18-064; Repump Station No. 8310 Upgrades and Improvements - Technical Specifications.pdf
PDF 16 MB Posted
- Solicitation number
- IFB 720 WUD 18-064 5
- Issued by
- Palm Beach County, Florida
About this file
Summary
This document is a Technical Specifications package for Palm Beach County Water Utilities Department (PBCWUD) for Repump Station No. 8310 Upgrades and Improvements (WUD 18-064), prepared by Mathews Consulting and Baxter & Woodman, Inc. The project involves the demolition of an existing re-pump pumping station and construction of a new replacement facility, including auger cast pile supported concrete equipment pads, a pole barn, retaining wall, mechanical and electrical equipment, and site improvements. The scope includes furnishing and installation of a new Programmable Logic Controller (PLC) based Remote Telemetry Unit (RTU) with antenna tower structures, redundant suction and discharge pressure transmitters, relocation of existing flow meters, installation of instrumentation surge suppressors, and comprehensive control system integration. The project requires the contractor to coordinate with the County's programmer for PLC programming and provide as-built documentation in International Society of Automation (ISA) standard format. The specifications detail requirements across 47 specification divisions covering concrete, metals, electrical systems, protective coatings, and instrumentation components necessary for a complete, operable booster pumping system.
Payment for the project is structured as a lump-sum contract with unit prices for various pay items as detailed in the Schedule of Values and Measurement and Payment sections. The contractor must provide detailed cost breakdowns for mobilization (not to exceed 8 percent of total contract price), NPDES permit compliance, trench safety measures, dewatering operations, site work, demolition, mechanical/structural/electrical/instrumentation improvements, protective coatings, and as-built record drawings. The contract includes multiple allowances totaling approximately $100,000 for site work, utility relocation, permit fees, and miscellaneous instrumentation changes. The contractor is responsible for all labor, materials, equipment, permits (City of South Bay Building Permit, South Florida Water Management District Dewatering Permit), testing services, temporary facilities, site restoration, and closeout documentation. Work must be performed while the existing pumping station remains operational with no interruption to Belle Glade Wastewater Treatment Plant flow, with site access limited to 6:00 a.m. to 8:00 p.m. and maximum outage duration of 2 hours unless bypass pumping is provided. The project requires extensive coordination with PBCWUD personnel, submission of detailed construction schedules using Primavera P6 software, comprehensive submittal procedures including shop drawings and technical manuals, and a one-year warranty period commencing upon substantial completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PALM BEACH COUNTY
WATER UTILITIES DEPARTMENT
REPUMP STATION NO. 8310
UPGRADES AND IMPROVEMENTS
WUD 18-064
BID SET TECHNICAL SPECIFICATIONS
MARCH 2021
Baxter & Woodman, Inc.
Illinois
815.459.1260
Wisconsin 262.763.7834
Florida
561.655.6175
PBCWUD
WUD 18-064
REPUMP STATION NO. 8310 UPGRADES AND IMPROVEMENTS
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 – General Requirements
01 11 00 Summary of Work 01 14 00 Work Restrictions 01 14 13 Access To Site 01 20 00 Price and Payment Procedures 01 21 00 Allowances 01 25 13 Product Substitution Procedures 01 26 63 Change Orders 01 29 00 Measurement and Payment 01 29 73 Schedule Of Values 01 31 13 Project Coordination 01 32 16 Construction Progress Schedule 01 32 36 Video Monitoring and Documentation 01 33 00 Submittal Procedures 01 35 13 Special Project Procedures 01 35 29 Health, Safety, and Emergency Response Procedures 01 35 53 Security Procedures 01 42 13 Abbreviations and Acronyms 01 42 19 Reference Standards 01 45 00 Quality Control 01 45 29 Testing Laboratory Services 01 52 13.13 Storage Sheds 01 55 26 Traffic Control 01 57 00 Temporary Controls 01 57 13 Temporary Erosion and Sediment Control 01 60 00 Product Requirements 01 66 00 Product Storage and Handling Requirements 01 71 13 Mobilization 01 71 23 Field Engineering 01 73 29 Cutting and Patching 01 74 30.13 Pressure Pipe Testing 01 75 00 Starting and Adjusting 01 76 10 Protection of Existing Facilities 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 79 00 Owner Staff Training
DIVISION 02 – Existing Conditions
02 00 00 Existing Conditions 02 30 00 Subsurface Investigation 02 41 00 Demolition 02 41 13.23 Utility Line Removal
DIVISION 03 - Concrete
03 00 00 Concrete 03 11 00 Concrete Forming 03 15 16 Concrete Construction Joints 03 20 00 Concrete Reinforcing 03 30 00 Cast-In-Place Concrete 03 60 00 Grouting
DIVISION 05 – Metals
05 50 00 Metal Fabrications 05 50 59 Premanufactured Booster Pump Skid
DIVISION 07 – Thermal and Moisture Protection
07 90 00 Joint Protection
DIVISION 09 – Finishes
09 96 00 Protective Coatings
DIVISION 26 – Electrical
26 00 00 Electrical Work, General 26 05 19 Low Voltage Electrical Power Conductors and Cables 26 05 23 Control-Voltage Electrical Power Cables 26 05 26 Grounding 26 05 33 Raceways and Boxes for Electrical Systems 26 05 43 Underground Ducts and Raceways for Electrical Systems 26 05 44 Sleeves and Sleeve Seals for Electrical Raceways and Cabling 26 05 53 Identification for Electrical Systems 26 09 23 Lighting Control Devices 26 24 16 Panelboards 26 27 26 Wiring Devices 26 18 16 Enclosure Switches and Circuit Breakers 26 32 13 Emergency Standby Engine-Generator Systems 26 36 23 Automatic Transfer Switches 26 41 16 Lightning Prevention and Dissipation 26 43 13 Surge Protection for Low-Voltage Electrical Power Circuits
DIVISION 31 – Earthwork
31 10 00 Site Clearing 31 11 00 Clearing and Grubbing 31 20 00 Earth Moving 31 22 13 Rough Grading 31 22 19 Finish Grading 31 23 00 Excavation and Fill 31 23 19 Dewatering 31 23 23.33 Flowable Fill 31 23 33 Trenching and Backfilling 31 25 00 Erosion and Sedimentation Controls 31 34 19 Geotextiles 31 62 16.13 Steel Sheet Piles
DIVISION 32 – Exterior Improvements
