Amendment_0003_DESCRIPTION_OF_CHANGES.pdf
PDF 2 MB Posted
- Attached to
- EC-RAX 4158 GREEN MTN PENSTOCK REHAB
- Solicitation number
- 140R6018R0004
About this file
Amendment 0003
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GRN_MTN__amendment_4.pdf | ||
| Amendment_2.pdf | ||
| 140R6018R0004__Amendment_0001.pdf | ||
| 16.__Solicitation_GRN_MTN__May__29__2018.pdf | ||
| FedConnect File | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R6018R0004 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Billings MT 59107
R60
PO Box 36900 Regional Office Great Plains Region Bureau of Reclamation
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE
07/10/2018
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/29/2018
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Green Mountain Powerplant Penstock Rehabilitation, Colorado Big Thompson Project, Colorado
See Page 2 for changes incorporated in this amendment.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Paris Everson
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Amendment 0003 Solicitation 140R6018R0004
____________________________________________________________________ Page 2 of 5
1. DESCRIPTION OF CHANGES:
SECTION 01 54 20 – Use of Government Cranes:
a. Remove Section 01 54 20 in its entirety and therefor insert Revised Section 01 54 20.
SECTION 09 97 02 – Impacted Immersion Coatings:
a. Remove pages 09 97 02 -19 and 09 97 02 -20 and therefor insert pages Revised 09 97 02 -19 and Revised 09 97 02 -20.
SECTION 52 00 00 – Drawings
a. Remove Section 52 00 00 in its entirety and therefor insert Revised Section 52 00 00.
DRAWINGS:
a. Insert informational drawing 245-D-1528 as Sheet 90A – Green Mountain Power Plant – Substructure – Concrete Outline – Longitudinal Sections – Second Stage – Sheet 1 of 2.
b. Insert drawing 245-D-411 as Sheet 43A – Green Mountain Dam – Outlet Works – Gate Chamber, Shaft and Hoist House.
2. QUESTIONS AND ANSWERS:
Question 9.
Question: The Contractor will be required to remove existing valve bases. Concrete Repair specifications Section 038114, Paragraph 3.01A mentions, “unexpected embedded items,” and Drawing 245-D-1527 (provided within the solicitation) indicates there is a section A-A on Drawing 245-D-1528.
This second Drawing was not part of the Issued set. Please provide Drawing 245-D-1528, as part of an amendment.
Answer 9.
Reference “For Information Only” drawing 245-D-1528 (sheet 90A) included with this amendment. All existing conditions shall be field verified by contractor.
Question 10.
Question: Since the proposals due date has been extended, via Amendment No. 0001, would Reclamation consider having another Pre-Proposal Site Visit on this project? As an alternative, would it be acceptable to contact the Green Mountain powerplant representative, listed in the specifications, to visit the site when it's convenient for the powerplant personnel?
Answer 10.
No, there will be no additional pre-proposal site visits. Also the proposal due date was extended in Amendment 0002, not Amendment 0001.
____________________________________________________________________ Page 3 of 5
Question 11.
Question: Will the contractor have use of Reclamation's manbasket that is currently stored in the hoist house?
Answer 11.
Reclamation’s manbasket will be available for emergency egress only. No other use of the basket will be permitted.
Question 12.
Question: Steel Piping specifications Section 352194, Paragraph 2.01.C.2.b requires ASME BPVC VIII, Division 1, Appendix 2 code for the 50" flange upstream of the new jet flow gate valves. Is it acceptable to use AWS D1.1 welding code for this?
Answer 12.
No, it is not acceptable to use AWS D1.1 welding code.
Question 13.
Question: Photo 9 in specifications Section 510030 shows the facility access platform mounted beneath the runner. Will the contractor be permitted to use the platform to access the work area for cavitation inspection and repair? Are there installation instructions or drawings available for the platform?
Answer 13.
No, the existing access platform is not available for contractor use.
Question 14.
Question: Are there stop logs or other means of flow stoppage upstream of the Gate Chamber Valves for the respective penstocks?
Answer 14.
No.
Question 15.
Question: During the outage periods, will the Owner’s staff be available for operating the Owner’s equipment (cranes, valves, etc.) during a night shift or on a 24 hours/day basis? If so, is there a cost to the contractor for the availability of personnel?
Answer 15.
No, reference specifications Section 015420, Paragraph 1.06.A, for availability of scheduling Government cranes.
Question 16.
Question: Are there other costs to the Owner that the contractor will be required to pay in order to work 24/7 during the outage periods?
____________________________________________________________________ Page 4 of 5
Answer 16.
No, reference specifications Section 011412, Paragraph 1.02.C.1, for allowable work hours.
Question 17.
Question: Are all of the owner provided items to be received at the same time?
Answer 17.
Question is unclear. There is no Government-furnished equipment referenced in the solicitation.
Question 18.
