Summary: Statement of Work – MRG Riprap Supply 2026

This Statement of Work details riprap supply and stockpiling services for the U.S. Bureau of Reclamation's Middle Rio Grande river maintenance program. The contractor must supply, haul, and stockpile a total of 9,680 tons of riprap across three New Mexico locations: 3,300 tons of 12-inch nominal diameter riprap at the Bernalillo stockpile site; 5,500 tons of 16-24 inch diameter riprap at the HWY 380 stockpile site; and 880 tons of 16-24 inch diameter riprap at the RM 201.8 site (located on Sandia Pueblo and subject to separate approval). All work must include dust abatement during hauling and stockpiling. The contract period extends from award through July 1, 2027, with work beginning within 15 calendar days of the Notice to Proceed. Delivery to the Bernalillo and HWY 380 sites occurs upon contract award, while the RM 201.8 delivery depends on Contracting Officer's Representative approval and may be redirected to the Bernalillo site if pueblo approval is not granted before contract expiration. Work hours are limited to Monday through Friday from 6:00 a.m. to 6:00 p.m. at all sites.

The contractor bears all costs for labor, materials, transportation, equipment, supervision, and tooling under a fixed-price arrangement. Riprap must meet strict specifications including hard, dense, durable rock with specific gravity minimum of 2.65, maximum absorption of 2 percent, maximum sulfate soundness loss of 10 percent, predominantly angular shape with maximum dimension not exceeding three times minimum dimension, and well-graded sizing per provided gradation tables. All material must be reasonably clean as visually inspected by the Contracting Officer's Representative. Measurement and payment are based on certified weighmaster tickets documenting gross, tare, and net weights at state-tested scales. The contractor must submit detailed proposals including quarry location, material testing results, weighmaster qualifications, sediment control plans, and traffic control plans at least 15 days prior to material delivery and site mobilization.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140R4026Q0098 - MRG Riprap Supply 2026 Attachment 1

STATEMENT OF WORK

MRG Riprap Stockpile

Prepared by

Bureau of Reclamation Upper Colorado Basin Region

Albuquerque Area Office

Table of Contents

1. INTRODUCTION / BACKGROUND

2. SCOPE OF WORK

3. GENERAL REQUIREMENTS

4. GOVERNMENT-FURNISHED PROPERTY

5. PERMITS AND ACCESS

6. SPECIAL REQUIREMENTS

7. PERIOD OF PERFORMANCE/SCHEDULE

8. PROPOSALS

9. SITE VISIT

10. LIST OF SPECIFICATIONS

1. INTRODUCTION / BACKGROUND

The U.S. Bureau of Reclamation (Reclamation) has authority for river maintenance of the Rio Grande between Velarde, New Mexico, and the headwaters of Caballo Reservoir under the Flood Control Acts of 1948 and 1950. “River maintenance” refers to river and infrastructure maintenance and restoration actions that accomplish one or more of the following (the order listed does not imply importance):

• Provide for effective transport of water and sediment to Elephant Butte Reservoir

• Conserve surface water within the Middle Rio Grande (MRG) Basin.

• Protect riverside structures and facilities

• Reduce and/or eliminate aggradation in the MRG

• Reduce the rate of channel degradation from Cochiti Dam south to Socorro

• Restore natural river processes

• Provide habitat improvement for the Endangered Species Act-listed species within the MRG Project Area

This riprap supply contract will provide Reclamation needed materials to meet its river maintenance responsibilities, specifically the protection of riverside structures and facilities during an emergency.

Three sites will receive riprap on this contract.

The Bernalillo Stockpile Site is approximately 17 miles north of the junction of I-25/I-40 and accessed from the eastside frontage road north of US 550.

35°21'9.21"N 106°28'58.42"W

The HWY 380 stockpile that is approximately 1.4 miles East from the junction of I-

25/HWY 380. 33°55'16.70"N 106°51'19.43"W

The RM 201.8 Site is located on Sandia pueblo and requires a specific route that needs to be taken once on the Pueblo. 35°18'4.15"N 106°34'27.49"W

2. SCOPE OF WORK

The Contractor shall provide a fixed cost to perform the following:

1. Supply all labor, materials, transportation, supervision, tools, equipment, and expertise necessary to furnish, haul, and stockpile 3,300 tons of 12-inch nominal diameter riprap at Bernalillo stockpile, 5,500 tons of 16-24 inch diameter riprap at the HWY 380 stockpile and 880 tons of 16-24 inch diameter riprap at the RM

201.8 Site and provide dust abatement at all sites when delivering riprap. Figure 1-3 shows the delivery location for the riprap material. With a total of 9,680 tons of riprap required.

