This is a Statement of Work (SOW) Amendment 0001 for the manufacturing and delivery of two hydraulic turbine runners for Hoover Dam Units A2 and N7, issued by the Department of the Interior, Bureau of Reclamation, Lower Colorado Dams Office.
The contract requires the contractor to design, manufacture, and deliver two 196,000 HP turbine runners—one counterclockwise for Unit A2 and one clockwise for Unit N7—that are hydraulically and dimensionally identical to existing Wide Head runner designs previously installed in Units A1, N5, N6, and N8. Principal deliverables include: the turbine runners with associated runner cones and coupling bolts; design and installation of a roughening air admission system including pipework and support cone; supply of four stationary seal rings (upper and lower for each unit); in-place machining of seal ring seats; and contractor witness participation in performance testing. The work is located at Hoover Dam, approximately eight miles northeast of Boulder City, Nevada. Key milestone dates include: solicitation issue on 6/10/2026, proposal due date of 8/10/2026, anticipated award on 11/30/2026, new stationary seal rings delivery by 7/28/2027, in-place machining completion by 11/25/2027 (A2) and 3/24/2028 (N7), air admission completion by 9/20/2028, and new turbine deliveries by 11/19/2028 (A2) and 5/18/2029 (N7). The contract is awarded on a sole source basis per FAR 6.3021(a)(2). The contractor must submit multiple Required Submittal Numbers (RSNs) including approval drawings and design data, material certifications, casting inspection reports, dimensional check reports, welding inspection reports, balancing reports, final NDT reports, and final data packages. Payment terms include 10 percent withholding until all submittals are received and approved. The contractor must comply with extensive technical standards including ASME, ASTM, AWS, IEC, and CCH specifications for materials, welding, non-destructive testing, surface finish, and balancing. The contractor must warrant the runner against mechanical defects, excessive cavitation, cracks, and deformities for two years from the date the unit is placed in service. On-site work requirements include security clearance (PIV card) compliance, safety protocols, personnel qualifications with minimum five years' hydroelectric experience, and compliance with all applicable OSHA, RSHS, and HECP standards. The government will supply labor for runner removal and installation, performance testing, and cableway crane operation up to 150 tons.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement Of Work: A2 & N7 Wide Head Turbine
Department of the Interior
Bureau of Reclamation
LCDO - Hoover Dam
Statement of Work Amendment 0001
SECTION 1 - GENERAL 5
1.01 SUMMARY 5
1.02 DEFINITIONS 5
1.03 CURRENT EQUIPMENT 6
1.04 SCHEDULE FOR THE WORK 6
1.05 MEASUREMENT AND PAYMENT 7
1.06 PERSONNEL QUALIFICATIONS 7
SECTION 2 - SUBMITTALS 8
2.01 SUBMITTAL REQUIREMENTS 8
2.02 SUBMITTAL PROCEDURES 9
2.03 REVIEW OF SUBMITTALS 10
2.04 TRANSMITTAL ADDRESSES 11
2.05 SHIPPING AND DELIVERY 11
2.06 RECEIVING 11
2.07 SHOP ACCESS 12
2.08 SUBMITTAL ITEMS 12
2.09 LIST OF SUBMITTALS 15
SECTION 3 - RUNNER DESIGN AND ANALYSIS 18
3.01 REFERENCE STANDARDS 18
3.02 CURRENT UNIT RATING AND DATA 19
3.03 UNIT STRESSES AND FATIGUE ANALYSIS 20
3.04 DESIGN AND PERFORMANCE REQUIREMENTS 21
3.05 NON-DESTRUCTIVE TESTING AND INSPECTIONS 21
3.06 PERFORMANCE TESTING 25
SECTION 4 - RUNNER MANUFACTURING 26
4.01 MATERIAL REQUIREMENTS 26
4.02 CASTING 26
4.03 RUNNER BLADE TEMPLATES 27
4.04 INTEGRAL SEAL RINGS 28
4.05 ASSEMBLY 28
4.06 WELDING 30
4.07 FINISHING AND TRAILING EDGES 31
4.08 BALANCING 31
4.09 CLEANING AND PASSIVATING 32
SECTION 5 - ASSOCIATED EQUIPMENT 34
5.01 FASTENERS 34
5.02 TURBINE NAMEPLATE 35
5.03 STATIONARY SEAL RINGS 35
5.04 SEAL RING INSTALL AND MACHINING 35
5.05 ROUGHING AIR ADMISSION 36
SECTION 6 - ADDITIONAL REQUIREMENTS 37
