18157 Addendum No. 5.pdf

PDF 362 KB Posted

Attached to
761/18157. SAR Hoskins Manufacturing Site
Solicitation number
RFQ 171 200000000224 6
Issued by
Oscoda County, Mio CDP, Michigan

About this file

This is Construction Bid Addendum No. 5 issued by the Department of Technology, Management and Budget, State Facilities Administration Design and Construction Division on behalf of the Department of Environment, Great Lakes, and Energy for the Hoskins Manufacturing Site remediation project located at 830 East Kittle Road, Mio, Michigan. The project involves surveying, tree clearing for equipment access, installation of temporary power infrastructure, drilling and extraction well installation (ten wells total, with two flush-mounted wells EW-9 and EW-10 equipped with submersible pumps), well development and water management, pump installation, and soil flushing system construction, operation, and decommissioning. The addendum addresses questions and answers from bidders regarding contract clarifications, material specifications, sequencing, and permit requirements. The original bid opening date was April 15, 2020, at 2:00 pm local time, with addendum issuance on April 27, 2020, and a revised bid due date of April 29, 2020. The contract duration was revised from 730 days to 365 days from Notice-to-Proceed. Site examination can be arranged by contacting Clara Austin at AECOM, 616-481-0125.

Bidders must submit bids electronically through the SIGMA VSS website and must acknowledge receipt of all addenda on the bid summary form. A performance bond and payment bond are required for all bids exceeding $50,000.00, and each bid must be accompanied by a five percent bid guarantee. Key clarifications in the addendum address the cash allowance for power grid installation, soil flushing preparation sequencing, wellhead completion specifications, inclusion of submersible pump and equipment costs in the bid schedule, material specifications for riser pipes, contractor ownership of equipment upon decommissioning, SESC permit requirements, payment request procedures for the $940,000 cash allowance for injectate purchases, groundwater discharge permit exemptions, and surface restoration as a lump-sum item. The project includes funding from the State of Michigan with a funding code of 454625. Bidders are required to certify Qualified Disabled Veteran and Michigan-Based Business status.

View the file

Other files

File Type Posted
Addendum No. 4.pdf PDF
18157 Advertisment Revised.doc DOC document
Addendum No. 2.pdf PDF
18157 DCSpec_Rev_03-12-2020.pdf PDF
Addendum 3 18157.pdf PDF
Hoskins_Addendum No. 1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 RFP (Rev 6/16)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

CONSTRUCTION BID ADDENDUM NO. 5

This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals. Addenda will be numbered by the Project Director and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL BIDDERS

DATE ISSUED

4/27/2020

PROJECT NAME

Hoskins Manufacturing Site

FILE NUMBER

761/18157.SAR

PROJECT DIRECTOR

Sadi Rayyan, PE

BID OPENING DUE DATE:

4/29/2020

ADDENDUM ITEMS:

Questions and Answers:

Q1 Addendum #4 – Q&A #3: A new BID SUMMARY form is necessary showing: 1. the CONTRACT

TIME(S) revised from 730 Days from Notice‐to‐Proceed (duration or deadline) to 365 Days from Notice‐to‐Proceed (duration or deadline); and, 2. Providing for Bidder acknowledgement of receipt of more than 3 Addenda..

A1 The bid summary form has been revised and attached to this addendum.

Q2 Addendum #4 – Q&A #2: Clarify what costs are allowed under the ‘Cash Allowance for Installation of

Power Grid’? For example, a certified electrician will be required to obtain the electrical permit, install the power pole(s), meter socket(s), circuit breaker panel(s), terminations to temporary mobile office trailer, etc. Is the cost for a certified electrician, permit and materials included under the Cash Allowance? If no, then is the cost for certified electrician and ancillary costs to be included under lump sum Item 3 – Site Preparation? For general information, attached are some additional photos of the existing power line and power.

A2 We recognize the cost for the power to extend service is unknown; hence the cash allowance. Cost to complete the drop and equipment, and hire an electrician can be within the cash allowance or a separate line item if necessary.

Q3 Addendum #4 – Q&A #19:

SECTION 01015 RECOMMENDED CONSTRUCTION SEQUENCE

1. This recommended construction sequence is provided solely to assist the CONTRACTOR in setting up his operations. The CONTRACTOR shall submit to the OWNER and PROFESSIONAL a proposed schedule showing completion dates for various segments of the Work. It is anticipated that the remedial action construction and operation activities will be performed in stages.

The general work shall include, but not be limited to, the following:

1.1 Pre-construction design and development activities:

1.2 Construction activities:

(a) Mobilize equipment, personnel, and construction facilities (including construction trailer and sanitary facilities, as needed).

