Keystone Project - Solicitation No. DOL-ETA-20-R-00010.pdf

PDF 2 MB Posted

Attached to
Complete the Construction of New Welcome Center at the Keystone Job Corps Center
Solicitation number
1630DC-20-R-00010
Issued by

About this file

This federal solicitation seeks design-build services for the completion of construction of a new Welcome Center at the Keystone Job Corps Center in Drums, Pennsylvania. The U.S. Department of Labor is soliciting proposals from qualified Service Disabled Veteran Owned Small Businesses. The project scope involves completing construction of an incomplete 2,600 square foot building and associated site work. The period of performance is 372 calendar days for substantial completion and 402 days for final completion. Evaluation factors are past experience with similar project size and scope, including references, as well as safety credentials. Proposals are due by March 26, 2020 with original bid bonds due by that date. A site visit will be held on March 5, 2020 and questions are due by March 10, 2020. The estimated value is between $500,000 and $1 million.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT TITLE: DESIGN BUILD – COMPLETE THE CONSTRUCTION OF NEW WELCOME CENTER

at the KEYSTONE JOB CORPS CENTER, DRUMS, PENNSYLVANIA

The project is to provide design and construction services to complete construction of the Welcome Center at the Keystone Job Corps Center, Drums, PA. The project was a training opportunity for the center’s Building Construction Technology students, but construction was suspended and the facility remains incomplete. Design of the facility was finished in 2009 and original construction drawings are available at http://www.solicitationattachments.com/keystonewelcomecenter. Currently, completed construction includes only the building’s 2,600 gross square feet envelope, rough in of interior walls, nominal mechanical, and limited electrical and plumbing. Placement of various exterior concrete slabs was also finished but may not be adequate. The underground sanitary sewer system was installed as part of the construction and must be validated as adequate and code compliant. Limited reporting in the sanitary system’s installation and condition is available.

The work includes, but is not limited to, miscellaneous site improvements in the form of general landscaping, roads, parking, drainage, connection to all utility lines and site/security lighting. The design-build project when complete will produce a code-compliant, fully functional facility

Keystone Job Corps Center 235 West Foothills Drive

Drums, PA 18222

- This requirement has been set-aside for a competitive Service Disabled Veteran Owned Small Business (SDVOSB)

- The estimated Construction Cost is between $500,000 and $1,000,000

- Please Reference Section C for the Statement of Work.

- Contractor shall submit one copy of the proposal via email to ramso.bryan@dol.gov by the solicitation due date. Paper copy submittals are not required for this solicitation. Include the solicitation number in the subject line of the email. Original bid bonds must be received by the proposal due date or the proposal will be considered nonresponsive. Bid bonds shall be sent to the address in Block 7 to the attention of Bryan Ramso.

- Please see Section L for further offeror instructions.

X

1. SOLICITATION NO. 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

A. NAME B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12B.)

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 4-85) STANDARD FORM 1442

Prescribed by GSA YFAR (48 CFR) 52.236-1(d) NSN 7540-01-155-3212

SOLICITATION, OFFER

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION, OFFER

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL: Bryan Ramso, Contract Specialist (202) 693-3618

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____10______ calendar days and complete it within ___402___ calendar days after receiving award, notice to proceed. This performance period is X mandatory, negotiable. (See _____________________________.)

YES NO

A. Sealed offers in original and __One (1)__copies to perform the work required are due at the place specified in Item 8 by _2:00 PM Eastern Time (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference

D. Offers providing less than ___120 ______ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NOTICE: SET-ASIDE for SDVOSB Competitive

1630DC-20-R-00010

2-20-2020 1 of 115

U.S. Department of Labor, ETA/OCM SEE SECTION L Division of Job Corps Procurement 200 Constitution Avenue, NW Room N-4643 Washington DC 20210

52.211-10

X Ten (10) Days

March 26, 2020 mailto:ramso.bryan@dol.gov

See Block 7

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO.

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within 90 calendar days after the date offers are due.