32 01 18 Pavement Repair and Resurfacing 32 10 00 Bases, Ballasts, and Paving 32 12 16 Asphalt Paving 32 16 33 Driveways 32 31 13 Chain Link Fences and Gates 32 91 13 Soil Preparation 32 92 19 Seeding
DIVISION 33 – Utilities
33 01 12 Sewer Flow Control 33 95 50 PVC Pressure Piping, Rubber Joints
DIVISION 40 – Process Interconnections
40 05 00 Piping, General 40 05 02 Piping Identification 40 05 07 Pipe Supports 40 05 19 Ductile Iron Process/Pressure Pipe 40 05 30.13 PVC Process/Pressure Pipe 40 05 93 Common Motor Requirements for Process Equipment 40 46 00 Process Corrosion Protection 40 90 00 Process Control and Instrumentation 40 97 00 Variable Frequency Drives
DIVISION 43 – Process Gas and Liquid Handling, Purification, and Storage Equipment
43 20 00 Pumps, General 43 23 05 Horizontal Close-Coupled End Suction Pumps 43 30 00 Valves General 43 30 12 Valve Actuators 43 30 16 Check Valves 43 30 18 Ball Valves 43 30 24 Plug Valves 43 30 52 Miscellaneous Valves
DIVISION 46 – Water and Wastewater Equipment
46 00 00 Equipment General Provisions
APPENDICES
Appendix 1 – Lead-Based Paint Survey and Report
Appendix 2 – Asbestos-Containing Materials Survey and Report
Appendix 3 – Photographs for Demolition, Removal, Salvage, and Relocation
DIVISION 01
GENERAL REQUIREMENTS
PBCWUD No. 18-064 SUMMARY OF WORK
02/19/2021 PAGE 01 11 00 - 1
SECTION 01 11 00 – SUMMARY OF WORK
PART 1 -- GENERAL
1.1 THE SUMMARY
A. Construct Work as described in the Contract Documents.
1. Provide the materials, equipment, and incidentals required to make the Project completely and fully operable.
2. Only the materials listed in Palm Beach County Water Utilities Department Engineering Services Division - Approved Materials and Equipment List (Latest Version) are approved for use within the PBCWUD service area, or as specified herein.
3. Provide the labor, equipment, tools, and consumable supplies required for a complete Project.
4. Provide civil, architectural, structural, mechanical, electrical, instrumentation and all other Work required for a complete and operable Project.
5. Test and place the completed Project in operation.
6. Provide the special tools, spare parts, lubricants, supplies, or other materials as indicated in Contract Documents for the operation and maintenance of the Project.
7. Arrange and coordinate with Supplier for deliveries of OWNER purchased products in accordance with construction schedule, coordinate to avoid conflict with work and conditions at the site. Unload the products at the site, and store and protect the products in accordance with the Supplier’s instructions.
a. Coordinate the delivery, unloading, moving, and placement of the PBCWUD obtained generator with PBCWUD as noted on the Drawings.
8. The WORK shall be complete, and all work, materials, and services not expressly indicated or called for in the Contract Documents which may be necessary for the complete and proper construction of the WORK in good faith shall be provided by the CONTRACTOR and coordinated with the ENGINEER as though originally so indicated, at no increase in cost to the OWNER.
9. CONTRACTOR shall comply with all applicable federal, state and local safety regulations, laws and standards, as well as any specific Palm Beach County or Water Utilities Department requirements while completing the work.
10. Except as specifically noted, the CONTRACTOR shall provide and pay for:
a. Labor, materials, and equipment.
b. Tools, equipment and machinery.
02/19/2021 PAGE 01 11 00 - 2
c. Water, electricity, and other utilities required to complete project.
d. Other facilities and services necessary for proper execution and completion of the work.
e. Permits, surveys, and testing.
1) CONTRACTOR shall pay for all permit fees including, but not limited to:
a) City of South Bay Building Permit
b) South Florida Water Management District Dewatering permit
c) NPDES permit is not required as construction site is less than 1 acre.
Reference:
https://floridadep.gov/sites/default/files/CGP%20NOI%2062- 621.300_4b_0.pdf
2) Permit fees will be reimbursed to Contractor using Allowances Section 01 21 00.
B. The CONTRACTOR and its SUBCONTRACTORS shall meet the qualification requirements as defined in the Front End (Division 00) specifications.
1.2 DESCRIPTION OF WORK
A. Work is described in general, non-inclusive terms as:
1. The demolition of an existing re-pump pumping station and abandoned building and construction of a new replacement pumping station, including auger cast pile supported concrete equipment pads, a pole barn, retaining wall, and mechanical and electrical equipment; relocation of an existing generator, portable engine drive pump, and chemical storage and feed equipment; and site grading and site improvements.
2. Furnishing and installation of new Programmable Logic Controller (PLC) based Remote Telemetry Unit (RTU), including telemetry antenna tower structures as shown in the drawings and described in the specifications.
3. Furnishing, installation, and calibration of redundant suction pressure transmitters and discharge pressure transmitter as shown in the drawings and described in the specifications.
4. Relocation of existing flow meter and transmitter complete as shown in the drawings and specifications for a complete working system in place.
5. Furnish and install instrumentation surge suppressors as indicated in the drawings and described in the specifications.
6. PLC, Local HMI and SCADA HMI programming shall be performed by the County.
The Contractor shall coordinate start-up and commissioning with County’s programmer and provide all services, site visits, loop testing and support required to start-up the modified process instrumentation and control system.
https://floridadep.gov/sites/default/files/CGP%20NOI%2062-621.300_4b_0.pdf https://floridadep.gov/sites/default/files/CGP%20NOI%2062-621.300_4b_0.pdf
02/19/2021 PAGE 01 11 00 - 3
7. Create as-built documentation for the station control system wiring, including the RTU and pump Variable Frequency Drives (VFD’s). The deliverable for this effort shall be accurate control loop diagrams in standard International Society of Automation (ISA) format. All labor and materials, including site visits, shall be provided.