Question: Do penstock support brackets have to be removed and replaced to allow the penstock pipe to be coated in the area concealed by the brackets?
Answer 18.
Refer to specifications Section 099620, Paragraph 3.10, Tabulation No. 1a. The walkway support brackets are welded onto the penstock and do not have to be removed.
Question 19.
Question: Is any painting required on the gate?
Answer 19.
No.
Question 20.
Question: During the site visit, a reference was made to handrail that doesn't meet OSHA? Which handrail? Will it have to be replaced by the contractor prior to the start of work?
Answer 20.
Reclamation is aware of the dimensions of the existing hand railing. Replacing the railing is not in the scope of work, and is not required under this solicitation.
Question 21.
Question: Can the power house gantry crane be used for the stoplog installation and testing? The as-builts lead us to thinking the existing footprint of the gantry cannot make this reach and therefor an outside crane service will be utilized for this activity.
Answer 21.
No. The bridge crane cannot reach the area required to install or remove the stoplogs. The contractor is required to provide a crane, operator, rigging, etc. for this work.
Question 22.
Question: What will be the upstream limits to the Blast/Recoat of Interior Penstock pay item? Will it include any of the existing ring seal gates?
____________________________________________________________________ Page 5 of 5
Answer 22.
Reference specifications Section 099702, Paragraph 3.10, Tabulation No. 1, Note No. 4.
Question 23.
Question: Will any of the existing handrail need modification to reach todays OSHA standards? Site visit narrative led us to assume this.
Answer 23.
Refer to answer provided for question 20.
Question 24.
Question: Has Reclamation had any preliminary correspondence with any of the Jet Flow Gate suppliers and determine anticipated lead time delivery dates?
Answer 24.
No.
Question 25.
Question: Specifications Section 352225, Paragraph 3.01 B calls for modification and reuse of existing floor grating and supports. Specifications Section 055000, Paragraph 1.01.A.b calls for removal and disposal of the grating, beam and connection components. Please confirm which specifications section is correct.
Answer 25.
Specifications Section 055000 is correct. Reference revised specifications Section 352225 included with this amendment.
NOTE: Last time and date to submit questions:
The final time and date to submit questions is 12:00 pm (local time), July 13, 2018. Questions after this time and date will not be addressed. This is to ensure the government has time to respond and then advertise response so interested parties can react. The RFP due date & time remains the same as stated in Amendment 0002.
3. LIST OF ATTACHMENTS:
SECTION 01 54 20 – Use of Government Cranes:
SECTION 09 97 02 – Impacted Immersion Coatings: Pages 19-20 SECTION 52 00 00 – Drawings Informational Drawing 245-D-1528 Drawing 245-D-411
This page intentionally left blank
Green Mountain Powerplant Penstock Rehabilitation Amendment No. 003 Colorado Big Thompson Project, Colorado Solicitation No. 140R6018R0004
Use of Government Cranes
Revised 01 54 20 - 1
SECTION 01 54 20
USE OF GOVERNMENT CRANES
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include cost in prices offered in the Price Schedule for equipment requiring use of Government cranes.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME B30.2-2011 Overhead and Gantry Cranes (Top Running Bridge, Single or Multiple Girder, Top Running Trolley Hoist)
2. ASME B30.26-2010 Rigging Hardware
B. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.
html
C. Code of Federal Regulations (CFR)
1. 29 CFR 1910.179 Occupational Safety and Health Standards - Overhead and Gantry Cranes
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 54 20-1, Crane Use Schedule:
1. Week schedule: Schedule for following week.
2. As required: 3 days in advance of need.
1.04 PROJECT CONDITIONS
A. Government-owned cranes in powerplant and hoist house may be used for:
1. Unloading and loading equipment, parts, tools, and supplies at powerplant and hoist house.
Revised 01 54 20 - 2
2. Removing existing equipment from powerplant and hoist house.
3. Moving equipment, parts, tools, and supplies within powerplant and hoist house.
4. Emergency egress.
B. Crane Capacities:
1. Powerplant: 50 tons.
2. Hoist House: 25 tons.
C. Hoist House Crane Travel Time:
1. It takes 13.5 to 14 minutes to travel the one way distance from top to floor of gate chamber.
1.05 CRANE USE
A. Government will provide crane operator. Operation of cranes by Contractor personnel is not permitted.
B. Contactor shall provide experienced, competent crane signaler.
C. Safety: Comply with ASME B30.2, RSHS, and 29 CFR 1910.179. Where there is a conflict between the standards, the more stringent shall prevail.
D. Contractor shall provide slings, shackles, and rigging required for use of crane in accordance with ASME B30.26.
E. Contractor is responsible for proper rigging of equipment and connections to crane.
1. Comply with ASME B30.2 and 29 CFR 1910.179.
1.06 SCHEDULING
A. Availability: 7:00 AM through 5:00 PM, Monday through Saturday.
B. Make written request for each use of Government crane to COR at least 3 days before crane is required.
C. Coordinate use of Government cranes with COR during weekly coordination meetings.
D. Government use of cranes will have priority over Contractor use; however the Government will make cranes available for Contractor use to the maximum amount possible while still accomplishing Government maintenance and operations.
