This document is an Amendment No. 3 to Agreement No. 18B01 between the Florida Department of Environmental Protection (DEP) and Broward County for the Broward County Shore Protection Project - Segment II. The project is located between Department of Environmental Protection moments R36 to R41.3 and R51 to R72 along the Atlantic Ocean in Broward County, Florida. Initially restored in 1970 and expanded through subsequent nourishments, the project involves construction and post-construction monitoring of shore protection and erosion control structures. The amendment extends the agreement for a 12-month period from July 2, 2023, to July 1, 2024, and replaces previous attachments with a Third Revised Grant Work Plan.
The total project costs are estimated at $8,502,876.35, with a state cost share of 40.72%. The project is divided into two primary tasks: Construction ($8,059,664.35) and Monitoring ($443,212.00). Funding sources include federal, state (DEP), and local contributions, with the federal estimated project costs at $1,554,605.00, DEP contribution at $1,473,571.00, and local contribution at $2,145,218.29. The project timeline indicates both construction and monitoring tasks beginning on 12/01/2015 with a deliverable due date of 02/01/2024. The local sponsor will be responsible for auditing travel reimbursement expenses and providing detailed scopes of work, cost estimates, and progress reports to the DEP Project Manager.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ORCP Additional Signatures
DEP Grant Manager
DEP QC Reviewer
Local Sponsor may add additional signatures if needed below.
File details come from the government source that posted it. Updated .