1.3 CONTRACT METHOD
A. The WORK hereunder will be constructed under a Lump Sum Unit Prices contract.
1. Lump Sum Unit Prices for various Pay Items will be summed to establish a Total Base Bid Price for the project.
1.4 WORK UNDER OTHER CONTRACTS
A. The following construction work is not included in this Contract, but may impact construction scheduling, testing, and startup:
Owner Description Palm Beach County Water Utilities Department None anticipated.
City of South Bay None anticipated.
B. Obtain clarification from the OWNER in the case of a disagreement between the above list and those specified elsewhere in the Contract Documents.
C. Completion of the Work described in this Contract may impact the construction and testing of the items listed above.
1. Coordinate construction activities through the OWNER.
2. Pay claims for damages which result from the late completion of the Project or any specified Milestones.
1.5 WORK BY OTHERS
A. Interference With Work On Utilities: The CONTRACTOR shall cooperate fully with all utility forces of the OWNER or forces of other public or private agencies engaged in the relocation, altering, or otherwise rearranging of any facilities which interfere with the progress of the WORK, and shall schedule the WORK so as to minimize interference with said relocation, altering, or other rearranging of facilities.
1.6 WORK SEQUENCE
A. The CONTRACTOR's attention is directed to the fact that during the entire period of construction, no interruption in the sanitary sewage flow to the site or to the Belle Glade Wastewater Treatment Plant can be accommodated, and the CONTRACTOR shall schedule its construction operations so that no interference with the operation of the pumping system will occur during the construction period.
02/19/2021 PAGE 01 11 00 - 4
B. Access to the site is limited to the hours of 6:00 a.m. to 8:00 p.m. during the construction period.
1.7 CONTRACTOR USE OF SITE
A. The CONTRACTOR's use of the Site shall be limited to its construction operations, including on-site storage of materials, on-site fabrication facilities, and field offices.
B. The CONTRACTOR shall not use the City of South Bay Wastewater Treatment Plant site adjacent to the Construction Site for any of its construction operations.
1.8 OUTAGE PLAN AND REQUESTS
A. Unless the Contract Documents indicate otherwise, the CONTRACTOR shall not remove from service, de-energize, or modify settings for any existing operating pipelines, valves, equipment, structure, road or driveway, or any other facility without permission from the ENGINEER.
1. Outages and service connections shall be performed during the dry weather season (September 15 to June 1), unless specifically allowed by the ENGINEER to occur during the wet weather season.
2. The maximum duration of any outage shall be 2 hours, unless bypass pumping equipment and operations are provided.
3. The minimum time between outages shall be 2 hours, unless bypass pumping equipment and operations are provided.
B. Where the WORK requires modifications to existing facilities or construction of new facilities and connection of new facilities to existing facilities, the CONTRACTOR shall submit a detailed outage plan and schedule for the ENGINEER'S approval a minimum of 2 weeks in advance of the time that such outage is planned.
C. A completed System Outage Request form (blank form furnished by the ENGINEER) shall accompany each outage plan. The outage plans shall be coordinated with the construction schedule and shall meet the restrictions and conditions of the Contract Documents. The outage plan shall describe the CONTRACTOR's method for preventing bypassing of other treatment units; the length of time required to complete said operation; any necessary temporary power, controls, instrumentation or alarms required to maintain control, monitoring, and alarms for the treatment plant processes; and the manpower, plant, and equipment which the CONTRACTOR will furnish for proper operation of associated treatment units. All costs for preparing and implementing the outage plans shall be at no increase in cost to the OWNER.
D. The ENGINEER shall be notified in writing at least two weeks in advance of the required outage if the schedule for performing the work has changed or if revisions to the outage plan are required.
E. The CONTRACTOR shall provide written confirmation of the shutdown date and time 2 working days prior to the actual shutdown.
02/19/2021 PAGE 01 11 00 - 5
1.9 OWNER USE OF THE SITE AND OCCUPANCY
A. The CONTRACTOR shall cooperate and coordinate with the OWNER and ENGINEER to facilitate the OWNER's operations and to minimize interference with the CONTRACTOR's operations at the same time. In any event, the OWNER shall be allowed access to the Site during the period of construction.
B. The CONTRACTOR’s Testing of equipment and appurtenances including specified test periods, training, and startup does not constitute acceptance for operation.
C. OWNER may accept the facility for continued use after startup and testing at the option of the OWNER. If acceptance is delayed at the option of the OWNER, shut down facilities per approved Operation and Maintenance procedures.
D. The execution of bonds indicates the consent of the surety to these provisions for occupancy of the structures and use of equipment.
E. Provide an endorsement from the insurance carrier permitting occupancy of the structures and use of equipment during the remaining period of construction.
F. Conduct operations to ensure the least inconvenience to the Owner and general public.
1.10 CONSTRUCTION OF UTILITIES
A. Utility companies or their CONTRACTOR’s will provide new or enhanced utilities for this Project. Coordinate with others performing Work associated with this Project.
B. Power and Electrical Services:
1. Pay for temporary power, including but not limited to construction cost, meter connection, fees and permits.
2. CONTRACTOR may use the permanent power source in lieu of temporary power source when permanent power is available at the Site.
a. Notify ENGINEER and OWNER to use the permanent power source.
b. Arrange with the power utility and pay the charges for connections and monthly charges for use of this power.
3. Pay for the power consumed until the Project has been accepted as substantially complete, unless noted otherwise.
4. The Contractor shall furnish and install the electric meter base in accordance with the Drawings and NEC standards and requirements.
5. The utility company is to provide the electric meter and shall install and connect upon notification of completed work by the CONTRACTOR.
