17b. Server Room Final Specifications.pdf
PDF 2 MB Posted
- Attached to
- B2400 Server Room P209 Federal contract opportunity
- Solicitation number
- FA441822R0016
About this file
This solicitation document describes a firm-fixed price construction contract opportunity with the Department of the Air Force Air Mobility Command. The contractor will complete a project to provide a new server room in existing room P209 at Building 2400 on Joint Base Charleston Naval Weapons Station in Goose Creek, South Carolina. Work includes moving the existing server room from D216 to the new room P209, installing new racks, cable management, UPS, and in-row cooling to handle the process load. Space for servers and network engineers will be provided, with internal access control between the server room and office space. New distribution breakers will be installed in P103 and fiber run from D216 to P209. A separate HVAC system will be provided for the server room. The performance period is 360 days. A pre-proposal conference is scheduled for August 3, 2022 and the solicitation number is FA441822R0016. This is a 100% HUBZone small business set-aside.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment 04.pdf | ||
| Revised B2400 Server Room Questions.pdf | ||
| B2400 Server Room Questions.pdf | ||
| Solicitation Amendment 03.pdf | ||
| B2400 Server Room Sign-in.jpg | JPG image | |
| Solicitation Amendment 02.pdf | ||
| Solicitation Amendment 01.pdf | ||
| Davis Bacon Act WD SC20220022 Berkeley County Mod 2 22JUL22.pdf | ||
| 17. B2400 Server Room Final Drawings.pdf | ||
| Davis Bacon Act WD SC20220022 Berkeley County Mod 1 25FEB22.pdf | ||
| 15. AF 66-SUB Register - DSN B2400 Server Room.xlsx | XLSX spreadsheet | |
| Solicitation - FA441822R0016.pdf | ||
| 17a. Server Room Final 01 General Requirements.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract No.: FA441821C0038
SPECIFICATIONS
DSN B2400 Server Room
DKGV1110361
At Joint Base
Charleston, South Carolina
Final Design Submittal
Date: 04/28/2022
PREPARED BY:
LBE, INC
370 Rembert C. Dennis
Moncks Corner, SC 29461
UNCLASSIFIED/FOR OFFICIAL USE ONLY
Page Intentionally Left Blank
DSN B2400 Server Room Final Design Submittal Joint Base Charleston, SC Contract No: FA441821C0038
PROJECT TABLE OF CONTENTS
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 05/10, CHG 2: 02/19 DEMOLITION AND DECONSTRUCTION
DI VI SI ON 03 - CONCRETE
03 30 53 05/14 MISCELLANEOUS CAST-IN-PLACE CONCRETE
DI VI SI ON 05 - METALS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL
07 81 00 02/11 SPRAY-APPLIED FIREPROOFING
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 51 13 05/19 ALUMINUM WINDOWS
08 71 00 02/16, CHG 3: 08/20 DOOR HARDWARE
08 81 00 05/19 GLAZING
DI VI SI ON 09 - FI NI SHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 51 00 08/20 ACOUSTICAL CEILINGS
09 62 38 08/17, CHG 1: 08/18 STATIC-CONTROL FLOORING
09 90 00 02/21 PAINTS AND COATINGS
DI VI SI ON 10 - SPECI ALTI ES
10 14 00.20 08/20 INTERIOR SIGNAGE
10 44 16 11/19 FIRE EXTINGUISHERS
DI VI SI ON 21 - FI RE SUPPRESSI ON
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DI VI SI ON 22 - PLUMBI NG
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING FOR HVAC
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC
PROJECT TABLE OF CONTENTS Page 1
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 23 00 08/21 REFRIGERANT PIPING
23 30 00 05/20 HVAC AIR DISTRIBUTION
23 81 23 11/20 COMPUTER ROOM AIR CONDITIONING UNITS
DI VI SI ON 26 - ELECTRI CAL
26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 20 00 08/19, CHG 2: 05/21 INTERIOR DISTRIBUTION SYSTEM
26 33 53 05/19 STATIC UNINTERRUPTIBLE POWER SUPPLY
(UPS)
26 51 00 05/20, CHG 1: 05/21 INTERIOR LIGHTING
DI VI SI ON 27 - COMMUNI CATI ONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 31 70 08/20 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE
DI VI SI ON 31 - EARTHWORK
31 23 00.00 20 02/11, CHG 2: 08/15 EXCAVATION AND FILL
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 92 19 08/17, CHG 1: 08/21 SEEDING
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SECTION 02 41 00
DEMOLITION AND DECONSTRUCTION
05/ 10, CHG 2: 02/ 19
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.6 (2006) Safety & Health Program Requirements for Demolition Operations - American National Standard for Construction and Demolition Operations
CARPET AND RUG INSTITUTE (CRI)
CRI 104 (2015) Carpet Installation Standard for Comnmercial Carpet
CRI 105 (2015) Carpet Installation Standard for Residential Carpet
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
U.S. DEFENSE LOGISTICS AGENCY (DLA)
DLA 4145.25 (Jun 2000; Reaffirmed Oct 2010) Storage and Handling of Liquefied and Gaseous Compressed Gases and Their Full and Empty Cylinders http://www.aviation.dla.mil/UserWeb/aviationengineering/HazInfo/
U.S. DEPARTMENT OF DEFENSE (DOD)
DOD 4000.25-1-M (2006) MILSTRIP - Military Standard Requisitioning and Issue Procedures
MIL-STD-129 (2014; Rev R; Change 1 2018; Change 2 2019) Military Marking for Shipment and Storage
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 61 National Emission Standards for Hazardous Air Pollutants
49 CFR 173.301 Shipment of Compressed Gases in Cylinders and Spherical Pressure Vessels
SECTION 02 41 00 Page 1
1.2 PROJECT DESCRIPTION
1.2.1 Definitions
1.2.1.1 Demolition
Demolition is the process of wrecking or taking out any load-supporting structural member of a facility together with any related handling and disposal operations.
