FPC DULUTH – BAS SYSTEM

PROJECT 4C2X QUESTIONS & ANSWERS

SOLICITATION 15B40218B00000003

BBA Construction:

1. Part 2.1.D of the Specification states “…together with associated Point Sheets and Drawings…”. The Point Sheet is necessary for each building to provide a description of all points in each building getting connected to the existing devices via existing wiring as stated in Paragraph A of Part 2.

1. Is a Point Sheet available for each affected building?

Clarification: There is a Point Sheet available for each building.

2. Confirm the BAS will be connected to existing devices using existing wiring.

Clarification: The existing devices and existing wiring will be used to connect the BAS. Some wiring may be needed on a case by case basis.