6. Utility pole mounted transformers to be provided and installed to the new overhead lines by the utility company.
02/19/2021 PAGE 01 11 00 - 6
7. The utility is to provide power cable from the secondary of the transformer to the weatherhead.
C. Telephone Services: Not applicable or required.
1.11 REQUIREMENTS OF OTHER AGENCIES
A. When performing Work on facilities owned by agencies other than OWNER, comply with all requirements of such agencies which are more restrictive than those specified herein.
1.12 PROTECTION OF EXISTING STRUCTURES
A. The CONTRACTOR shall assume full responsibility for the protection of all existing buildings, structures, poles, signs, services to buildings, fire hydrants, drains, ductbanks and electric and telephone cables, whether or not they are shown on the Drawings. The CONTRACTOR shall carefully support and protect all such structures and utilities from injury of any kind. Any damage resulting from the CONTRACTOR’s operations shall be repaired by the CONTRACTOR at CONTRACTOR’s expense.
B. Protection and temporary removal and replacement of existing structures as described in this Section shall be a part of the Work under the Contract and all costs in connection therewith shall be included in the Unit Price Bid prices.
PART 2 -- PRODUCTS (NOT USED)
PART 3 -- EXECUTION (NOT USED)
END OF SECTION
PBCWUD No. 18-064 WORK RESTRICTIONS
02/19/2021 PAGE 01 14 00- 1
SECTION 01 14 00– WORK RESTRICTIONS
PART 1 -- GENERAL
1.1 THE SUMMARY
A. WORK shall be scheduled, sequenced, and performed in a manner which minimizes disruption to the public and to the operation and maintenance of existing facilities.
B. The CONTRACTOR shall incorporate the construction and schedule constraints of this Section in preparing the construction schedules required under Section 01 32 16 – Construction Progress Schedule.
1.2 EXISTING PUMPING STATION
A. The WORK shall be executed while the existing pumping station is in operation. Operation of the existing pumping station shall not be jeopardized as a result of the execution of the
WORK.
B. Unless indicated otherwise, temporary pumping, piping, power, lighting, controls, instrumentation, alarms, security devices, and safety devices shall be provided by the CONTRACTOR whenever its activity or interruption due to its activity affects the existing facility.
C. The construction constraints in this Section do not include every item affecting the completion of the WORK, but are intended to describe the sequence of critical events necessary to minimize disruption to the ongoing pumping operations. It shall be understood and agreed by the CONTRACTOR that the critical events described are not inclusive and that additional items of WORK not included may be required to minimize disruption and ensure compliance. Deviation from or modification of these suggested sequences is permitted if techniques and methods known to the CONTRACTOR will result in reducing disruption to the facility operation, and if deviation is approved in advance by the ENGINEER.
1.3 OPERATION OF PUMPING STATION EQUIPMENT
A. Operational functions or shutdown of the existing pumping station required to facilitate CONTRACTOR's operation will be done by the OWNER's personnel only.
B. The OWNER’s operation and maintenance personnel will cooperate in every way practical to facilitate the CONTRACTOR's operations. However, certain shutdown and connections may only be permissible at times other than normal working hours such as nights or weekends. No additional payment will be made to the CONTRACTOR for any night, weekend, or holiday premium or overtime payments.
C. If it becomes necessary for the proper operation or maintenance of portions of the pumping station, the OWNER may require the CONTRACTOR to reschedule an approved shutdown. The CONTRACTOR shall then reschedule its operations so there shall be no conflict with necessary operations or maintenance of the facility. The CONTRACTOR shall, within 2 days, furnish the ENGINEER a revised outage request and a plan for
02/19/2021 PAGE 01 14 00- 2
rescheduling the shutdown in accordance with the requirements of the construction schedule.
1.4 BYPASSING
A. Bypassing of untreated or partially treated sewage to surface waters or drainage courses is prohibited during construction. In the event accidental bypassing is caused by the CONTRACTOR's operations, the OWNER shall immediately be entitled to employ others to stop the bypassing and costs incurred therefore will be deducted from the CONTRACTOR's construction progress payments.
1.5 OUTAGE REQUESTS
A. Modifications to existing facilities, the construction of new facilities, and the connection of new to existing facilities may require the temporary outage or bypass of existing pumping or facilities. In such cases, the CONTRACTOR shall coordinate WORK with the ENGINEER as described below. The CONTRACTOR shall submit a detailed outage plan and time schedule for construction activities which will make it necessary to remove a tank, pipeline, channel, electrical circuit, equipment, structure, road or driveway, or other facilities from service.
B. The outage plans shall be submitted to the ENGINEER for acceptance a minimum of 2 weeks in advance of the time that such outages are required. The outage plans shall be coordinated with the construction schedule and shall meet the restrictions and conditions of this Section. The outage plan shall describe the CONTRACTOR's method for bypassing of sewage; the length of time required to complete the operation; any necessary temporary power, controls, instrumentation, or alarms required to maintain control, monitoring, and alarms for the station processes; and the manpower and equipment which the CONTRACTOR shall provide to ensure proper operation of the station. Costs for preparing and implementing the outage plans shall be the responsibility of the CONTRACTOR as part of the WORK.
C. The CONTRACTOR shall not begin any alteration affecting existing facilities until specific written approval has been granted by the ENGINEER in each case.
D. The ENGINEER will coordinate the CONTRACTOR's planned procedure with the facility personnel. The ENGINEER has the authority to modify any proposed shutdown procedures if such procedures would adversely impact the pumping station operations.
E. The ENGINEER shall be notified in writing at least one week in advance of the required outage if the schedule for performing the WORK has changed or if revisions to the outage plan are required. The CONTRACTOR shall provide written confirmation of the shutdown date and time 2 days prior to the actual shutdown.
1.6 TEMPORARY CONNECTIONS
A. Making connections to existing facilities or other operations that interfere with the operation of the existing equipment shall be thoroughly planned in advance, and required equipment, materials, and labor shall be on hand at the time of undertaking the connections. WORK shall be completed as quickly as possible and with as little delay as
02/19/2021 PAGE 01 14 00- 3
possible and shall proceed continuously (24 hours a day and seven days a week) if necessary to complete modifications and/or connections in the minimum time.