1. Normal Government maintenance work hours are 7:00 am to 5:00 pm, Monday through Thursday.
E. Each crane will not be available for use during a period of 6 hours each month when the Government performs preventative crane maintenance. Also, each crane will not be
Revised 01 54 20 - 3 available for 2 days each year when the Government performs extensive annual maintenance.
F. Prepare crane use schedule after weekly coordination meeting:
1. Schedule shall cover 6 weeks.
2. Schedule for upcoming week shall be detailed. Start and stop times for crane(s) shall be listed with anticipated deviations of no more than 2 hours.
3. Schedule for out weeks may be less detailed with approximate times required for crane(s). Deviations from the scheduled times during weeks 2 and 3 should not be more than 1 day. Deviations from the schedule for weeks 4 through 6 should not be more than 1 week.
G. Notify COR at least 48 hours before changes to requested crane use during the current week.
H. Show crane use for major lifts on construction schedule.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Revised 01 54 20 - 4
This page intentionally left blank.
Impacted Immersion Coatings
Revised 09 97 02 - 19
e. Compressed air quality.
f. Dry film thickness (DFT).
g. Discontinuity (Holiday) testing.
h. Coating adhesion testing (when requested by the COR).
E. Final inspection will take place after repairs, but before placing into service.
3.08 REPAIR AND REMEDIAL WORK
A. Repair defective or damaged coatings as approved by COR.
1. Where repair of defective or damaged areas of coatings, requires partial removal of coating, test adhesion of remaining coating with a knife blade applied under the edge of remaining coating in accordance with ASTM D6677. Remove coatings which lift.
2. Physically repair pinholes, blisters, air bubbles, or dry spray by scrubbing with a brush or rag wet with ketone solvent before applying succeeding coat.
3. If corrosion is present, spot repair defective area. Prepare area using specified surface preparation method. Scrub remaining coating with ketone.
3.09 PROTECTION OF NEWLY COATED SURFACES
A. Do not walk on, subject to abrading action, or move items until coats are hardened sufficiently to resist damage.
3.10 COATING TABULATIONS
Impacted Immersion Coatings
Revised 09 97 02 - 20
Tabulation No. 1 - Impacted Immersion
Items to be coated:
a. Unit 1 and Unit 2: Blast and recoat interior surfaces of penstock and outlet tube, including appurtenances and other metalwork. Each unit penstock is approximately 900 linear feet and 102- to 84-inch diameter. Each unit outlet tube is approximately 150 feet in length and 50-inch diameter. There is approximately 25 and 5 linear feet of 8-inch diameter encased drain pipe from first bend to sump valve for Unit 1 and 2, respectively; 2 linear feet of 8-inch diameter by-pass pipe per unit; and 14 linear feet, including 4-foot wyes, of 14-inch diameter embedded penstock air vent pipe per unit.
b. Unit 1 and Unit 2: Blast and recoat interior surfaces of scroll case, including stay vanes. There is approximately 1,100 square feet per unit.
c. Unit 1 and Unit 2: Blast and recoat draft tube pier nose and pier grating. There is approximately 25 square feet per unit.
d. Unit 1 and Unit 2: Spot repair turbine runner on damaged coating surfaces and stainless steel cavitation repairs. There is approximately 90 square feet in Unit 1 and 120 square feet in Unit 2.
e. Unit 1 and Unit 2: Blast and recoat draft tube steel lining. There is approximately 155 square feet per unit.
f. Blast and coat new stoplogs and lifting beam. There is approximately 730 square feet.
g. Blast and coat new 40-inch jet-flow gate interior and exterior surfaces, including downstream body, upstream body, gate leaf, nuts, bolts, upstream pipe spool, wall gland spool, etc. There are two jet-flow gates total, and they require approximately 700 square foot of coating each.
h. Blast and coat interior and exterior surfaces of new 4-inch diameter and 14-inch diameter steel piping. There is approximately 470 linear feet of 14-inch diameter pipe and 4 linear feet of 4-inch diameter pipe.
i. Blast and coat interior and exterior surfaces of new steel pipe for air valve assembly and drain valves.
Drawings
Revised 52 00 00 - 1
SECTION 52 00 00
DRAWINGS
PART 1 GENERAL
1.01 DISCREPANCIES, ERRORS, OR OMISSIONS
A. Inform the CO of discrepancies discovered on drawings in accordance with clause at FAR 52.236-21, Specifications and Drawings for Construction.
B. In accordance with clause at FAR 52.236-21, Specifications and Drawings for Construction, in case of discrepancies, written specifications take precedence over drawings unless otherwise specified.
