Leadville Mine Treatment Plant and Facilities Water Treatment Plant Replacement
Leadville Mine Drainage Tunnel Project, Colorado
FOREWORD
Work is located on the north side of Leadville, Colorado in Lake County at and near the Leadville Mine Drainage Tunnel Water Treatment Plant, 749 Highway 91, Leadville, Colorado 80461.
A. Overview: Work consists of constructing a new 3.2 million gallons per day (MGD) Water Treatment Plant (WTP) adjacent to an existing 3.2 MGD WTP, then demolition of the existing WTP.
B. Contractor is responsible for staging areas, including space for construction trailers, material storage, and construction staff parking.
C. Contractor is responsible for investigations before beginning any construction, including:
1. Exploratory excavations and contacting utility owners, to determine locations and type of existing utilities, including:
a. Service connections, prior to commencing work which could result in damage to such utilities.
b. Immediately notify Reclamation to utilities discovered in a different position than indicated in contract documents or not indicated in contract documents.
D. Install:
1. Traffic control measures, protection measures for existing components, and temporary fencing.
2. Erosion control measures and maintain temporary safety fence and protection of existing installations as needed.
3. Site retaining walls.
4. Contractor designed unwatering and/or dewatering system to perform excavations to facilitate construction.
5. Hot tap with isolation valve on an existing potable water line on south side of Colorado State Highway 91. Coordinate with Parkville Water District and Colorado Department of Transportation.
6. Potable water piping via auger bore under Colorado State Highway 91.
Coordinate with Colorado Department of Transportation.
7. Potable water piping along River Road from Colorado State Highway 91 to WTP site. Coordinate with Lake County.
8. New treatment building.
9. New storage building.
10. New diesel emergency generators.
11. Site improvements, including yard piping, duct banks, stormwater, perimeter fencing and access point modifications, relocation of two existing flammables container buildings, relocation of one 250-gallon diesel fuel storage tank and supporting structure, surface treatments, landscaping, site lighting, and restoration of construction-impacted areas.
E. Site grading, cuts, and fills as required.
F. Receive delivery of, store, install, startup, and commission water treatment equipment from three Government-furnished equipment supply contracts.
G. Modify:
1. Permanent power supply to WTP site. Coordinate with Xcel Energy.
2. Natural gas service to WTP site. Coordinate with Xcel Energy.
3. Site’s existing septic system. Coordinate with Lake County:
a. Provide septic tank hauling services as needed per Contractor’s schedule in accordance with Sections 01 14 00 – Work Restrictions and 01 32 10 – Construction Program.
b. Dispose of existing leach field soil material per Lake County requirements, including performing analyses required by the receiving landfill.
4. Telecommunication service to WTP site. Coordinate with current provider.
5. Existing pond pump station to reuse existing wet well and replace pump station.
H. Replace:
1. Programmable logic controller (PLC) hardware and program new PLC at existing mine drainage well facility 10+25 Well Pump Station located approximately 0.25 miles south-southeast of existing WTP site.
2. Programmable logic controller (PLC) hardware and program new PLC at existing mine drainage well facility 46+96 Well Pump Station located approximately 1-mile south-southeast of existing WTP site.
3. Existing holding pond lining system and associated components.
I. Commission new WTP building and water treatment systems, including all associated disciplines work.
J. Maintain continuity of existing WTP operations during project construction until existing WTP has been decommissioned:
1. Relocate existing filter press on temporary concrete pad complete with infrastructure and utilities required for operation until new WTP building has been commissioned, then demolish components required for existing filter press operation.
K. Plug, seal, and abandon existing WTP building’s commercial well, Colorado Department of Water Resources well permit 158302, in accordance with Code of Colorado
Regulations 2 CCR 402-2, Rules and Regulations for Water Well Construction, Pump Installation, Cistern Installation, and Monitoring and Observation Hole/Well Construction.
L. Demolish:
1. Existing storage building.
2. Existing water treatment plant building and adjacent structures, including decommissioning existing WTP.
M. Remove existing sediment from existing 18-inch diameter PVC stormwater outfall line from existing catch basin CB-3 north to the pipe outlet, approximately 175 feet. For existing conditions, in accordance with Section 51 33 01 – Storm and Clearwell Drain Line Systems Inspection Report.
N. Remove existing sediment from existing 18-inch diameter stormwater outfall line from existing northeast catch basin north to the outlet, approximately 60-feet.
O. Remove traffic control measures, protection measures for existing components, and temporary fencing.
P. Demobilize for winter shutdown(s) as necessary.
Q. Project management and administration, including scheduling, obtaining permits, and coordination with Reclamation.
PRE-BID SITE VISIT: A PREBID SITE VISIT WILL BE HELD ON {insert date}, {insert location}, BEGINNING AT {insert time}. ATTENDEES ARE TO PROVIDE AND WEAR
SAFETY BOOTS, HARD HATS, SAFETY VESTS.
FOR DATE AND PLACE OF BID OPENING, SEE "SOLICITATION, OFFER, AND
AWARD," STANDARD FORM 1442.
FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION
"RECLAMATION SAFETY AND HEALTH STANDARDS" WHICH IS APPLICABLE
TO WORK UNDER THIS CONTRACT, SEE CLAUSE AT "WBR 1452.223-81 SAFETY
AND HEALTH."
This page intentionally left blank.