6.01 WARRANTY 37
6.02 DELIVERY, STORAGE AND HANDLING 38
6.03 MAINTENANCE 38
6.04 RECOMMENDED CAVITATION REPAIR PROCEDURE 39
SECTION 7 - DRAWINGS 40
7.01 GENERAL 40
7.02 MANUFACTURING AND DETAIL DRAWINGS 40
7.03 ASSEMBLY AND INSTALLATION DRAWINGS 41
7.04 FINAL DRAWINGS 41
7.05 LIST OF PROVIDED DRAWINGS 42
SECTION 8 - ON-SITE REQUIREMENTS 46
8.01 SECURITY 46
8.02 SAFETY 47
8.03 PARKING 47
8.04 USE OF GOVERNMENT LAND 47
8.05 PROTECTION OF EXISTING INSTALLATIONS 48
8.06 GOVERNMENT-SUPPLIED LABOR AND MATERIALS 48
8.07 GOVERNMENT FURNISHED FACILITIES 48
SECTION 9 - APPENDIX 49
9.01 APPENDIX A - EXCERPT FROM PAGE 14 OF THE HSS SUSPECT/COUNTERFEIT
ITEMS AWARENESS TRAINING 49
9.02 APPENDIX B – EXCERPTS FROM PAGE 22 AND 23 OF THE HSS
SUSPECT/COUNTERFEIT ITEMS AWARENESS TRAINING 50
SECTION 1 - GENERAL
1.01 SUMMARY
A. This requirement is being solicited on a sole source basis pursuant to FAR 6.3021(a)(2), Only One
Responsible Source. The turbine runners for Units A2 and N7 must be hydraulically and dimensionally identical to the existing Wide Head runner designs installed in Units A1, N5, N6, and
N8. Compatibility with existing hydraulic performance characteristics, cavitation behavior, structural safety factors, and the Hoover Dam runner interface geometry requires the use of this same design and manufacturing source.
B. The work is located at Hoover Dam and Powerplant, approximately 8 miles northeast of Boulder
City, Nevada and 32 miles from Las Vegas, Nevada in Clark County, Nevada and Mohave County, Arizona.
C. Principal features of the work under this solicitation include:
1. Hydraulic turbine runner manufacturing and delivery of two (2) 196,000 HP turbine runners, one for Unit A2 (counterclockwise) and one for Unit N7 (clockwise), including associated runner cone and coupling bolts and nuts.
2. Design and installation of a roughening air system, including the pipework leading into the headcover and a support cone for the pipework in the turbine runner.
3. The supply of two upper and two lower stationary seal rings for the two units (1 upper and 1 lower per unit).
4. In-place machining of the four new stationary seal rings.
5. Providing a contractor engineer to witness performance testing to determine if the newly installed turbine runners meet hydroelectric efficiency guarantees.
a. The cost is to be included in the lump sum schedule prices for each turbine runner.
D. The two new turbine runners shall be hydraulically similar to the turbine runners supplied to the
Hoover Dam previously for N8, N5, N6, and A1 in Contract No. R10PC30013. N7 shall use the design for N5/6 (clockwise) and A2 shall use the design for A1 (counterclockwise).
1.02 DEFINITIONS
ASME American Society of Mechanical Engineers.
ASNT American Society for Nondestructive Testing.
ASTM American Society for Testing and Materials International.
AWS American Welding Society
CFD Computational Fluid Dynamics
CLIN Contract Line-Item Number
CO Contracting Officer
COR Contracting Officer Representative
Days Calendar days.
FEA Finite Element Analysis
IEC
MT
International Electrotechnical Commission
Magnetic Particle Testing
NDT Non-Destructive Testing
PT Dye Penetrant Testing
Ra Roughness average
RFI Request For Information
RSN Required Submittal Number, identifies items to be submitted together as a complete submittal.
RT Radiographic Testing
SOW Statement of Work, Submittals Includes drawings, data, manuals, certifications, test reports, curves, samples, brochures, and other items furnished by the Contractor for approval, informational, or other purposes.
UT Ultrasonic Testing
1.03 CURRENT EQUIPMENT
A. The Lower Colorado Dams Office (LCDO) currently operates 19 hydro units at Hoover Dam, including 17 large generators (15 with nominal capacity of 130 MW each and 2 with nominal capacity of 60 MW each) and 2 small station service generators with nominal capacity of 3 MW each.