1.02 PROJECT CONDITIONS
A. Where there are differences as determined by the CO between details and dimensions shown on drawings and details and dimensions of existing features at jobsite, use details and dimensions of existing features at jobsite.
1.03 SPECIFICATION DRAWINGS
A. Reference drawings referred to on specification drawings and not considered necessary for contract purposes are not included in specifications.
1.04 INFORMATION DRAWINGS
A. Drawings marked "For Information Only" in the drawing list are included to show existing features about which knowledge is required to perform work under this contract.
These drawings do not show work to be performed under this contract.
B. If there are differences as determined by the CO between details and dimensions shown on these drawings and those of existing features at jobsite, use details and dimensions of existing features at jobsite.
1.05 STANDARD DRAWINGS
A. Standard drawings may show details which are not a part of work under this contract.
Disregard details shown on these drawings which are not applicable to work under this contract.
1.06 COPIES OF DRAWINGS
A. Two sets of full-size (22 inches by 34 inches) drawings, except standard drawings, will be furnished to the Contractor.
Revised 52 00 00 - 2
B. Upon request, additional half-size (11 inches by 17 inches) copies of standard drawings will be furnished to the Contractor.
1.07 LIST OF DRAWINGS
A. Drawings listed in Table 52 00 00A – List of Drawings, are made a part of Section C – Description/Specifications.
1.08 DRAWING NUMBERS IN NUMERICAL ORDER
A. Specification drawings are listed in numerical order in Table 52 00 00B - Drawings in Numerical Order.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
Table 52 00 00A - List of Drawings
Sheet No.
Drawing No. Title
General:
1 245-D-60046 Location Map
2 245-D-60047 Site Use Plan
3 245-D-60048 Construction Callouts
Metalwork:
4 245-D-60065 Miscellaneous Metalwork – Walkway and Ladders - Plan and Sections
5 245-D-60066 Miscellaneous Metalwork – Walkways - Plans, Sections, and Details
6 245-D-60067 Miscellaneous Metalwork – Pipe Guardrail – Sections and Details
7 245-D-60068 Miscellaneous Metalwork – Stair Landings L1 & L2 – Plan, Sections, and Details
Revised 52 00 00 - 3
Table 52 00 00A - List of Drawings
Sheet No.
Drawing No. Title
8 245-D-60069 Miscellaneous Metalwork – Grating - El. 7704.00 – Plan, Sections, and Details
Mechanical:
9 245-D-60024 Stoplog Layout – Installation – Sheet 1 of 1
10 245-D-60025 Upper Stoplog – Assembly – List of Parts – Sheet 1 of 3
11 245-D-60026 Upper Stoplog – Detail – Part – Sections – Sheet 2 of 3
12 245-D-60027 Upper Stoplog – Parts – Sheet 3 of 3
13 245-D-60028 Intermediate Stoplogs – Assembly – List of Parts – Sheet 1 of 3
14 245-D-60029 Intermediate Stoplogs – Detail – Part – Sections – Sheet 2 of 3
15 245-D-60030 Intermediate Stoplogs – Parts – Sheet 3 of 3
16 245-D-60031 Lower Stoplog – Assembly – List of Parts – Sheet 1 of 3
17 245-D-60032 Lower Stoplog – Detail – Part – Sections – Sheet 2 of 3
18 245-D-60033 Lower Stoplog – Parts – Sheet 3 of 3
19 245-D-60034 Lifting Beam – Assembly – List of Parts – Parts – Sheet 1 of 1
20 245-D-60037 40-Inch Jet-Flow Gate – Installation – Sheet 1
21 245-D-60038 40-Inch Jet-Flow Gate – Assembly – Sheet 2
22 245-D-60039 40-Inch Jet-Flow Gate – List of Parts – Sheet 3
23 245-D-60040 40-Inch Jet-Flow Gate – Upstream Body – Sheet 4
24 245-D-60041 40-Inch Jet-Flow Gate – Downstream Body – Sheet 5
25 245-D-60042 40-Inch Jet-Flow Gate – Bonnet Cover – Seal Ring – Seal Clamp Ring – Sheet 6
26 245-D-60043 40-Inch Jet-Flow Gate – Leaf – Sheet 7
27 245-D-60044 40-Inch Jet-Flow Gate – Motor Operator – Bushing – Stem Nuts – Seats – Sheet 8
28 245-D-60045 40-Inch Jet-Flow Gate – Stand, Spanner Wrench, Wall Gland – Spool – Sheet 9
Revised 52 00 00 - 4
Table 52 00 00A - List of Drawings
Sheet No.
