19-Scope of Services.pdf

PDF 234 KB Posted

Attached to
Engineering Services for Regional Biosolids Facility Design
Solicitation number
PNC2132449P1
Issued by
Broward County, Florida

About this file

This is a Scope of Services document for Broward County Water and Wastewater Services (WWS) seeking a qualified engineering firm to provide comprehensive design, permitting, and technical support services for the development of a new Regional Biosolids Drying Facility to be located at or near 3100 North Powerline Road in Pompano Beach, Florida. The project involves designing a thermal drying facility that will serve eleven regional utilities through the Regional Biosolids Solutions Work Group, processing approximately 39,000 dry tons of biosolids annually by 2043. The facility will utilize a multi-train belt drying system with N+1 redundancy configured for a minimum evaporative capacity of 64,000 pounds of water per hour with an installed capacity of 76,000 pounds per hour, achieving Class AA biosolids quality in compliance with Florida and federal environmental regulations. The consultant will deliver a complete Basis of Design Report (BODR), final design and construction documents at 30%, 60%, 90%, and 100% milestones, permit applications, and support the Managing General Contractor (MGC) during GMP development. The project is structured in three phases: Phase I Preliminary Engineering (6 months), Phase II Design and Permitting with GMP Development Support (12 months plus 6 months), and Phase III Engineering Services During Construction (24 months).

The scope encompasses evaluation of existing solids production, geotechnical and topographic investigations, hydraulic and structural analyses, cost estimation, project scheduling, regulatory coordination, and public outreach. Services include design of cake receiving and storage systems, the thermal drying process with heating and condensing units, product handling and storage with truck loadout facilities, odor and air-pollution control systems, supporting infrastructure including electrical service, natural gas supply, water connections, SCADA systems, a thermal dryer building with laboratory and maintenance areas, site development with grading and parking, and relocation of the existing septage receiving system. The consultant will remain the Engineer of Record (EOR) throughout construction, providing Engineering Services During Construction including site inspections, submittal reviews, RFI/RFS processing, schedule and budget monitoring, change order evaluation, startup and commissioning support, punch list preparation, final completion certification, record drawing preparation, and training program development for WWS operations staff. The contract includes provisions for optional additional services as directed through work authorizations, with all services to be executed in planned phases with separate Notices to Proceed issued by WWS for each phase.

View the file

Other files

File Type Posted
16-Instructions to Vendors - RFP-RFQ-RLI.pdf PDF
8-OESBD Affiliated Entities of the Principals Certification.docx DOCX document
5-Criminal History Screening Practices Certification.docx DOCX document
9-Security Requirements.docx DOCX document
1-Summary of Vendor Rights for Broward County Competitive Solicitations.docx DOCX document
20-Addendum No. 1.pdf PDF
4-Litigation History.docx DOCX document
21-CBE - Good Faith Effort Evaluation Form Addendum 1.pdf PDF
12-Vendor Reference Verification - RFP-RFQ-RLI.docx DOCX document
6-Agreement Exceptions - RFP-RFQ-RLI.docx DOCX document
14-Location Certification - RFP-RFQ-RLI.docx DOCX document
7-Vendor Questionnaire and Standard Certifications - RFP-RFQ-RLI.docx DOCX document
13-Domestic Partnership Act Certification.pdf PDF
25-List of Proposers.pdf PDF
23-CBE - Monthly Utilization Report Form Addendum 1.pdf PDF
11-Minimum Insurance Requirements.pdf PDF
15-Volume of Previous Payments Attestation - RFP-RFQ-RLI.docx DOCX document
10-OESBD - CBE Goal Participation.docx DOCX document
18-Evaluation Criteria.pdf PDF
2-Subcontractors-Subconsultants-Suppliers Requirement.docx DOCX document
24-Analytical Report dated June 10, 2026 Addendum 1.pdf PDF
3-Lobbyist Registration Requirement Certification.docx DOCX document
17-Regional Biosolids Solids Solution Conceptual Study - Phase 2 (Brown and Caldwell, April 2025).pdf PDF
22-CBE - Letter of Intent Form Addendum 1.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF SERVICES

Engineering Services for Regional Biosolids Facility Design

A. Background

1. Broward County (County) seeks a qualified engineering firm (Consultant) to provide design, permitting, and technical support during development of the Guaranteed Maximum Price (GMP) by the Managing General Contractor (MGC) as well as engineering services during construction for a new Regional Biosolids Drying Facility to be constructed at or near 3100 North Powerline Road, Pompano Beach, Florida, in close proximity to the County’s North Regional Wastewater Treatment

Plant (NRWWTP). This Project supports the development of a long-term regional biosolids management solution in the form of a new regional biosolids drying facility (Regional Biosolids Drying

Facility) to address diminishing land-application capacity, rising disposal costs, and increasingly stringent regulatory requirements in the State of Florida. The County intends to deliver the Project through an MGC project delivery method. An MGC will be procured under a separate solicitation to provide pre-construction services and construction services, including development of the GMP. The

Consultant shall coordinate with the County’s selected MGC during design and construction phases of the Project.