AMOUNTS CLIN 0001 …………………………………………………………………………….….$ _______________

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20B. SIGNATURE 20C. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c) ( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation, is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work, requisitions identified award consummates the contract. which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER

TO SIGN

30B. SIGNATURE 30C. DATE 31B. UNITED STATES OF AMERICA

BY

OFFER

AWARD

STANDARD FORM 1442(REV. 4-85)BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14)

(Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) MARIA J. PIZARRO, CPCM CFCM Contracting Officer

Division of Job Corps Procurement

(Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

ETA

U.S. Department of Labor ETA Payment Office 200 Constitution Avenue NW, Suite N-4702 Washington, DC 20210

1630DC-20-R-00010

Table of Contents

PART I - THE SCHEDULE ............................................................................................................................... A-1

SECTION A - SOLICITATION/CONTRACT FORM .................................................................................... A-1

SF 1442 SOLICITATION, OFFER, AND AWARDNOTICE: Total SET-ASIDE (Construction, Alteration, or Repair) ................................................................................................................................... A-1

SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS .................................................................. B-1

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK ......................................... C-1

[For this Solicitation, there are NO clauses in this Section] .................................................................................. C-1

SECTION D - PACKAGING AND MARKING ............................................................................................... D-1

SECTION E - INSPECTION AND ACCEPTANCE ....................................................................................... E-1

E.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE .................................. E-1 E.2 INSPECTION AND ACCEPTANCE ............................................................................................................ E-1

SECTION F - DELIVERIES OR PERFORMANCE ....................................................................................... F-1

F.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE ................................... F-1

F.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

ALTERNATE I (APR 1984) ........................................................................................................................ F-1 F.3 52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEPT 2000) .................................................. F-1 F.4 PERIOD OF PERFORMANCE ..................................................................................................................... F-2 F.5 PLACE OF PERFORMANCE ........................................................................................................................ F-2

SECTION G - CONTRACT ADMINISTRATION DATA .............................................................................. G-1

G.1 PRE-CONSTRUCTION CONFERENCE ..................................................................................................... G-1 G.2 PERIODIC PROJECT MEETINGS .............................................................................................................. G-1 G.3 SUBCONTRACTS ........................................................................................................................................ G-1 G.4 SHOP DRAWINGS ....................................................................................................................................... G-1 G.5 OPERATIONS, STORAGE AREAS AND SECURITY .............................................................................. G-2 G.6 PROJECT SAFETY ....................................................................................................................................... G-3 G.7 DISPOSAL OF REFUSE ............................................................................................................................... G-3 G.8 SCHEDULE OF PROGRESS ........................................................................................................................ G-3 G.9 PAYMENTS TO CONTRACTOR ................................................................................................................ G-4 G.10 METHOD OF PAYMENT .......................................................................................................................... G-4 G.11 FURNISHING INFORMATION AND RECORDS .................................................................................... G-4 G.12 WORKERS’ COMPENSATION LAWS .................................................................................................... G-5 G.13 REQUIRED INSURANCE .......................................................................................................................... G-5 G.14 EQUITABLE ADJUSTMENTS .................................................................................................................. G-6 G.15 WEATHER DELAYS (EXCUSABLE DELAY) ........................................................................................ G-8 G.16 TEST RESULTS .......................................................................................................................................... G-8 G.17 SUBSTANTIAL COMPLETION ................................................................................................................ G-8 G.18 CONTRACT CLOSEOUT .......................................................................................................................... G-9 G.19 PRECEDENCE OF PLANS, SPECIFICATIONS, AND CLAUSES ......................................................... G-9 G.20 INVOICE PREPARATION AND SUBMISSION .................................................................................... G-10

SECTION H - SPECIAL CONTRACT REQUIREMENTS ........................................................................... H-1

H.1 COMMENCEMENT OF WORK .................................................................................................................. H-1 H.2 SUBCONTRACTING RESPONSIBILITIES ............................................................................................... H-1 H.3 ENVIRONMENTAL COMPLIANCE .......................................................................................................... H-1 H.4 INSTALLATION RULES AND REGULATIONS ...................................................................................... H-1 H.5 SPECIAL UTILITY PROVISION ................................................................................................................ H-1 H.6 DESIGNATION OF GOVERNMENT INSPECTOR ................................................................................... H-1 H.7 ACCOUNTING AND AUDITING SERVICES ........................................................................................... H-1 H.8 SUBMISSION OF CORRESPONDENCE .................................................................................................... H-2 H.9 OTHER CONTRACTORS ............................................................................................................................ H-2 H.10 DISPOSITION OF MATERIAL ................................................................................................................. H-2 H.11 HAZARDOUS OCCUPATION ORDERS .................................................................................................. H-2 H.12 DATA COLLECTION FOR THE DEPARTMENT OF LABOR ............................................................... H-2 H.13 RIGHTS AND OBLIGATIONS .................................................................................................................. H-3 H.14 INITIATION OF LIQUIDATED DAMAGES ............................................................................................ H-3 H.15 MODIFICATIONS AND CHANGE ORDERS .......................................................................................... H-3 H.16 PERMITS ..................................................................................................................................................... H-4 H.17 OVERTIME WORK .................................................................................................................................... H-4 H.18 2020-01 CONTRACTOR PERSONNEL TELEWORK ............................................................................. H-4