1.2.1.2 Demolition Plan
Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.
1.2.2 Demolition Plan
Prepare a Demolition Plan and submit proposed demolition, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress. Identify components and materials to be salvaged for reuse or recycling with reference to paragraph Existing Facilities to be Removed. Append tracking forms for all removed materials indicating type, quantities, condition, destination, and end use. Coordinate with Waste Management Plan in accordance with Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. Provide procedures for safe conduct of the work in accordance with EM 385-1-1 . Plan shall be approved by Contracting Officer prior to work beginning.
1.2.3 General Requirements
Do not begin demolition until authorization is received from the Contracting Officer. The work of this section is to be performed in a manner that maximizes the value derived from the salvage and recycling of materials. The work includes demolition, , salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1 , Section 23, Demolition, and other applicable Sections.
1.3 ITEMS TO REMAIN IN PLACE
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer.
Coordinate the work of this section with all other work indicated.
Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, or demolition work performed under this contract. Do not overload structural elements . Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.
SECTION 02 41 00 Page 2
1.3.1 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.
1.3.2 Weather Protection
For portions of the building to remain, protect building interior and materials and equipment from the weather at all times. Where removal of existing roofing is necessary to accomplish work, have materials and workmen ready to provide adequate and temporary covering of exposed areas.
1.3.3 Trees
Protect trees within the project site which might be damaged during demolition or deconstruction, and which are indicated to be left in place, by a 6 foot high fence. Erect and secure fence a minimum of 5 feet from the trunk of individual trees or follow the outer perimeter of branches or clumps of trees. Replace any tree designated to remain that is damaged during the work under this contract with like-kind or as approved by the Contracting Officer.
1.3.4 Utility Service
Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, .
1.3.5 Facilities
Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities. Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished or deconstructed, unless directed otherwise by the Contracting Officer.
Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract.
1.4 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted . Where burning is permitted, adhere to federal, state, and local regulations.
1.5 AVAILABILITY OF WORK AREAS
Areas in which the work is to be accomplished will be available in accordance with the following schedule:
SECTION 02 41 00 Page 3
Schedule
Area Date
1.6 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Demolition Plan; G
Existing Conditions
SD-07 Certificates
Notification; G
1.7 QUALITY ASSURANCE
Submit timely notification of demolition and renovation projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61 , Subpart M. Notify the and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61 , Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSP A10.6 .
Comply with the Environmental Protection Agency requirements specified.
Use of explosives will not be permitted.
1.7.1 Dust and Debris Control
Prevent the spread of dust and debris to occupied portions of the building and avoid the creation of a nuisance or hazard in the surrounding area.
Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Vacuum and dust the work area as required.
1.8 PROTECTION
1.8.1 Traffic Control Signs
a. Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Notify the Contracting Officer prior to beginning such work.
1.8.2 Protection of Personnel
Before, during and after the demolition work continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the project site. No area, SECTION 02 41 00 Page 4 section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.
1.9 RELOCATIONS
Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items as approved by the Contracting Officer.
1.10 EXISTING CONDITIONS
Before beginning any demolition work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inch will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results.
PART 2 PRODUCTS
2.1 FILL MATERIAL
a. Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition or deconstruction of structures. Fill material shall be waste products from demolition until all waste appropriate for this purpose is consumed.
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
Inspect and evaluate existing structures onsite for reuse. Existing construction scheduled to be removed for reuse shall be disassembled.
Dismantled and removed materials are to be separated, set aside, and prepared as specified, and stored or delivered to a collection point for reuse, remanufacture, recycling, or other disposal, as specified.
Materials shall be designated for reuse onsite whenever possible.
3.1.1 Utilities and Related Equipment
3.1.1.1 General Requirements
Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition
SECTION 02 41 00 Page 5 or deconstruction work until all utility disconnections have been made.
Shut off and cap utilities for future use, as indicated.
3.1.1.2 Disconnecting Existing Utilities
Remove existing utilities , as indicated and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to a location in accordance with instructions of the Contracting Officer.