2. The Consultant’s design for the Regional Biosolids Drying Facility shall provide a complete thermal drying process for dewatered municipal biosolids to achieve Class AA quality in full compliance with

Chapter 62-640, Florida Administrative Code (F.A.C.). Consultant’s design must also satisfy all applicable requirements of the Florida Department of Environmental Protection (FDEP) and the

United States Environmental Protection Agency (EPA) under 40 Code of Federal Regulations (CFR)

Part 503. The facility shall be designed for continuous operation while meeting all applicable FDEP and EPA standards for biosolids treatment and beneficial reuse.

3. The Regional Biosolids Solutions (RBS) Work Group, established in 2022-2023, is a regional coordination among eleven utilities, including Broward County Water and Wastewater Services

(WWS), Cooper City, Coral Springs Improvement District, Town of Davie, City of Fort Lauderdale, City of Hollywood, City of Margate, City of Miramar, City of Pembroke Pines, City of Plantation, and City of Sunrise. Dewatered biosolids from each participating utility will be hauled to the Regional Biosolids

Drying Facility for thermal drying and final processing. The facility will be designed for the full maximum receiving capacity based on the combined regionally projected biosolids tonnage from all eleven utilities. This design capacity will be established regardless of whether each utility ultimately utilizes the facility or commits to long‑term participation. Each utility may share in the cost determined from the percent of biosolid tonnage generated from their individual treatment Plants and estimated to be delivered to the facility. If the designed capacity is not needed immediately, it will be addressed in the early portions of bidding process of the construction phase. The County will own and operate the facility and manage the final product.

4. The RBS Work Group is collectively projected to generate approximately 39,000 dry tons of biosolids annually by the year 2043. The average total solids content of the dewatered cake is estimated at

15–16 percent and may include a combination of anaerobically digested, aerobically digested, and undigested waste-activated sludge. The thermal drying system must be designed by the Consultant for a minimum evaporative capacity of 64,000 pounds of water per hour, with an installed capacity not less than 76,000 pounds of water per hour and will incorporate an N+1 redundancy configuration

(normal operation with an additional unit) to ensure continuous operation.

5. Following a detailed dryer technology evaluation, the RBS Work Group selected belt drying as the preferred process for the Regional Biosolids Drying Facility. Therefore, the Regional Biosolids Drying

Facility will utilize a multi-train belt drying system with pelletizers as the core technology, providing a proven, energy-efficient, and scalable solution suitable for large-scale biosolids processing.

Consultant’s design shall provide flexibility for future expansion and integration with advanced thermal-treatment technologies for regulatorily driven requirements such as Per-and Polyfluoroalkyl

Substances (PFAS) destruction.

6. The Project site is owned by the County and currently contains the existing septage receiving system operated by WWS. Relocation and incorporation of that facility will be included in the Consultant’s design to accommodate the construction of the new Regional Biosolids Drying Facility. The selected location provides direct access to major utilities, transportation corridors, and the NRWWTP, ensuring operational efficiency and future expansion potential.

B. General Description of Services

1. The Services include professional engineering services for the design, permitting, technical support during GMP development by the MGC, and engineering services during construction of a new

Regional Biosolids Drying Facility. The Consultant shall perform all activities necessary to deliver a complete Basis of Design Report (BODR), including preparation of technical and supporting reports as required. Services include evaluation of existing solids production and dewatered biosolids analysis, development of solids-loading projections and design criteria. Performance of hydraulic, structural, mechanical, electrical, and site analyses, including topographic and geotechnical investigations. The Consultant shall prepare cost estimates, project schedules, and permit applications in accordance with County standards, coordinate with regulatory agencies, and participate in public outreach and engagement. Technical assistance shall also be provided by the

Consultant to WWS and participating RBS Work Group members to support interlocal agreements, data validation, and regional integration. The preliminary design criteria documented in the Regional

Biosolids Solution Conceptual Study - Phase 2 (Brown and Caldwell, April 2025) shall serve as the technical foundation for this work.

2. Beginning at the 30% design milestone, the Consultant shall coordinate with the MGC to support constructability reviews, cost validation, phased construction planning, and reconciliation of scope of work with cost estimates prepared by the MGC. The Consultant shall remain the Engineer of Record

(EOR) and retain full professional responsibility for the Construction Documents.