Water Treatment Plant Replacement Amendment No. 0002 Leadville Mine Drainage Tunnel Project, Colorado Solicitation No. 140R4023R0011
Table of Contents
Revised 00 01 10 - 1
SECTION C – DESCRIPTION/SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 12 10 Other Contracts 01 14 00 Work Restrictions 01 14 10 Use of Site 01 14 30 Interruption of Service 01 31 19 Project Management and Coordination 01 32 10 Construction Program 01 33 00 Submittals 01 33 26 Electrical Drawings and Data 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 35 50 Site Security 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 46 25 Special Inspections 01 51 00 Temporary Utilities 01 52 10 Field Office 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 20 Existing Fences 01 56 26 Temporary Fencing 01 56 32 Temporary Safety Fence 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 35 Oil Spill Prevention 01 57 40 Pesticides 01 57 50 Tree and Plant Protection 01 57 60 Protected Species 01 60 00 Product Requirements 01 64 40 Government-Furnished Products 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents 01 79 20 Training 01 86 30 Information System Security 01 91 16 Commissioning
Revised 00 01 10 - 2
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 02 83 33 Removal and Disposal of Equipment with Coatings Containing Regulated Metals
DIVISION 03 – CONCRETE
03 11 10 Concrete Forming 03 15 18 Rubber Joint Strips 03 20 00 Concrete Reinforcing 03 20 30 Post-Installed Reinforcing Bars 03 20 60 Concrete Anchors 03 30 00 Cast-In-Place Concrete 03 35 10 Concrete Floor Hardener 03 48 00 Precast Concrete Structures 03 62 20 Nonshrink Grout for Equipment and Metalwork 03 63 00 Epoxy Grout
DIVISION 04 – MASONRY
04 22 10 Reinforced Concrete Unit Masonry Assemblies
DIVISION 05 – METALS
05 12 10 Structural Steel 05 21 23 Steel Joist and Joist Girders 05 31 00 Metal Decking 05 40 00 Cold-Formed Metal Framing 05 50 00 Metal Fabrications 05 51 10 Stairs 05 51 20 Equipment Support Structure, Platforms and Stairs
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 82 10 Fiberglass Reinforced Plastic (FRP) Fabrications 06 83 00 Fiberglass Reinforced Paneling
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 19 20 Silane Water Repellent 07 21 20 Extruded Polystyrene Foam Insulation 07 21 40 Batt and Blanket Insulation 07 21 50 Spray-Applied Polyurethane Foam Insulation 07 41 13 Pre-Insulated Metal Roof Panels 07 42 13 Pre-Insulated Metal Wall Panels 07 84 00 Firestopping 07 92 00 Joint Sealants and Masonry Joints
Revised 00 01 10 - 3
DIVISION 08 – OPENINGS
08 11 10 Steel Doors and Frames 08 31 25 Floor Access Hatches 08 33 20 Roll-Up Doors 08 41 10 Aluminum Framed Entrances and Storefronts 08 51 20 Steel Windows 08 71 00 Door Hardware 08 81 00 Glazing
DIVISION 09 – FINISHES
09 29 00 Gypsum Board 09 30 10 Ceramic Tile 09 50 00 Acoustical Ceilings 09 65 10 Resilient Wall Base 09 68 13 Tile Carpeting 09 96 20 Coatings
DIVISION 10 – SPECIALTIES
10 14 00 Signage 10 14 01 Exterior Signage 10 14 26 Utility Markers 10 26 00 Wall and Door Protection 10 28 13 Toilet Room Accessories 10 44 20 Fire Extinguishers 10 51 00 Lockers 10 56 51 Wall-Mounted Shelves 10 75 16 Ground Set Flagpole
DIVISION 11 – EQUIPMENT
11 53 00 Laboratory Equipment
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 12 30 00 Casework and Countertops 12 48 13 Entrance Floor Mats and Frames
DIVISION 13 – SPECIAL CONSTRUCTION
13 34 20 Metal Building System 13 34 23 Generator Roof Canopy
Revised 00 01 10 - 4
DIVISION 14 – CONVEYING EQUIPMENT
14 20 10 Machine Room-less (MRL) Electric Traction Passenger Elevator
DIVISION 21 – FIRE SUPPRESSION
21 13 13 Water Based Fire Suppression Systems 21 22 00 Deleted 21 25 00 Hybrid Water Mist Fire Suppression System
DIVISION 22 – PLUMBING
22 00 00 Plumbing System 22 05 00 Common Work Results for Plumbing 22 05 13 Common Motor Requirements for Plumbing Equipment 22 05 17 Sleeves and Sleeve Seals for Plumbing Piping 22 05 19 Meters and Gauges for Plumbing Piping 22 05 23 Valves for Plumbing Piping 22 05 29 Hangers and Supports for Plumbing Piping and Equipment 22 05 33 Heat Tracing for Plumbing Piping 22 05 48 Vibration Controls for Plumbing Piping and Equipment 22 05 53 Identification for Plumbing Piping and Equipment 22 07 19 Plumbing Piping Insulation 22 11 16 Facility Water Distribution Piping 22 11 19 Facility Water Piping Specialties 22 11 20 Service Water Equipment 22 11 23 Inline, Domestic-Water Pumps 22 13 00 Facility Sanitary Sewers 22 13 16 Sanitary Waste and Vent Piping 22 13 19 Sanitary Waste Piping Specialties 22 13 23 Oil Interceptors 22 14 19 Chemical Drainage Piping Systems 22 14 30 Sump Pumping Systems 22 15 00 General Service Compressed Air System 22 23 11 Facility Natural Gas Piping 22 35 00 Water Heaters 22 42 00 Plumbing Fixtures 22 45 00 Emergency Plumbing Fixtures
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 Heating, Ventilating, and Air-Conditioning (HVAC) Systems 23 05 00 Common Work Results - HVAC 23 05 13 Common Motor Requirements - HVAC Equipment 23 05 16 Expansion Fittings and Loops - HVAC Piping 23 05 17 Sleeves and Sleeve Seals - HVAC Piping
Revised 00 01 10 - 5