B. The turbine systems for units A2 and N7 were originally supplied by Baldwin Southwark. New replacement turbine runners manufactured by Voest Alpine were installed in 1989 for A2 and 1982 for N7.
1.04 SCHEDULE FOR THE WORK
A. The Government anticipates issuing the sole source award on or about November 30, 2026. All milestone dates below are based on this projected award date and will be adjusted if the award date changes.
B. Milestone Schedule Dates during this contract:
DATE ACTION ITEM
6/10/2026 Issue Solicitation
8/10/2026 Proposal Due date 11/30/2026 Anticipated contract award date 7/28/2027 New stationary seal rings (2 upper, 2 lower) delivered to Hoover 11/25/2027 In-place machining completed on A2 3/24/2028 In-place machining completed on N7 9/20/2028 Air Admission for A2 and N7 completed (excluding turbine component installation) 11/19/2028 New A2 turbine delivered to Hoover 5/18/2029 New N7 turbine delivered to Hoover
C. The dates listed for receipt of submittals listed in Table 1 - List of Submittals are required dates to be met by the contractor under this contract.
D. Delivery dates are milestones; earlier delivery will be accepted and considered beneficial to the project.
1.05 MEASUREMENT AND PAYMENT
A. Cost:
1. Include cost of submittals in prices offered in the schedule for contract line items.
B. Payment:
1. Ten percent (10%) of the payment for contract line items will be withheld until all submittals related to that item are received and approved by the Government.
1.06 PERSONNEL QUALIFICATIONS
A. If the contractor elects to use a sub-contractor, the awardee of the sub-contracted work must have at least 5 years of experience with work in or related to hydro-electric power.
1. Relevant experience can be tabulated by a total of 5 years, but the most recent experience must be no more than 6 months before the award of this solicitation.
2. Experience will be evaluated by the Government prior to mobilization. The contractor is required to provide the government with an advance of 45 business days prior to sub-contractors expected date to be onsite.
3. The government will have 14 business days after receiving sub-contractor experience to evaluate qualifications.
SECTION 2 - SUBMITTALS
2.01 SUBMITTAL REQUIREMENTS
A. In the case where an RSN described in a separate section of this SOW contains different submittal requirements than listed in this section, contractor shall follow the requirements listed there within.
B. General:
1. Identify submittal with contract number, title, and RSN.
2. Submit as an electronic PDF unless otherwise noted.
3. Units: US customary.
C. Drawings:
1. Unless otherwise stated, all drawings included in submittals for this solicitation must meet the requirements listed within Section 7.
D. Product Data:
1. Contractor shall mark the manufacturer’s data for commercial products and equipment used in the completion of this contract.
a. Include manufacturer’s name, type, model, size, and characteristics of the product.
b. Providing markings that products meet requirements of specifications and reference standards as applicable.
c. Ensure markings are furnished in a manner that is visible and can be photographed.
d. Strike through any items that do not apply.
E. Certifications:
1. Certifications must be signed and sealed by a registered professional in the subject which the certification pertains to.
2. Manufacturer certifications must be signed by an authorized representative of the manufacturer.
F. Castings
1. Furnish to the COR certificates showing the results of the ladle analysis and material properties.
G. Mill or Shop Orders
1. The Contractor shall send the COR, upon request, a copy of each mill or shop order for material purchased by the Contractor for use in the fabrication of turbine components.
a. The copies of the orders are to state the place at which the material is to be manufactured.
b. All such mill or shop orders are to quote the requirements of the special conditions and drawings for articles, materials, and supplies to be furnished.
H. Manuals:
1. Copies: Provide hard copies (bound and indexed) and one set of electronic copy either in
Word document (.doc) or Adobe Acrobat document (.pdf) format.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
c. As-built drawings and test records or reports required by the specifications.
I. Inlet/Discharge Edge Templates
1. Submit drawings showing positioning of the templates for reference.
J. Photographs and Images:
1. Include contract number, name of equipment, and view title.
2. Digital files shall be submitted in .jpeg format.
3. Photos shall be in 1080p quality or better.
4. Ensure the subject of each photo is visible and photos do not contain blur or camera shake.
2.02 SUBMITTAL PROCEDURES
A. Contractor shall submit complete sets of required materials for each RSN.
B. Provide submittals in accordance with the “No. of sets to be sent to:” column in Table 1 – List of
Submittals. Contact information is provided in section 2.04.
