This Addendum No. 4, issued April 11, 2019, by the Wisconsin Department of Military Affairs Construction and Facilities Office, modifies the original contract documents for the replacement of exterior doors at the Madison Aviation Armory located at 1954 Pearson Street, Madison, Wisconsin. The addendum revises the bid opening date to April 18, 2019, at 2:00 P.M. for GPC bidders and replaces Addendum 3 in its entirety. Key modifications include revisions to door demolition and new door elevation drawings (sheets A101, A201, and A202), with specific changes to window shade handling requiring existing shades to be removed and salvaged for reinstallation by the contractor after door assembly replacement. Additional notes have been added to door assemblies 122 South and 122 North for ballistic and blast requirements, and glazing specifications have been updated to include PVB interlayer requirements on specified details.
The addendum specifies technical modifications to the specifications, including the omission of Specification Section 12 24 00 regarding shades, as shades will now be salvaged rather than replaced as originally planned. All prospective bidders must acknowledge receipt of this addendum by inserting the addendum number and issue date on their bid forms, with failure to do so potentially resulting in disqualification. The revised bid submission deadline is April 18, 2019, at 2:00 P.M., and the addendum includes two attached revised drawings (A201 and A202) that form part of the contract documents.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 17G1H-BD-00-Drawings.pdf | ||
| Z-19000 Project 17G1H Doors.docx | DOCX document | |
| 17G1H-00-BD-Addendum1.pdf | ||
| 17G1H-00-BD-Specifications.pdf | ||
| 17G1H-00-BD-Addendum2.pdf | ||
| 17G1H-00-BD-Addendum3.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 4 1
ISSUE DATE: 04/11/2019 2
RE: REPLACE EXTERIOR DOORS 4
MADISON AVIATION ARMORY 5
DEPARTMENT OF MILITARY AFFAIRS 6
MADISON, WISCONSIN 7
Division Project No. 17G1H 9 REVISED BID OPENING: GPC BIDDERS: 2:00 P.M., April 18, 2019. 11 FROM: Department of Military Affairs 13
Construction and Facilities Office 14 Madison, WI 15
TO: Prospective Bidders 17 This addendum forms a part of the Contract Documents and modifies the original Contract Documents dated 19 February 15, 2019 as noted below. Acknowledge receipt of this Addendum by inserting the number and issue 20 date of this addendum in the blank space provided on the Bid Form. Failure to do so may subject the Bidder to 21 disqualification. 22 This Addendum consists of one page of text and two attached drawings: A201 and A202. 24
CHANGES TO ADDENDUM: THIS ADDENDUM 4 REPLACES ADDENDUM 3 IN ITS ENTIRETY. 26
CHANGES TO DRAWINGS: 28
1. Sheet A101A. 29
a. Revise sheet number in title block to A101. 30
2. Sheet A101 (A101A) – Door Demolition Elevations. 31
a. Details 05/A101 and 13/A101 32
i. Revise window shade note to “EXISTING SHADE TO BE REMOVED AND 33
SALVAGED FOR REINSTALLATION BY CONTRACTOR AFTER DOOR 34
ASSEMBLY REPLACEMENT”. 35
3. Sheet A201 – New Door Elevations. See revised sheet attached. 36
a. Add additional notes to detail 05/A201 and 13/A201 for door assemblies 122 South and 122 37
North for ballistic and blast requirements. Revise window shade notes to remove and replace 38 existing. 39
b. Detail 07/A201 – Revise note for window shade to remove and replace existing. 40
c. Detail 08/A201 – Append glazing note “…WITH PVB INTERLAYER”. 41
4. Sheet A202 – New Door Elevations. See revised sheet attached. 42
a. Add additional notes to detail 05/A202, 13/A202 and 21/A202 for single door assembly blast 43 requirements. 44
b. Detail 04/A202 – Revise to detail title to “DOOR JAMB DETAIL”. 45
c. Detail 13/A202 – Append glazing note “…WITH PVB INTERLAYER”. 46
CHANGES TO SPECIFICATIONS: 48
5. Advertisement for Bids – Sheet A-1. 49
a. Revise bids due date to April 18, 2019 @ 2:00 PM 50
6. Specification Section 12 24 00 – Shades. 51
a. Omit this section. Shades will be salvaged for reinstallation. 52
END OF ADDENDUM 54
Angus Young Associates Division of Facilities Development 57 555 South River Street Department of Administration 58 Janesville Wisconsin 53548 Madison Wisconsin 53707-7866 59
2 04/11/19 DMA ADDENDUM 04
2 04/11/19 DMA ADDENDUM 04
Addendum 4