consumables and the driver's labor are included in the transport prices.
6. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF THE WORKS
6.1. Laying of the materials
The Contractor shall perform what it is included in the technical sheets of the materials.
7. SITE ORGANIZATION AND SAFETY
In addition to the provisions of the SOW, the following remains established:
1. upon delivery of the works, the Contractor shall designate by name a technical assignment employed by or registered in a specific professional register with the task of directing the organization of the site and supervising the conditions of safety and use of the manpower, equipment and materials. Said technician is required to always be present on site.
2. The Contractor is required, during the preparation of the site, the execution of the works to observe the rules on accident prevention and occupational hygiene referred to Italian and U.S.
Laws and subsequent amendments and or modifications.
3. The Contractor has the obligation to comply with the "safety plan" or the one amended following the supplementary proposals formulated by him and to comply with the related implementing provisions that will be issued during the works by the "safety coordinator during the execution of the works"; the Contractor shall draw up and promote to the COR, in the manner established by the combined provisions of the aforementioned Legislative Decree 81/2008, an operational safety plan that takes into account the organizational, technical, procedural and technological reality of the Contractor itself. In the event of a temporary association of companies, the above applies to the agent Contractor or Contractor designated as group leader. In the event that the drafting of the safety and coordination plan is not envisaged, the Contractor shall draw up and deliver its own replacement safety plan to the COR within the terms established by the Rule. It should be noted that the amount of the charges deriving from the implementation of the provisions of the aforementioned construction site safety documents, expressly indicated in the specifications, are understood to be offset and included in the unit and/or bulk prices of the various items of the estimate. Having established that the percentage safety incidence of the safety charges of each individual estimate item is conventionally assumed to be equal to the ratio between the global work costs and the gross amount of the safety charges, the portion of the amount not to be subject to a discount will be equal to product of the aforementioned incidence by the gross amount booked.
4. The Contractor is obliged to adapt the working hours to the User's needs, with the obligation to obtain the information in advance.
5. The Contractor, through its manager, shall keep a register updated on the construction site, to be shown for inspection by the Project Manager himself or someone on his behalf, such as in the work itself or to be noted on a daily basis materials and inflows on site to be used in the works, those used in the execution of the works themselves and those removed from the site, with the resultant of the materials stored there. He shall keep the packing slips/supply of materials in absolute order in special catalogues/binders prepared for this purpose.
6. It is absolutely forbidden to access the site for Contractor personnel who, where requested, refuse to submit to personal checks or checks on things in tow. The contracting station declines any responsibility if the refusal referred to in this paragraph causes delays, hindrances or even the impossibility of executing the contract.
7. The Contractor shall maintain discipline on construction sites and is obliged to observe and away from his agents and his agents, the regulations and provisions in general issued by the contracting station and by the competent authorities for the good order and discipline of the works. The Contractor shall employ suitable persons for his agents, foremen and workers. The construction manager has the right to order the change of duties of the Contractor's personnel in cases of ineptitude and the removal of personnel from the works in cases of insubordination and bad faith. In any case, the Contractor remains liable for damages caused by the inexperience, negligence or bad faith of the personnel themselves.