C. Transmittal Letters:
1. Contractor shall provide a transmittal letter in .PDF format with submittals
2. Include the following information in transmittal letters:
a. Contract number and title.
b. RSN for each attached submittal.
c. Primary point of contact.
d. Number of sets for each RSN.
e. Identify submittal as initial or resubmittal.
3. More than one RSN may be submitted under a transmittal letter, provided the point of contact is the same.
i. Submittals not approved:
1. Revise and resubmit for approval.
2. Show changes and revisions with revision date.
a. Resubmitted drawings shall include a revision block with the date of revision.
3. Describe reasons for significant changes in transmittal letter.
4. Resubmit returned submittals within 14 days after receiving the comments, unless otherwise specified.
5. Requirements for initial submittals apply to resubmittals.
6. Resubmittals shall include all items required for the submittal without reference to the original submittal.
7. The contractor shall not change designs without re-approval of the COR after drawings, documentation, and technical data have been approved by the COR.
2.03 REVIEW OF SUBMITTALS
A. Submit all submittals to the COR for review and acceptance.
B. Time Required:
1. Submittal review will be completed within 21 days for each submittal or resubmittal, unless otherwise specified.
2. Time required for review begins after the complete set of materials required for a particular submittal or resubmittal are received by the government.
C. Time in Excess of Specified:
1. The CO may extend the required delivery date for submittals to allow additional time for completing work affected by extended review times.
a. The time extension will be to the extent that extended review time caused a delay to the required contract completion date.
b. Time extension will not exceed time used in excess.
D. Return of Submittals:
1. Return of submittals will be by email or hard copy as applicable.
2. One set of submittals required for approval will be returned either approved, approved subject to identified changes, or not approved.
a. Submittals that are not approved shall be revised and resubmitted for approval.
b. No details of a submittal item may be changed after the submittal has been approved without approval from the CO and review of proposed changes.
c. Exception: Schedules may be accepted, partially accepted, or not accepted.
3. Responses to RFIs shall be provided to contractor within 14 days of receiving the request.
4. Responses to general correspondence with the COR shall be provided within 14 days.
2.04 TRANSMITTAL ADDRESSES
A. Provide transmittal letters and RSNs to the following. See Table 1 - List of Submittals, column: No.
of Sets to be Sent to, to determine which address(s) to send the given quantity of transmittal and submittal items to.
B. Information regarding transmittal addresses, including the Contracting Officer and Contracting
Officer Representative, will be provided at the time of award
2.05 SHIPPING AND DELIVERY
A. Deliver shipments to the following address:
• Hoover Dam Central Warehouse
• NV State Route 172
• Boulder City, NV 89004
• ATTN: [name of the COR]
B. Receiving hours are 0730-1530 PST, Monday through Friday, excluding Federal holidays.
C. Notify the COR of inbound shipments at least two business days prior to anticipated delivery date.
D. Ship only via freight carriers which possess fleets of sufficient size to ensure the shipment is delayed not more than two days due to breakdown, vehicle or driver unavailability, or any other circumstances, excluding inclement weather.
E. If the vehicle transporting material is involved in an accident and a reasonable person would consider it prudent to inspect the material for damage before use at Hoover Dam, the Contractor shall arrange for the material to be transported to its shop and inspect the material completely before reshipment to Hoover Dam.
2.06 RECEIVING
A. The Government will accept shipments on behalf of the Contractor at the Hoover Dam Central
Warehouse during normal business hours.
1. The Government will not inspect shipments which are accepted on behalf of the Contractor.
The Contractor is responsible for inspection of shipments for any damage incurred in transit.
2. The Government will not transport shipments. The Contractor is responsible for the transportation of shipments from the Hoover Dam Central Warehouse to the worksite.
2.07 SHOP ACCESS
A. If specified in the SOW, the Contractor shall permit the Government access to any facilities where the Contractor is executing work under this contract or is storing material which will be used under this contract at any time when work under this contract is being executed.
2.08 SUBMITTAL ITEMS
A. RSN A-1, Payment Information
1. Information for payment of invoices by Electronic Funds Transfer.
B. RSN A-2, Project Schedules
1. The total project schedule, using Critical Path Method (CPM) techniques and a logic diagram and bar chart showing the major items of work contained in the proposal, their durations, and anticipated start and finish dates. The schedule should show float, material, manpower (shifts and days per week), equipment resources, major submittals required, and the logical relations or interface between activities.