Delineate exclusion and decontamination zones and install and maintain appropriate warning and access controls.

http://www.michigan.gov/SIGMAVSS

(b) Conduct site clearing to establish access for drilling rigs and trailer-mounted pumping equipment to the proposed extraction well locations (EW-1 through EW-8).

(c) Remove asphalt and concrete from Soil Flushing Area B.

(d) Install Extraction wells

a. Install and develop EW-9 and EW-10. See Section 02935 for directions on IDW procedures.

b. Install and develop wells EW-1 through EW-8.

(e) Install Soil Flushing System

Based on the Answer to Question #19, A#19: The Western most injection points labeled as “Soil Flushing Prep” on Figure 5 will be completed prior to construction the soil flushing system, it appears that these injection points will be installed after installation of EW‐9 and EW‐10 and prior to installation of the Soil Flushing System. Is this assumption correct? If yes, approximately how long will it take for completion of the “Soil Flushing Prep” work performed by others? Also relevant is that the project specifications require a minimum of 5 days between installation of an extraction well and the development of an extraction well.

A3 The injection work will begin after installation and development of one of the two extraction wells.

We’re assuming the injection work done by others will be completed approximately two weeks after well installation.

Q4 There appears to be a discrepancy in the Project Specifications about completion of wellheads:

SECTION 01010 SUMMARY OF WORK

General

1.1. DESCRIPTION OF WORK

(a)…… extraction wells installation (one flush-mounted well and nine (9) wells with “stickups” with protective casings and lockable covers);………..

2.7 WELLHEAD

B. The EW-9 and EW-10 wellheads shall be completed as a flush-mounted well with 3 X 3 concrete pad. Separately supply an electrical service box to connect the pump to a temporary source of electrical power. Submit profile and plan-view drawings of the EW-9 and EW-10 well heads showing the proposed pump and electrical and plumbing connections

3.5 WELLHEAD COMPLETION

A. EW-9 and EW-10 shall be situated on a 6-inch thick, well compacted layer of Coarse Aggregate Fill, and be installed so that the completed concrete pad is approximately 2 inches above the surrounding ground surface.

A4 We acknowledge there will be two flush mounted wells (EW-9 and EW-10).

Q5 Base Bid Item No. 6 is a Unit Pay Item having Bid Quantity of 10. However, 2 of the 10 Extraction

Wells will have submersible pumps, riser pipes, electrical connections materials, etc. Given this, the 2 Extraction Wells (9 & 10) do not equally fit with the other 8 Per Well units. Measurement and Payment for Item 6 does not clearly mention inclusion of pumps and ancillary materials. Clarify where to include the cost of the submersible pumps, riser pipes, electrical, etc. for base bids and the eventual Schedule of Values? Suggestion, include the costs for the non‐unit costs in Lump Sum Base Bid Item No. 8 Installation of Soil Flushing System.

A5 The bidders can include cost as they deem appropriate. Be sure to explain where the costs are distributed in the bid.

Q6 Addendum #4 – Q & A #11: Clarify what type(s) of material is required or acceptable for the riser pipes from the submersible pumps to the SCH80 PVC Main?

A6 For this installation, the Trade Contractor should be able to use the conventional aircraft cable to hang the pump (as prescribed by the manufacturer). For this temporary installation, we should be able to run 2‐inch braided (reinforce) hose from the pump to the ground surface.

Q7 Addendum #4 – Q & A #13, Q & A #26 and Base Bid Item No. 16 – Decommissioning: Measurement and Payment provides overall requirement. There is no Division specific to Decommissioning. Some other Divisions provide some information about Decommissioning. Clarify if the Trade Contractor will have ownership of the metering pumps, submersible pumps, electrical appurtenances, riser pipes, flush‐mount covers, etc. upon Decommissioning?

A7 The Trade Contractor will have ownership of this equipment upon decommissioning.

Q8 During the mandatory virtual pre‐bid meeting it was stated that the requirement for SESC permit(s) would be clarified in Addendum. Addendum #4 does not address SESC permit(s) requirements and needs to be clarified.

A8 It is not anticipated that the Trade Contractor will need a SESC permit for the private land but the

Trade Contractor should check with the county to see what their requirements are for SESC.

Q9 Because the CASH Allowance for purchase of injectate is a high amount of $940,000, and some or all vendors will limit the payment period in a Purchase Order, clarify when the Trade Contractor will be allowed to submit Payment Request for the cost of the injectates?

A9 Multiple payment requests can be submitted as material is purchased.

Q10 Addendum #4 – Q&A #23, provide written confirmation of the exemption (and/or cite the specific exemption in the Rule(s)) from a Groundwater Discharge Permit (or equivalent) for the injection project.

A10 We presented to and have approval from EGLE InSRT committee to discharge amended groundwater via the injection and soil flushing program.