3. The Consultant shall prepare detailed construction drawings and technical specifications for the

Regional Biosolids Drying Facility. The Consultant’s design shall include cake receiving and storage systems with truck unloading areas, live-bottom hoppers, silos, and conveyance equipment sized for continuous and reliable feed to the drying system. The thermal-drying process designed by the

Consultant shall consist of multiple belt-dryer trains with N+1 redundancy, incorporating cake-feeding and back-mixing systems, heating and condensing units, pelletizers, and automated process controls to achieve Class AA biosolids. The Consultant’s design for product handling and storage shall include dried-product conveyance, storage silos, truck loadout facilities, and odor and air-pollution control systems.

4. The Consultant’s design for supporting infrastructure shall include new electrical service, natural-gas supply, reclaimed and potable water connections, process and condensate piping, cooling towers, heat exchangers, fire-protection and safety systems, HVAC, lighting, stormwater management, and an integrated Supervisory Control and Data Acquisition (SCADA) system for process monitoring and control.

5. The Consultant shall also design a thermal dryer building to house the dryer room, electrical and control rooms, operations area with laboratory, maintenance and storage areas, offices, and locker facilities. Site development shall include grading, access roads, parking, lighting, restoration of affected areas. The Consultant’s design shall provide flexibility for future expansion and integration with advanced thermal-treatment technologies regulatorily driven requirements such as for PFAS destruction.

6. The Consultant’s design shall also incorporate the relocation of the existing septage receiving system and associated pump station and infrastructure. The Consultant shall also accommodate connection of the gravity sewer serving NW 32nd Street and tie in for the Fire Station in the design.

7. Services will be executed in planned phases with amendments for subsequent stages, including

Phase III – Engineering Services During Construction. The detailed Scope of Services will be proposed by the selected Consultant, negotiated with the County, and subject to final County approval.

C. Scope of Services

The Consultant’s Services shall include, but not be limited to, the following phases and tasks. A separatee Notice to Proceed will be issued by WWS for each phase.

1. Phase I Services – Preliminary Engineering

1.1 The Consultant shall prepare for and participate in a Project kick-off meeting with WWS within fourteen (14) calendar days of the Notice to Proceed effective date, at a time convenient to the

Contract Administrator. The meeting agenda shall include, but not be limited to, establishing contacts for each major Project component, reviewing the objectives of the Project, identifying available data and reports, discussing preliminary design criteria and preferences, reviewing sludge quality and characteristics, and discussing equipment preferences and scheduling approach. The Consultant shall prepare the minutes for the kick-off meeting, which shall be subject to review and approval by Contract Administrator.

1.2 The Consultant shall prepare the BODR for the Regional Biosolids Drying Facility. The

Consultant’s activities shall include, but not be limited to, field investigation and survey of existing site conditions, sludge quality analysis, confirmation of preliminary design criteria, and preparation of schematic layouts, construction sequencing, and phasing recommendations. The

BODR shall, at a minimum, include the following items:

a. Discussion outlining design criteria and parameters for each major component of the

Project. The discussion shall include applicable design standards and building codes, design loads, materials and equipment descriptions, existing site conditions, constructability, and preliminary structural layouts.

b. Recommendations for relocating and expanding the septage receiving system, including preliminary demolition plans for existing structures and new facility layout.

c. Results of the sludge quality analysis and recommendations for specified sludge characteristics and design criteria of the dryer system.

d. Design capacity and maximum capacity of the thermal dryer facility, including solids, water, and energy mass balances for the new facility.

e. Preliminary site plans showing the relocated septage receiving system, cake receiving and storage facility, dryer building, future location of advanced thermal-treatment technologies for regulatorily driven requirements such as PFAS, truck scales, product storage, parking areas, roadways and traffic patterns, utilities, odor control facilities, and stormwater management.

f. Preliminary design of the cake receiving and storage facility, including live-bottom hoppers, silos, and conveyance systems.

g. Preliminary design of the new thermal drying building, including space allocation for dryer room, electrical and control rooms, laboratory, offices, maintenance, and locker areas.

h. Preliminary design of the belt-drying system, including but not limited to cake-feeding systems, belt-dryer trains with redundancy, heating system, off-gas and condensing system, pelletizer, and odor control system.

i. Preliminary design of on-site piping to connect potable water, reclaimed water, natural gas, and wastewater to the dryer building.

j. Evaluation and recommendations regarding the main power supply, emergency generators, switchgear.

k. Evaluation of alternative power and fuel sources for the thermal dryer building.