Drawing No. Title
29 245-D-60060 3-Inch Air Vent – Sheet 1
30 245-D-60061 14-Inch Air Vents – Sheet 1
31 245-D-60062 Valves and Equipment – Sheet 1
32 245-D-60063 Expansion Joint Packing – Sheet 1
33 245-D-60064 Jet Flow Gate Pipe – Spool – Sheet 1
Electrical:
34 245-D-60071 Conduit Plan – Jet-Flow Gates and Flowmeters – Sheet 1
35 245-D-60072 Conduit Plan – Jet-Flow Gates and Flowmeters Routing Details – Sheet 1
36 245-D-60073 Network Diagram – Jet-Flow Gates and Flowmeters Communications – Sheet 1
37 245-D-60074 Single Line Diagram – 240/120 VAC Station Service System – Sheet 1
38 245-D-60075 Cabinet Layout – Jet-Flow Gates Remote I/O – Sheet 1
39 245-D-60077 Block Diagram – Jet-Flow Gates Power and Communications – Sheet 1
40 245-D-60078 Block Diagram – Flowmeters Power and Communications – Sheet 1
41 245-D-60079 Conduit Plan – Flowmeters – Sheet 1
Information Drawings:
42 245-D-406 Green Mountain Dam – General Plan and Sections
43 245-D-410 Green Mountain Dam – Outlet Works – Alinement, Profile and Sections
43A 245-D-411 Green Mountain Dam – Outlet Works – Gate Chamber, Shaft and Hoist House
44 245-D-514 Green Mountain Dam – Blue River Bridge – Plan – Elevation – Sections – Sheet 1 of 4
45 245-D-515 Green Mountain Dam – Blue River Bridge – Abutment – Skewbacks – Sheet 2 of 4
Revised 52 00 00 - 5
Table 52 00 00A - List of Drawings
Sheet No.
Drawing No. Title
46 245-D-516 Green Mountain Dam – Blue River Bridge – Railing – Deck Slab – Floor System – Sheet 3 of 4
47 245-D-517 Green Mountain Dam – Blue River Bridge – Steel Arch – Bearings – Sheet 4 of 4
48 245-D-849 Green Mountain Power Plant – General Arrangement – Transverse Sections
49 245-D-850 Green Mountain Power Plant – General Arrangement – Plan
– Floor El. 7704.0 – 7715.25 – 7724.0
50 245-D-851 Green Mountain Power Plant – General Arrangement – Plan
– Floor El. 7690.00 and Longitudinal Section
51 245-D-1020 Green Mountain Power Plant – Station Service and Control System – Conduit Installation – El 7700 to El 7712
52 245-D-1024 Green Mountain Power Plant – Substructure – Concrete Outline – Plan Thru Draft Tubes
53 245-D-1025 Green Mountain Power Plant – Substructure – Concrete Outline – Plan at El. 7690.00 – First Stage
54 245-D-1026 Green Mountain Power Plant – Substructure – Concrete Outline – Plan at El. 7704.00 – First Stage
55 245-D-1027 Green Mountain Power Plant – Substructure – Concrete Outline – Plan at El. 7704.00 – First and Second Stage
56 245-D-1028 Green Mountain Power Plant – Substructure – Concrete Outline – Front and Rear Elevations E-E and K-K
57 245-D-1030 Green Mountain Power Plant – Substructure – Concrete Outline – Longitudinal Sections F-F and G-G
58 245-D-1032 Green Mountain Power Plant – Substructure – Concrete Outline – Transverse Sections L-L and M-M
59 245-D-1089 Green Mountain Dam – Outlet Works – 44” Tube Valve – Valve to Wall Connection Gland
60 245-D-1090 Green Mountain Dam – Outlet Works – 3” Air Outlet and 14” Air Inlet Pipes above El. 7954.00
61 245-D-1107 Green Mountain Dam – Outlet Works – Penstock Encasement – Concrete Outline – Floor and Sump
Revised 52 00 00 - 6
Table 52 00 00A - List of Drawings
Sheet No.
Drawing No. Title
62 245-D-1181 Green Mountain Dam – Outlet Works – Gate Chamber Control Piping – General Arrangement
63 245-D-1182 Green Mountain Dam – Outlet Works – Gate Chamber Control Piping – Pressure Supply and Sump Drain Piping
64 245-D-1183 Green Mountain Dam – Outlet Works – Gate Chamber Control Piping – Seal Control Valve and Gate Blow Off Piping
65 245-D-1184 Green Mountain Dam – Outlet Works – Gate Chamber Control Piping – Gate Air Piping Below El. 7958.50
66 245-D-1195 Green Mountain Dam – Outlet Works – 44” Tube Valve – Control Piping
67 245-D-1205 Green Mountain Dam – Penstocks and Outlet Pipes – Plan and Elevation – Tunnel Portion
68 245-D-1206 Green Mountain Dam – Penstocks and Outlet Pipes – Plan – Embedded Portion
69 245-D-1207 Green Mountain Dam – Penstocks and Outlet Pipes – Sections and Drains
70 245-D-1209 Green Mountain Dam – Penstocks and Outlet Pipes – Expansion Joint and Piezometer Connection
71 245-D-1210 Green Mountain Dam – Penstocks and Outlet Pipes – Supporting Rings
72 245-D-1211 Green Mountain Dam – Penstocks and Outlet Pipes – Branch Outlet
73 245-D-1212 Green Mountain Dam – Penstocks and Outlet Pipes – Flanges and Turbine Connections
74 245-D-1213 Green Mountain Dam – Penstocks and Outlet Pipes – Manholes
75 245-D-1214 Green Mountain Dam – Penstocks and Outlet Pipes – Stair and Walkway – Sheet 1 of 2
76 245-D-1215 Green Mountain Dam – Penstocks and Outlet Pipes – Stair and Walkway – Sheet 2 of 2
Revised 52 00 00 - 7
Table 52 00 00A - List of Drawings
Sheet No.