2. The Bernalillo stockpile and HWY 380 stockpile will be delivered upon award of the contract. The RM 201.8 site will be delivered once the COR gives approval for delivery to the site. The RM 201.8 riprap may need to be delivered to the Bernalillo stockpile site if approval is not granted by the Sandia pueblo before the contract expires.

3. Should the riprap provided not conform to the specified sizes outlined in the contract, the contractor is required to remove any incorrectly sized riprap and deliver materials that meet the stipulated requirements.

Riprap Stockpile Sites

Figure 1-Bernalillo Stockpile route

Figure 2- HWY 380 Stockpile route

Figure 3- Site Rm 201.8 route

3. GENERAL REQUIREMENTS

• Contractor shall comply with all applicable Federal, State, and municipal regulations and laws.

• Contract shall comply with Reclamation Safety and Health Standards (RSHS).

The latest version of the RSHS can be found at the following web address.

http://www.usbr.gov/ssle/safety/RSHS/rshs.html

• Contractor shall comply with all specifications outlined in this Statement of Work.

4. GOVERNMENT-FURNISHED PROPERTY

No government-furnished property will be provided to the contractor.

5. PERMITS AND ACCESS

The Government will arrange for the necessary environmental permits for the work defined in this Statement of Work. Contractor shall complete an Access Permit and a THPO Permit (See Attachments 1 and 2) and shall provide Covid-19 protocols when required. Lack of access to the work sites shall be reported immediately to the Contracting Officer’s Representative (COR). Bureau of Reclamation may assist in acquiring permits if it is necessary. Contractor shall acquire any permits required by the New Mexico Department of Transportation.

6. SPECIAL REQUIREMENTS

6.1. Dust Abatement

The Contractor shall provide dust abatement at all sites while hauling and stockpiling riprap.

7. PERIOD OF PERFORMANCE/SCHEDULE

The Contractor shall begin work within 15 calendar days after receipt of the Notice to Proceed, or within an agreed amount of time as discussed and approved by the CO/COR. The period of performance will be from the date the contract is awarded to 7/1/2027.

7.1. RM 201.8 Site

• The contractor may deliver the 16-24 inch riprap material after the COR gives the notice to proceed. This delivery may not be approved until later in the contract performance period.

• Work hours at the sites shall be Monday through Friday from 6:00 a.m. to 6:00 p.m.

8. PROPOSALS

Contractor proposals shall include the following:

• Quarry Mineral Report documenting the rock specification detailed in Section 31 37 00 Part 2.

9. SITE VISIT

A site visit can be requested by contacting the COR.

10. LIST OF SPECIFICATIONS

01 33 00 Submittals 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 55 20 Traffic Control 31 02 10 Water for Dust Abatement 31 37 00 Riprap

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for other items of work.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME):

1. ASME Y14.1-2005(2010) Decimal Inch Drawing Sheet Size and Format

B. National Institute of Building Sciences (NIBS):

1. NIBS NCS-2011 United States National CAD Standards, Version 5

1.03 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

C. Submittal Types, as listed in Table 01 33 00A – List of Submittals:

1. A – Action:

a. Government will respond as to adequacy of submittal.

2. I – Informational:

a. The Government will acknowledge receipt of Informational submittals.

b. The Government may reject an Informational submittal when the submittal does not comply with the contract. The Contractor shall correct mistakes or deficiencies in rejected Informational submittals and resubmit.

D. Acronyms

1. CO: Contracting Officer

2. COR: Contracting Officer's Representative

3. COTR: Contracting Officer's Technical Representative

1.04 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

C. Submit number of sets specified in “No. of sets to be sent to:” columns in Table 01 33 00A - List of Submittals.

D. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for each attached submittal.