PART II - CONTRACT CLAUSES ................................................................................................................... I-1

SECTION I - CONTRACT CLAUSES ............................................................................................................ I-1

I.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE .....................................I-1 I.2 INFORMATION REGARDING RESPONSIBILTY OF MATTERS (FEB 2012) ..........................................I-4

I.3 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRCT

AWARDS (OCT 2018) ..................................................................................................................................I-5 I.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013) ...........I-7

I.5 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS

ACT (DEC 2010) (DEVIATION) ..................................................................................................................I-8 I.6 52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (OCT 2015) ..................................................I-10

I.7 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND

CONSTRUCTION CONTRACTS (SEPT 2013) ........................................................................................I-12

I.8 52.223-3 HAZARDOUS MATERIAL IDENTIFICAITON AND MATERIAL

SAFETY DATA (JAN 1997) .......................................................................................................................I-12 I.9 52.225-9 BUY AMERICAN - CONSTRUCTION MATERIALS (MAY 2014) .........................................I-13

I.10 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT - CONSTRUCTION

MATERIALS (MAY 2014) ........................................................................................................................I-16 I.11 52.227-4 PATENT INDEMNITY—CONSTRUCTION CONTRACTS (DEC 2007) ALT I (DEC 2007).I-17 I.12 52.228-15 PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION (OCT 2010) ....................I-17 I.13 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017) ...........................I-18 I.14 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) ........................I-24 I.15 52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994) .................................................................I-25 I.16 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) ..................................................I-26

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS .................................... J-1

SECTION J - LIST OF ATTACHMENTS ........................................................................................................ J-1

J.1 WAGE DETERMINATION ............................................................................................................................ J-1 J.1 JCH 814 ............................................................................................................................................................ J-1

SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF

OFFERORS OR RESPONDENTS ........................................................................................................... K-1

K.1 NOTICE LISTING SOLICITATION PROVISIONS INCORPORATED BY REFERENCE ..................... K-1 K.2 52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985) ......................... K-1 K.3 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2020) ................................... K-2 K.4 52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS (OCT 2015) ......................... K-4 K.5 52.219-1 SMALL BUSINESS PROGRAM REPRESENTATIONS (OCT 2014) ........................................ K-5 K.6 SIGNATURE BLOCK .................................................................................................................................. K-8

SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS ........................................................................................................................................ L-1

L.1 NOTICE LISTING SOLICITATION PROVISIONS INCORPORATED BY REFERENCE ...................... L-1

L.2 52.215-20 REQUIREMENTS FORCERTIFIED COSTOR PRICING DATA AND DATA

OTHER THAN CERTIFIED COST OR PRICING DATA (OCT 2010) ................................................ L-1 L.3 52.216-1 TYPE OF CONTRACT (APR 1984) ............................................................................................. L-2

L.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) ................................................. L-2 L.5 52.233-2 SERVICE OF PROTEST (SEP 2006) ............................................................................................. L-3 L.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE 1 (FEB 1995) .............................. L-4 L.7 52.236-28 PREPARATION OF PROPOSALS—CONSTRUCTION (OCT 1997) ...................................... L-4 L.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) .................... L-4 L.9 52.252-3 ALTERATIONS IN SOLICITATIONS (APR1984) ....................................................................... L-4 L.10 GENERAL PROPOSAL PREPARATION INSTRUCTIONS ................................................................... L-4

SECTION M – EVALUATION FACTORS FOR AWARD ........................................................................... M-1

1630DC-20-R-00010 Section B Supplies or Services and Price/Costs

B-1

PART I - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS

PRICE/COST SCHEDULE

CLIN SUPPLIES/

SERVICES

QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 LS --------- $

Firm Fixed Price

The Contractor shall provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform the Design and Construction Services for the Design/Build – Complete the Construction of New Welcome Center at the Keystone Job Corps Center.