Drawing No. Title
77 245-D-1217 Green Mountain Power Plant – Miscellaneous Structural Steel – Hatch Frames – Covers - Rails
78 245-D-1245 Green Mountain Power Plant – Architectural Elevations and Details
79 245-D-1248 Green Mountain Power Plant – Superstructure – Concrete Outline – Plan at El. 7724.00
80 245-D-1260 Green Mountain Power Plant – Superstructure – Concrete Outline – Transverse Sections
81 245-D-1276 Green Mountain Dam – Outlet Works – 44” Regulating Tube Valve – Installation – Sheet 1 of 1
82 245-D-1277 Green Mountain Dam – Outlet Works – 44” Regulating Tube Valve – Assembly – Sheet 1 of 8
83 245-D-1279 Green Mountain Dam – Outlet Works – 44” Regulating Tube Valve – Body – Sheet 3 of 8
84 245-D-1280 Green Mountain Dam – Outlet Works – 44” Regulating Tube Valve – Bearing Carrier – Stem Cap – Bearing – Sheet
85 245-D-1281 Green Mountain Dam – Outlet Works – 44” Regulating Tube Valve – Bevel Gear – Pinion – Shaft – Seal – Ring – Sheet 5 of 8
86 245-D-1283 Green Mountain Dam – Outlet Works – 44” Regulating Tube Valve – Tube – Seat Ring – Gland – Packing – Sheet 7 of 8
87 245-D-1285 Green Mountain Dam – Outlet Works – 44” Regulating Tube Valve Control – Assembly – Sheet 1 of 8
88 245-D-1301 Green Mountain Power Plant – Drainage of Powerhouse Area – Sections – Sheet 2 of 2
89 245-D-1526 Green Mountain Power Plant – Substructure – Concrete Outline – Sectional Plan at Elevation 7704.00 – Second Stage
90 245-D-1527 Green Mountain Power Plant – Substructure – Concrete Outline – Sectional Plan Thru Passageways – Second Stage
Revised 52 00 00 - 8
Table 52 00 00A - List of Drawings
Sheet No.
Drawing No. Title
90A 245-D-1528 Green Mountain Power Plant – Substructure – Concrete Outline – Longitudinal Sections – Second Stage – Sheet 1 of 2
91 245-D-1531 Green Mountain Power Plant – Substructure – Concrete Outline – Transverse Sections and Plan of Generator Foundation – Second Stage
92 245-D-1544 Green Mountain Dam – Outlet Works – Penstock Encasement – Plan at El. 7709.00 – Concrete Outline
93 245-D-1546 Green Mountain Dam – Outlet Works – Penstock Encasement – Sections – Concrete Outline
94 245-D-1554 Green Mountain Dam – Outlet Works – Penstock Tunnel – Electrical Installation
95 245-D-1678 Green Mountain Dam – Outlet Works – Pressure Supply and Penstock Drain Lines
96 245-D-1692 Green Mountain Dam – Outlet Works – Gate Chamber Tunnel Plug – 102” Ring Seal Gates - Reinforcement
97 245-D-1693 Green Mountain Dam – Outlet Works – Gate Chamber Tunnel Plug – 102” Conduits and Inlet Transition – Reinforcement
98 245-D-1719 Green Mountain Dam – Outlet Works – Gate Chamber Tunnel Plug – Concrete Outline
99 245-D-1720 Green Mountain Dam – Outlet Works – Gate Chamber Tunnel Plug – Inlet Transition – Interior Outline
100 245-D-1779 Green Mountain Power Plant – Station Service and Control System – Exposed Conduit – Details – El. 7690.0 to El.
7722.00
101 245-D-9601 Green Mountain Powerplant and Switchyard – Electrical Installation – Equipment Location Key Plan
102 245-600-1916 Green Mountain Powerplant – Repairs to Stoplog Guides – Plan and Section A-A – Sheet 1 of 3
103 245-600-1915 Green Mountain Powerplant – Repairs to Stoglog Guides – Sections, Typical Pier, and Detail – Sheet 2 of 3
Revised 52 00 00 - 9
Table 52 00 00A - List of Drawings
Sheet No.