3.1.2 Masonry
Sawcut and remove masonry so as to prevent damage to surfaces to remain and to facilitate the installation of new work. Where new masonry adjoins existing, the new work shall abut or tie into the existing construction as indicated . Provide square, straight edges and corners where existing masonry adjoins new work and other locations.
3.1.3 Concrete
Saw concrete along straight lines to a depth of a minimum 2 inch. Make each cut in walls perpendicular to the face and in alignment with the cut in the opposite face. Break out the remainder of the concrete provided that the broken area is concealed in the finished work, and the remaining concrete is sound. At locations where the broken face cannot be concealed, grind smooth or saw cut entirely through the concrete.
3.1.4 Miscellaneous Metal
Salvage shop-fabricated items such as access doors and frames, steel gratings, metal ladders, wire mesh partitions, metal railings, metal windows and similar items as whole units. Salvage light-gage and cold-formed metal framing, such as steel studs, steel trusses, metal gutters, roofing and siding, metal toilet partitions, toilet accessories and similar items. Recycle scrap metal as part of demolition and deconstruction operations. Provide separate containers to collect scrap metal and transport to a scrap metal collection or recycling facility, in accordance with the Waste Management Plan.
3.1.5 Carpentry
Salvage for recycle lumber, millwork items, and finished boards, and sort by type and size. Chip or shred and recycle salvaged wood unfit for reuse, except stained, painted, or treated wood. Salvage windows, doors, frames, and cabinets, and similar items as whole units, complete with trim and accessories. Brace the open end of door frames to prevent damage.
3.1.6 Carpet
Remove existing carpet for reclamation in accordance with manufacturer recommendations and as follows. Remove used carpet in large pieces, roll tightly, and pack neatly in a container. Remove adhesive according to recommendations of the Carpet and Rug Institute (CRI). Adhesive removal solvents shall comply with CRI 104 / CRI 105 . Recycle removed carpet cushion.
SECTION 02 41 00 Page 6
3.1.7 Acoustic Ceiling Tile
Remove, neatly stack, and recycle acoustic ceiling tiles. Recycling may be available with manufacturer. Otherwise, priority shall be given to a local recycling organization. Recycling is not required if the tiles contain or may have been exposed to asbestos material.
3.1.8 Patching
Where removals leave holes and damaged surfaces exposed in the finished work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces, using on-site materials when available. Where new work is to be applied to existing surfaces, perform removals and patching in a manner to produce surfaces suitable for receiving new work. Finished surfaces of patched area shall be flush with the adjacent existing surface and shall match the existing adjacent surface as closely as possible as to texture and finish. Patching shall be as specified and indicated, and shall include:
a. Concrete and Masonry: Completely fill holes and depressions, left as a result of removals in existing masonry walls to remain, with an approved masonry patching material, applied in accordance with the manufacturer's printed instructions.
b. Where existing partitions have been removed leaving damaged or missing resilient tile flooring, patch to match the existing floor tile.
c. Patch acoustic lay-in ceiling where partitions have been removed. The transition between the different ceiling heights shall be effected by continuing the higher ceiling level over to the first runner on the lower ceiling and closing the vertical opening with a painted sheet metal strip.
3.1.9 Cylinders and Canisters
Remove all fire suppression system cylinders and canisters and dispose of in accordance with the paragraph entitled "Disposal of Ozone Depleting Substance (ODS)."
3.1.10 Locksets on Swinging Doors
Remove all locksets from all swinging doors indicated to be removed and disposed of. Deliver the locksets and related items to a designated location for receipt by the Contracting Officer after removal.
3.1.11 Mechanical Equipment and Fixtures
Disconnect mechanical hardware at the nearest connection to existing services to remain, unless otherwise noted. Disconnect mechanical equipment and fixtures at fittings. Remove service valves attached to the unit. Salvage each item of equipment and fixtures as a whole unit;
listed, indexed, tagged, and stored. Salvage each unit with its normal operating auxiliary equipment. Transport salvaged equipment and fixtures, including motors and machines, to a designated storage area as directed by the Contracting Officer. Do not remove equipment until approved. Do not offer low-efficiency equipment for reuse.
SECTION 02 41 00 Page 7
3.1.11.1 Preparation for Storage
Remove water, dirt, dust, and foreign matter from units; tanks, piping and fixtures shall be drained; interiors, if previously used to store flammable, explosive, or other dangerous liquids, shall be steam cleaned.
Seal openings with caps, plates, or plugs. Secure motors attached by flexible connections to the unit. Change lubricating systems with the proper oil or grease.
3.1.11.2 Piping
Disconnect piping at unions, flanges and valves, and fittings as required to reduce the pipe into straight lengths for practical storage. Store salvaged piping according to size and type. If the piping that remains can become pressurized due to upstream valve failure, end caps, blind flanges, or other types of plugs or fittings with a pressure gage and bleed valve shall be attached to the open end of the pipe to ensure positive leak control. Carefully dismantle piping that previously contained gas, gasoline, oil, or other dangerous fluids, with precautions taken to prevent injury to persons and property. Store piping outdoors until all fumes and residues are removed. Box prefabricated supports, hangers, plates, valves, and specialty items according to size and type.
