This document is a Pre-Bid Questions file for Solicitation 15BFTD25Q00000008, covering the purchase, installation, and removal of an HVAC rooftop unit for Building 5845 at FCI Fort Dix. The solicitation seeks a contractor to replace a 30-ton package rooftop heating and cooling system, with specific requirements including a York model unit using R454B refrigerant, bottom return/supply configuration, and meeting detailed technical specifications.

Key procurement details include a small business set-aside, lowest price technically acceptable source selection process, and critical dates: site visit on March 13, 2025, NCIC submission deadline of March 5, 2025, questions due by March 17, 2025, questions answered on March 19, 2025, and bid submission due March 20, 2025 at 11:59 PM ET. The project involves removing the existing HVAC unit, installing a new unit with specific performance requirements, and adhering to strict security protocols at the Federal Correctional Institution, with work to be completed during normal hours (7:30 AM - 3:30 PM) and potentially on weekends with approval.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-BID QUESTIONS SOLICITATION 15BFTD25Q00000008

FCI FORT DIX PURCHASE, INSTALLATION & REMOVAL OF HVAC ROOFTOP

BUILDING 5845

Eagle Solutions

1. Existing Unit and Curb Measurements: * Distance from Roof Edge: Measure and document the exact distance from all roof edges to the existing HVAC unit's curb. Note any obstructions (parapet walls, equipment, level changes) in the vicinity. * Curb Dimensions: Record the length, width, and height of the existing curb. Please provide detailed photographs from multiple angles. * Unit Dimensions: Measure the existing unit's length, width, and height. Document the location of all utility connections (electrical, gas, etc.).

See SOW Schedule of Delivery Performance.

2. Crane Accessibility and Location: * Distance from Building:

Identify potential crane locations on the ground and measure the horizontal distance to the building's edge. Document any obstacles between the crane location and the rooftop (trees, power lines, etc.). * Vertical Reach: Measure the building's height from the ground to the rooftop. Calculate the required lift height to place the new unit onto the curb. * Ground Conditions: Assess the ground conditions at potential crane locations (level, stable, etc.). Note the presence of any underground utilities. * Access Routes: Evaluate access routes for the crane (narrow roads, low bridges, etc.).

See SOW Description of Building 5845.

3. York Curb Box Compatibility: * York Specifications: Provide the detailed specifications for the proposed York HVAC unit, including required curb dimensions. * Curb Compatibility: Verify the compatibility of the new York curb box with the existing roof opening and structure. * Curb Adaptability: Determine if curb adapters will be necessary. Important Considerations: * Safety is paramount. All work must be performed by qualified professionals. * Ensure compliance with all applicable building codes and regulations. * A professional on-site assessment by an HVAC contractor and crane operator is highly recommended.

See SOW Schedule of Delivery Performance.

R&R Logistics

1. Will ducting be required for this installation or is there existing ducting that can be used for the new installation?

See SOW Description of Heating/Cooling Unit.

2. Is there a brand that is preferred by the facility or are they open to any brand that fits the specifications needs?

Any brand that fits the specification in SOW Description of Heating/Cooling Unit.

3. Are you able to provide pictures for this project?

Pictures shall be posted.

Universal Mechanical Group

1. Lead times for the project could be about 16 weeks from suppliers. Can this work if awarded the contract.

FTD is aware this is an as built unit from the manufacturer and expect lead times to be between 8-26 weeks.

2. If it takes us 4 days to complete the swap and installation of the new unit, would this be allowed?

See SOW Schedule of Performance.

Wireless Network Group Inc

1. Can we set up crane and drop new equipment day prior to swap?

Crane and equipment can be brought on site a few days prior in preparation of the unit installation.

2. We are reaching over powerlines. Can they be de-energized or we need to have covered for crane?

The utility poles and high voltage wires are approximately 26 feet away from the outer perimeter fence. The crane can position on the outer perimeter roadway between the outer fence and utility poles/high voltage wires. The crane operator should be able to position whereas to not disturb the electric. The lines will not be de-energized during this project.

3. We were given standard time limits of 7:30amto 3:30pm. We will need a 12hr window.

See SOW Schedule of Performance. FTD will coordinate with contractor during scheduled installation to approve for time beyond normal working hours.