This document is a Work Order form for a Water Main Extension project under the 2025-2028 Term Contract, likely issued by a municipal engineering services department. The form is designed for documenting water infrastructure installation work, specifically for WRP 02 Work Order, with checkboxes and sections for various water infrastructure components including DIP Pressure Class 150 pipe, AWWA C-900 DR 18 PVC pipe, tapping saddles, gate valves, fire hydrants, water service connections, and associated utility repairs. The document provides a template for tracking project quantities, unit prices, and specific infrastructure installation details, with space for sketches, measurements, calculations, and contractor verification.

The work order form includes provisions for multiple infrastructure elements such as trenching, utility cut repairs (concrete, asphalt, base rock), erosion/sediment control, traffic control, and job site safety. While no specific quantities or prices are filled in on this template, the form is structured to capture detailed project information including start and completion dates, GIS sketch completion, and mutual verification by city representatives and contractors. The document appears to be part of a standardized process for managing water main extension projects, allowing precise documentation and tracking of infrastructure installation work across multiple potential job sites within a defined contract term.

View the file

Other files

Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sketch/Measurements

(Attach additional sheet if necessary)

See Attached Sketch

Calculations

(Attach additional sheet if necessary)

See Attached Calculations

(Attach concrete/asphalt tickets)

Quantities verified (City): __________________ Quantities Agreed (Contractor): __________________ initial date initial date

( ) Traffic Control

( )" Water Serive Connection (Long > 20')

Erosion/Sediment Control

Contractor Name (Print):

( x )" Tapping Saddle

Fire Hydrant (≤ 5' Bury Depth)

Fire Hydrant Riser (> 5' Water Main Bury Depth)

Ductile Iron Fittings

GIS Sketch Complete: ________________

Anchor Coupling / Foster Adapter

( )" Gate Valve & Box (MJxMJ/FL)

Description of work: ____________________________________________________________________

Asphalt Utility Cut Repair

( x )" Tapping Saddle

Unit Price Comment/DescriptionPay Quantities Quantity

( )" AWWA C-900 DR 18 PVC

2025-2028 Term - Water Main Extension - WRP 02 Work Order

Start Date:

Completion Date:

Address: __________________

Total

------ ------TOTAL =

( )" DIP Pressure Class 150

( )" AWWA C-900 DR 18 PVC

( )" Pipe Casing ( )

Base Rock Utility Cut Repair

( )" Tapping Sleeve

( )" Tapping Sleeve

( )" Gate Valve & Vault (MJxMJ/FL)

( )" Water Serive Connection (Short ≤ 20')

( )" Gate Valve & Box (MJxMJ/FL)

( ) Traffic Control

Trenching Depth ( Deep)

Trenching Depth ( Deep)

Conctete Utility Cut Repair

Job Site Safety

Flowable Fill / 2-Sack Backfill

P:\Engineering Services\Engineering Projects\2025\U25-08 WRP 02\02 LEGAL\2.3 Bid Packet\012.1 WRP02 WO TYP

Sketch/Measurements

Calculations

P:\Engineering Services\Engineering Projects\2025\U25-08 WRP 02\02 LEGAL\2.3 Bid Packet\012.1 WRP02 WO TYP

File details come from the government source that posted it. Updated .