Wrap sprinkler heads individually in plastic bags before boxing. Classify piping not designated for salvage, or not reusable, as scrap metal.
3.1.11.3 Ducts
Classify removed duct work as scrap metal.
3.1.11.4 Fixtures, Motors and Machines
Remove and salvage fixtures, motors and machines associated with plumbing, heating, air conditioning, refrigeration, and other mechanical system installations. Salvage, box and store auxiliary units and accessories with the main motor and machines. Tag salvaged items for identification, storage, and protection from damage. Classify broken, damaged, or otherwise unserviceable units and not caused to be broken, damaged, or otherwise unserviceable as debris to be disposed of by the Contractor.
3.1.12 Electrical Equipment and Fixtures
Salvage motors, motor controllers, and operating and control equipment that are attached to the driven equipment. Salvage wiring systems and components. Box loose items and tag for identification. Disconnect primary, secondary, control, communication, and signal circuits at the point of attachment to their distribution system.
3.1.12.1 Fixtures
Remove and salvage electrical fixtures. Salvage unprotected glassware from the fixture and salvage separately.
3.1.12.2 Electrical Devices
Remove and salvage switches and conductors including wire and nonmetallic sheathed and flexible armored cable, instruments, plates, circuit breakers, outlet boxes, and similar items. Box and tag these items for identification according to type and size.
SECTION 02 41 00 Page 8
3.1.12.3 Wiring Ducts or Troughs
Remove and salvage wiring ducts or troughs. Dismantle plug-in ducts and wiring troughs into unit lengths. Remove plug-in or disconnecting devices from the busway and store separately.
3.1.12.4 Conduit and Miscellaneous Items
Salvage conduit except where embedded in concrete or masonry. Consider corroded, bent, or damaged conduit as scrap metal. Sort straight and undamaged lengths of conduit according to size and type. Classify supports, knobs, tubes, cleats, and straps as debris to be removed and disposed.
3.1.13 Items With Unique/Regulated Disposal Requirements
Remove and dispose of items with unique or regulated disposal requirements in the manner dictated by law or in the most environmentally responsible manner.
3.2 CONCURRENT EARTH-MOVING OPERATIONS
Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition or deconstruction work in areas occupied by structures to be demolished or deconstructed until all demolition and deconstruction in the area has been completed and debris removed. Fill holes, open basements and other hazardous openings.
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials and equipment removed and not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
3.3.2 Reuse of Materials and Equipment
Remove and store materials and equipment listed in the Demolition Plan to be reused or relocated to prevent damage, and reinstall as the work progresses. Coordinate the re-use of materials and equipment with the re-use requirements in accordance with Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. Capture re-use of materials in the diversion calculations for the project.
3.3.3 Salvaged Materials and Equipment
Remove materials and equipment that are listed in the Demolition Plan to be removed by the Contractor and that are to remain the property of the Government, and deliver to a storage site .
SECTION 02 41 00 Page 9
a. Salvage items and material to the maximum extent possible.
b. Store all materials salvaged for the Contractor as approved by the Contracting Officer and remove from Government property before completion of the contract. Coordinate the salvaged materials with tracking requirements in accordance with Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. Capture salvaged materials in the diversion calculations for the project.
c. Remove salvaged items to remain the property of the Government in a manner to prevent damage, and packed or crated to protect the items from damage while in storage or during shipment. Items damaged during removal or storage must be repaired or replaced to match existing items. Properly identify the contents of containers. Deliver the following items reserved as property of the Government to the areas designated.
3.3.4 Transportation Guidance
Ship all ODS containers in accordance with MIL-STD-129 , DLA 4145.25 (also referenced one of the following: Army Regulation 700-68, Naval Supply Instruction 4440.128C, Marine Corps Order 10330.2C, and Air Force Regulation 67-12), 49 CFR 173.301 , and DOD 4000.25-1-M .
3.3.5 Unsalvageable and Non-Recyclable Material
Dispose of unsalvageable and non-recyclable noncombustible material in the disposal area determined by Contracting Office.. The fill in the disposal area shall remain below elevation determined by Contracting Office. and after disposal is completed, the disposal area shall be uniformly graded to drain. Dispose of unsalvageable and non-recyclable combustible material in the location determined by Contracting Office..
3.4 CLEANUP
Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified in the Waste Management Plan .
3.5.2 Burning on Government Property
Transport combustible materials removed from demolished and deconstructed structures to the areas designated for burning. Control fires for protection of persons and property. Monitor fires continuously until the fires have burned out or have been extinguished. Comply with Federal, State and local laws regulating the building and maintaining of brush and trash fires.
SECTION 02 41 00 Page 10
3.5.3 Removal to Spoil Areas on Government Property
Transport noncombustible materials removed from demolition and deconstruction structures to designated spoil areas on Government property.