TOTAL **$

**Enter amount on Page 2 of SF 1442, Block 17.

B.2 DELIVERABLE - RELEASABLE COPIES - FREEDOM OF INFORMATION ACT

The Freedom of Information Act (FOIA) permits withholding information under several exemptions, including Exemption 4 which protects "trade secrets and commercial or financial information obtained from a person [that is] privileged or confidential," 5 U.S.C. 552(b) (4). Within five business days of contract award, the contractor shall provide a statement that the contract is available for full disclosure under the FOIA or provide a scanned PDF of the redacted copy of the contract identifying the specific potions the contractor believes are covered by the particular exemption requested. Any redactions must be fully supported under the FOIA. In the event the Government notifies the contractor that it does not agree with a proposed redaction, the contractor shall have five business days to submit additional information to support the requested redaction. For subcontracts, within 5 business days of the contractor's award of any subcontract over $500,000 the contractor shall provide the Government a scanned PDF copy of the subcontract with a statement that the copy is either available for full disclosure, or identifying the specific portions believed to be covered by the particular exemption requested.

Redactions should be limited to those protections provided under the FOIA. Following the procedures above, the Government has the right to notify the contractor of any disagreement with proposed redaction or exemption requests.

1630DC-20-R-00010 Section C Description/Specifications

C-1

DESIGN-BUILD SCOPE OF WORK

FOR

COMPLETE THE CONSTRUCTION OF NEW WELCOME CENTER

AT THE

KEYSTONE JOB CORPS CENTER

DRUMS, PENNSYLVANIA

U.S. DEPARTMENT OF LABOR

PROJECT NO. 4021

September 2019 DESIGN-BUILD SOW

C-2

TABLE OF CONTENTS

I. GENERAL .......................................................................................................................... C-4 II. SPECIFIC REQUIREMENTS/INSTRUCTIONS .............................................................. C-4

A. LEGALLY MANDATED STANDARDS ..................................................................... C-4

1. Code of Federal Regulations ..................................................................................... C-4

2. National and State Building Codes ........................................................................... C-5

3. Permits and Licenses................................................................................................. C-5

B. JOB CORPS GUIDELINES ........................................................................................... C-5

1. JCH-814: Planning, Design, and Construction Administration Guidelines ............ C-5

C. OTHER STANDARDS.................................................................................................. C-6

1. Life Cycle Cost (LCC) Analyses .............................................................................. C-6

2. Sustainable Design and Building Requirements ....................................................... C-6

3. Energy Conservation ................................................................................................. C-6

4. Environmentally Preferable Products ....................................................................... C-7

5. Asbetos-Containing Materials and PCF Flourescent Light Ballasts......................... C-7

6. Commissioning ......................................................................................................... C-7

7. Existing Facility Investigative Survey ...................................................................... C-7

D. SPECIFIC INSTRUCTIONS .......................................................................................... C-8

1. Keystone Center Operation ....................................................................................... C-8

2. Contractor Responsibilites ........................................................................................ C-8

3. Submittal Requirements ............................................................................................ C-8

4. Web Based Project Management System ............................................................... C-10

5. Building Design ...................................................................................................... C-11

6. Site Visits – Construction Observation – Construction Progress Meetings ........... C-11

7. Availability of Existing Documents........................................................................ C-12

III. USE OF THE SITE ........................................................................................................... C-12 IV. EXTENT OF WORK ........................................................................................................ C-12

A. SITE IMPROVEMENTS AND UTILITIES ................................................................ C-12

1. Design Objectives ................................................................................................... C-12

2. Site Improvements .................................................................................................. C-12

3. Site Survey .............................................................................................................. C-13

4. Site Utilitlies ........................................................................................................... C-13

B. GENERAL BULDINGS DESIGN REQUIREMENTS ............................................... C-13

1. Architectural ........................................................................................................... C-13

2. Structural ................................................................................................................. C-13

3. Mechanical/Plumbing ............................................................................................. C-14

4. Electrical ................................................................................................................. C-15

5. Radon ...................................................................................................................... C-16

6. Warranties ............................................................................................................... C-16

C. FUNCTIONAL BUILDING DESIGN REQUIREMENTS ......................................... C-17

1. Programmatic Requirements ................................................................................... C-17

V. CONSTRUCTION REQUIREMENTS/SPECIFIC INSTRUCTIONS .............................. C-18 A. SPECIFIC INSTRUCTIONS........................................................................................ C-18

C-3

1. Testing and Inspection ............................................................................................ C-18

