This document contains Questions and Answers related to the PLC Upgrade and Replacement solicitation, Solicitation Number 15A00024R00000087, issued by the Department of Justice Bureau of Alcohol, Tobacco, Firearms, and Explosives (ATF). The key details are:
The solicitation is for a commercial item to upgrade an existing Programmable Logic Controller (PLC) and I/O cards at the ATF's Fire Research Laboratory. Offerors may submit any past performance information they deem relevant, as the government will review CPARS and other databases to evaluate technical capability. Proposals are due by 09:00 AM EDT on 07/19/2024 and must remain valid for 30 calendar days. This is a small business set-aside competitive acquisition, evaluated using the Lowest-Price-Technically-Acceptable (LPTA) method. The solicitation incorporates various FAR commercial provisions and clauses.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 4 - PLC Upgrade Project Site Details.docx | DOCX document | |
| 15A00024R00000087.pdf | ||
| Attachment 2 - Evaluation Criteria.docx | DOCX document | |
| Attachment 1 - Instructions.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
15A00024R00000087 - Questions & Answers
1. We respectfully solicit the provision of the following information: Panel drawings and visual documentation, Site layout plans, Any notable design limitations, Availability of existing PLC code.
· See attached document titled “PLC Upgrade Project Site Details.”
2. Will HMI or Panel views be required?
· No
3. Our understanding of a perpetual license is that it is restricted to version 36 with no upgrades. Can you clarify if this is your understanding as well and that you do not have any concerns with this constraint?
· We were not aware of this, however, if the ATF requires some function or capability not available in ver. 36, we will seek a solution at that time.
4. Is there a desire/requirement for spare parts?
· There is no requirement for spare parts. We are moving away from discontinued hardware and expect any replacements needed to be readily available.
5. Will the contractor have access to drawings? Is there a requirement to update drawings?
· We can supply the paper copies we have after award. We will expect updated drawings, both paper and electronic at the completion of the project.
6. The materials list does not include a UPS, is there one in place, or should this be included as an additional item?
· The building has multiple UPS units, and our equipment utilizes circuits tied to these UPS units. Standalone UPS for the PLCs will not be required.
7. The instructions indicate that no Past Performance information is required/desired and that CPARS and other databases will be used; however, not all projects have a CPARS on file. It is unclear how the government will know what clients/projects to research/reference if no past performance information is provided. It would seem beneficial to have at least agency name, project name, contract number, and point of contact provided. Please clarify if this information can be included for Past Performance to ensure all relevant experience is appropriately considered.