23 05 23 Valves - HVAC Piping 23 05 29 Supports - HVAC 23 05 48 Vibration Controls - HVAC Piping and Equipment 23 05 53 Identification - HVAC 23 05 93 Testing, Adjusting, and Balancing - HVAC 23 07 13 Duct Insulation - HVAC 23 07 19 Piping Insulation - HVAC 23 08 00 Commissioning - HVAC 23 09 00 Instrumentation and Control - HVAC 23 09 23 Direct Digital Control (DDC) System - HVAC 23 09 24 Hydronic Control Valves 23 09 25 Control Dampers 23 21 00 Hydronic Piping 23 21 16 Hydronic Piping Specialties 23 21 23 Hydronic Pumps 23 23 00 Refrigerant Piping 23 25 13 Water Treatment for Closed Loop Hydronic Systems 23 31 00 Ducts - HVAC 23 33 00 Air Duct Accessories 23 34 00 Fans - HVAC 23 35 00 Welding Fume Exhaust Systems 23 36 00 Air Terminal Units 23 37 00 Air Inlets and Outlets 23 52 00 Heating Boilers 23 54 13 Electric Resistance Duct Heater 23 54 16 Gas-Fired Furnaces 23 55 00 Fuel-Fired Heaters 23 62 00 Condensing Units 23 73 13 Indoor, Custom Air-Handling Units 23 73 39 Indoor, Direct-Fired Heating and Ventilating Units 23 81 26 Split System Air Conditioners 23 82 39 Electric Heat Units
DIVISION 25 – INTEGRATED AUTOMATION
25 00 01 Water Treatment Plant (WTP) Control System 25 00 03 System Datasheets
DIVISION 26 – ELECTRICAL
26 05 02 Basic Electrical Materials and Methods 26 05 10 Conductors and Cables 26 05 26 Grounding and Bonding 26 05 33 Raceways and Boxes 26 05 36 Cable Trays 26 05 90 Wiring Checkout and Tests
Revised 00 01 10 - 6
26 09 55 Lighting Control Panel 26 16 14 480-Volt Metal-Enclosed Switchgear 26 19 45 Cable Bus 26 24 13 Switchboard 26 24 16 Distribution Panelboards 26 24 19 600V Motor Control Centers 26 24 20 Control Panels and Enclosures 26 26 10 Transformer Load Center 26 27 40 Wiring Devices 26 30 10 Automatic Transfer Switches 26 32 10 Engine-Generator Sets 26 33 46 125V DC Battery System 26 33 48 DC Switchboard 26 33 53 Uninterruptible Power Supply (UPS) 26 51 10 Interior Lighting 26 52 20 Emergency Lighting 26 56 60 Exterior Lighting
DIVISION 27 – COMMUNICATIONS
27 21 01 Communications Systems 27 30 01 Telephone System
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 10 01 Security and Surveillance System 28 31 00 Fire Detection and Alarm
DIVISION 31 – EARTHWORK
31 02 10 Water for Dust Abatement and Dust Palliative 31 03 10 Diversion and Care of Holding Pond Water 31 03 33 Removal and Control of Water 31 11 00 Clearing and Grubbing 31 14 10 Stripping 31 23 02 Compacting Earth Materials 31 23 10 Earthwork 31 23 22 Pipe Trench Earthwork 31 23 39 Disposal of Excavated Materials 31 23 70 Controlled Low Strength Material (CLSM) 31 25 10 Erosion Control 31 32 30 Liner System 31 32 35 Geocomposite 31 32 36 Geomembrane
Revised 00 01 10 - 7
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 22 Asphalt Concrete Pavement 32 17 20 Painted Traffic Lines and Markings 32 31 10 Chain Link Fence 32 31 18 Chain Link Vertical Pivot Gate 32 32 00 Retaining Walls 32 92 20 Seeding and Soil Supplements
DIVISION 33 – UTILITIES
33 05 19 Metal Pipe 33 05 21 Bored Utility Crossing 33 11 14 Reinforced Concrete Pressure Pipe 33 11 17 PVC Gravity Drain 33 11 18 HDPE Pressure Pipe 33 11 50 Pipe Crossings at Existing Utility Pipelines 33 14 19 Fire Hydrants 33 46 40 Underslab Drainage
DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION
35 22 14 Valves and Equipment
DIVISION 40 – PROCESS INTERCONNECTIONS
40 00 00 Process Interconnection 40 05 07 Hangers and Supports for Process and Chemical Piping 40 05 23 Stainless-Steel Process Piping 40 05 24 Steel Pipe 40 05 31 Thermoplastic Pipe 40 05 33 High-Density Polyethylene Piping 40 05 36 Fiberglass Reinforced Plastic Pipe 40 05 53 Process Valves and Accessories 40 05 63 Chemical Valves 40 05 97 Identification for Process and Chemical Piping 40 41 00 Process Piping and Equipment Heat Tracing 40 42 00 Process Piping and Equipment Insulation 40 70 00 Instrumentation Index 40 71 00 Flow Measurement 40 72 00 Level Measurement 40 73 00 Pressure Measurement 40 74 00 Temperature Measurement 40 75 00 Analytical Instrumentation 40 79 00 Instrument Valves and Fittings
Revised 00 01 10 - 8
DIVISION 41 – MATERIAL PROCESS AND HANDLING EQUIPMENT
41 12 13 Conveyors 41 22 10 Davit Arm Cranes 41 22 14 Overhead Bridge Crane 41 22 23 Monorail Crane 41 62 23 Forklift Trucks
DIVISION 42 – PROCESS HEATING, COOLING AND DRYING EQUIPMENT
42 12 00 Process Heaters
DIVISION 43 – PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND
STORAGE EQUIPMENT
43 23 00 Vertical Lineshaft Pumping Units 43 23 71 Air-Operated Diaphragm Reciprocating Pumps 43 41 13 Welded Steel Tanks 43 41 43 Polyethylene Tanks 43 41 45 Fiberglass Reinforced Plastic Tanks
DIVISION 46 – WATER AND WASTEWATER EQUIPMENT
46 05 00 General Requirements for Equipment 46 33 00 Liquid Chemical Feed Equipment 46 33 42 Diaphragm-Type Metering Pumps 46 33 44 Peristaltic Metering Pumps 46 33 66 Liquid Chemical Transfer Pumps 46 33 83 Liquid Chemical Feed Accessories and Safety Equipment 46 40 10 Air Stripper Equipment 46 41 13 Inline Rapid Mixers 46 41 17 Inline Static Mixers 46 41 41 Top-Entering Tank Mixers
DIVISION 51 – INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 00 10 Existing Storage Building Photographs 51 00 12 Existing Holding Pond Photographs 51 00 14 Existing Pond Pump House Photographs 51 00 16 Existing WTP Site Photographs 51 00 18 Existing WTP Building Photographs 51 00 20 Existing 10+25 Well Pump Station Photographs 51 00 22 Existing 46+96 Well Pump Station Photographs 51 00 24 Miscellaneous Existing Conditions Photographs 51 00 50 Electronic Media Release 51 02 80 Hazardous Materials Reports