2. Temporary Facilities and Controls.......................................................................... C-19

3. Adherence to Scope of Work .................................................................................. C-20

4. Incidental Cutting and Patching .............................................................................. C-20

5. Coordination of Work ............................................................................................. C-20

VI. SKETCHES ....................................................................................................................... C-21 A. LOCATION MAP ........................................................................................................ C-21 B. VICINITY MAP ........................................................................................................... C-21 C. SITE PLAN ................................................................................................................... C-22 D. ASK-1 – FLOOR PLAN CHANGES ........................................................................... C-23 E. EXISTING SANITARY SEWER MAP ....................................................................... C-24

VII. PROJECT SCHEDULE .................................................................................................... C-25 ATTACHMENT 1 CONTRACTOR QUICK REFERENCE CHECKLIST ........................... C-26

ATTACHMENT 2 QUALITY CONTROL, TESTING, AND INSPECTION SERVICES .... C-31

REQUIREMENTS

C-4

DESIGN-BUILD SCOPE OF WORK

COMPLETE THE CONSTRUCTION OF NEW WELCOME CENTER

AT THE

KEYSTONE JOB CORPS CENTER

I. GENERAL

The project is to provide design and construction services to complete construction of the Welcome Center at the Keystone Job Corps Center, Drums, PA. The project was a training opportunity for the center’s Building Construction Technology students, but construction was suspended and the facility remains incomplete. Design of the facility was finished in 2009 and original construction drawings are available at http://www.solicitationattachments.com/keystonewelcomecenter. Currently, completed construction includes only the building’s 2,600 gross square feet envelope, rough in of interior walls, nominal mechanical, and limited electrical and plumbing. Placement of various exterior concrete slabs was also finished but may not be adequate. The underground sanitary sewer system was installed as part of the construction and must be validated as adequate and code compliant. Limited reporting in the sanitary system’s installation and condition is available.

The work includes, but is not limited to, miscellaneous site improvements in the form of general landscaping, roads, parking, drainage, connection to all utility lines and site/security lighting. The design-build project when complete will produce a code-compliant, fully functional facility. The extent of work is described in Parts IV of this Scope of Work (SOW).

“Contractor Quick Reference Checklist,” Attachment 1, is a required form that identifies a simplified but not an all-inclusive list of issues that the Contractor needs to address as due diligence items during the design phase. The JCH-814 paragraphs shown provide an initial design reference; however, reference to other sources may be required to address the issue fully.

“Quality Control, Testing, and Inspection Services Requirements”, Attachment 2, outlines the minimum quality control, testing, and inspection procedures and practices which are required to ensure the completed construction meets or exceeds both the contract requirements and the Government-accepted contractor design.

II. DESIGN REQUIREMENTS/ SPECIFIC INSTRUCTIONS

A. LEGALLY MANDATED STANDARDS

The Contractor shall conform to:

1. Code of Federal Regulations

a) Safety and Health………………………………………..OSHA CFR Part 1926.62

b) Disability/Accessibility…………………………………28 CFR Part 36

The design must be in strict conformance with the Architectural Barriers Act Accessibility Standard (ABAAS) of 2007 from the General Services Administration.

The Contractor shall conduct a thorough research of these guidelines and, without http://www.solicitationattachments.com/keystonewelcomecenter

C-5 exception, comply to the fullest extent, including those guidelines pertaining to the visually and hearing impaired.

No deviations from these guidelines are allowed. However, if the Contractor, at any Design Review Submittal, demonstrates that the compliance requirements would be technically infeasible or that compliance will cause an undue burden as defined by the guidelines, the Contractor is obligated to notify the Contracting Officer, in writing, for a final decision on such requirements.

(These standards can be printed from the website at http://www.access.gpo.gov/nara/cfr/cfr-table-search.html).

c) Life Safety Code………………………………………………………NFPA-101

The Contractor’s responsibility for safety related requirements extends to all impacted areas and access ways affected by the work.

2. National and State Building Codes

The Contractor shall conform to all applicable construction codes, ordinances, and regulations including the National Building Code used in the local area, laws and local ordinances. The most recent version of the IBC shall be used for all seismic related design, and the version shall be coordinated with the local jurisdiction on the version for the non-seismic design. Deviations and interpretations shall be subject to the approval of the Contracting Officer. Consider whether special requirements should be included because of the geographic location, i.e. hurricane, heavy wind, or storm features for the United States Northeast Region.