3.5.4 Removal from Government Property
Transport waste materials removed from demolished and deconstructed structures, except waste soil, from Government property for legal disposal. Dispose of waste soil as directed.
3.6 REUSE OF SALVAGED ITEMS
Recondition salvaged materials and equipment designated for reuse before installation. Replace items damaged during removal and salvage operations or restore them as necessary to usable condition.
-- End of Section --
SECTION 02 41 00 Page 11
SECTION 03 30 53
MISCELLANEOUS CAST-IN-PLACE CONCRETE
05/14
PART 1 GENERAL
1.1 SUMMARY
Perform all work in accordance with ACI 318 .
1.2 UNIT PRICES
1.2.1 Concrete Payment
Payment will cover all costs associated with furnishing, delivering, placing, finishing, and curing of concrete for the various items of the schedule, including the cost of all formwork. Payment for concrete, for which payment is made as a lump sum, is not to be included in this unit price payment item. Payment for grout, preformed expansion joints, field-molded sealants, waterstops, reinforcing steel bars or wire reinforcement is not to be included in this unit price payment item.
1.2.2 Measurement
Concrete will be measured for payment on the basis of the actual volume of concrete within the pay lines of the structures as indicated. Measurement of concrete placed against the sides of any excavation without the use of intervening forms will be made only within the pay lines of the structure. No deductions will be made for rounded or beveled edge, for space occupied by metal work, for electrical conduits or timber, or for voids or embedded items that are either less than 5 cubic feet in volume or 1 square foot in cross section.
1.2.3 Unit of Measure
Unit of measure: cubic yard.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary
ACI 301 (2016) Specifications for Structural Concrete
ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete
ACI 305R (2020) Guide to Hot Weather Concreting
SECTION 03 30 53 Page 1
ACI 306R (2016) Guide to Cold Weather Concreting
ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;
Errata 6 2016; Errata 7-9 2017) Building Code Requirements for Structural Concrete (ACI 318-14) and Commentary (ACI 318R-14)
ACI 347R (2014; Errata 1 2017) Guide to Formwork for Concrete
ACI SP-66 (2004) ACI Detailing Manual
ASTM INTERNATIONAL (ASTM)
ASTM A615/A615M (2020) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A1064/A1064M (2017) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete
ASTM C31/C31M (2021a) Standard Practice for Making and Curing Concrete Test Specimens in the Field
ASTM C33/C33M (2018) Standard Specification for Concrete Aggregates
ASTM C39/C39M (2021) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens
ASTM C94/C94M (2021a) Standard Specification for Ready-Mixed Concrete
ASTM C143/C143M (2020) Standard Test Method for Slump of Hydraulic-Cement Concrete
ASTM C150/C150M (2021) Standard Specification for Portland Cement
ASTM C172/C172M (2017) Standard Practice for Sampling Freshly Mixed Concrete
ASTM C173/C173M (2016) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method
ASTM C231/C231M (2017a) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260/C260M (2010a; R 2016) Standard Specification for Air-Entraining Admixtures for Concrete
ASTM C309 (2019) Standard Specification for Liquid Membrane-Forming Compounds for Curing
SECTION 03 30 53 Page 2
Concrete
ASTM C494/C494M (2019) Standard Specification for Chemical Admixtures for Concrete
ASTM C595/C595M (2021) Standard Specification for Blended Hydraulic Cements
ASTM C618 (2019) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C685/C685M (2017) Standard Specification for Concrete Made by Volumetric Batching and Continuous Mixing
ASTM C920 (2018) Standard Specification for Elastomeric Joint Sealants
ASTM C989/C989M (2018a) Standard Specification for Slag Cement for Use in Concrete and Mortars
ASTM C1064/C1064M (2017) Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete
ASTM C1157/C1157M (2020a) Standard Performance Specification for Hydraulic Cement
ASTM C1602/C1602M (2018) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete
ASTM D75/D75M (2019) Standard Practice for Sampling Aggregates
ASTM D1752 (2018) Standard Specification for Preformed Sponge Rubber, Cork and Recycled PVC Expansion Joint Fillers for Concrete Paving and Structural Construction
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 247 Comprehensive Procurement Guideline for Products Containing Recovered Materials
1.4 SUBMITTALS
Government approval is required for submittals with a "G" classification. Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Installation Drawings; G
SD-03 Product Data
SECTION 03 30 53 Page 3
Air-Entraining Admixture Water-Reducing or Retarding Admixture Curing Materials Expansion Joint Filler Strips, Premolded Joint Sealants - Field Molded Sealants Conveying and Placing Concrete Formwork Mix Design Data; G Ready-Mix Concrete Curing Compound Mechanical Reinforcing Bar Connectors
SD-06 Test Reports
Aggregates Concrete Mixture Proportions; G Compressive Strength Testing; G Slump; G Air Content Water
SD-07 Certificates
Cementitious Materials Pozzolan Aggregates Delivery Tickets
SD-08 Manufacturer's Instructions
Curing Compound
1.5 QUALITY ASSURANCE
Indicate specific locations of Concrete Placement on installation drawings and include, but not be limited to, square feet of concrete placements, thicknesses and widths, plan dimensions, and arrangement of cast-in-place concrete section.