C. RSN 001, Extended Warranty
1. Extended Warranty as required in Section 6.01.
D. RSN 002, Approval Drawings and Design Data
1. Hill chart for A2 and N7.
2. Detailed drawings of the runner including fabrication details and blade shape, runner cone, coupling bolts, seal rings, and material limits and locations for balancing.
3. Provide the following design data as part of this submittal item.
a. Weight of runner, cone and seal rings.
b. Materials list for runner crown, blades, band, and cone including the chemical composition of all runner components.
c. Materials list and assembly details for turbine runner to turbine shaft coupling bolts.
d. Design clearances between rotating seal surfaces on turbine runner and stationary seal rings. Stepped labyrinth seals shall not be used for the turbine runner or stationary seal design. Grooved stationary seal ring design will be allowed, but any modifications to the original design will require review from the COR.
e. Wear ring interference calculations.
f. Maximum downward thrust – both with design seal ring clearances and with 2x design seal ring clearances.
g. Maximum upthrust – both with design seal ring clearances and with 2x design seal ring clearances.
h. Maximum sustained runaway speed at 565 feet of head, various gate positions.
i. Provide transient analysis results, including wicket gate timing as part of this submittal.
i. Moment of inertia (WR2) of the runner both watered and un-watered.
j. Design calculations and complete information showing the maximum unit stresses used in the design.
k. Operating range for the unit.
4. Inspection plan detailing nondestructive test methods contractor will use for locating casting defects and weld defects of the runner components and fabricated runner and methods to measure Dimensional check of the runner.
a. Inspection requirements are described in section 3.05.
5. Heat treatment procedure.
6. Runner balancing procedure.
7. Fatigue analysis.
8. Efficiency and power characteristics.
9. Cavitation repair procedures including recommended weld rod materials, preparation, weld procedures, post-weld heat treatment, and template locating drawings.
10. Drawings showing the dimensions and positioning of runner blade inlet edge templates and runner blade discharge edge templates.
11. Drawings showing the design and location of the roughening air admission system and all related components.
E. RSN 003, Runner Fabrication Logistics
1. Casting, plate, forging, and fabrication locations.
2. Transportation information.
F. RSN 004, Runner Material Certification
1. Provide certifications for all materials to be used for the turbine runner and associated equipment.
a. Requirements for material certifications are defined in section 4.01.E.
G. RSN 005, Casting Inspection Reports
1. Reports of NDT of all castings to be used for fabricating the turbine runner and associated equipment prior to assembly.
a. Government approval is required before contractor may begin repair welding.
b. Refer to sections 3.05 and 4.02.C for more details.
H. RSN 006, Initial Dimensional check Inspection Reports
1. Report of the turbine runner Dimensional check after tack welding and trial assembly.
a. Government approval is required before contractor may adjust/relocate components.
b. Refer to sections 3.05 and 4.05.D for more details.
I. RSN 007, Welding Inspection Reports
1. Reports of NDE/NDT of welds made to assembly the turbine runner crown, band, and blades. Inspections shall also include regions affected by the heat during the weld process.
a. Government approval is required before contractor makes repairs to the welds or components with heat affected surfaces.
b. Refer to sections 3.05 and 4.06.G for more details.
J. RSN 008, Balancing Report
1. Final report of runner balancing once assembly is complete.
a. Include in the report a description of changes made and drawings that include the location of balance modifications.
b. Include results from final balance test and the balance quality achieved for government review.
c. Refer to section 4.08 for more details.
K. RSN 009, Final NDT and Dimensional Check Report
1. Final NDT report after assembly and final machining.
a. Refer to sections 3.05 and 4.05.E for final NDT requirements.
2. Final dimensional check inspection report after assembly and final machining.
a. Refer to sections 3.05 and 4.05.D for final dimensional check requirements.
L. RSN 010, Runner Final Data
1. As-built drawings with final runner dimensions and machined weight.
2. Templates and drawings for runner repair as per section 4.03.
a. Submit drawings showing positioning of the templates for reference.
3. As-built drawings with final seal ring dimensions and upstream/downstream and river/canyon clearances.
4. All drawings provided within this submittal shall become property of the government.
M. RSN 011, Seal Ring Material Certification
1. Provide certifications of seal ring materials for government review.
a. Refer to section 5.03.A for material requirements.
b. Provide heat treatment procedure, furnace type, and controls for seal rings as part of this submittal.
c. Any material found unsatisfactory will require replacement. Refer to section 4.01.G if specified materials are unavailable.
