17197_Addendum-1_Narrative_2020-02-20.pdf

PDF 112 KB Posted

Attached to
Y1LB--900 MM-FY24-003 Replace Center Road, New Curbs and Irrigation Main
Solicitation number
36C78624B0015
Issued by

About this file

This addendum pertains to a federal contract solicitation to replace Center Road, install new curbs, and replace the irrigation main line at the Prescott National Cemetery in Prescott, Arizona. The Department of Veterans Affairs National Cemetery Administration issued solicitation number 36C78624B0015 for the project, which includes replacing approximately 2,500 linear feet of roadway, 1,500 linear feet of curb and gutter, and 3,800 linear feet of irrigation main line. The addendum provides specification changes including removing certification pages and network analysis schedule sections from the contract documents and adding a revised network analysis schedule section. No changes were made to the drawings.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

13605 1st Avenue North #100, Plymouth, MN 55441 P 763.412.4000 F 763.412.4090 ae-mn.com

REPLACE CENTER ROAD AND IRRIGATION MAIN LINE

Prescott, Arizona Addendum No. 1 VA Project Number: 900-MM-FY23-004 Anderson Project Number: 17197

ADDENDUM NO. 1

SPECIFICATION CHANGES:

ITEM 1: Certification Page 2 through 5 shall be omitted from the contract documents.

ITEM 2: 00 01 10 Table of Contents Division 01 Specifications have been updated to reflect the following changes:

ITEM 3: 01 32 16.13 Network Analysis Schedules: Specification section has been removed from the Contract

Documents

ITEM 4: 01 32 17 Network Analysis Schedules: Specification section has been added to the Contract

Documents

DRAWING CHANGES:

NONE

END OF ADDENDUM NO. 1