Revised 00 01 10 - 9
51 31 03 Existing Monitoring Well Water Quality Data 51 33 01 Storm and Clearwell Drain Line Systems Inspection Report 51 33 03 Existing Commercial Well Permit 51 33 05 Utility Potholing Reports 51 46 43 Solids Contact Clarifiers (SCC) Supply Contract Approval Drawings and Data 51 46 61 Membrane Filtration System (MFS) Supply Contract Approval Drawings and
Data 51 46 76 Filter Presses (FP) Supply Contract Approval Drawings and Data
DIVISION 52 – DRAWINGS
52 00 00 Drawings
DIVISION 53 – GEOLOGIC INVESTIGATIONS AND RECORDS
53 00 05 Baseline Conditions 53 10 01 Geotechnical Supporting Documents 53 20 00 Geologic Investigations 53 20 01 Preconstruction Geologic Design Data
END OF CONTENTS
Revised 00 01 10 - 10
This page intentionally left blank.
Summary of Work
Revised 01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work is located on the north side of Leadville, Colorado, in Lake County at and near the Leadville Mine Drainage Tunnel Water Treatment Plant, 749 Highway 91, Leadville, Colorado 80461.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Overview: Work consists of constructing a new 3.2 million gallons per day (MGD) Water Treatment Plant (WTP) adjacent to an existing 3.2 MGD WTP, then demolition of the existing WTP.
B. Contractor is responsible for staging areas, including space for construction trailers, material storage, and construction staff parking.
C. Contractor is responsible for investigations before beginning any construction, including:
1. Exploratory excavations and contacting utility owners, to determine locations and type of existing utilities, including:
a. Service connections, prior to commencing work which could result in damage to such utilities.
b. Immediately notify Reclamation to utilities discovered in a different position than indicated in contract documents or not indicated in contract documents.
D. Install:
1. Traffic control measures, protection measures for existing components, and temporary fencing.
2. Erosion control measures and maintain temporary safety fence and protection of existing installations as needed.
3. Site retaining walls.
4. Contractor designed unwatering and/or dewatering system to perform excavations to facilitate construction.
5. Hot tap with isolation valve on an existing potable water line on south side of
Colorado State Highway 91. Coordinate with Parkville Water District and Colorado Department of Transportation.
Revised 01 11 00 - 2
6. Potable water piping via auger bore under Colorado State Highway 91.
Coordinate with Colorado Department of Transportation.
7. Potable water piping along River Road from Colorado State Highway 91 to WTP site. Coordinate with Lake County.
8. New treatment building.
9. New storage building.
10. New diesel emergency generators.
11. Site improvements, including yard piping, duct banks, stormwater, perimeter fencing and access point modifications, relocation of two existing flammables container buildings, relocation of one 250-gallon diesel fuel storage tank and supporting structure, surface treatments, landscaping, site lighting, and restoration of construction-impacted areas.
E. Site grading, cuts, and fills as required.
F. Receive delivery of, store, install, startup, and commission water treatment equipment from three Government-furnished equipment supply contracts.
G. Modify:
1. Permanent power supply to WTP site. Coordinate with Xcel Energy.
2. Natural gas service to WTP site. Coordinate with Xcel Energy.
3. Site’s existing septic system. Coordinate with Lake County:
a. Provide septic tank hauling services as needed per Contractor’s schedule in accordance with Sections 01 14 00 – Work Restrictions and 01 32 10 – Construction Program.
b. Dispose of existing leach field soil material per Lake County requirements, including performing analyses required by the receiving landfill.
4. Telecommunication service to WTP site. Coordinate with current provider.
5. Existing pond pump station to reuse existing wet well and replace pump station.
H. Replace:
1. Programmable logic controller (PLC) hardware and program new PLC at existing mine drainage well facility 10+25 Well Pump Station located approximately
0.25 miles south-southeast of existing WTP site.
2. Programmable logic controller (PLC) hardware and program new PLC at existing mine drainage well facility 46+96 Well Pump Station located approximately 1-mile south-southeast of existing WTP site.
3. Existing holding pond lining system and associated components.
Revised 01 11 00 - 3
I. Commission new WTP building and water treatment systems, including all associated disciplines work.
J. Maintain continuity of existing WTP operations during project construction until existing WTP has been decommissioned:
1. Relocate existing filter press on temporary concrete pad complete with infrastructure and utilities required for operation until new WTP building has been commissioned, then demolish components required for existing filter press operation.
K. Plug, seal, and abandon existing WTP building’s commercial well, Colorado Department of Water Resources well permit 158302, in accordance with Code of Colorado Regulations 2 CCR 402-2, Rules and Regulations for Water Well Construction, Pump Installation, Cistern Installation, and Monitoring and Observation Hole/Well Construction.