B. The cost of any temporary facilities and night, weekend, or holiday activity and overtime payments required during process interruptions shall be included in the WORK.
C. Temporary facilities and piping shall be located to minimize interference with CONTRACTOR's construction facilities and OWNER's operation and maintenance of the pumping station. Unless otherwise indicated, each temporary pipeline shall be of the same size as its connection to the existing or permanent facility at the downstream end of the pipeline. Piping materials shall be suitable for the material being conveyed and be as required in the Contract Specifications.
D. When temporary electrical power, controls, instrumentation, or alarms are required for routine continuous operations of existing or new equipment, the CONTRACTOR shall provide the necessary equipment and appurtenances. Prior to installing said equipment and appurtenances, CONTRACTOR shall furnish a submittal on the proposed components and installation for ENGINEER's review and approval.
E. A plan showing the size and location of the temporary facilities and piping shall be submitted to the ENGINEER at the same time as the outage plan required under this Section. Costs for design, provision, operation, and removal of temporary facilities and piping shall be part of the WORK.
1.7 CONSTRUCTION SEQUENCING
A. Construction activities shall be scheduled and sequenced to ensure continuous operation of the existing pumping station. The CONTRACTOR's scheduling shall develop construction sequencing so that the WORK will not adversely impact continuous operation of the pumping station. The CONTRACTOR shall be responsible for development of the construction sequencing. In implementing the construction sequencing, the CONTRACTOR shall maintain the existing facilities in service until a temporary bypass facility has been installed, tested and approved for operation prior to taking the existing facilities out of service. When new facilities are operational, the temporary bypass facilities may be taken out of service. The following general guidelines shall be used by the CONTRACTOR in planning the sequence of construction.
1. Safe working conditions for personnel shall be maintained during rehabilitation, modification, and demolition WORK. The foregoing includes at least proper trench excavation, the provision of temporary equipment guards, supports, warning signs, walkways, covers over openings, handrailing, and protection of electrical equipment and power supply.
2. Temporary facilities shall be constructed in accordance with applicable codes and regulations to operate safely and properly.
3. Valves to be temporarily shut off during the WORK shall be tagged as such and shall be wired shut with a crimped lead seal and padlocked.
4. Electrical and mechanical equipment shall be similarly shut down.
02/19/2021 PAGE 01 14 00- 4
1.8 PERMITS
A. The CONTRACTOR shall abide by the conditions of permits and shall obtain proof of satisfaction of conditions from issuers of permits prior to acceptance of the WORK by the
OWNER.
B. Conditions affecting the CONTRACTOR are found in the following permits. Copies of permit conditions are attached at the end of this Section.
1. City of South Bay Building Permit
2. Florida Department of Health – Palm Beach County Permit
1.9 SEQUENCE AND SCHEDULE CONSTRAINTS
A. General: It is the CONTRACTOR's responsibility to coordinate and plan the construction activities to integrate each schedule constraint into performance of the overall WORK.
B. The listing of sequence and schedule constraints below does not mean that every constraint or special condition has been identified. The list does not substitute for the CONTRACTOR's coordination and planning for completion of the WORK within the Contract Times.
PBCWUD No. 18-064 ACCESS TO SITE
02/19/2021 PAGE 01 14 13 - 1
SECTION 01 14 13 – ACCESS TO SITE
PART 1 -- GENERAL
1.1 THE SUMMARY
A. The CONTRACTOR shall provide safe access to the project site with minimal disruption to vehicular and pedestrian traffic.
B. Related sections:
1. Section 01 11 00 – Summary of Work
2. Section 01 66 00 – Product Storage and Handling Requirements
1.2 CONTRACTOR SUBMITTALS
A. The CONTRACTOR shall submit 3 copies of a traffic control plan to the appropriate permitting entity for approval a minimum of 6 weeks prior to construction. The appropriate permitting shall be allowed access to observe these traffic control plans in use and to make any changes as field conditions warrant. Any changes required by the appropriate permitting shall supersede these plans and be done solely at the CONTRACTOR's expense.
1.3 HIGHWAY LIMITATIONS
A. The CONTRACTOR shall make its own investigation of the condition of available public and private roads and of clearances, restrictions, bridge load limits, and other limitations affecting transportation and ingress and egress to the site of the WORK. It shall be the CONTRACTOR's responsibility to construct and maintain any haul roads required for its construction operations.
1.4 TEMPORARY CROSSINGS
A. General:
1. Continuous, unobstructed, safe, and adequate pedestrian and vehicular access shall be provided to fire hydrants.
2. The CONTRACTOR shall cooperate with parties involved in the removal of trash and garbage so as to maintain existing schedules for such services.
B. Street Use:
1. Nothing herein shall be construed to entitle the CONTRACTOR to the exclusive use of any public road during the performance of the WORK hereunder, and it shall conduct its operations to not interfere unnecessarily with the authorized work of utility companies or other agencies in such roadways.
2. No street or road shall be closed to the public without first obtaining permission of the ENGINEER and proper governmental authority.
02/19/2021 PAGE 01 14 13 - 2
3. Where excavation is being performed in primary streets or highways, one lane in each direction shall be kept open to traffic at all times unless otherwise indicated.
4. Toe boards shall be provided to retain excavated material if required by the ENGINEER or the agency having jurisdiction over the street or highway.
5. Fire hydrants on or adjacent to the WORK shall be kept accessible to firefighting equipment and vehicles.
6. Temporary provisions shall be made by the CONTRACTOR to assure the use of storm drain inlets and other drainage facilities
C. Safety:
1. The CONTRACTOR shall take necessary precautions for the protection of the WORK and the safety of the public.
2. All signs, signals, and barricades shall conform to the requirements of Subpart G, Part 1926, of the OSHA Safety and Health Standards for Construction.