Drawing No. Title
104 245-713-1543 Green Mountain Power Plant – Outlet Works – Bypass Valves - Control Cabinet SX Schematic Diagram – Sheet 1 of 1
105 245-713-1544-01 Green Mountain Powerplant – Outlet Works – Bypass Valves – Control Cabinet SX, S7, & S8 – Wiring Diagram – Sheet 1 of 3
106 245-713-1544-02 Green Mountain Powerplant – Outlet Works – Bypass Valves – Control Cabinet SX, S7, & S8 – Wiring Diagram – Sheet 2 of 3
107 245-713-1544-03 Green Mountain Powerplant – Outlet Works – Bypass Valves – Control Cabinet SX, S7, & S8 – Wiring Diagram – Sheet 3 of 3
108 154620 The Newport News Shipbuilding and Dry Dock Company – Newport News, Virginia – Engineering Department – Hydraulic Division – Green Mountain Power Plant – Colorado-Big Thompson Project, Colorado – General Arrangement – Single Vertical Turbine
109 154623 The Newport News Shipbuilding and Dry Dock Company – Newport News, Virginia – Engineering Department – Hydraulic Division – Green Mountain Power Plant – Colorado-Big Thompson Project, Colorado – Foundation – Single Vertical Turbine
110 154624 The Newport News Shipbuilding and Dry Dock Company – Newport News, Virginia – Engineering Department – Hydraulic Division – Green Mountain Power Plant – Colorado-Big Thompson Project, Colorado – Draft Tube – Single Vertical Turbine
111 154625 The Newport News Shipbuilding and Dry Dock Company – Newport News, Virginia – Engineering Department – Hydraulic Division – Green Mountain Power Plant – Colorado-Big Thompson Project, Colorado – Draft Tube Liner – Single Vertical Turbine
Revised 52 00 00 - 10
Table 52 00 00A - List of Drawings
Sheet No.
Drawing No. Title
112 154626 The Newport News Shipbuilding and Dry Dock Company – Newport News, Virginia – Engineering Department – Hydraulic Division – Green Mountain Power Plant – Colorado-Big Thompson Project, Colorado – Spiral Casing – Single Vertical Turbine
113 154628 The Newport News Shipbuilding and Dry Dock Company – Newport News, Virginia – Engineering Department – Hydraulic Division – Green Mountain Power Plant – Colorado-Big Thompson Project, Colorado – Speed Ring – Single Vertical Turbine
114 154629 The Newport News Shipbuilding and Dry Dock Company – Newport News, Virginia – Engineering Department – Hydraulic Division – Green Mountain Power Plant – Colorado-Big Thompson Project, Colorado – 77 136 R. H.
Runner and Runner Tip – Single Vertical Turbine
115 245-713-XXXXX Green Mountain Power Plant – Control System – Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSA – Cabinet Layouts – Sheet 1 of 1
116 CCSA-1 Rev B Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSA Cabinet Layout. – Sheet 1 of 7
117 CCSA-2 Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSA PLC AA Modules Wiring Diagram – Sheet 2 of 7
118 CCSA-3 Rev-A Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSA PLC AB Modules Wiring Diagram – Sheet 3 of 7
119 CCSA-4 Rev B Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSA Right Side Panel Wiring Diagram – Sheet 4 of 7
120 CCSA-5 Rev E Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSA Back Panel (1 of 2) Wiring Diagram – Sheet 5 of 7
121 CCSA-6 Rev D Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSA Back Panel Wiring Diagram – Sheet 6 of 7
122 CCSA-7 Rev B Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSA Left Side Wiring Diagram – Sheet 7 of 7
123 245-713-XXXXX Green Mountain Power Plant – Control System – Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSE – Cabinet Cutouts – Sheet 1 of 1
Revised 52 00 00 - 11
Table 52 00 00A - List of Drawings
Sheet No.
Drawing No. Title
124 CCSE-1 Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSE Cabinet Layout – Sheet 1 of 6
125 CCSE-2 Rev A Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSE PLC AC Modules Wiring Diagram – Sheet 2 of 6
126 CCSE-3 Rev A Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSE PLC AD Modules Wiring Diagram – Sheet 3 of 6
127 CCSE-4 Rev A Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSE Right Side Panel Wiring Diagram – Sheet 4 of 6
128 CCSE-5 Rev D Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSE Back Side Wiring Diagram – Sheet 5 of 6
129 CCSE-6 Rev B Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSE Left Side Panel Wiring Diagram – Sheet 6 of 6
130 CCSE-7 Supervisory Control Remote Terminal Unit (RTU) – Cabinet CCSE Watchdog Timer Schematic – Sheet 7 of 7
Standard Drawings:
131 40-D-6602 Miscellaneous Metalwork – Ladder – Type 3
132 40-D-6603 Miscellaneous Metalwork – Ladder – Type 4
133 40-D-7094 Electrical Installation – Conduit Clamp and Conduit Supports – Typical Details – Sheet 1 of 1
134 40-D-7102 Government Drawing Format - Drawing Border, Sample Title Block and Signature Lines
135 104-D-1150 Major Power / Pumping Plants – Electrical Installation – Device Designations and Symbols To Be Used on Single- Line and Schematic Diagrams
136 104-D-1165 Design Data Typical Power Plant _ Pumping Plant – Electrical Installation – Main Control Board – CSA – Panel 7R – Wiring Diagram
Revised 52 00 00 - 12
Table 52 00 00B - Drawings in Numerical Order
Drawing No. Sheet No.