3. Permits and Licenses

The Keystone Job Corps Center is leased from Luzerne County, Commonwealth of Pennsylvania.

The Contractor shall research, and be responsible for obtaining and paying for, all regulatory, permitting and licensing requirements required to perform this work in Drums, Pennsylvania and in accordance with JCH-814, Section 1.7. No drawings or specifications shall be submitted for building permits unless express notification in writing is received from the Contracting Officer (CO).

B. JOB CORPS GUIDELINES

1. JCH-814: Planning, Design, and Construction Administration Guidelines for Architects and

Engineers.

Job Corps publication JCH-814, September 2013 "Planning, Design, and Construction Administration Guidelines for Architects and Engineers," including Amendment 1 dated September 2015, is a companion document to this scope of work. This reference will from this point forward be referenced as “JCH-814.” The JCH-814 can be found at

C-6 http://www.solicitationattachments.com/jch814. It presents the Contractor additional design criteria not specifically stated in the Scope of work. Where conflicts occur between the requirements of the contract and JCH-814, the requirements of the contract will take precedence.

C. OTHER STANDARDS

1. Life Cycle Cost (LCC) Analyses

LCC shall be utilized as the basis for recommendations in making the selections of energy sources, systems and equipment, and building materials. However, the design must be consistent and in accordance with the extent of the scope of work and the budget. At the 15% Schematic submittal, the LCC analyses for the mechanical systems and fuel shall be submitted with recommendations for review, and shall be approved and revised as necessary as equipment is selected and specified. The LCC's shall be run on NIST's BLCC and Discount software programs. On request, the Department of Labor will furnish this software to the Contractor free of charge. The BLCC program shall be run on the OMB A-94 guidelines, using the discount factor from the latest edition of OMB Circular No. A-94 under “Real Interest Rates.”

(The BLCC software is also available on the Federal Energy Management Program website at http://www1.eere.energy.gov/femp/information/download_blcc.html under the heading “BLCC 5.3(latest version)” for a Windows version).

2. Sustainable Design and Building Requirements

The Contractor shall provide materials and equipment that comply with the – GREEN “CHEAT SHEET” JOB CORPS SUSTAINABILITY GUIDELINES which is available for download and reference at http://www.solicitationattachments.com/jch814/green_sheet_20171205.pdf

3. Energy Conservation

All new work is to be designed in accordance with energy conservation opportunities and applicable federal directives. In response to energy conservation concerns, all proposed construction shall conform to the current edition of the Model Energy Code of the Commonwealth of Pennsylvania and ASHRAE 90.1-2013 for all buildings except low rise residential buildings.

It is the Department of Labor’s policy to purchase energy and water consuming products which are in the upper 25% of energy and water efficiency whenever practicable and cost effective. All work must be designed to meet or exceed the requirements of the Energy Policy Act of 2005 (or latest version), which includes Sections 103, 104, 109, 131, 553;

Executive Order 13693; and all other applicable federal, state, and local codes and directives.

New equipment shall be Energy Star or FEMP designated products where applicable.

Building annual energy consumption calculations, methods and presentation shall conform to nationally recognized standards such as found in ASHRAE Handbooks. A calculation http://www.solicitationattachments.com/jch814.

http://www.solicitationattachments.com/jch

C-7 summary statement of the estimated annual energy consumption, expressed in BTU/GSF/YR shall be submitted with the 60% and final review submittal for the building. Building energy shall include lighting, all HVAC energy including heating, cooling, and ventilating loads, fans and pump motors energy, and domestic hot water supply energy.

The Contractor shall submit an energy analysis per ASHRAE 90.1-2013 Appendix G showing that the design reduces energy consumption by at least 30% (20% for Renovations) compared to the baseline building. This analysis will be provided with the 60% design submission and will be revised as necessary with succeeding submittals.

4. Environmentally Preferable Products

The Contractor shall evaluate options for the use of environmentally preferable products and environmentally preferable building design and shall include a description of recommended options in the DESIGN NARRATIVE (see JCH-814 for narrative requirements).

5. Asbestos-Containing Materials and PCB Fluorescent Light Ballasts

No asbestos-containing materials or PCBs are known to exist. For bidding purposes, the contractor shall assume that there is no asbestos-containing materials or PCBs in the building.

If asbestos-containing materials or PCBs are discovered during the Work the contractor shall immediately cease work activities in the location suspect materials are identified, immediately notify the Contracting Officer, and await direction.