D. Traffic Control:
1. For the protection of traffic along public roads, the CONTRACTOR shall provide, place, and maintain necessary barricades, traffic cones, warning signs, lights, and other safety devices in accordance with the requirements of the "Manual on Uniform Traffic Control Devices," published by American Association of State Highway and Transportation Officials (AASHTO MUTCD-10) and other authorities having jurisdiction over the street or highway.
2. The CONTRACTOR shall take necessary precautions for the protection of the WORK and the safety of the public. Barricades and obstructions shall be illuminated at night, and lights shall be kept burning from sunset until sunrise.
3. The CONTRACTOR shall station such guards or flaggers and shall conform to such special safety regulations relating to traffic control as may be required by the public authorities within their respective jurisdictions.
4. Signs, signals, and barricades shall conform to the requirements of Subpart G, Part 1926, of the OSHA Safety and Health Standards for Construction.
5. The CONTRACTOR shall remove traffic control devices when no longer needed, repair damage caused by installation of the devices, and shall remove post settings and backfill the resulting holes to match grade.
E. Temporary Street Closure:
1. If closure of any street is required during construction, the CONTRACTOR shall apply in writing to the City Engineer and any other jurisdictional agencies at least 30 Days in advance of the required closure. A Detour and Traffic Control Plan shall accompany the application.
02/19/2021 PAGE 01 14 13 - 3
1.5 PARKING
A. The CONTRACTOR shall:
1. Provide temporary parking areas on PBCWUD property as follows:
2 spaces for the OWNER
1 space for the ENGINEER
2. When space on the Site is not available, the CONTRACTOR shall make 2 additional spaces available within the CONTRACTOR’s parking area for the OWNER's use.
3. The CONTRACTOR shall direct its employees to park in areas indicated on the Drawings or as requested by the ENGINEER.
4. Traffic and parking areas shall be maintained in a sound condition, free of excavated material, construction equipment, mud, and construction materials. The CONTRACTOR shall repair breaks, potholes, low areas which collect standing water, and other deficiencies.
1.6 SECURITY PROGRAM
A. The CONTRACTOR shall:
1. Protect WORK, existing premises, and the OWNER'S operations from theft, vandalism, and unauthorized entry.
2. Initiate program in coordination with OWNER'S existing security system at mobilization.
3. Maintain program throughout construction period.
1.7 ENTRY CONTROL
A. The CONTRACTOR shall:
1. Restrict entry of persons and vehicles into Site and existing facilities.
2. Allow entry only to authorized persons with proper identification.
3. Maintain log of workmen and visitors and make log available to OWNER on request.
4. Coordinate access of OWNER'S personnel to Site in coordination with OWNER'S security forces.
B. The OWNER will control the entrance of persons and vehicles to those related to the OWNER'S operations.
02/19/2021 PAGE 01 14 13 - 4
1.8 PERSONNEL IDENTIFICATION
A. The CONTRACTOR shall:
1. Provide identification card to each person authorized to enter premises.
2. Maintain a list of authorized persons and submit copy to OWNER on request.
3. Require return of cards.
B. Card shall include personal photograph, name and assigned number, expiration date, and employer.
1.9 RESTRICTIONS
A. The CONTRACTOR shall not allow cameras on site or photographs taken except by written approval of OWNER.
PBCWUD No. 18-064 PRICE AND PAYMENT PROCEDURES
02/19/2021 PAGE 01 20 00 - 1
SECTION 01 20 00 – PRICE AND PAYMENT PROCEDURES
PART 1 -- GENERAL
1.1 THE SUMMARY
A. Submit Applications for Payment to the Owner in accordance with the schedule established by the General Conditions of the Contract Documents.
B. The Contract Price is to include costs for:
1. All home office overhead costs and expenses, including profit made directly or indirectly for the Project;
2. Project management, contract administration, field office and field operations staff, including supervision, clerical support, and technology system support;
3. Professional services including design fees, legal fees, and other professional services;
4. Bonds and insurance;
5. Permits, licenses, patent fees, and royalties;
6. Taxes;
7. Providing all documentation and submittals required by the Contract Documents;
8. Facilities and equipment at the Site including:
a. Field offices, office furnishings, and all related office supplies, software, and equipment,
b. Storage facilities for CONTRACTOR’s use, storage facilities for stored materials and equipment, including spare parts storage,
c. Shops, physical plant, construction equipment, small tools, vehicles, technology, and telecommunications equipment,
d. Safety equipment and facilities to provide safe access and working conditions for workers and for others working at the Site,
e. Temporary facilities for power and communications,
f. Potable water and sanitation facilities, and
g. Mobilization and demobilization for all of these facilities and equipment;
9. Products, materials, and equipment stored at the Site or other suitable location;
10. Products, materials, and equipment permanently incorporated into the Project;
02/19/2021 PAGE 01 20 00 - 2
11. Temporary facilities for managing water and sewage, including facilities for pumping, storage, and treatment as required for construction and protection of the environment;
12. Temporary facilities for managing environmental conditions and Constituents of Concern;
13. Temporary facilities such as storage facilities, working areas, and other facilities required for construction of the Project;
14. Temporary and permanent facilities for protection of all overhead, surface, or underground structures or features;
15. Temporary and permanent facilities for removal, relocation, or replacement of any overhead, surface, or underground structures or features;
16. Products, materials, and equipment consumed during the construction of the Project;
17. CONTRACTOR labor and supervision to complete the Project, including that provided through Subcontractors or Suppliers;
18. Correcting Defective Work during the Contract Times, during the Correction Period, or as required to meet any warranty provision of the Contract Documents;
19. Risk associated with weather and environmental conditions, startup, and initial operation of facilities including equipment, processes, and systems;
20. Maintenance of facilities, including equipment, processes, and systems until operation is transferred to OWNER;
21. Providing warranties, extended or special warranties, or extended service agreements;
22. Cleanup and disposal of any and all surplus materials; and
23. Demobilization of all physical, temporary facilities not incorporated into the Project.
C. Include the cost not specifically set forth as an individual payment item but required to provide a complete and functional system in the Contract Price.
D. Submit Payment Application for completed WORK and for materials and equipment in accordance with the Contract Documents.