l. Identification of a Supervisory Control and Data Acquisition (SCADA) system and strategy required to monitor and manage plant operations, with recommendations for major system components, redundancy, and software integration.

m. Discussion of construction and operational permitting and regulatory requirements for the

Project, including but not limited to air permitting and Class AA biosolids regulations

n. A technical memorandum outlining a PFAS mitigation plan. The plan should include addressing PFAS at the source, PFAS reduction strategies, PFAS encapsulation strategies, and available PFAS destruction strategies and technologies.

o. Preliminary design of the facility to accommodate future expansion and integration of potential PFAS thermal-treatment technologies, which may include, but are not limited to, a separate building with advanced thermal treatment systems, controls, utilities, and emissions-control equipment.

p. Evaluation of different belt dryer manufacturers and recommendation on procurement strategy and delivery schedule for the dryer equipment.

q. Preliminary market assessment for the dried biosolids product and definition of final product constraints for specific end-use alternatives.

r. Methods to minimize nuisance odors from truck traffic, cake receiving, and dryer operations.

s. Implementation plan for design, procurement, and construction, including recommendations for phasing, construction packaging strategy to support procurement by the MGC, and sequencing to maintain continuous operations.

t. Evaluation and recommendations for project funding and financing options.

u. Technical assistance as the County develops agreements with the RBS Work Group members.

v. Discussion of restoration requirements for all areas disturbed by construction.

w. Preliminary opinion of Class 3 probable construction cost for the Project, including major equipment, utilities, and site development.

x. Preliminary Project schedule covering design, permitting, procurement, construction, and startup milestones.

The Consultant shall provide all required submittals necessary to support the Project, consistent with County standards and as further defined in the Consultant’s Scope of

Services.

2. Phase II Services – Engineering Design

Services provided by the Consultant shall include, but not be limited to, the following:

2.1 Final Design

a. Prepare final design and Construction Documents based on the results of the approved

BODR.

b. Submit design and Construction Documents following the typical 30% / 60% / 90% design development milestones and 100% Issued for Construction (IFC) documents for all required disciplines, incorporating County and MGC review and comment.

c. Prepare procurement documents for belt dryer system and long lead equipment items and provide technical support to the MGC during construction package procurement and selection coordination.

d. Prepare final Construction Documents to support development of the Guaranteed

Maximum Price (GMP) and construction procurement by the MGC, incorporating review comments received from WWS and revisions resulting from constructability reviews, value engineering coordination, and cost reconciliation efforts.

e. County shall review deliverable(s), complete all County comments, and meet with Consultant to discuss comments within thirty (30) days of Consultant's delivery of the deliverable(s) to

County. Contract Administrator may extend the time for County to provide comments beyond thirty (30) days.

2.2 Permitting

a. Prepare and submit permit applications as required for the Project.

b. Obtain all permits necessary for construction and operation of the Regional Biosolids

Drying Facility.

c. Coordinate with all applicable environmental and regulatory agencies.

2.3 GMP Development and Procurement Support:

a. Assist WWS and the MGC during development of the GMP, including participation in constructability reviews, reconciliation of cost estimates, review of construction package scope alignment with the Construction Documents, and clarification of technical requirements as needed.

b. Provide technical support to the MGC during construction package procurement activities, including review of scope packages for consistency with the Construction Documents and responses to technical inquiries.

2.4 Contract Documents

a. Prepare complete Construction Documents, including technical specifications.

Construction Documents shall incorporate revisions resulting from constructability reviews and GMP development coordination with MGC.

b. Prepare Construction Documents in accordance with County requirements. Consultant shall provide all required submittals necessary to support the project, consistent with

County standards and as further defined in the Consultant’s Scope of Services.

2.5 Optional Additional Services

a. As directed by the Contract Administrator through Work Authorizations related to final design, permitting, Construction Documents, and GMP development/procurement support.

3. Phase III Services - Engineering Services During Construction

3.1 The Consultant shall provide Engineering Services During Construction (ESDC), including technical review and observations of the work for general conformance with the design intent, and coordination with WWS and Contractor. Construction means, methods, sequencing, site safety, and schedule control shall remain the responsibility of the MGC. Services shall include, but are not limited to, the following:

a. Assist the Contractor with permit compliance and coordination.

b. Observe, inspect, monitor, and document construction activities for general conformance with the Construction Documents, and verify that required testing and regulatory inspections are performed in accordance with applicable permits. Prepare written site visits reports documenting observations during periodic field visits and provide project certifications as required.

c. Serve as a liaison between the Contractor and WWS to facilitate daily coordination and communication.

d. Participate in and document technical aspects of pre-construction, progress, and coordination meetings. Prepare and distribute meeting minutes.