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 7 days after receiving the comments, unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

F. More than one RSN may be submitted under a transmittal letter, provided the responsible code is the same.

1.05 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 7 days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.

B. Time in Excess of Specified:

1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.

a. The time extension will be to the extent that excess review time caused delay to the contract completion date.

b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.

2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to the extent that:

a. Approval was required under the contract, and

b. Requests for approval were properly and timely submitted and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.

C. Return of Submittals:

1. Action Submittals: One set of submittals required for action will be returned either approved, approved subject to identified changes, or not approved.

a. Revise and resubmit submittals not approved.

b. Do not change designs without approval of the CO after drawings, documentation, and technical data have been approved.

2. Informational Submittals: The Government will acknowledge Informational submittals.

a. Informational submittals will not be returned when they comply with the specifications.

b. Informational submittals that do not comply with the specifications may be returned for resubmittal or additional information may be requested.

1.06 TRANSMITTAL

A. Addresses for codes listed in Table 01 33 00A - List of Submittals:

1. Contracting Officer:

Kristen Ruiz Jimenez Bureau of Reclamation 555 Broadway Blvd. NE, Suite 100 Albuquerque, NM 87102-2352 kruizjimenez@usbr.gov

2. Contracting Officer Representative:

Bryan Lawlis Bureau of Reclamation 555 Broadway Blvd. NE, Suite 100 Albuquerque, NM 87102-2352 blawlis@usbr.gov

B. Send original transmittal letter with appropriate number of sets to office listed in “Responsible Code” column in Table 01 33 00A – List of Submittals.

C. Send copy of transmittal letter with appropriate number of sets to offices that are not the responsible code, but show “No. of sets to be sent to” in Table 01 33 00A

– List of Submittals.

D. When “No. of sets to be sent to” is 0, send a copy of transmittal letter to that office.

E. Submittals required by the specifications, but not listed in Table 01 33 00A - List of Submittals:

1. Mark Changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 7 days after receiving the comments, unless otherwise directed.

4. Requirements.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

mailto:kruizjimenez@usbr.gov mailto:blawlis@usbr.gov

SECTION 01 35 20

SAFETY AND HEALTH

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. Reclamation Safety and Health Standards

a. Available on the Internet at:

http://www.usbr.gov/ssle/safety/RSHS/rshs.html.

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 20-1, Safety program:

1. Written safety program in accordance with Section 3 of RSHS.

C. RSN 01 35 20-2, Monthly accident summary report:

1. Form 7-2218 or other acceptable form in accordance with paragraph 3.8 of RSHS.

1.04 PROJECT CONDITIONS

A. Comply with RSHS.

B. Provide and maintain a work environment and procedures that will:

1. Safeguard the public and Government's personnel exposed to Contractor operations and activities.

2. Avoid interruptions of site operations and delays in project completion dates.

3. Control costs in contract performance.

C. Do not require persons employed in performance of this contract, including subcontracts, to work under conditions which are unsanitary, hazardous, or dangerous to the employee’s health or safety.

D. Provide appropriate safety barricades, signs, and signal lights.

E. Maintain accurate record of and report to the CO the following occurrences during performance of this contract:

1. Death.

2. Occupational disease.

3. Traumatic injury to employees or the public.

4. Property damage in excess of $2,500.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Table 01 33 00A. - List of Submittals

* Submittal types: A – Action, I – Information

RSN

Clause or Section Title

Submittals required

Due date or delivery time

Type

Respons ible code

No. of sets to be sent to:

CO COR

01 35 20-

Safety and Health Safety program

Submit 15 days prior to mobilization to work site. A COR 0 1

01 35 20-

Safety and Health

Monthly accident summary report Monthly I COR 0 1

01 35 30-

Contractor’s Onsite Safety Personnel Qualifications

Submit 15 days prior to mobilization to work site. I COR 0 1

01 55 20- 1 Traffic Control

Traffic control plan

Submit 15 days prior to mobilization to work site. A COR 0 1

31 37 00- 1 Riprap

Location of existing or proposed source(s) for riprap With Proposal I COR 0 1

31 37 00- 2 Riprap

Material Testing Results

Submit 15 days prior to delivering material A COR 0 1

31 37 00- 3 Riprap

Contractor’s Weighmaster

Submit 15 days prior to delivery and setup of scales. A COR 0 1

31 37 00- 4 Riprap

Weight Tickets for Furnishing and Stockpiling Monthly A COR 0 1

SECTION 01 35 30

CONTRACTOR’S ONSITE SAFETY PERSONNEL

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for other items of work.