E. Related Sections:
1. Agreement between the OWNER and the CONTRACTOR
2. General Conditions of the Contract Documents
3. Section 01 26 63 – Change Orders
02/19/2021 PAGE 01 20 00 - 3
4. Section 01 29 00 – Measurement and Payment
5. Section 01 32 16 – Construction Progress Schedule
1.2 REFERENCE SPECIFICATIONS, CODES, AND STANDARDS
A. Section 01 29 73 – Schedule of Values
B. Section 01 77 00 – Closeout Procedures
1.3 FORMAT AND DATA REQUIRED
A. Submit applications on the form required by and provided by the OWNER, with itemized data typed on 8½ inch X 11 inch white paper continuation sheets, and Excel computer file.
B. Provide itemized data on continuation sheets:
1. Format, schedules, line items and values: Those of the Schedule of Values accepted by the OWNER, Section 01 29 73 – Schedule of Values.
1.4 CONTRACTOR SUBMITTALS
A. Submit a schedule of the anticipated Payment Applications showing the application numbers, submission dates, and the anticipated amount to be requested.
B. Update the schedule of anticipated payments as necessary to provide a reasonably accurate indication of the funds required to make payments each month to the CONTRACTOR for WORK performed.
1.5 PROCEDURES FOR SUBMITTING A PAYMENT APPLICATION
A. Submit a draft Payment Application to the OWNER at the end of the payment period as established in the Agreement. Review the draft Payment Application with the OWNER to determine concurrence with:
1. The earned value for each lump sum item including the value of properly stored and documented materials and equipment for each item in the original Contract;
2. The quantity of WORK completed for each unit price item;
3. Values requested for materials and equipment consistent with invoices for materials and equipment; and
B. Submit Payment Applications as a Working File. Do not leave any cells empty or incomplete. If information is not applicable, enter N.A. in the space provided.
1. Number each application sequentially and include the dates for the application period.
2. Show the total amounts for Earned Value of Original Contract Performed, Earned Value for Work on Approved Contract Modifications, and Net Set-offs. Show total amounts that correspond to totals indicated on the attached tabulation for each.
02/19/2021 PAGE 01 20 00 - 4
Execute the Certification with the signature of a responsible officer of the CONTRACTOR’s firm. The Certification shall state that “all WORK, including materials, covered by this Application for Payment has been completed or delivered and stored in accordance with the Contract Documents, that all amounts have been paid for WORK, materials, and equipment for which previous payment has been made by the OWNER, and that the current payment amount shown in this Payment Application is now due.”
1.6 SUBSTANTIATING DATA FOR PROGRESS PAYMENTS
A. The CONTRACTOR shall submit suitable information, with a cover letter identifying:
1. Project Name.
2. Application number, date and period of coverage.
3. Detailed list of enclosures.
4. For stored products:
a. Item number and identification as shown on the application.
b. Description of specific material.
5. Submit updated Construction Schedule.
6. Provide record drawings for piping installation within the payment period.
B. Submit one (1) copy of data with each original application.
1.7 PREPARATION OF APPLICATION FOR FINAL PAYMENT
A. Fill in Application form as specified for progress payments.
B. Use continuation sheet for presenting the final statement of accounting.
C. Final payment requires additional procedures and documentation per Section 01 77 00 Closeout Procedures.
D. The final Payment Application is to incorporate adjustments to the Contract Price including those for:
1. Adjustments of estimated quantities to actual quantities;
2. Approved Change Orders;
3. Allowances not previously adjusted by Change Order;
4. Deductions for Defective Work that has been accepted by the OWNER;
02/19/2021 PAGE 01 20 00 - 5
5. Penalties and bonuses;
6. Deductions for liquidated damages;
7. Deduction for all final Set-offs; and
8. Other adjustments if needed.
1.8 SUBMITTAL PROCEDURE
A. Submit Applications for Payment to the OWNER at the times stipulated.
B. Submit not less than three (3) originals of each Application.
C. When the OWNER finds the Application to be properly completed and correct, it will be processed for payment.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
PBCWUD No. 18-064 ALLOWANCES
02/19/2021 PAGE 01 21 00 - 1
SECTION 01 21 00 – ALLOWANCES
PART 1 -- GENERAL
1.1 THE SUMMARY
A. Include in the Contract Sum all allowances stated in the Contract Documents.
B. Designate in the Schedule of Values the amount of each Allowance approved by the
OWNER.
1.2 REFERENCE SPECIFICATIONS, CODES AND STANDARDS
A. General Conditions of the Contract Documents.
B. Section 01 20 00 – Price and Payment Procedures
C. Section 01 26 63 – Change Orders
D. Section 01 32 16 – Construction Progress Schedule
E. Section 01 32 36 – Video Monitoring and Documentation
1.3 CONTRACT ALLOWANCES
A. Include in the Contract the following lump sum allowances:
1. Site Work Allowance: Lump Sum amount not to exceed $25,000.00 net.
a. Related to OWNER/ENGINEER requested changes to excavation, regrading, paving, restoration, etc.
2. Utility Relocation Allowance: Lump Sum amount not to exceed $15,000.00.
a. Work, if required, to upgrade, reinstall, or modify the Florida Power & Light
Company electric service to the site.
3. Permit Fees Allowance: Lump Sum amount not to exceed $50,000.00.
a. Following award of the contract, CONTRACTOR shall provide a construction cost for the project exclusive of general conditions, overhead and profit, bonds, and insurance. This construction cost will be used to establish the City of South Bay Building Permit fee.
4. Miscellaneous Instrumentation and Programming Allowance: Lump Sum amount not to exceed $10,000.00.
a. Work, if required, to revise or otherwise change instrumentation and programming features as requested by the OWNER or ENGINEER.
B. Do not include any additional amounts for installation, overhead or profit in the Contract Sum. Change Orders will include such additional amounts as provided in the General Conditions of the Contract Documents.
C. The CONTRACTOR shall make arrangements for all testing services required. The costs of testing services shall be paid by the CONTRACTOR.