L. Demolish:
1. Existing storage building.
2. Existing water treatment plant building and adjacent structures, including decommissioning existing WTP.
M. Remove existing sediment from existing 18-inch diameter PVC stormwater outfall line from existing catch basin CB-3 north to the pipe outlet, approximately 175 feet. For existing conditions, in accordance with Section 51 33 01 – Storm and Clearwell Drain Line Systems Inspection Report.
N. Remove existing sediment from existing 18-inch diameter stormwater outfall line from existing northeast catch basin north to the outlet, approximately 60-feet.
O. Remove traffic control measures, protection measures for existing components, and temporary fencing.
P. Demobilize for winter shutdown(s) as necessary.
Q. Project management and administration, including scheduling, obtaining permits, and coordination with Reclamation.
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.
Revised 01 11 00 - 4
1.04 DEFINITIONS
A. When specifications use word or term defined in Federal Acquisition Regulations (FAR), definition of word or term shall be in accordance with FAR sections in effect at time solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 53:
1. CO: Contracting Officer.
2. COR: Contracting Officer’s Representative.
3. OGR: Onsite Government Representative.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Submittals
Revised 01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in Price Schedule 1 for other items of work.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-20 Decimal Inch Drawing Sheet Size and Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittals: Considered “shop drawings” within terms of clause at FAR 52.236-21, Specifications and Drawings for Construction.
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included in this section take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement Units: US Customary Units.
C. Drawings:
1. Minimum Identification in Title Block:
a. Contract number and title.
b. Contractor’s or supplier’s title and drawing number.
Revised 01 33 00 - 2
c. Date.
2. Reserve 3- by 3-inch space next to title block for review stamps.
3. Size: ANSI D size (22- by 34-inches).
4. Draw to scale using computer drafting.
a. In accordance with NIBS NCS.
b. Electronic file format: Compatible with AUTOCAD, Version 2021 or later.
c. Compile using “eTransmit” utility in AUTOCAD.
d. Government will provide electronic AutoCAD and Revit format template.
e. Title block and sheet format:
1) As shown on Standard Drawing 40-D-7102.
2) Government will supply template.
3) Government will supply specific title block information to be used.
f. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
D. Manuals:
1. Copies:
a. Printed copies: Bound and indexed.
b. Electronic copies: Adobe pdf submitted to Microsoft Teams:
1) Bookmark longer files to assist in navigating file.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Schematics and wiring diagrams.
c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
d. As-built drawings, photographs, and test records or reports if required by the specifications.
E. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets:
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in manner that will photocopy (no highlighter).
Revised 01 33 00 - 3
d. Strike through items that do not apply.
F. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.
G. Photographs and Isometric Images:
1. Professional quality:
a. Include contract number, name of equipment, and view title.
b. Digital files in .jpeg.
H. Videos:
1. Include digital file in MP4 format.
2. Upload to Microsoft Teams.
I. Samples and Color Selection Submittals:
1. Mark to attention of appropriate TSC department and submit all samples to Technical Service Center Denver, CO.
a. Ship samples to:
a) Bureau of Reclamation Attn: 86-68160 Building 67, Denver Federal Center 6th Avenue West and Kipling Street P.O. Box 25007 Denver, CO 80225-0007
2. Label with complete manufacturer’s product and color identification.
3. Include type and quantity of materials specified in the referenced section in each “set” of samples.
4. Samples: Representative of product to be installed. Xerographic sheets for color selection are not acceptable.
5. Color Chips: Sample paint chips. Ink color reproductions are not acceptable.
6. Label each sample, sample kit, set of color chips, of color chart with contract number and title.
7. Government will select architectural color and pattern after product approval.
Revised 01 33 00 - 4
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A – List of Submittals. Complete set includes all listed items for RSNs with multiple parts.
C. Submit in accordance with “No. of sets to be sent:” columns in Table 01 33 00A – List of Submittals:
1. Electronic submittals:
a. In single Portable Document Format (PDF):
1) Optical Character Recognition (OCR).
2) 508 compliant.
3) RSNs having more than one requirement shall be bookmarked.
4) RSNs with requirements for files other than PDF (e.g., .XER, .PLF, .DWGs, etc.) shall be combined using WINZip.
5) Include RSN transmittal letter.
6) Each submittal shall be submitted as one PDF or WINZip.
b. Personally Identifiable Information (PII) shall be encrypted using WINZip or Adobe Acrobat before transmitting electronically.
2. Submit electronic submittals via Microsoft Teams:
a. Access to Microsoft Teams will be made available for transmission of submittals and information sharing following Notice to Proceed.
b. Submittals received after 5:00 p.m. Mountain Time, shall be documented as received the next business day.
D. Include the following information in transmittal letters:
1. Cover Letter:
a. Contract number and title.
b. RSN for each attached submittal.
c. Responsible code.
d. Identify submittal as initial or resubmittal.
2. Submittal contents following cover letter:
a. Shall include all listed items for RSNs with multiple parts.
Revised 01 33 00 - 5
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
a. Resubmitted drawings shall include a revision block with date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 21 calendar days after receiving comments.
4. Requirements for initial submittals apply to resubmittals.
5. Resubmittals shall be complete submittals without reference to the original submittal.
F. Submit each RSN under separate transmittal letter. Multiple RSNs submitted under single letter will be returned for resubmittal.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 28 calendar days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for RSN are received and extends through return email date.
3. Provide Submittal Register as required within specifications Section 01 32 10 – Construction Program. Submittal Register shall be complete and include anticipated submittal dates for each RSN:
a. Division 1 submittals shall be provided per due date or delivery time provided within Table 01 33 00A – List of Submittals.
b. Sequence Division 2 through 46 submittals to maintain Contractor’s construction schedule, with submittals intentionally staggered. Submit no more than 5 submittals, counting original and resubmittals, per Division(s) listed below within one 7-day period.
