16.1012.08-19.10.11-Final Bid Spec Vol 1.pdf
PDF 5 MB Posted
- Attached to
- Y1NB--552-19-107: Replace Boilers (Building 147) Federal contract opportunity
- Solicitation number
- 36C25020B0014
About this file
This pre-solicitation notice announces an upcoming solicitation for a construction project to replace boilers at a Department of Veterans Affairs medical center. The project is set aside for Service-Disabled Veteran-Owned Small Businesses and involves phased removal of an existing boiler system and installation of upgraded boilers with associated controls at the Dayton VA Medical Center. The contractor must complete all work within 960 calendar days of receiving the notice to proceed. The solicitation documents will be posted on SAM.gov around June 1st with proposals due approximately 30 days later. The project value is between $5-10 million under NAICS code 238220 with a small business size standard of $16.5 million. The SDVOSB contractor must perform a minimum of 25% of construction work. Bid, payment and performance bonds will be required along with a one-time site visit. Questions should be emailed by the deadline specified. This notice provides information on the upcoming solicitation but does not include the solicitation itself.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25020B0014 A00002.docx | DOCX document | |
| 36C25020B0014 A00001.docx | DOCX document | |
| 013526 - Safety Requirements.pdf | ||
| Boiler Site Visit 9.9.2020.pdf | ||
| Pre-Bid RFIs (Responses).pdf | ||
| 16.1012.08-19.10.11-Final Bid Spec Vol 2.pdf | ||
| 16.1012.08-19.10.11-Final Bid Drawings.pdf | ||
| 36C25020B0014_2.docx | DOCX document | |
| P07. Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPLACE BOILERS (BLDG. 147)
Project No. 552-19-107
For the
Department of Veterans Affairs
Dayton VA Medical Center 4100 West Third Street
Dayton, OH 45428
PROJECT SPECIFICATIONS VOL. 1
DIVISIONS 00 – 05, 07 – 09, 13
BID DOCUMENTS
October 11, 2019
GUIDON DESIGN, INC.
HEAPY ENGINEERING
Department of Veterans Affairs October 11, 2019
Dayton VA Medical Center Bid Documents
Replace Boilers (Bldg. 147) Project No. 552-19-107
00 01 10 – 1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 10-17
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 05-16
01 45 00 Quality Control 01-18
01 45 29 Testing Laboratory Services 11-18
01 57 19 Temporary Environmental Controls 01-11
01 74 19 Construction Waste Management 09-13
01 91 00 General Commissioning Requirements 10-15
01 99 99 Project Closeout
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 09-15
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 12-15
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grouting 02-16
04 20 00 Unit Masonry 08-17
DIVISION 05 – METAL
05 12 00 Structural Steel Framing 11-18
05 50 00 Metal Fabrications 08-18
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 11 13 Bituminous Damp proofing 02-16
07 60 00 Flashing and Sheet Metal 07-14
07 72 00 Roof Accessories 07-14
07 84 00 Firestopping 02-16
07 92 00 Joint Sealants 10-17
Replace Boilers (Bldg. 147) Project No. 552-19-107
00 01 10 – 2
DIVISION 08 - OPENINGS
08 41 13 Aluminum-Framed Entrances and Storefronts 08-16
08 71 00 Door Hardware 01-16
08 80 00 Glazing 10-15
08 90 00 Louvers and Vents 05-15
DIVISION 09 – FINISHES
09 06 00 Schedule for Finishes 04-15
09 91 00 Painting 01-16
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-14
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-16
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 05 23 General-Duty Valves for Plumbing Piping 09-15
22 07 11 Plumbing Insulation 09-15
22 11 00 Facility Water Distribution 09-15
22 13 00 Facility Sanitary and Vent Piping 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 10 Common Work Results for Boiler Plant and Steam