PBCWUD No. 18-064 ALLOWANCES
02/19/2021 PAGE 01 21 00 - 2
D. The CONTRACTOR shall pay the entire cost of all re-testing and of all additional or supplemental testing that is required or requested by the OWNER.
E. At the close-out of the Contract, monies remaining in the Allowances will be credited to the OWNER in the Final Adjusting Change Order.
1.4 ADJUSTMENT OF COSTS
A. Should the net cost be more or less than the specified amount of the Allowance, the Contract Sum will be adjusted accordingly by Change Order.
B. Submit any claims for anticipated additional costs at the site or other expenses caused by the selection under the Allowance, prior to execution of the WORK.
C. Failure to submit claims within the designated time will constitute a waiver of claims for additional costs.
D. At contract close-out, reflect all approved changes in Contract Amounts in the final statement of accounting.
PART 2 -- PRODUCTS (NOT USED)
PBCWUD No. 18-064 PRODUCT SUBSTITUTION PROCEDURES
02/19/2021 PAGE 01 25 13 - 1
SECTION 01 25 13 – PRODUCT SUBSTITUTION PROCEDURES
PART 1 -- GENERAL
1.1 THE SUMMARY
A. Section Includes:
1. Furnish and install products specified, under options and conditions for substitutions stated in this Section.
B. Related sections:
1. Section 01 60 00 – Product Requirements
2. Section 01 77 00 – Closeout Procedures
1.2 CONTRACTOR SUBMITTALS
A. Products List:
1. Within thirty days after Award of the Contract, submit to the ENGINEER five copies of a complete list of major products proposed for installation.
2. Tabulate products by Specification Section Number and Title.
3. For products specified only by reference standards, list the following information for each such product:
a. Name and address of manufacturer.
b. Trade name.
c. Model or catalog designation.
d. Manufacturer's data including reference standards and performance test data.
B. CONTRACTOR’s Options
1. For products specified only by reference standard, select products meeting that standard, by any manufacturer.
2. For products specified by naming several products or manufacturer's, select any one of those products and manufacturers named which comply with the Specifications.
3. For products specified by naming only one or more products or manufacturers and stating "or equal", submit a request as for substitutions, for any product or manufacturer which is not specifically named.
4. For those specified by naming only one product and manufacturer, there is no option and no substitution will be allowed.
02/19/2021 PAGE 01 25 13 - 2
1.3 SUBSTITUTIONS
A. Within a period of thirty days after Award of the Contract, the ENGINEER will consider formal requests from the CONTRACTOR for substitutions of products in place of those specified. The burden of proof as to the type, function, and quality of any such substitution product, material or equipment shall be on the CONTRACTOR.
1. After the end of the thirty day period, requests will be considered only in case of product unavailability or other conditions beyond the control of the CONTRACTOR.
B. Submit a separate request for each substitution. Support each request with the following:
1. Complete data substantiating compliance of the proposed substitution with the requirements stated in the Contract Documents:
a. Product identification, including manufacturer's name and address.
b. Manufacturer's literature identifying:
1) Product description.
2) Reference standards.
3) Performance and test data.
c. Samples, as applicable.
d. Name and address of a minimum of 5 similar projects on which the product has been used, the date of each installation, and contact information for a reference for those projects.
2. An itemized comparison of the proposed substitution with the product specified, listing all variations.
3. Data relating to changes in the construction schedule.
4. Any effect of the substitution on separate contracts.
5. List of changes, if any, required in other work or products.
6. Accurate cost data comparing proposed substitutions with the product specified.
7. Designation of required license fees or royalties.
8. Availability of maintenance services and sources of replacement materials.
C. Substitutions will not be considered for acceptance when:
1. They are indicated or implied on Shop Drawings or product data submittals without a formal request from the CONTRACTOR.
2. They are requested directly by a subcontractor or a supplier.
02/19/2021 PAGE 01 25 13 - 3
3. Acceptance will require substantial revisions to the Contract Documents.
4. There is added cost deemed unwarranted by the OWNER.
5. The substitution results in a time delay.
D. The ENGINEER shall evaluate each proposed substitution within a reasonable period of time.
E. The ENGINEER will record the time required by the ENGINEER in evaluating substitutions proposed by the CONTRACTOR and in making changes by the CONTRACTOR in the Contract Documents subject to the substitution.
F. Substitute products shall not be ordered or installed without written acceptance of the
ENGINEER.
G. The ENGINEER will be the sole judge as to the type, function, and quality of any such substitution and the ENGINEER’s decision shall be final.
H. The ENGINEER may require the CONTRACTOR to furnish additional data about the proposed substitution.
I. The OWNER may require the CONTRACTOR to furnish a special performance guarantee or other surety with respect to any substitution.
J. Acceptance by the ENGINEER of a substitution item proposed by the CONTRACTOR shall not relieve the CONTRACTOR of the responsibility for full compliance with the Contract Documents and for adequacy of substitution.
K. Without any increase in cost to the OWNER, the CONTRACTOR shall be responsible for and pay all costs in connection with proposed substitutions and of inspections and testing of equipment or materials submitted for review prior to the CONTRACTOR’s purchase thereof for incorporation in the WORK, whether or not the ENGINEER accepts the proposed substitution or proposed equipment, or material. The CONTRACTOR shall reimburse the OWNER for the charges of the ENGINEER for evaluating each proposed substitution.
L. The CONTRACTOR shall pay all costs of implementing accepted substitutions, including redesign and changes to WORK necessary to accommodate the substitution.
1.4 QUALITY ASSURANCE
A. Certifications
1. In making formal requests for substitutions, the CONTRACTOR certifies that:
a. CONTRACTOR has investigated the proposed product and has determined that it is equal to or superior in all respects to that specified.
b. CONTRACTOR will provide, at a minimum, the same warranties or bonds for substitute products as for the product specified unless otherwise required by paragraph 1.3.I of this specification section.
02/19/2021 PAGE 01 25 13 - 4
c. CONTRACTOR will coordinate installation of accepted substitutions into the WORK, and will make such changes required for the WORK to be…