1) Division 2.
2) Division 4 and 5.
3) Division 6 through 14.
4) Division 21 through 23.
5) Division 25 through 28.
6) Division 31 through 32.
7) Division 33 through 35.
8) Division 40.
Revised 01 33 00 - 6
9) Division 41 through 43.
10) Division 46.
c. Contractor and Government shall mutually agree to a revised review time for submittals received in excess of 5 submittals per 7-day period for Division(s) listed above.
B. Time in Excess of Specified:
1. CO may extend contract completion date to allow additional time for completing work affected by excess review time:
a. Time extension will be to extent that excess review time caused delay to contract completion date.
b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.
2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to extent that:
a. Approval was required under contract, and
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of clause at FAR 52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as term is used in that clause.
C. Submittal Response:
1. Response letter will indicate whether submittal is approved, not approved, acceptable, not acceptable, or acknowledged receipt:
a. Revise and resubmit submittals not approved or not acceptable.
b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.
2. Request for Information (RFI): Response will be provided within 28 calendar days.
3. General Correspondence to CO/COR: Response will be provided within 28 calendar days.
Revised 01 33 00 - 7
1.07 TRANSMITTAL
A. Microsoft Teams access will be established for uploading transmittals in Table 01 33 00A
– List of Submittals.
B. Submittals required by specifications, but not listed in Table 01 33 00A – List of Submittals:
1. Submit in accordance with this Section.
2. Submit to CO/COR unless otherwise specified.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
Table 01 33 00A – List of Submittals ** CO indicates Contracting Officer; COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals Required Due Date or
Delivery Time
Respon-sible code
Sets to be sent: **
CO COR
1 Performance and Payment Bonds - Construction 52.228-15
Performance and Payment Bonds
Within 10-calendar days after award
CO 1 electronic 0
2 Additional Bond Security 52.228-2
Additional Bond Security
Within 10-calendar days after award
CO 1 electronic
3 Insurance-Work on a Government Installation 1452.228-70
1) Written certification that the required insurance has been obtained
2) Current certification of insurance for each subcontractor
Before commencing onsite work
CO 1 electronic
1 electronic
4 Liability Insurance 1452.228-70
Acceptable Certificate of Liability Insurance
Prior to commencement of work under the contract
CO 1 electronic 0
5 Equal Opportunity 52.222-26
Information required by Executive Order 112246
(SF-100)
Within 30 days following award
CO 1 electronic 0
Revised 01 33 00 - 8
Table 01 33 00A – List of Submittals ** CO indicates Contracting Officer; COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals Required Due Date or
Delivery Time
Respon-sible code
Sets to be sent: **
CO COR
6 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10
Certification that executive compensation and subcontract awards were reported
Within 10 days of each report being submitted
CO 1 electronic 0
7 Release of Claims 1452.204-70
Release of Claims (DI-
137) against the Government
After completion of the work and prior to final payment
CO 1 electronic 0
8 Personal Identity Verification 52.204-09
SF-85 and OF-306 for each employee and subcontractor employee working on site
Within 10 days after receipt of Notice to Proceed (NTP) or 28 days before onsite arrival (for new hire)
CO 1 electronic 0
9 Labor Standards Data 52.222-11
1) List of subcontractors
Within 14 days after award of contract
COR 1 electronic 1 electronic
10 Labor Standards Data 52.222-11
2) Statement and acknowledgement Form (SF-1413) for each subcontract
Within 14 days after award of contract
COR 1 electronic
1 electronic
11 Payrolls and Basic Records 52.222-08
Copies of all payrolls Weekly for each week of contract performance
COR 1 electronic encrypted
1 electronic encrypted
12 Site Security
WBR 1452.237-80
List of contractor and subcontractor employees
At least 28 days prior to arriving at worksite
COR 0 1 electronic encrypted
13 Site Security
WBR 1452.237-80
List of vehicles and equipment to be brought on site
At least 28 days prior to arriving at worksite
COR 0 1 electronic encrypted
14 Superintendence by the Contractor 52.236-6
Site Superintendent Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 14 00-1 Work Restrictions Existing Facility Access Request
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 14 30-1 Interruption of Service
Interruption of Service Request
Submitted and approved at least 56 days before required interruption
COR 0 1 electronic
Revised 01 33 00 - 9
Table 01 33 00A – List of Submittals ** CO indicates Contracting Officer; COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals Required Due Date or
Delivery Time
Respon-sible code
Sets to be sent: **
CO COR
01 31 19-1 Project Management and Coordination
Weekly Coordination Meeting Agenda
Weekly, 3-business days prior to meeting
COR 0 1 electronic
01 31 19-2 Project Management and Coordination
Weekly Coordination Meeting Minutes
Within 5 days of meeting
COR 0 1 electronic
01 31 19-3 Project Management and Coordination
WTP Control System and Design Meeting Agenda
3-business days prior to meeting
COR 0 1 electronic
01 31 19-4 Project Management and Coordination
WTP Control System and Design Meeting Minutes
Within 5 days of meeting
COR 0 1 electronic
01 32 10-1 Construction Program
Representative Information
Submitted and approved 7 days after
NTP
COR 1 1 electronic
01 32 10-2 Construction Program
Baseline Schedule Submitted and approved 21 days after NTP
COR 1 1 electronic
01 32 10-3 Construction Program
Submittal Register Submitted and approved 21 days after NTP and updated monthly
CO 1 1 electronic
01 32 10-4 Construction Program
Updated Schedule Reports
