Amendment_No._0003.pdf

PDF 124 KB Posted

Attached to
Guernsey Powerplant - Surge Tank Recoating, North Platte Project, Wyoming
Solicitation number
140R6018R0005
Issued by

About this file

Amendment No. 0003

View the file

Other files

File Type Posted
Amendment_No._0002.pdf PDF
Amendment_No._0001.pdf PDF
Solicitaton_No._140R6018R0005.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140R6018R0005 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Billings MT 59107

R60

PO Box 36900 Regional Office Great Plains Region Bureau of Reclamation

05/29/20180003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/16/2018

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Gerri Voto-Braun

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Guernsey Powerplant - Surge Tank Recoating, North Platte Project, Wyoming

The final list of questions and answers from prospective contractors is attached to this amendment.

Receipt of Proposals: The hour and date for receipt of proposals is extended to 2:00 pm MDT on June 27, 2018.

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Solicitation No. 140R6018R0005 – Guernsey Powerplant – Surge Tank Recoating Prospective Contractor Questions and Answers

8. Can the NACE III Inspector be an employee of the contractor or must they be third party? Also, is the NACE III Inspector required to be onsite full time during cleaning and painting operations or is spot inspection allowed?

In accordance with specifications Section 099620, Paragraph 1.04.C, the coating inspector shall be NACE CIP Level III or SSPC CPI Level III certified. The coating inspector may be a contractor employee or an independent third party. The coating inspector shall be onsite to conduct the Contractor Field Quality Testing specified in Section 099620, Article 3.08.

9. Specifications call for “Area ambient air monitoring results by EPA Air Method TO- 13A. [Submit] Personal and area air monitoring results for coal tar concentrations during coating removal activities. Air Samples for coal tar components are to be analyzed by EPA Air Method TO-13A….Do not exceed ambient air quality standards.”

A. Will BOR accept monitoring and analysis of occupational exposures by NIOSH method 5042?

B. WDEQ indicates that there are no specific ambient standards for coal tar or its PAH components. What ambient standard would be used?

C. Given that ambient standards do not appear to exist, and that TO 13a is quite expensive, would BOR accept NIOSH 5042 for the other air sampling requirements?

D. Specifications mention that existing coating contains heavy metals. Analytical indicates modest levels of chromium and lead are present (0.1% by weight). Will air monitoring before, during and after the work be required for these metals in addition to coal tar?

Contractor shall perform sampling, testing and monitoring in accordance with specifications Section 028910 for coal tar products and heavy metals.

File details come from the government source that posted it.