Generation
08-17
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
08-17
23 05 51 Noise and Vibration Control for Boiler Plant 08-17
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15
23 07 11 HVAC and Boiler Plant Insulation 02-15
23 08 00 Commissioning of HVAC Systems 11-16
23 08 11 Demonstrations and Tests for Boiler Plant 08-17
23 09 11 Instrumentation and Control for Boiler Plant 08-17
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 11 Boiler Plant Piping Systems 09-17
23 25 00 HVAC Water Treatment 02-15
23 50 11 Boiler Plant Mechanical Equipment 11-17
23 51 00 Breechings, Chimneys, and Stacks 08-17
23 52 39 Fire-Tube Boilers 08-17
Replace Boilers (Bldg. 147) Project No. 552-19-107
00 01 10 – 3
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 73 Overcurrent Protective Device Coordination Study 01-18
26 08 00 Commissioning of Electrical Systems 11-16
26 24 16 Panelboards 01-18
26 27 26 Wiring Devices 01-18
26 29 11 Motor Controllers 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 41 00 Facility Lightning Protection 01-17
26 43 13 Surge Protective Devices 01-17
26 51 00 Interior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 15 00 Communications Structured Cabling 01-16
- - - E N D - - -
Replace Boilers (Bldg. 147) Project No. 552-19-107
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI000 COVER SHEET
GI100 CODE ANALYSIS
GI200 GENERAL PHASING PLANS AND BID ALTERNATES
STRUCTURAL
SI001 STRUCTURAL GENERAL NOTES
SD101 FIRST FLOOR DEMO PLAN
SD102 EXISTING BEAM DEMO PLAN
SD103 PLATFORM DEMO PLAN
SF101 FIRST FLOOR PLAN
SF102 ROOF PLAN
SF301 FRAMING ELEVATIONS
SF401 STRUCTURAL SECTIONS AND DETAILS
ARCHITECTURAL
AS001 ARCHITECTURAL SYMBOLS AND ABBREVIATIONS
AD101 FIRST FLOOR DEMOLITION PLAN
AD102 THIRD FLOOR DEMOLITION PLAN
AD103 ROOF DEMOLITION PLAN
AS101 FIRST FLOOR ARCHITECTURAL PLAN
AS102 SECOND FLOOR ARCHITECTURAL PLAN
AS103 THIRD FLOOR ARCHITECTURAL PLAN
AS300 ROOF PLAN
AS400 BUILDING ELEVATIONS
AS500 WALL SECTIONS
MECHANICAL
M001 LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
MD111 FIRST FLOOR PLAN – REMOVALS – PHASE 1
MD112 FIRST FLOOR PLAN – REMOVALS – PHASE 2
MD113 FIRST FLOOR PLAN – REMOVALS – PHASE 3
MD114 FIRST FLOOR PLAN – REMOVALS – PHASE 4
M101 BASEMENT PLANS – PHASE 1
Replace Boilers (Bldg. 147) Project No. 552-19-107
00 01 15 - 2
M102 BASEMENT PLANS – PHASE 2
M103 BASEMENT PLANS – PHASE 3
M104 BASEMENT PLANS – PHASE 4
MH111 FIRST FLOOR PLAN – PHASE 1
MH112 FIRST FLOOR PLAN – PHASE 2
MH113 FIRST FLOOR PLAN – PHASE 3
MH114 FIRST FLOOR PLAN – PHASE 4
MH115 PIPING SUPPORT SYSTEM
M121 ROOF PLANS – PHASE 1
M122 ROOF PLANS – PHASE 2
M123 ROOF PLANS – PHASE 3
M124 ROOF PLANS – PHASE 4
M401 ENLARGED PLANS
M402 STEAM BOILER PLANT ISOMETRIC
M403 STEAM BOILER PLANT ELEVATIONS
M404 STEAM BOILER PLANT ELEVATIONS
M501 DETAILS
M502 DETAILS
M503 DETAILS
M601 SCHEDULES
M602 STEAM BOILER PIPING SCHEMATIC – REMOVALS
M603 STEAM BOILER PIPING SCHEMATIC – NEW WORK
M604 TYPICAL STEAM BOILER PIPING
M701 STEAM CONTROL SCHEMATIC LEGEND
M702 STEAM CONTROL SCHEMATIC
M703 STEAM CONTROL SCHEMATIC POINTS LIST
ELECTRICAL
E001 LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
ED111 FIRST FLOOR PLAN – REMOVALS – PHASE 1
ED112 FIRST FLOOR PLAN – REMOVALS – PHASE 2
ED113 FIRST FLOOR PLAN – REMOVALS – PHASE 3
ED114 FIRST FLOOR PLAN – REMOVALS – PHASE 4
ED121 SECOND FLOOR PLAN – REMOVALS – PHASES 1,2,3 & 4
EP111 FIRST FLOOR PLAN – NEW WORK – PHASE 1
EP112 FIRST FLOOR PLAN – NEW WORK – PHASE 2
EP113 FIRST FLOOR PLAN – NEW WORK – PHASE 3
Replace Boilers (Bldg. 147) Project No. 552-19-107
00 01 15 - 3
EP114 FIRST FLOOR PLAN – NEW WORK – PHASE 4
EP121 SECOND FLOOR PLAN – NEW WORK – PHASES 1,2,3 & 4
E601 SINGLE LINE DIAGRAM
E602 SCHEDULES