N. RSN 012, Runner to Shaft Coupling Stud and Nut Design Data
1. Provide design drawings or product information for coupling studs and nuts that meet the requirements listed in sections 5.01 and 4.01.B.
O. RSN 013, Associated Equipment As-Built Drawings
1. Provide as-built drawings of the following components:
a. Stationary seal rings machining with final dimensions.
b. Roughing air admission system components:
i. Air admission piping for the turbine pit, headcover, and turbine runner.
ii. Turbine shaft cap.
iii. Air admission support cone.
2. All drawings provided within this submittal shall become property of the government.
P. RSN A-3, Release of Claims Release of Claims (DI-137) against the United States
1. Release of Claims (DI-137) against the United States.
2.09 LIST OF SUBMITTALS
A. Table 1-List of Submittals
RSN Item Primary
POC
Submittals required
No. of sets to be sent to: Due Date or delivery time
CO COR
A-1 Payment Information CO Information for payment of invoices by Electronic Funds
Transfer. Ensure payment data in System for Award
Management database is current, accurate, and complete.
1 1 14 days prior to first payment.
A-2 Project Schedule CO Project baseline schedule updated once per month with actual progress. The initial schedule must be accepted by the Government prior to the start of work.
1 1 Baseline schedule submittal within 30 days of contract award
A-3 Performance and
Payment Bonds
CO Within 14 days of award 2 0 Prior to issue of Notice to
Proceed
A-4 Release of Claims CO Release of Claims (DI-137)
Against the United States
1 0 After completion of the work and prior to final payment
001 Extended Warranty CO Refer to requirements in 6.01. 2 2 Within 30 days of contract award
002 Approval Drawings and Design Data
COR Provide all relevant design data and information as per
Section 3
2 2 Within 270 days of contract award
003 Runner Fabrication
Logistics
COR Provide logistics for runner component fabrication as described in section 4.01.D.
1 2 Within 60 days prior to casting or fabrication of components
004 Runner Material
Certification
COR Provide material certifications for all materials used for the turbine runner and associated equipment. Refer to section
4.01.E for more details.
1 2 Within 7 days of receipt of materials
005 Casting Inspection
Reports
COR Provide an inspection report for all cast materials. Refer to sections 3.05, and 4.02.C for more details.
1 2 Within 14 days of receipt of cast materials
006 Initial Dimensional
Check Inspection
Reports
COR Provide a report on the turbine runner dimensional check in trial assembly. Refer to sections 3.05 and 4.05.D for more details.
1 2 Within 5 days of tack welding and trial assembly of the turbine runner
007 Welding Inspection
Reports
COR Provide a report on all inspections performed on assembly welds. Refer to sections 3.05 and 4.06.G for more details.
1 2 Within 14 days of completing welding and assembly of the turbine runner.
008 Balancing Report COR Provide a report on the final balance and modifications
1 2 Within 7 days of completing balancing.
made to achieve balance.
Refer to section 4.08 for more details.
009 Final NDT and
Dimensional Check
Report
COR Provide an inspection report of the final inspections performed on the runner prior to delivery. Refer to sections
3.05, 4.05.D, and 4.05.E for more details.
2 2 Within 30 days of completing assembly, machining, and balancing.
010 Runner Final Data COR Provide drawings and design data as per section 3, including all machining and adjustments made after assembly, templates for runner repair as described in section 4.03, and details on balancing as per section 4.08.
2 2 7 days prior to planned shipment of runner
011 Seal Ring Material
Certification
COR Provide certification for the materials listed in section 5.03 in addition to seal ring heat treatment logistics.
1 2 Within 7 days of receipt of materials
012 Coupling Nut Design
Data
COR Provide information on coupling nut design selection.
Requirements are described in sections 5.01 and 4.01.B
1 2 Within 14 days prior to purchase/fabrication of coupling nuts
013 Associated
Equipment As-Built
Drawings
COR Provide as-built drawings of the stationary seal rings machining with final dimensions, roughing air admission piping (both in the turbine pit/headcover and turbine runner), shaft cap, and support cone.
1 1 Within 28 days of completing final stationary seal ring machining and installation of air admission system.
A-3 Release of Claims
Against the
Government
CO Release of Claims (DI-137) against the United States
1 0 After completion of the work and prior to final payment.