6. Commissioning

The building shall be commissioned by an experienced Commissioning Agent (CxA).

Commissioning standards shall be per the Building Commissioning Association’s Building Commissioning Handbook, Second Edition. Building Commissioning shall be as indicated on the Building Commissioning Compliance Form. The CxA may be from an independent firm hired by the Contractor or a member of the contractors ‘design team firm, but not a member of the design team itself. In addition, the CxA shall:

a) Provide 60% and 100% design phase reviews and comment of selected mechanical systems. These reviews are to be included in the design submissions.

b) Provide training and orientation of commissioned systems to the appointed maintenance and operations staff. The CxA shall provide a video of this training.

c) Provide a systems operating manual for the facility maintenance staff with the information needed to understand and optimally operate the commissioned systems.

7. Existing Facility Investigative Survey

The work is to be performed on an existing building for which complete plans are not available. The Contractor shall perform an investigative survey to determine if there are hidden conditions or elements which will impact the proposed design. Demolition may be required to expose suspected unknown elements.

C-8

a) The survey will determine if multiple ceilings exist or if there are multiple layers of floor covering.

b) The survey will determine the extent of any hidden structural elements. The design and spacing of hidden structural elements will be investigated.

c) The survey will locate any hidden mechanical or electrical components, the presence of which would impact the proposed design.

d) Any openings in the exposed finishes created to perform the investigative survey will be sealed and restored in all areas where there are occupants. Any opening hidden by the exposed finish ̧such as a drop-in ceiling, need only be sealed.

D. SPECIFIC INSTRUCTIONS

1. Keystone Job Corps Center Operation

The Contractor shall, as part of this contract, coordinate with DOL’s Engineering Support Contractor (ESC) and develop a set of construction documents that will minimize disruption of center operations during construction. Proper scheduling of the construction work is required to allow the center to operate in a normal fashion during construction.

2. Contractor Responsibilities

The Contractor’s design shall meet the programmatic requirements as outlined in this scope of work, in the JCH-814 and as supplemented by ASK-1 – FLOOR PLAN CHANGES in Section VI.

Although this scope of work may identify specific elements of construction, it is the Contractor's responsibility to provide all elements, which are incidental to provide a fully complete and functional facility.

The Contractor is required to provide twenty (10) high quality photographs in digital and paper format to document the completed facility. Submission of the requisite photo record shall be following remediation of the Substantial Completion Punch List.

3. Submittal Requirements

The required Submissions are as follows; percentages are an approximate fraction of completed construction documents.

Pre-Design Study 15% Progress Contract Documents 60% Final Contract Documents and Coordination Drawings 100% For-Construction Documents Final

All submittals will be in accordance with JCH-814, Section 8.4.

All submittals shall be in accordance with JCH-814, Section 8.4.

C-9

This project will require the following submittals:

The A/E contractor shall provide a Pre-Design Study (15%) report submission within six weeks of receipt of the Notice to Proceed. The report will present the results of a thorough investigation of the proposed construction and provide qualified recommendations. The study will include, but not be limited to discussion and derived conclusions from a complete review of available construction record documents that were produced prior to suspension of the former project. The study will report on the findings and recommendations resulting from a forensic investigation and evaluation of the condition of the existing sanitary sewer system and any other installed infrastructure, existing building structural system, and existing mechanical, electrical and plumbing systems. The intent of the study is to identify previously constructed work and infrastructure work that can reliably be adopted and/or adapted into the new project. Original solicitation and record construction documents are listed in Appendices A and B and are located at http://www.solicitationattachments.com/keystonewelcomecenter.

The Contractor shall provide a Progress Construction Documents (60%) submission based on the schedule contained in Section VII, including all corrections and design review comment responses from the 15% submission.

The Contractor shall provide a Final Contract Documents and Coordination Drawings (100%) submission, including all corrections and design review comment responses from the 60% submission, based on the schedule contained in Section VII.

The For Construction Documents, to include all corrections and design review comment responses from the 100% submission, shall be submitted within two (2) weeks from receipt of the Final Contract Documents and Coordination Drawings approval by the Center Director.

Three copies of the updated CONTRACTOR QUICK REFERENCE checklist shall be provided with each design submission.

Submittals for Review, The Contractor shall submit five (5) sets of the Pre-Design Study to the Contracting Officer for evaluation.

