This is Addendum No. 3 issued by the Virginia Department of Transportation (VDOT) for IFB 159297 regarding the Stanardsville Area Headquarters Combo Building project (Project Code 501-18130-047). The addendum, dated December 20, 2024, includes changes and clarifications for the project located in Ruckersville, Virginia. Bids are due December 26, 2024, at 2:00 PM, with a prebid conference held on December 9, 2024. The addendum addresses multiple technical questions regarding construction specifications, including revisions to workstation areas, door weather stripping requirements, overhead door specifications, and helical pile requirements.
Key technical clarifications include: no load testing required for helical piles (70-Kip exterior/20-Kip interior capacity), permission for square helical pile lead anchors, confirmation of epoxy coated rebar requirements for the Chemical Storage Building, elimination of concrete cradle requirements for existing pipes, and rejection of the Hormann Steel Ranger 9500 LS as an approved overhead door. The addendum also clarifies that the WQU and UST shown on prototype drawings are not applicable to this project, as a new salt pond will control runoff. The document specifies that no fire-rated walls are required for the Prototype Combination Office and Maintenance Building.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF TRANSPORTATION
Stephen C. Brich, P.E. 1401 East Broad Street (804) 786-2701 Commissioner Richmond, Virginia 23219 Fax: (804) 786-2940 December 20, 2024
ADDENDUM No. 3 TO ALL BIDDERS:
Reference-IFB: 159297 Commodity Stanardsville Area Headquarters Combo Building
Project Code: 501-18130-047 Dated: November 26, 2024
For Delivery To: Virginia Department of Transportation (VDOT) Attention: Joshua Saunders
Bids Due: December 26, 2024 @ 2:00PM Prebid Conference December 9, 2024
The above is hereby changed to read:
1. In Reference to Addendum #3 sealed by William L. Allen of Virginia A&E. (3 pages) to include Questions and Responses.
Note:
Acknowledgement of this addendum or any subsequent addenda must be prior to the bid due date and time or signed and uploaded as an attachment with the electronic bid submission. Failure to acknowledge or submit the addendum may be grounds for declaring the bid non-responsive.
Sincerely, Joshua Saunders Joshua Saunders, VCCO, VCO, Senior Procurement Officer
Name of Firm
Signature Title Date
Addendum No. 3 VDOT Stanardsville Area Headquarters IFB No. 159297 Project Code No. 501-18130-047 VAE Project No. 23021
5. Question: Helical piles: Will a load test be required? On the Bid form it says 70 KIPS but, it reads Ninety
KIPS.
Response: No load test is required. Exterior helical piles are 70-Kip ultimate load capacity, minimum.
Interior helical piles are 20-Kip ultimate load capacity, minimum. Change “ninety” to “seventy” under Bid Form, Part F.
6. Question: Specifications Section number 316613, page 1.7B: It says no square bar shall be used. Does this include the lead Section? Most all leads are square shaft and then transition to the round shaft. The theory is that the square shaft is in laterally supported soil. This one is important because round shaft leads are specially made. Cost are expensive.
Response: Square helical pile lead anchors are permitted. All pile extensions above the lead anchor shall be round shaft.
7. Question: Does Chemical Storage Building require epoxy coated rebar?
Response: Yes, refer to Concrete Note 5 on Drawing 4S3.
8. Question: Storm Sewer Details on Drawing C10: SWM-DR detail shows Concrete Cradle schedule. Is encasement required as pipe is existing?
Response: A concrete cradle is not required on the existing pipe.
9. Question: OFF-SITE WATERLINE PLAN Drawing C9: Casing indicated of 45 LF 4inch DR-11 pipe. 4 inch DR-11 comes in 40 ft sticks. Would reducing the casing to 40 ft be allowed?
Response: A minimum of 45 feet must be provided to allow for sufficient offset from the edge of pavement.
10. Question: Chemical Storage Building Drawing A4.2: SALT STORAGE TANK schematic for the WQU and UST, indicates an overflow line, which presumably goes to Str 26. Does this overflow line replace the run shown between Str 27 and Str 26? Implying Str 27 is moved to other side of pad? (to be close to UST) or does 27 - 26 stay as shown, and a 2nd catch basin (+130 LF pipe) be assumed to make the UST system functional?
Response: The WQU and UST shown on Prototype Chemical Storage Building Drawing A4.2 are not located or identified on the Stanardsville AHQ Site Drawings and therefore not applicable to this project, as a new salt pond will control runoff from pads.
11. Question: Chemical Storage Building Drawing A4.2: Please provide sizing on ADS Water Quality Unit.
Civil Set Cover Sheet page G, Note 3. states VDOT will provide and install any calcium chloride or brine pumps and associated power on this project. Please confirm the site contractor will furnish and install 20,000 gallon tank only.
Response: The 20,000 gallon underground storage tank and associated water quality unit shown on Prototype Chemical Storage Building Drawing A4.2 are not located or identified on the Stanardsville AHQ Site Drawings and therefore not applicable to this project.
12. Question: Refer to Office & Maintenance Building Drawing FP1: Please provide wall fire rating types.
Response: None of the walls associated with the Prototype Combination Office and Maintenance Building are required to be fire rated.
13. Question: Refer to Specification Section 033000, page 1, paragraph 1: Concrete specification makes no mention of the requirement for using epoxy coated rebar at all cast-in-place concrete applications. Please confirm epoxy coated rebar is required.
Addendum No. 3 VDOT Stanardsville Area Headquarters IFB No. 159297 Project Code No. 501-18130-047 VAE Project No. 23021
Response: Referenced Specification Section is for Protype Combo Building which does not require epoxy coated rebar. Per Specifications Outline Item 2 on Page 6 of the Project Manual - Volume 1 Table of Contents, the same specification is applicable to the Sitework Equipment Storage Building, and Fuel Station; all of which do not require epoxy coated rebar. Per Concrete Note 5 on Drawing 4S3, epoxy coated rebar is required for the Chemical Storage Building.
14. Question: Refer to Specification Section 083323, page 1, paragraph 1: Specification 083323 lists approved overhead coiling door manufacturers, please advise if Horman Steel Ranger LS door would be considered as an approved equal.
Response: Hormann Steel Ranger 9500 LS overhead door is NOT an approved equal due to available motor voltages/phasing, no indication of compliance with UL 235, no indication of compliance with NFPA 70, slat material thickness, and springless construction.
15. Question: Refer to Prototype Chemical Storage Building Drawing A4.2 - Salt Storage Tank: During the pre-bid it was mentioned that either build the salt pond or salt storage tank. Both are shown on the plans and if it is either/or, please advise which one is preferred.
Response: Refer to Questions 10 and 11 above.