1.02 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 30-1, Resume:

1. Contractor’s Onsite Safety Representative

1.03 QUALIFICATIONS

A. Contractor’s Onsite Safety Representative:

1. Competent supervisory employee with appropriate level of safety related training and experience.

1.04 APPLICATION

A. Designate an employee as the Contractor’s Onsite Safety Representative prior to start of deliveries.

B. Contractor’s Onsite Safety Representative authorities, duties, and responsibilities:

1. Review and approve the Contractor’s Safety Program prior to submittal.

2. Responsible for effective implementing the Contractor’s Safety Program

3. Full authorization to correct unsafe acts on the spot.

4. Prepare safety inspection reports.

5. Physically onsite during any and all deliveries.

1.05 QUALITY ASSURANCE

A. Contractor’s Onsite Safety Representative:

1. The effectiveness of the Contractor’s Onsite Safety Representative in prosecuting the safety program shall be subject to continued review and approval by the CO.

B. Safety Program:

1. The effectiveness of the Contractor’s Safety Program will be subject to continued review and approval by the CO.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

SECTION 01 55 20

TRAFFIC CONTROL

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost: Include in prices offered in the schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Federal Highway Administration, Department of Transportation

1. MUTCD, Part 6 Part 6, Temporary Traffic Control, Manual on Uniform

Traffic Control Devices, 2009 Edition with Revisions 1 and 2, May 2012 (https://mutcd.fhwa.dot.gov/kno_2009r1r2.htm), accessed April 11, 2017

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 55 20-1, Traffic control plan.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 TRAFFIC CONTROL

A. Meet requirements of MUTCD, Part 6.

B. Contractor shall comply with all state, federal, and municipal regulations regarding hauling on public roads and highways.

C. Provide cones, delineators, concrete safety barriers, barricades, flasher lights, danger signals, signs, and other temporary traffic control devices as required to protect work and public safety.

D. Provide flaggers and guards as required to prevent accidents and damage or injury to passing traffic.

https://mutcd.fhwa.dot.gov/kno_2009r1r2.htm

E. Do not begin work along public or private roads until proper traffic control devices for warning, channeling, and protecting motorists are in place in accordance with approved traffic control plan.

F. Maintain traffic flow and conduct delivery operations to minimize obstruction and inconvenience to public traffic.

G. Provide unobstructed, smooth, and dustless passageway for traffic through delivery operations.

H. Protect roads closed to traffic with effective barricades and warning signs.

Illuminate barricades and obstructions from sunset to sunrise.

I. Remove traffic control devices when no longer needed.

SECTION 31 02 10

WATER FOR DUST ABATEMENT

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost: The contractor shall provide all water necessary for dust abatement. The cost of this water shall be included in the prices submitted for other items of work..

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 APPLYING WATER FOR DUST ABATEMENT

A. Provide means of conveying water to point of use and applying water.

B. Use pressure spray or distributor bar to apply water evenly.

C. Apply water for dust abatement as directed by the COR.

SECTION 31 37 00

RIPRAP AND BASE COURSE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Riprap:

1. Measurement: Riprap and Base Course shall be weighed on platform scales furnished at the Contractor’s expense.

a. Weight slips by a certified public weighmaster stated at public scales or a certified weighmaster stationed at the quarry site are accepted.

1) Weigh tickets shall contain the following information: date, load number, truck number, gross weight, tare weight, net weight, riprap size, stockpile location, time of weighing, and the signature of the certified weighmaster.

b. Scales furnished by the Contractor shall be state tested and certified, at the Contractor’s expense.

1) State licensed scale representative shall approve, test, and certify Contractor’s scales. The Contractor shall recertify scales as deemed necessary to ensure accuracy or when requested by the COR.

c. Weighing of the materials by anyone other than the certified weighmaster may result in non-payment of materials as determined by the CO.

d. Hauling vehicle shall have tare weight determined twice weekly or as required by COR.

e. Double-draft weighing of dump trucks with trailers is prohibited.