8. The works shall be carried out in a workmanlike manner and the materials to be used shall be of the best quality available on the market, free from any general and special defect, meet all the other requirements indicated in the technical specifications and in the specifications as well as in the Decrees bearing the conditions mandatory general techniques. When it comes to national products, the Contractor is free to procure materials where he deems the best, provided that they have requirements where prescribed by the contract, unless in these general conditions, in the special chapter or in the price tariff, special requirements are prescribed on origins some materials. The Contractor shall justify, with the presentation of suitable documents, the actual origin of the materials, and lend himself to subjecting them to all the tests that the project manager deems appropriate to ascertain their quality and resistance. The materials cannot be used if they have not been previously accepted by the construction manager who has the right to refuse those he does not recognize as suitable for the goodwill of the works. The rejected materials shall be removed from the construction sites within the term established by the COR and at a convenient distance; failing the Contractor to comply with the relevant provision, the COR has the right to do so directly, charging the Contractor the related expense, which will be deducted from the first advance certificate. Acceptance does not affect the right of the contracting station to refuse, at any time until testing, the works performed with materials that do not comply with the contractual conditions, materials to proceed, pursuant to current laws, in the case of construction defects. When the Contractor presents concrete for and the relative samples, the contracting station may examine proposals to replace the quality of the materials and their origin, if prescribed, however reserving the full right to accept and reject said proposals. If, even without opposition from the site manager, the Contractor has on his own initiative used materials of a better prescribed excess weight and size, or of a more accurate quality or mastery, he is not entitled to any price increase, whatever the the advantages that can derive from the contracting station; and in this case the accreditation of the
Contractor is done as if the materials found the weight and dimensions, the qualities and the mastery established in the contract. Conversely, objects or materials of weight, characteristics and/if smaller than those prescribed, or of lower quality or less accurate workmanship are used, they will be counted by reducing in proportion to the lower weight, smaller dimensions and different quality and processing the corresponding prices. All general and specific charges, in any case connected to the obligations listed above, are to be paid in full and at the expense of the Contractor, having taken them into account in determining the individual unit prices, by measure or as a whole of the tender specifications.
7.1. DAMAGE
1. The Contractor is responsible for all measures, including provisional works and all obligations to avoid the occurrence of damage to the works, the environment, people, and things in the execution of the contract pursuant to current law.
2. No compensation is due for damage caused by force majeure to temporary works, scaffolding or site vehicles and equipment.
8. AFTER AWARD ACTIVITIES
8.1. Contract phase
Within 15 calendar days of the date of award, the Contractor shall submit the following documentation to the Embassy’s Technical Office:
· A final and detailed work schedule of the various interventions and relative length of time required to carry out all the work requested in the contract.
· A final Safety Plan as set forth in the General chapter, finalized with the names of all actors and with the results of the discussions with the POSHO.
· A list of the names, complete with biodata, of all the employees, as well as possible suppliers and sub-Contractors for specific work, who will require access to the work-site. Furthermore, the
Contractor shall submit a complete list of vehicles to be used during the project, indicating the make, model and license number.
· Designation of someone who will be in charge of the project on behalf of the Contractor and who will be fully authorized to discuss and decide together with the COR any variations during the course of the project, both concerning methodology of the work and the supplies.
· Designation of a Safety Manger who will address all safety issues and will monitor the daily operations.
· The register of submittals.
The Contractor shall be responsible to obtain and pay any fee due to the occupancy of public area should any need arise during the execution of the work.
8.2. Implementation phase
· The implementation phase starts with the Notice to proceed (NTP).
· No work shall be performed before the submission of the shop drawings and relevant approval.
· No materials shall be installed prior the relevant submission and approval.
· Normal working hours are from 08:00-08:30 up to 17:30 during weekdays. Any work to be carried out after normal working hours or during the weekend shall be agreed upon in advance with the COR in order to obtain all the necessary authorizations and approvals.
· Demolitions, perforations and other high noise operations shall be carried out no earlier than 09.30.
The quiet rule shall apply even during the time 12.30 to 15.30, during workdays.
· The worksite shall be kept as clean as possible.
· Areas for storing material shall be agreed upon, together with the COR, based on logistical-operative criteria.
· Any temporary interruptions of utilities shall be scheduled at least 5 days in advance and shall be subject to approval from the COR.
· Tests on the correct operation of the systems and consignment of parts of completed work shall be carried out in the presence of the person designated by the Contractor and someone authorized by the Consulate. The Contractor shall be responsible for drawing up the necessary delivery reports for the work and systems carried out and shall be subject to verification and acceptance by the COR.
8.3. Conclusion phase
· Once the project is completed a final inspection shall be carried out with representatives of the
Contractor and the Embassy, in order to verify that the project has been carried out correctly, that it is in compliance with the technical specifications and that the systems operate correctly.