Submitted and approved 14 days prior to monthly progress payments
COR 1 1 electronic
01 32 10-5 Construction Program
Time Impact Analysis Within 14 days after CO directs a contract change, with any proposal for a future modification, with any value engineering proposal, or with any request or claim for an equitable adjustment to the contract
COR 1 1 electronic
01 32 10-6 Construction Program
Schedule of Values Submitted and approved before any payment other than bonds and insurance
COR 0 1 electronic
01 35 10-1 Safety Data Sheets Complete LHM and
SDS
At least 28 days before jobsite delivery of hazardous material
Revised 01 33 00 - 10
Table 01 33 00A – List of Submittals ** CO indicates Contracting Officer; COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals Required Due Date or
Delivery Time
Respon-sible code
Sets to be sent: **
CO COR
01 35 10-2 Safety Data Sheets Updated LHM and SDS At least 28 days before jobsite delivery of hazardous material not previously listed
COR 0 1 electronic
01 35 20-1 Safety and Health Safety Program Submitted and accepted at least 28 days before mobilization
COR 0 1 electronic
01 35 20-2 Safety and Health Monthly Accident Summary Reports
Monthly COR 0 1 electronic
01 35 20-3 Safety and Health Respirator User Documentation
Submitted and accepted at least 28 days before beginning onsite work
COR 0 1 electronic encrypted
01 35 20-4 Safety and Health Crane Operation Certificates
Submitted and accepted at least 28 days before beginning onsite work
COR 0 1 electronic
01 35 20-5 Safety and Health Exposure Assessment Form
Submitted and accepted at least 28 days before beginning onsite work
COR 0 1 electronic
01 35 20-6 Safety and Health Other Training Certificates
Submitted and accepted at least 28 days before beginning onsite work
COR 0 1 electronic
01 35 20-7 Safety and Health Pandemic Notification Submitted and accepted within 24 hours of positive test
COR 0 1 electronic encrypted
01 35 20-8 Safety and Health Employee Return to Work Documentation
Submitted and accepted 7 days prior to returning to work
COR 0 1 electronic encrypted
01 35 30-1 Contractor’s Onsite Safety Personnel
Qualifications Submitted and accepted at least 28 days before mobilization
COR 0 1 electronic encrypted
01 35 30-2 Contractor’s Onsite Safety Personnel
Safety Inspection Reports
Weekly COR 0 1 electronic
Revised 01 33 00 - 11
Table 01 33 00A – List of Submittals ** CO indicates Contracting Officer; COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals Required Due Date or
Delivery Time
Respon-sible code
Sets to be sent: **
CO COR
01 35 50-1 Site Security Site Security Plan Submitted and approved at least 28 days prior to beginning onsite work
COR 0 1 electronic encrypted
01 35 50-2 Site Security Employee Information Submitted and approved at least 28 days prior to beginning onsite work
COR 0 1 electronic encrypted
01 46 00-1 Quality Procedures Contractor Quality Control Program
Submitted and approved within 28 days of NTP
COR 0 1 electronic
01 46 00-2 Quality Procedures Contractor’s Daily Reports
Weekly COR 0 1 electronic
01 46 00-3 Quality Procedures Quality Control Supervisor Resume
Submitted and approved within 28 days of NTP
COR 0 1 electronic encrypted
01 46 00-4 Quality Procedures Contractor’s Quality Testing Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 46 00-5 Quality Procedures Summary of Test Results
Monthly COR 0 1 electronic
01 46 20-1 Testing Agency Services
Testing Agency Services Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 46 25-1 Special Inspections Preconstruction Submittals
Submitted and approved at least 28 days before required inspections
COR 0 1 electronic
01 46 25-2 Special Inspections Test Reports Submitted and accepted within 7 days of completion of tests
COR 0 1 electronic
01 46 25-3 Special Inspections Certificates Submitted within 28 days after preconstruction meeting
COR 0 1 electronic
01 46 25-4 Special Inspections Final Reports Submitted and accepted within 28 days after completion of inspection
Revised 01 33 00 - 12
Table 01 33 00A – List of Submittals ** CO indicates Contracting Officer; COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals Required Due Date or
Delivery Time
Respon-sible code
Sets to be sent: **
CO COR
01 51 00-1 Temporary Utilities Temporary Power Plan Submitted and approved at least 28 days before beginning onsite work
COR 0 1 electronic
01 51 00-2 Temporary Utilities Temporary Power Schedule
Submitted and approved at least 28 days before beginning on-site work
COR 0 1 electronic
01 51 00-3 Temporary Utilities Temporary Power Removal Plan
Submitted and approved at least 28 days before beginning on-site work
COR 0 1 electronic
01 52 10-1 Field Office Delivery Schedule Submitted and accepted 28 days before mobilization
COR 0 1 electronic
01 55 20-1 Traffic Control Traffic Control Plan Submitted and approved at least 28 days before affecting public traffic
COR 0 1 electronic
01 56 10-1 Protection of Existing Installations
Plan for Protecting Existing Installations
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 56 10-2 Protection of Existing Installations
Initial Construction Site Photographs and Video
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 56 10-3 Protection of Existing Installations
Post Construction Site Photographs and Video
Submitted and accepted at least 2 days before demobilization
COR 0 1 electronic
01 56 15-1 Protection of Existing Utilities
Utility Owner Acknowledgment
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 56 26-1 Temporary Fencing Approval Data Submitted and approved at least 28 days before beginning onsite work
Revised 01 33 00 - 13
Table 01 33 00A – List of Submittals ** CO indicates Contracting Officer; COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals Required Due Date or
Delivery Time
Respon-sible code
Sets to be sent: **
CO COR
01 57 30-1 Water Pollution Control
Pollution Prevention Plan
Submitted and approved at least 28 days before beginning onsite work
COR 0 1 electronic