2. Payment: Payment for furnishing, hauling and stockpiling riprap will be made at the applicable unit price per ton as stated in the schedule.

a. Includes furnishing, hauling, and stockpiling riprap.

b. Costs of developing, operating, and restoring the quarry as required by these specifications.

c. All costs associated with royalty fees.

d. Dust abatement of hauling roads and work sites.

1.02 REFERENCE STANDARDS

A. ASTM International (ASTM)

1. ASTM C 88-05 Soundness of Aggregates by Use of Sodium

Sulfate or Magnesium Sulfate

2. ASTM C 97-02(2008) Absorption and Bulk Specific Gravity of

Dimension Stone

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 – Submittals.

B. RSN 31 37 00-1, Location of quarry for obtaining riprap and transporting materials:

1. Methods of loading, and stockpile material.

2. Sediment control plan for quarry operations.

3. Contractor shall submit at the time of their proposal, the location of the proposed stockpile site. Prior to processing material, Reclamation shall inspect the proposed quarry site for Cultural Clearances.

C. RSN 31 37 00-2, Material Testing

1. Material Testing Results as specified in Section 31 37 00, Part 2

(Products)

a. Submit 15 days prior to hauling riprap material.

D. RSN 31 37 00-3, Contractor’s Weighmaster:

1. Contractor’s furnished scales:

a. Submit 30 days prior to delivery and setup of scales, Operator’s New Mexico state weight-scale qualifications and certifications.

E. RSN 31 37 00-4, Weight Tickets for Furnishing and Stockpiling

1. Weight slips by a certified public weighmaster stated at public scales or a certified weighmaster stationed at the quarry site are accepted.

PART 2 PRODUCTS

2.01 ROCK

A. Hard, dense, and durable.

1. Specific gravity, ASTM C 97, minimum: 2.65

2. Absorption, ASTM C 97, maximum: 2 percent.

3. Loss, Sulfate Soundness, ASTM C 88, maximum: 10 percent.

B. Either quarried rock or boulders may be used for riprap.

C. Shape:

1. Predominantly angular.

2. Maximum dimension not greater than 3 times minimum dimension.

D. Cleanliness:

1. Riprap to be delivered will be reasonably clean to the extent possible.

Cleanliness will be based on visual inspections. Photos 1 and 2 should be used as a reference for what Reclamation will determine to be clean and unclean.

Photo 1 – Clean Riprap

Photo 2 – Unclean Riprap

E. Riprap Gradation: The riprap shall be reasonable well-graded within the following limits:

Table 31 37 00A. – Gradation Requirements for Nominal 16-inch riprap

Nominal Size

Percent Passing by Weight 24-inch 20-inch 16-inch 6-inch

16-inch 70-100 50-70 35-50 2-10

Table 31 37 00B. – Gradation Requirements for Nominal 12-inch riprap

Nominal Size

Percent Passing by Weight 20-inch 17-inch 12-inch 4-inch

12-inch 70-100 50-70 35-50 2-10

Sizes denote square screen openings which shall be used to determine percent passing by weight. Sample material shall be visually inspected by the COR.

PART 3 STOCKPILES

3.01 DESIGNATED AREA PREPARATION

A. The Riprap shall be stockpiled within the boundaries located in the field by the Contracting Officer’s Representative.

B. All riprap stockpiles shall be placed on the existing rock pad as directed by the Contracting Officer’s Representative.

C. All stockpiles are to be heaped up to a maximum of 10-feet with the use of a front-end loader or similar earthmoving equipment to provide efficient use of space available at the stockpile site.

D. The Contractor shall construct acceptable stockpiles after the riprap is hauled and dumped at the stockpile site.

1. INTRODUCTION / BACKGROUND
2. SCOPE OF WORK
3. GENERAL REQUIREMENTS
4. GOVERNMENT-FURNISHED PROPERTY
5. PERMITS AND ACCESS
6. SPECIAL REQUIREMENTS
7. PERIOD OF PERFORMANCE/SCHEDULE
8. PROPOSALS
9. SITE VISIT
10. LIST OF SPECIFICATIONS

File details come from the government source that posted it. Updated .