· When the work has been completed and accepted by the COR, the Contractor shall submit the following documents to the COR:
· detailed “as-built” drawings showing the new constructions, both the architectural/structural aspects as well as all the systems. The drawings shall be submitted on paper and software in ".dwg" format.
· Technical cards of the most important materials used in the project, with a list indicating the location of the vendors and local suppliers.
· Certification of conformity and tests carried out by the manufacturers for materials, as well as guarantee of the correct installation of all the materials by the Contractor with regard to the project realization and law requirements.
8.4. Performance time
The contract performance time and the methods with which these times will be calculated are fully described in the solicitation package and here listed for convenience.
Period of time to complete the project, from mobilization to final cleaning:
120 solar days from the "Notice to proceed".
For this reason, it would be appropriate that the works start with two different Team Work.
Penalties for delays in completing the project are those described in the tender documents.
8.5. Subcontracting and piecework
In the subcontracting authorization request and in the subcontracting agreement, the Contractor shall promptly indicate the operational scope of the subcontract, in terms of performance, and specify in unambiguously, in particular, the name of the subcontractor, the description of the work or services to be subcontracted – indicating the relative quantities or dimensional parameters referred to each execution area and process phase and referring to the project - the individual areas the individual process phases in which the subcontracted work or services will be performed.
In any case, the Contractor remains responsible towards the contracting authority for the execution of the works subject to subcontracting, relieving the contracting authority itself from any claims of subcontractors or from claims for damages made by third parties as a result of the execution of subcontracted works.
It should be noted that in the event of subcontracting of works, the Contractor will be solely responsible for the technical and professional suitability of the subcontractor.
In addition, the expected times for the work covered by the contract, the subcontracting shall be compatible and congruent with the work program of the main contract (Gantt Chart), by updating it, with the Contractor's commitment to produce the work program updated to the works manager before the start of the subcontracted works.
8.6. Material equivalents
The contractor shall verify and ensure that all the materials supplied are new and without defects and that their use and/or installation is carried out using the best techniques and fully respecting the instructions supplied by the manufacturers.
Special parts shall be manufactured solely by workshops that are highly qualified in that specific sector.
The makes indicated in this SOW (Scope of Work) are intended as a point of reference and therefore, the words or approved equivalent are implicit.
Therefore, the makes and products listed are deemed equivalent to each other. Different selections implemented by the Contractor will be approved in advance by the COR, after submission of samples and technical cards.
8.7. Work progress
In general, the Contractor shall have the faculty of developing the work in the way he believes more convenient and shall hand it over completed within the terms of the contract, as long as, in the opinion of the COR, this is not detrimental to the outcome of the project and the interests of the
Government.
The Government reserves the right to request that a specific task shall be carried out within a pre-determined period of time, or to dispose the order of the performance of the work in a way it deems more convenient, especially in relation to requirements depending on the performance of work and delivery of supplies excluded from the contract, without the Contractor having the possibility to refuse or ask for special compensation.
Before starting the work, the Contractor shall submit for the COR’s approval a detailed operative schedule and costs, which he will follow during the performance of the contract, in concurrence with the schedule.
8.8. Parking
The parking is allowed inside the Residence. The Contractor's vehicles will be allowed to park only for loading and unloading materials
9. REGISTRY OF SUBMISSION
FLOORING
Contractor shall submit the sample of the Photovoltaic TxActive and all the materials used for this project, per specification. Each material shall be submitted with its technical sheet for COR approval.
INSULATION
Contractor shall submit nr. 3 sample of the INSULATION Layer with 700Mpa (compression) used for this project, per specification. Each material shall be submitted with its technical sheet for
COR approval.
WATERPROOFING
Contractor shall submit nr. 3 sample of the WATERPROOFING LAYER used for this project, per specification. Each material shall be submitted with its technical sheet for COR approval.
SCREED FOR SLOPE
Contractor shall submit nr. 3 sample of the READY SCREED for Slope and his PRIMER used for this project, per specification. Each material shall be submitted with its technical sheet for COR approval.