PLUMBING
P001 LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
PD111 FIRST FLOOR PLAN – REMOVALS – PHASE 1
PD112 FIRST FLOOR PLAN – REMOVALS – PHASE 2
PD113 FIRST FLOOR PLAN – REMOVALS – PHASE 3
PD114 FIRST FLOOR PLAN – REMOVALS – PHASE 4
PP111 FIRST FLOOR PLAN – NEW WORK – PHASE 1
PP112 FIRST FLOOR PLAN – NEW WORK – PHASE 2
PP113 FIRST FLOOR PLAN – NEW WORK – PHASE 3
PP114 FIRST FLOOR PLAN – NEW WORK – PHASE 4
P501 DETAILS AND SCHEDULES
FIRE PROTECTION
FX001 LEGEND, SYMBOLS & INDEX OF DRAWINGS
FX002 GENERAL NOTES & DETAILS
FX101 FIRE SUPPRESSION FLOOR PLANS
Replace Boilers (Bldg. 147) Project No. 552-19-107 i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
1.10 RESTORATION
1.11 AS-BUILT DRAWINGS
1.12 WARRANTY MANAGEMENT
1.13 USE OF ROADWAYS
1.14 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.15 TEMPORARY TOILETS
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
1.17 TESTS
1.18 INSTRUCTIONS
1.19 RELOCATED EQUIPMENT AND ITEMS
1.20 CONSTRUCTION SIGN
1.21 SAFETY SIGN
1.22 PHOTOGRAPHIC DOCUMENTATION
1.23 HISTORIC PRESERVATION
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for REPLACEMENT OF BOILERS IN
BUILDING 147 as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
CONTRACTING OFFICER REPRESENTATIVE (COR).
C. Offices of GUIDON, 1221 N PENNSYLVANIA STREET INDIANAPOLIS, IN 46202, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting
Officer or his duly authorized representative.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. BID ITEM I, BASE BID: Work includes all labor, material, equipment, and supervision for phased removal of the boiler system and to provide upgrade boilers as indicated in the contract documents. Removal includes general construction, alterations, temporary measures, removal and patching of existing structures and construction, and removal and abatement of existing steam boilers and systems. Provide upgraded boilers includes the indicated upgraded steam boilers, controllers, connections, automatic combustion air dampers interlocked with each new boiler and associated louvers, replacement/upgrade of controllers for the existing deaerator and associated feed water pumps, replacement/upgrade of controllers for the existing condensate storage
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 2 tank and associated transfer pumps, and certain other items. The indicated Demolition, temporary measures, and of installation of upgrade walls, windows, frames, glazing, roof accessories, steel structure, metal access stairs and platforms, concrete, and finish points and coatings shall be coordinated with phases of boiler system work.
PERIOD OF PERFORMANCE: All work shall be completed within Nine Hundred
Sixty (960) calendar days after the contractor receives Notice to
Proceed.
BASE BID LUMP SUM: $
B. BID ITEM II, DEDUCT ALTERNATE 1: Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project in BID ITEM I, except existing Boiler
#2 shall not be included in the demolition scope, shall be operational throughout the work and protected in place. Boiler #2 burner modulation shall be integrated into the new master control system.
Permanently relocate existing master control panel. Combustion air dampers and louvers for Boiler #2 shall be provided, damper to remain closed. No new boiler shall be provided to replace existing Boiler #2.
Omit the demolition, temporary measures, and of installation of walls, windows, frames, glazing, roof accessories, steel structure, metal access stairs and platforms, and concrete indicated as preparations or upgrades associated with Boiler #2 phase of boiler system work.
PERIOD OF PERFORMANCE: All work shall be completed within Seven
Hundred Eighty (780) calendar days after the contractor receives Notice to Proceed.