Q11 Addendum #4, Q&A #30, because the estimated quantity of topsoil is large, we suggest that the topsoil be a unit price pay item, separate from the rest of the surface restoration.

A11 This item will remain lump sum.

Q12 Over many years, many State of Michigan projects have been delayed because of utility companies.

Because it appears that time is of the essence for this project, and the Trade Contractor is not allowed to perform any work on the project until the Notice to Proceed is issued, we suggest that the State of Michigan or AECOM consider contracting directly with the electrical utility to get the project on the utility companies schedule ASAP. The electrical utility company will not schedule work until they have a Contract and are paid in full. Then they will schedule the work to be completed within 18 business days. However, due to all of the delays caused by Covid‐19, utility companies will prioritize projects. For example, I have been notified by Consumers Energy that they are only performing “emergency” work during the Stay‐Home Order.

A12 This is a concern. The Professional will be looking into the timing of this.

END OF QUESTIONS

APPROVED BY: Sadi Rayyan, Project Director DATE: 4/27/2020

Bidding and Contract Document (R 11/19) Project Name: Hoskins Manufacturing Site File No. 761/18157.SAR

DTMB-0401D (R 05/19)

BID SUMMARY

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

STATE FACILITIES ADMINISTRATION

DESIGN AND CONSTRUCTION DIVISION

3111 W. St. Joseph Street Lansing, Michigan 48917

Bids must be submitted electronically through the SIGMA VSS website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService

FILE NUMBER

761/18157.SAR

FUNDING CODE

454625

DEPARTMENT/AGENCY

Department of Environment, Great Lakes, and Energy

CONTRACT TIME(S)

365 Days from Notice-to-Proceed (duration or deadline)

PROJECT NAME

Hoskins Manufacturing Site

LOCATION

830 East Kittle Road, Mio, Michigan 48647

BID OPENING DATE

April 15, 2020 at 2:00 pm Local Time

FOR AN EXAMINATION OF THE SITE CONTACT:

Clara Austin, AECOM, 616-481-0125

SEE SECTION 00100 INSTRUCTIONS TO BIDDERS AND SECTION 00700 GENERAL CONDITIONS PROVIDED WITH THE BIDDING DOCUMENTS.

BID: WE PROPOSE TO FURNISH, PERFORM AND COMPLETE THE ENTIRE WORK IN ACCORDANCE WITH THE CONTRACT DOCUMENTS

IN CONSIDERATION OF THE BID PRICE (S) STATED BELOW.

FIRM NAME AND COMPLETE ADDRESS TELEPHONE NUMBER and E-MAIL ADDRESS

□ Qualified Disabled Veteran

FEDERAL I.D. NUMBER (LAST 4 ONLY)

(protected information required for processing payments)

BIDDER'S SIGNATURE AND TITLE DATE

a)

ITNESS' SIGNATURE DATE

By signing this bid above, bidder certifies their enclosed Qualified Disabled Veteran and Michigan-Based Business Certifications.

BASE BID FROM BID SCHEDULE (Include specified Allowances):

____________________________________________________________________________Dollars $____________________ (use words) (in figures)

Alternate1: (Add/Subtract) ______________________________________________________ Dollars $ ____________________ (use words) (in figures)

Alternate 2: (Add/Subtract) ______________________________________________________Dollars $ ____________________ (use words) (in figures)

Builder’s Risk Insurance is NOT provided by the State of Michigan.

A PERFORMANCE BOND AND A PAYMENT BOND ARE REQUIRED FOR ALL BIDS OVER $50,000.00. EACH BID MUST BE ACCOMPANIED BY A

FIVE (5) PERCENT BID GUARANTEE.

BIDDERS ARE ALSO CAUTIONED TO FAMILIARIZE THEMSELVES WITH ALL OF THE OTHER CONDITIONS OF THE CONTRACT.

Project Scope of Work: Primary project activities include: surveying; tree clearing to provide temporary access for drilling and pumping equipment, installation of a temporary power drop for operation of pumps and other equipment, drilling, extraction well installation, well development and water management, pump installation, and soil flushing system construction, operation and decommissioning at the Hoskins Manufacturing site in Mio, Michigan. These activities will be conducted in parallel and complementary to groundwater remediation being implemented by others. The primary project activities related to the work is outlined in the bid schedule below and detailed in the Scope of Work in Section 01010 of these specifications.

The Bidder must figure its Base Bid on the specified, or Addendum-approved, materials and equipment only. No “or equal” or substitution proposals will be permitted after Bid opening, except as provided in the General Conditions.

Addenda: Bidder acknowledges receipt of Addenda: No. ___ dated: ________, No. ___ dated: ________ No. ___ dated: ________ No. ____ dated: ________, No. ____ dated:__________