15B10624Q00000008 FCC BUTNER FREEZER TRAILERS QUESTION AND ANSWERS - Amendment 2.pdf
PDF 93 KB Posted
- Solicitation number
- 15B10625Q00000008
About this file
This is a Questions and Answers document for solicitation 15B10624Q00000008 regarding freezer trailers at FCC Butner. The document clarifies four key points about the requirement.
The Q&A confirms this is a new contract with no incumbent. It specifies that a total of 9 freezer trailers are required for a 6-month period from April to September, despite line items 1-9 each listing 6 trailers. The delivery fee in line item 10 covers the delivery of all 9 trailers. The clean-up fee mentioned in the document is specifically for removing the trailers at the end of the 6-month contract period.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS FOR SOLICITATION 15B10624Q00000008 FCC BUTNER FREEZER TRAILERS
1. Is this a brand new contract or if there is (was) an incumbent performing these services. If not brand new, could you please provide the current/previous contract number?
Answer: This is a new contract.
2. Do you only need 6 trailers? I see the schedule of supplies with line items 1- 9 listing 6 trailers each. Can you please clarify?
Answer: The requirement is for a total of 9 trailers for a 6-month period from April to September.
3. Line item 10 only has a quantity of 9 for delivery fees. Do you only want 9 trailers delivered?
Answer: Yes, 9 trailers are required for delivery.
4. Can you please clarify the clean up fee? What debris will need cleaning?
Answer: The clean-up fee covers the cost of removing the trailers at the end of the 6-month period.
File details come from the government source that posted it. Updated .