BID ITEM II LUMP SUM: $
C. BID ITEM III, DEDUCT ALTERNATE 2: Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project in BID ITEM II, except existing
Boiler #1 shall not be included in the demolition scope, and shall operational throughout the work and protected in place. The existing
Boiler #1 control panel shall be relocated. Boiler #1 burner modulation
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 3 shall be integrated into the new master control system. No new combustion air dampers or louvers are to be provided for boiler 1 or boiler 2. No new boiler shall be provided to replace existing Boiler
#1. Omit the demolition, temporary measures, and of installation of walls, windows, frames, glazing, roof accessories, steel structure, metal access stairs and platforms, and concrete indicated as preparations or upgrades associated with Boiler #1 phase of boiler system work..
PERIOD OF PERFORMANCE: All work shall be completed within Six Hundred
(600) calendar days after the contractor receives Notice to Proceed.
BID ITEM III LUMP SUM: $
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
B. In the case of conflicts or discrepancies within or among the Contract
Drawings and Project Manual, the better quality, more stringent, requirements or greater quantity of work, as determined by the
Government, shall be provided.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 4
2. Before starting work, the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 5 to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Separate permits shall be issued for General Contractor and its employees for parking in designated areas only. Obtain parking passes from Police Services, Building 127.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 6 furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of the VA campus applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of the VA Medical Campus as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two working days.
3. Where access by VA personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 7
G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
H. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to
COR and Contractor.
I. Part of Bldg. 147 will be vacated by Government in accordance with above phasing beginning immediately after date of receipt of Notice to
Proceed and turned over to Contractor.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet)
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 8 minimum height, around the construction area. Provide gates as required for access with necessary hardware, including hasps and padlocks.
Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm
(15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.
K. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for the VA
Medical Campus at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems
(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS and 28 05 00, COMMON WORK
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 9
RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR .
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
N. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 10
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the
Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of doors, windows, walls and other surfaces not required to be altered throughout building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, etc. required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR
852.236-88).
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 11
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed, they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 12
2. Items not reserved shall become property of the Contractor and be removed by Contractor from VA Medical Campus.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 13 environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 14
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR’s review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the Resident COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 15
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 16
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance Bond: The Performance Bond must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for
Contractor response, and other details deemed necessary by the
Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 17 requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
Following oral or written notification by the Contracting Officer, the
Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the
Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
Code 1-Life Safety Systems
a. Fire suppression systems.
b. Fire alarm system(s).
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 18
Code 1-Air Conditioning Systems
a. Air conditioning leak in part of the building, if causing damage.
b. Air conditioning system not cooling properly.
Code 1 Doors
a. Overhead doors not operational, causing a security, fire or safety problem.
b. Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
Code 3-Doors
a. Overhead doors not operational.
b. Interior/exterior personnel doors or hardware not functioning properly.
Code 1-Electrical
a. Power failure (entire area or any building operational after 1600 hours).
b. Security lights.
c. Smoke detectors.
Code 2-Electrical
a. Power failure (no power to a room or part of building).
b. Receptacles and lights not operational (in a room or part of building).
Code 3-Electrical
a. Exterior lights not operational.
Code 1-Gas
a. Leaks and pipeline breaks.
Code 1-Heat
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 19
a. Power failure affecting heat.
Code 1-Plumbing
a. Hot water heater failure.
b. Leaking water supply pipes.
Code 2-Plumbing
a. Flush valves not operating properly
b. Fixture drain, supply line or any water pipe leaking.
c. Toilet leaking at base.
Code 3- Plumbing
a. Leaky faucets.
Code 3-Interior
a. Floors damaged.
b. Paint chipping or peeling.
c. Casework damaged.
Code 1-Roof Leaks
a. Damage to property is occurring.
Code 2-Water (Exterior)
a. No water to facility.
Code 2-Water (Hot)
a. No hot water in portion of building listed.
Code 3
a. All work not listed above.
E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting
Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 20 showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
1.13 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on VA Medical
Campus property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 21
C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.
1.14 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 22 replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
Boilers, pumps, feedwater heaters and auxiliary equipment must be operated as a complete system and be fully maintained by operating personnel. Boiler water must be given complete and continuous chemical treatment.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.15 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
Replace Boilers (Bldg. 147) Project No. 552-19-107
01 00 00 - 23
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the
COR a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted.
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code.