01 57 30-2 Water Pollution Control
Spill Prevention, Control, and Countermeasure (SPCC) Plan
Submitted and approved at least 28 days before delivery or storage of oil
COR 0 1 electronic
01 57 40-1 Pesticides Pesticide Use Plan Submitted and accepted 28 days prior to pesticide use
COR 0 1 electronic
01 57 50-1 Tree and Plant Protection
Protection Plan Submitted and approved at least 28 days before beginning onsite work
COR 0 1 electronic
01 64 40-1 Government- Furnished Products
Shortage Report Submitted and accepted within 14 days of shortage
COR 0 1 electronic
01 71 20-1 Surveying Surveying Plan Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 71 20-2 Surveying Resumes Submitted and approved at least 28 days before beginning survey work, and at least 28 days before personnel change
COR 0 1 electronic
01 71 20-3 Surveying Accuracy Check Results Submitted and approved at least 28 days before beginning survey work
COR 0 1 electronic
01 71 20-4 Surveying Quantity Survey Notes and Computations
Submitted and approved 14 days prior to monthly progress payments
Revised 01 33 00 - 14
Table 01 33 00A – List of Submittals ** CO indicates Contracting Officer; COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals Required Due Date or
Delivery Time
Respon-sible code
Sets to be sent: **
CO COR
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
Submitted and approved at least 28 days before beginning onsite work
COR 0 1 electronic
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
Submitted and accepted within 7 days of waste disposal
COR 0 1 electronic
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
Submitted and approved at least 28 days before beginning environmental assessment
COR 0 1 electronic
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
Submitted and approved within 14 days of completion of work
COR 0 1 electronic
01 78 30-1 Project Record Documents
Electronic Media Release Form
Submitted and accepted within 7 days after NTP
COR 0 1 electronic
01 78 30-2 Project Record Documents
As-built Drawings Submitted and accepted within 28 days of Government-issued substantial completion of work
COR 0 1 electronic
01 78 30-3 Project Record Documents
O&M Manual Set Submitted and accepted within 28 days of Government-issued substantial completion of work
COR 0 1 electronic + 1 hard copy after approval of electronic
01 78 30-4 Project Record Documents
Warranties Submitted and accepted within 28 days of Government-issued substantial completion of work
COR 0 1 electronic
01 79 20-1 Training Instructor Qualifications Submitted and accepted 28 days prior to training session
Revised 01 33 00 - 15
Table 01 33 00A – List of Submittals ** CO indicates Contracting Officer; COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals Required Due Date or
Delivery Time
Respon-sible code
Sets to be sent: **
CO COR
01 79 20-2 Training Training Materials Submitted and approved 28 days prior to training session
COR 0 1 electronic
01 79 20-3 Training Training Video Submitted and approved 28 days prior to training session
COR 0 1 electronic
01 86 30-1 Information System Security
Component and Network Documentation
Submitted and accepted concurrent with RSN 25 00 01-2
8430 0 1 electronic
01 86 30-2 Information System Security
Information System Inventory
Submitted and accepted concurrent with RSN 25 00 01-3
8430 0 1 electronic
01 86 30-3 Information System Security
Continency Plans Submitted and approved concurrent with RSN 25 00 01-9
8430 0 1 electronic
01 86 30-4 Information System Security
Event Records Documentation
Weekly 8430 0 1 electronic
01 86 30-5 Information System Security
Final System Documentation
Submitted and accepted concurrent with RSN 25 00 01-
8430 0 1 electronic
01 91 16-1 Commissioning Qualifications Submitted and approved 56 days prior to planned commissioning
COR 0 1 electronic
01 91 16-2 Commissioning Test Plan Submitted and approved 56 days prior to planned commissioning
COR 0 1 electronic
01 91 16-3 Commissioning Test and Inspection Procedures
Submitted and approved 56 days prior to planned commissioning
COR 0 1 electronic
01 91 16-4 Commissioning System Turnover Books Submitted and approved 28 days after commissioning
COR 0 1 electronic
01 91 16-5 Commissioning Issues and Resolution Log
Monthly COR 0 1 electronic
01 91 16-6 Commissioning Maintenance Log Monthly COR 0 1 electronic
Revised 01 33 00 - 16
Table 01 33 00A – List of Submittals ** CO indicates Contracting Officer; COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals Required Due Date or
Delivery Time
Respon-sible code
Sets to be sent: **
CO COR
01 91 16-7 Commissioning Discrepancy List Monthly COR 0 1 electronic
01 91 16-8 Commissioning Monitored Test (MT) Report
Submitted and accepted within 7 days of completing each test
COR 0 1 electronic
01 91 16-9 Commissioning Demonstration Test (DT) Report
Submitted and accepted within 7 days of completing each test
COR 0 1 electronic
02 41 00-1 Demolition Utility Identification Plan
In accordance with approved
RSN 01 32 10-3
Submittal Register
COR 0 1 electronic
02 41 00-2 Demolition Demolition Plan – Existing Storage Building
In accordance with approved
RSN 01 32 10-3
Submittal Register
COR 0 1 electronic
02 41 00-3 Demolition Demolition Plan – Existing Pond Pump House
In accordance with approved
RSN 01 32 10-3
Submittal Register
COR 0 1 electronic
02 41 00-4 Demolition Demolition Plan – Existing WTP Building
In accordance with approved
RSN 01 32 10-3
Submittal Register
COR 0 1 electronic
02 41 00-5 Demolition Demolition Plan – Existing Site Elements
In accordance with approved
RSN 01 32 10-3
Submittal Register
COR 0 1 electronic
02 41 00-6 Demolition ODS Recovery Plan In accordance with approved
RSN 01 32 10-3
Submittal Register
COR 0 1 electronic
02 41 00-7 Demolition Pre-Demolition Photographs and Video
In accordance with approved
RSN 01 32 10-3
Submittal Register
COR 0 1 electronic
02 41 00-8 Demolition Post-Demolition Photographs and Video
In accordance with approved
RSN 01 32 10-3
Submittal Register
Revised 01 33…