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
The Government retains the option to sample and test aggregates and concrete to determine compliance with the specifications. Provide facilities and labor as may be necessary to assist the Government in procurement of representative test samples. Obtain samples of aggregates at the point of batching in accordance with ASTM D75/D75M. Sample concrete in accordance with ASTM C172/C172M. Determine slump and air content in accordance with ASTM C143/C143M and ASTM C231/C231M, respectively, when cylinders are molded. Prepare, cure, and transport compression test specimens in accordance with ASTM C31/C31M. Test compression test specimens in accordance with ASTM C39/C39M. Take samples for strength tests not less than once each shift in which concrete is produced . Provide a minimum of five specimens from each sample; two to be tested at 28 days (90 days if pozzolan is used) for acceptance, two will be tested at 7 days for information and one held in reserve.
SECTION 03 30 53 Page 4
2.1.1 Strength
Acceptance test results are the average strengths of two specimens tested at 28 days (90 days if pozzolan is used). The strength of the concrete is considered satisfactory so long as the average of three consecutive acceptance test results equal or exceed the specified compressive strength, f'c, but not more than 20 percent, and no individual acceptance test result falls below f'c by more than 500 psi.
2.1.2 Construction Tolerances
Apply a Class "C" finish to all surfaces except those specified to receive a Class "D" finish. Apply a Class "D" finish to all post-construction surfaces which will be permanently concealed. Surface requirements for the classes of finish required are as specified in ACI 117 .
2.1.3 Concrete Mixture Proportions
Concrete mixture proportions are the responsibility of the Contractor.
Mixture proportions must include the dry weights of cementitious material(s); the nominal maximum size of the coarse aggregate; the specific gravities, absorptions, and saturated surface-dry weights of fine and coarse aggregates; the quantities, types, and names of admixtures; and quantity of water per yard of concrete. Provide materials included in the mixture proportions of the same type and from the same source as will be used on the project. The specified compressive strength f'c is 3,000 psi at 28 days (90 days if pozzolan is used). The maximum nominal size coarse aggregate is 1 inch, in accordance with ACI 304R . The air content must be between 4.5 and 7.5 percent with a slump between 2 and 5 inches. The maximum water-cementitious material ratio is 0.50 . Submit the applicable test reports and mixture proportions that will produce concrete of the quality required, ten days prior to placement of concrete.
2.2 MATERIALS
Submit manufacturer's literature from suppliers which demonstrates compliance with applicable specifications for the specified materials.
2.2.1 Cementitious Materials
Submit Manufacturer's certificates of compliance, accompanied by mill test reports, attesting that the concrete materials meet the requirements of the specifications in accordance with the Special Clause "CERTIFICATES OF COMPLIANCE". Also, certificates for all material conforming to EPA's Comprehensive Procurement Guidelines (CPG), in accordance with 40 CFR 247 .
Provide cementitious materials that conform to the appropriate specifications listed:
2.2.1.1 Portland Cement
ASTM C150/C150M, Type II, with tri-calcium aluminates (C3A) content less than 10 percent and a maximum cement-alkali content of 0.80 percent Na2Oe (sodium oxide) equivalent.
2.2.1.2 Blended Hydraulic Cement
Provide blended cement conforming to ASTM C595/C595M and ASTM C1157/C1157M , Type IP, IL or IS, including the optional requirement for mortar expansion and consist of a mixture of ASTM C150/C150M Type I, or Type II cement and
SECTION 03 30 53 Page 5 a complementary cementing material. The slag added to the Type IS blend must be ASTM C989/C989M ground granulated blast-furnace slag. The pozzolan added to the Type IP blend must be ASTM C618 Class F, interground with the cement clinker. Provide the manufacturer's written statement that the amount of pozzolan in the finished cement will not vary more than plus or minus 5 mass percent of the finished cement from lot-to-lot or within a lot. Do not change the percentage and type of mineral admixture used in the blend from that submitted for the aggregate evaluation and mixture proportioning.
2.2.1.3 Pozzolan
Provide pozzolan that conforms to ASTM C618, Class F, including requirements of Tables 1A and 2A.
2.2.2 Aggregates
For fine and coarse aggregates meet the quality and grading requirements of ASTM C33/C33M. Submit certificates of compliance and test reports for aggregates showing the material(s) meets the quality and grading requirements of the specifications under which it is furnished.
2.2.3 Admixtures
Provide admixtures, when required or approved, in compliance with the appropriate specification listed. Retest chemical admixtures that have been in storage at the project site, for longer than 6 months or that have been subjected to freezing, at the expense of the Contractor at the request of the Contracting Officer and will be rejected if test results are not satisfactory.
2.2.3.1 Air-Entraining Admixture
Provide air-entraining admixture that meets the requirements of
ASTM C260/C260M.