245-D-
245-D-406 42
245-D-410 43
245-D-411 43A
245-D-514 44
245-D-515 45
245-D-516 46
245-D-517 47
245-D-849 48
245-D-850 49
245-D-851 50
245-D-1020 51
245-D-1024 52
245-D-1025 53
245-D-1026 54
245-D-1027 55
245-D-1028 56
245-D-1030 57
245-D-1032 58
245-D-1089 59
245-D-1090 60
245-D-1107 61
245-D-1181 62
245-D-1182 63
245-D-1183 64
245-D-1184 65
Revised 52 00 00 - 13
Table 52 00 00B - Drawings in Numerical Order
Drawing No. Sheet No.
245-D-1195 66
245-D-1205 67
245-D-1206 68
245-D-1207 69
245-D-1209 70
245-D-1210 71
245-D-1211 72
245-D-1212 73
245-D-1213 74
245-D-1214 75
245-D-1215 76
245-D-1217 77
245-D-1245 78
245-D-1248 79
245-D-1260 80
245-D-1276 81
245-D-1277 82
245-D-1279 83
245-D-1280 84
245-D-1281 85
245-D-1283 86
245-D-1285 87
245-D-1301 88
245-D-1526 89
245-D-1527 90
245-D-1528 90A
Revised 52 00 00 - 14
Table 52 00 00B - Drawings in Numerical Order
Drawing No. Sheet No.
245-D-1531 91
245-D-1544 92
245-D-1546 93
245-D-1554 94
245-D-1678 95
245-D-1692 96
245-D-1693 97
245-D-1719 98
245-D-1720 99
245-D-1779 100
245-D-9601 101
245-D-60024 9
245-D-60025 10
245-D-60026 11
245-D-60027 12
245-D-60028 13
245-D-60029 14
245-D-60030 15
245-D-60031 16
245-D-60032 17
245-D-60033 18
245-D-60034 19
245-D-60037 20
245-D-60038 21
245-D-60039 22
245-D-60040 23
Revised 52 00 00 - 15
Table 52 00 00B - Drawings in Numerical Order
Drawing No. Sheet No.
245-D-60041 24
245-D-60042 25
245-D-60043 26
245-D-60044 27
245-D-60045 28
245-D-60046 1
245-D-60047 2
245-D-60048 3
245-D-60060 29
245-D-60061 30
245-D-60062 31
245-D-60063 32
245-D-60064 33
245-D-60065 4
245-D-60066 5
245-D-60067 6
245-D-60068 7
245-D-60069 8
245-D-60071 34
245-D-60072 35
245-D-60073 36
245-D-60074 37
245-D-60075 38
245-D-60077 39
245-D-60078 40
245-D-60079 41
Revised 52 00 00 - 16
Table 52 00 00B - Drawings in Numerical Order
Drawing No. Sheet No.
245-600-
245-600-1915 103
245-600-1916 102
245-713-
245-713-1543 104
245-713-1544-01 105
245-713-1544-02 106
245-713-1544-03 107
154620 108
154623 109
154624 110
154625 111
154626 112
154628 113
154629 114
245-713-
245-713-XXXXX 115
245-713-XXXXX 123
CSSA
CCSA-1 Rev B 116
CCSA-2 117
CCSA-3 Rev-A 118
CCSA-4 Rev B 119
CCSA-5 Rev E 120
CCSA-6 Rev D 121
CCSA-7 Rev B 122
Revised 52 00 00 - 17
Table 52 00 00B - Drawings in Numerical Order
Drawing No. Sheet No.
CSSE
CCSE-1 124
CCSE-2 Rev A 125
CCSE-3 Rev A 126
CCSE-4 Rev A 127
CCSE-5 Rev D 128
CCSE-6 Rev B 129
CCSE-7 130
40-D-
40-D-6602 131
40-D-6603 132
40-D-7094 133
40-D-7102 134
104-D-1150 135
104-D-1165 136
END OF SECTION
Revised 52 00 00 - 18
This page intentionally left blank.
90A
This page intentionally left blank
43A
| 09 97 02 - Impacted Immersion Coatings_Amd_003_Pg 19,20.pdf |
| 09 97 02 - Impacted Immersion Coatings 19 |
| 09 97 02 - Impacted Immersion Coatings 20 |
File details come from the government source that posted it.