For the remaining submissions the Contractor shall submit five (5) sets of drawings (2 sets full size, 3 sets ½ size) and project documents, as well as three (3) sets of life-cycle analyses, design calculations, and design narratives to the Center Director for review and acceptance.

One (1) set of drawings at the 60% stage shall be submitted to the Job Corps Data Center.

Keystone Job Corps Center Attn.: Center Director 235 West Foothills Drive Drums, Pennsylvania 18222

C-10

Job Corps Data Center Attn.: Greg Colvin 1215 Pine Haven Drive Morristown, TN 37814

Three (3) Finish Boards shall be submitted at the 60% design submission by the Contractor.

Two (2) Finish Boards shall be mailed by the Contractor to the Center Director, and one (1) Finish Board.

Each design submittal shall be incorporated into an “AutoCAD (version 14 or later)” and PDF compatible electronic “CD” and be delivered to the Department of Labor by the Contractor in addition to the drawing/specification sets required. Complete project documents shall also be furnished on electronic “CD” media that is “Word” (Microsoft Office) compatible.

The levels of detail required for each stage of the submittals are outlined in JCH-814, Section 8.4.

The Contractor is required to maintain the design-build schedule per the contract, and must indicate to the CO ways and means to recover lost time due to delays. No additional time will be given to the Contractor unless it is determined by the Center Director that the delay is legitimate and unavoidable and that the Contractor has prudently exercised all options within its authority and ability to avert such delays.

The Contractor shall, at a minimum, submit the following for approval before commencing construction:

• Schedule, CPM in Microsoft Project or Primavera P6, with electronic files

• Safety Plan

• Quality Plan

• Construction phasing and layout plan

• Installers qualifications

• Product data and shop drawings for all materials and equipment to be incorporated into the work.

• Safety Data Sheets for all materials and equipment as applicable.

4. Web Based Project Management System

The DOL shall provide, and requires the Contractor to use, the secure online construction management system, Submittal Exchange©, that will expedite submittal information and management exchanges between members of the Contractor’s team, the ESC, the DOL and other designated project stakeholders. Submittal Exchange will be provided at DOL’s expense and the Contractor will be required to attend a one-hour on-line training session before use.

The system offers an unlimited user automatic information exchange, and electronic closeout documentation for the entire project. The program service provides a comprehensive online

C-11 system for exchanging, reviewing, and archiving construction communications as well as product manufacturer training for users.

The extent of use of Submittal Exchange shall be determined by DOL and the General Contractor during the Pre-Construction Conference. The following features of Submittal Exchange may be utilized: Project Data and Shop Drawing Submittals, Construction Submittals, RFI’s, ASI's, Construction Updates, HPSB, Meeting Minutes, Monthly Executive Reports, Construction Photos, Applications for Payment, Construction Videos, Coordination Drawings, Reports, Deficiency Notices/Notice of Non-Compliance, Tests & Inspections, Warranties, Closeout, Punch Lists, Commissioning, and Operations and Maintenance Manuals.

Construction Schedules, Schedule of Values, Design Submissions, Proposal Requests, Potential Change Orders (PCOs), and Substantial Completion Requests shall not be posted to Submittal Exchange. These documents shall be submitted hard-copy or via email to DOL for review and approval.

5. Building Design

The Contractor must be familiar with Drums, Commonwealth of Pennsylvania construction methods and building materials, and shall provide a design that exemplifies the optimum balance of economy, aesthetics, life-safety, ease of maintenance and speed of construction.

July 2009 100% Design Documents are provided for the renovation as reference only at http://www.solicitationattachments.com/keystonewelcomecenter. Directed modifications are describe at Section VI. D. The reference documents delineate the original plans in terms of space allocation, room layout, adjacencies, building materials, etc., and represent the framework upon which the construction was based. Modification to these documents must be presented for consideration at the Progress Contract 60% design submittal for Center Director review and approval. Should the Center Director find the requested modifications to the reference plans unjustified, the Contractor shall be required to resubmit in accordance with the reference design at no additional time or cost to the Center...

6. Site Visits - Construction Observation – Construction Progress Meetings

The Contractor’s contract administration services shall include all duties and responsibilities as outlined in JCH-814, Chapter 9. The Contractor shall prepare a monthly construction progress report. The report shall include an updated CPM schedule, a minimum of 10 electronic photos of all aspects of the project and a list of open issues with the responsible person and target date for resolution identified.

This is the start of the file's text. The full file is on GovTribe.