2.2.3.2 Water-Reducing or Retarding Admixture
Provide water-reducing or retarding admixture meeting the requirements of ASTM C494/C494M, Type A, B, or D.
2.2.4 Water
Mixing and curing water in compliance with the requirements of ASTM C1602/C1602M ; free of injurious amounts of oil, acid, salt, or alkali. Submit test report showing water complies with ASTM C1602/C1602M .
2.2.5 Reinforcing Steel
Provide reinforcing bars conforming to the requirements of ASTM A615/A615M , Grade 60, deformed. Provide welded steel wire reinforcement conforming to the requirements of ASTM A1064/A1064M . Detail reinforcement not indicated in accordance with ACI 301 and ACI SP-66 . Provide mechanical reinforcing bar connectors in accordance with ACI 301 and provide 125 percent minimum yield strength of the reinforcement bar.
2.2.6 Expansion Joint Filler Strips, Premolded
Expansion joint filler strips, premolded of sponge rubber conforming to
SECTION 03 30 53 Page 6
ASTM D1752, Type I.
2.2.7 Joint Sealants - Field Molded Sealants
Conform to ASTM C920, Type M, Grade NS, Class 25, use NT for vertical joints and Type M, Grade P, Class 25, use T for horizontal joints.
Provide polyethylene tape, coated paper, metal foil, or similar type bond breaker materials. The backup material needs to be compressible, nonshrink, nonreactive with the sealant, and a nonabsorptive material such as extruded butyl or polychloroprene foam rubber. Immediately prior to installation of field-molded sealants, clean the joint of all debris and further cleaned using water, chemical solvents, or other means as recommended by the sealant manufacturer or directed.
2.2.8 Formwork
Design and engineer the formwork as well as its construction in accordance with ACI 301 Section 2 and 5 and ACI 347R . Fabricate of wood, steel, or other approved material. Submit formwork design prior to the first concrete placement.
2.2.9 Curing Materials
Provide curing materials in accordance with ACI 301 , Section 5.
2.3 READY-MIX CONCRETE
Provide ready-mix concrete with mix design data conforming to ACI 301 Part
2. Submit delivery tickets in accordance with ASTM C94/C94M for each ready-mix concrete delivery, include the following additional information: .
a. Type and brand cement
b. Cement content in 94-pound bags per cubic yard of concrete
c. Maximum size of aggregate
d. Amount and brand name of admixture
e. Total water content expressed by water cementitious material ratio
2.4 ACCESSORIES
2.4.1 Curing Compound
Provide curing compound conforming to ASTM C309. Submit manufactures instructions for placing curing compound.
PART 3 EXECUTION
3.1 PREPARATION
Prepare construction joints to expose coarse aggregate. The surface must be clean, damp, and free of laitance. Construct ramps and walkways, as necessary, to allow safe and expeditious access for concrete and workmen.
Remove snow, ice, standing or flowing water, loose particles, debris, and foreign matter. Satisfactorily compact earth foundations. Make spare vibrators available. Placement cannot begin until the entire preparation has been accepted by the Government.
SECTION 03 30 53 Page 7
3.1.1 Embedded Items
Secure reinforcement in place after joints, anchors, and other embedded items have been positioned. Arrange internal ties so that when the forms are removed the metal part of the tie is not less than 2 inches from concrete surfaces permanently exposed to view or exposed to water on the finished structures. Prepare embedded items so they are be free of oil and other foreign matters such as loose coatings or rust, paint, and scale. The embedding of wood in concrete is permitted only when specifically authorized or directed. Provide all equipment needed to place, consolidate, protect, and cure the concrete at the placement site and in good operating condition.
3.1.2 Formwork Installation
Forms must be properly aligned, adequately supported, and mortar-tight.
Provide smooth form surfaces, free from irregularities, dents, sags, or holes when used for permanently exposed faces. Chamfer all exposed joints and edges , unless otherwise indicated.
3.1.3 Production of Concrete
3.1.3.1 Ready-Mixed Concrete
Provide ready-mixed concrete conforming to ASTM C94/C94M except as otherwise specified.
3.1.3.2 Concrete Made by Volumetric Batching and Continuous Mixing
Conform to ASTM C685/C685M.
3.2 CONVEYING AND PLACING CONCRETE
Convey and place concrete in accordance with ACI 301 , Section 5.
3.2.1 Cold-Weather Requirements
Place concrete in cold weather in accordance with ACI 306R
3.2.2 Hot-Weather Requirements
Place concrete in hot weather in accordance with ACI 305R
3.3 FINISHING
3.3.1 Temperature Requirement
Do not finish or repair concrete when either the concrete or the ambient temperature is below 50 degrees F.
3.3.2 Finishing Formed Surfaces
Remove all fins and loose materials , and surface defects including filling of tie holes. Repair all honeycomb areas and other defects.