e. Attend meetings with stakeholders, subcontractors, and regulatory agencies as required.

f. Maintain complete engineering and construction administration records, including correspondence, reports, and meeting records.

g. Review, track, and process Contractor submittals such as Requests for Services (RFS), Requests for Information (RFI), shop drawings, product data, health and safety plans, quality control plans, warranties, operation and maintenance manuals, and testing protocols, etc., required by the Construction Documents.

h. Interpret and clarify Construction Documents as necessary to resolve questions or discrepancies. Notify the Contract Administrator of significant discrepancies, omissions, substitutions, or deficiencies in the Contractor’s work and document the corrective actions required.

i. Provide technical evaluation and written recommendations regarding change order proposals, and supporting documentation submitted by the MGC. Final approval, negotiation, and contractual execution of change order shall remain the responsibility of the County.

j. Review the MGC’s Baseline Schedule and provide comments to WWS regarding impacts to design coordination and project milestones. Facilitate review meetings, and coordinate approval with project stakeholders.

k. Review and approve Contractor's monthly schedule updates, using industry standards software analysis tools. Prepare monthly reports documenting changes in the schedule, construction sequence changes, identify delays, compare actual progress versus planned progress, evaluate critical path, etc. Such a report shall serve to evaluate time extension request by Contractor, delay responsibilities, claims and provide feedback on areas of opportunities to maintain the project progressing as planned and document on a monthly basis the project overall performance. It is expected that based on this report, the Consultant will review and determine if Contractor's monthly schedule update is acceptable based on the

Contract requirements. The Consultant shall provide for every schedule submitted by the

Contractor a written response including the evaluation of such schedule. The Consultant shall lead meetings and prepare minutes as necessary to discuss the monthly schedule updates with Contractor and Project Stakeholders.

l. Review and approve Contractor’s Schedule of Values.

m. Monitor construction progress and budget through review of reports and coordination meetings.

Notify WWS immediately if schedule or cost deviations are anticipated.

n. Review and approve Contractor’s As-Built drawings on a monthly basis.

o. Track, monitor, evaluate, provide recommendations for any Claims submitted by Contractor and provide technical evaluation and recommendations to WWS. Final contractual determinations and formal responses to claims shall be issued by WWS. The Consultant shall coordinate all technical responses with WWS.

p. Manage, support and facilitate the coordination of the startup and commissioning activities with

WWS as well as the Consultant's Engineer of Record (EOR)/representative witness.

EOR/representative shall witness the commissioning activities and sign off as accepted.

q. Assist Contractor as needed during startup and commissioning activities.

r. Provide technical assistance during startup and commissioning, including troubleshooting and resolution during the initial six (6) months of operation, extendable at WWS’ request.

s. Develop a detailed training program and schedule for WWS operations staff that consolidates the training provided by all major equipment manufacturers training programs.

t. The Consultant will update the market assessment prepared in Phase 1.

u. Conduct and document material inspections. Maintain a log of spare parts and materials provided by the Contractor and coordinate turnover to WWS.

v. Evaluate Contractor's request of Substantial Completion and determine if Substantial

Completion is achieved. Perform field inspections as necessary and prepare Punch List.

Prepare the Certificate of Substantial Completion and a Punch List. Provide a complete turnover package based on the documentation provided by Contractor including all documentation as required per the Construction Contract for Substantial Completion. Turnover packages shall be prepared for the County to assume responsibility of substantially completed work and have beneficial use.

w. Provide additional field inspections as necessary to verify Punch List completion and determine

Final Completion. Responsible for making sure that all Contract requirements are completed for Final Completion and review and process Contractor's final pay request.

x. Complete final certification and permit closeout documentation.

y. Prepare record drawings in accordance with WWS Minimum Drawing Requirements and applicable project permits.

z. Conduct a post-construction claims review and provide recommendations for resolution and process improvement.

3.2 Optional Additional Services

Provide additional engineering services during construction as may be directed by the County through Work Authorizations, including extended commissioning assistance, supplemental field inspections, or preparation of specialized technical analyses and reports.

D. Time for Performance

The anticipated timeline for the various phases of the Project are as follows. Phases may overlap and the timeframes may adjust to reflect the Consultant’s recommendations to meet the deadline.

Phase I Preliminary Engineering: 6 months

Phase II Design and Permitting: 12 months

Phase II GMP Development and Procurement Support: 6 months

Phase Ill Engineering Services During Construction: 24 months

The Construction Manager at Risk (MGC) will be procured under a separate solicitation and is anticipated to be engaged during Phase II, with participation beginning after the 30% design milestone.