Remove all unsound concrete from areas to be repaired. Ream or chip surface defects greater than 1/2 inch in diameter and holes left by removal of tie rods in all surfaces not to receive additional concrete and fill with dry-pack mortar. Brush-coat the prepared area with an approved
SECTION 03 30 53 Page 8 epoxy resin or latex bonding compound or with a neat cement grout after dampening and filling with mortar or concrete. Use a blend of portland cement and white cement in mortar or concrete for repairs to all surfaces permanently exposed to view shall be so that the final color when cured is the same as adjacent concrete.
3.3.3 Finishing Unformed Surfaces
Finish unformed surfaces in accordance with ACI 301 , Section 5.
FINISH LOCATION
Float
Trowel
Broom or Belt
3.3.3.1 Expansion and Contraction Joints
Make expansion and contraction joints in accordance with the details shown or as otherwise specified. Provide 1/2 inch thick transverse expansion joints where new work abuts an existing concrete. Provide expansion joints as indicated for slabs. Provide contraction joints as indicated. Cut contraction joints at a minimum of 1 inch(es) deep with a jointing tool after the surface has been finished.
3.4 CURING AND PROTECTION
Cure and protect in accordance with ACI 301 , Section 5.
3.5 FORM WORK
Provide form work in accordance with ACI 301 , Section 2 and Section 5.
3.5.1 Removal of Forms
Remove forms in accordance with ACI 301 , Section 2.
3.6 STEEL REINFORCING
Reinforcement must be free from loose, flaky rust and scale, and free from oil, grease, or other coating which might destroy or reduce the reinforcement's bond with the concrete.
3.6.1 Fabrication
Shop fabricate steel reinforcement in accordance with ACI 318 and ACI SP-66 .
Provide shop details and bending in accordance with ACI 318 and ACI SP-66 .
3.6.2 Splicing
Perform splices in accordance with ACI 318 and ACI SP-66 .
3.6.3 Supports
Secure reinforcement in place by the use of metal or concrete supports, SECTION 03 30 53 Page 9 spacers, or ties.
3.7 EMBEDDED ITEMS
Before placing concrete, take care to determine that all embedded items are firmly and securely fastened in place. Provide embedded items free of oil and other foreign matter, such as loose coatings of rust, paint and scale. Embedding of wood in concrete is permitted only when specifically authorized or directed.
3.8 TESTING AND INSPECTING
Report the results of all tests and inspections conducted at the project site informally at the end of each shift. Submit written reports weekly.
Deliver within three days after the end of each weekly reporting period.
See Section 01 45 00 QUALITY CONTROL.
3.8.1 Field Testing Technicians
The individuals who sample and test concrete must have demonstrated a knowledge and ability to perform the necessary test procedures equivalent to the ACI minimum guidelines for certification of Concrete Field Testing Technicians, Grade I.
3.8.2 Preparations for Placing
Inspect foundation or construction joints, forms, and embedded items in sufficient time prior to each concrete placement to certify that it is ready to receive concrete.
3.8.3 Sampling and Testing
a. Obtain samples and test concrete for quality control during placement. Sample fresh concrete for testing in accordance with ASTM C172/C172M. Make six test cylinders.
b. Test concrete for compressive strength at 7 and 28 days for each design mix and for every 100 cubic yards of concrete. Test two cylinders at 7 days; two cylinders at 28 days; and hold two cylinders in reserve. Conform test specimens to ASTM C31/C31M. Perform compressive strength testing conforming to ASTM C39/C39M.
c. Test slump at the for each design mix in accordance with ASTM C143/C143M. Check slump once during each shift that concrete is produced for each strength of concrete required.
d. Test air content for air-entrained concrete in accordance with ASTM C231/C231M. Test concrete using lightweight or extremely porous aggregates in accordance with ASTM C173/C173M. Check air content at least once during each shift that concrete is placed for each strength of concrete required.
e. Determine temperature of concrete at time of placement in accordance with ASTM C1064/C1064M . Check concrete temperature at least once during each shift that concrete is placed for each strength of concrete required.
SECTION 03 30 53 Page 10
3.8.4 Action Required
3.8.4.1 Placing
Do not begin placement until the availability of an adequate number of acceptable vibrators, which are in working order and have competent operators, has been verified. Discontinue placing if any lift is inadequately consolidated.
3.8.4.2 Air Content
Whenever an air content test result is outside the specification limits, adjust the dosage of the air-entrainment admixture prior to delivery of concrete to forms.
3.8.4.3 Slump
Whenever a slump test result is outside the specification limits, adjust the batch weights of water and fine aggregate prior to delivery of concrete to the forms. Make the adjustments so that the water-cementitious material ratio does not exceed that specified in the submitted concrete mixture proportion and the required concrete strength is still met.
SECTION 03 30 53 Page 11
SECTION 05 40 00
COLD-FORMED METAL FRAMING
05/ 15, CHG 1: 08/ 18
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN IRON AND STEEL INSTITUTE (AISI)
AISI S100 (2012) North American Specification for the Design of Cold-Formed Steel Structural Members
AISI S110 (2007; Suppl 1; Reaffirmed 2012)…
This is the start of the file's text. The full file is on GovTribe.