SECTION 3 - RUNNER DESIGN AND ANALYSIS
3.01 REFERENCE STANDARDS
A. Unless otherwise specified, all materials that will become a part of the completed work shall be new and will conform to the following standards and be of standard commercial quality.
B. American Society of Mechanical Engineers (ASME)
1. ASME B46.1-2019 Surface Texture (Surface Roughness, Waviness, and Lay)
2. ASME BPVC-2025 Boiler and Pressure Vessel Code
3. ASME PTC 18-20 Hydraulic Turbines and Pump-Turbine Performance Test Codes
4. ASME Y14.1-2020 Drawing Sheet Size and Format
5. ASME Y14.5-2018 (R2024) Geometric Dimension and Tolerancing
C. American Society for Testing and Materials International (ASTM International)
1. ASTM A193/A193M-25 Standard Specification for Alloy-Steel and Stainless-Steel Bolting for High Temperature or High-Pressure Service and Other Special Purpose Applications
2. ASTM A240/A240M-25a Standard Specification for Chromium and Chromium-Nickel
Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and for General Applications
3. ASTM A743/A743M-21 Standard Specification for Castings, Iron-Chromium, Iron-
Chromium-Nickel, Corrosion Resistant, for General Application
4. ASTM A751 Test Methods and Practices for Chemical Analysis of Steel Products
5. ASTM A802-19 Standard Practice for Steel Castings, Surface Acceptance Standards, Visual Examination
6. ASTM A903/A903M-99(2024) Standard Specification for Steel Castings, Surface
Acceptance Standards, Magnetic Particle and Liquid Penetrant Inspection
7. ASTM A967/A967M-25 Standard Specification for Chemical Passivation Treatments for
Stainless Steel Parts
8. ASTM E164-24 Standard Practice for Contact Ultrasonic Testing of Weldments
9. ASTM E165/E165M-18 Standard Practice for Liquid Penetrant Testing for General
Industry
10. ASTM E1742/E1742M-23 Standard Practice for Radiographic Examination
11. ASTM E186-20 Standard Reference Radiographs for Heavy-Walled (2 to 4 1/2 in. (50.8 to
114 mm)) Steel Castings
12. ASTM E280-21 Standard Reference Radiographs for Heavy-Walled (4 1/2 to 12 in. (114 to
305 mm)) Steel Castings
13. ASTM E390-20 Standard Reference Radiographs for Steel Fusion Welds
14. ASTM E446-20 Standard Reference Radiographs for Steel Castings Up to 2 in. (50.8 mm) in Thickness
15. ASTM E709-21 Standard Guide for Magnetic Particle Testing
D. International Electrotechnical Commission (IEC)
1. IEC 60193 (2019) Hydraulic turbines, storage pumps, and pump-turbines – Model acceptance tests
E. American Welding Society (AWS)
1. AWS D1.1/D1.1M:2020 Structural Welding Code - Steel
2. AWS D1.6/D1.6M-2017 Structural Welding Code - Stainless Steel
F. Cahier Des Charge (CCH)
1. CCH 70-4 (2014) Inspection of Steel Castings of Hydraulic Machines
3.02 CURRENT UNIT RATING AND DATA
A. General
1. The original turbines are vertical-shaft Francis-type and were installed between 1935 and
1941 by the Baldwin-Lima-Hamilton, Co.
2. The replacement runners for A2 and N7 were supplied by Voest-Alpine Int Corp under specifications DS-7403, awarded January 1980 and installed in 1989 (A2) and 1982 (N7).
3. Existing turbine output for units A2 and N7 with current wicket gates and 9.7” GVO is
157,300 hp at 490 feet, full gate.
4. The Nevada unit N7 rotates at 180 revs/min, clockwise, viewed from above.
5. The Arizona unit A2 rotates at 180 revs/min, counterclockwise, viewed from above.
6. The Hoover generators installed at Units N7 and A2 are currently rated at 133.3 MVA each.
B. Rough Zone
1. Rough zones currently occur at gate openings 25% to 80%.
C. Air Depression System
1. Units A2 and N7 use a system to admit compressed air to the draft tube to depress the water level in the turbine to reduce electrical load during condenser operation.
D. The effective head range on the turbine for power production may vary between 350 and 575 feet.
The expected range is 396 feet to 511 feet net head. The controlling water-surface elevations are as follows:
E. Table 2- Turbine operating conditions
Location Elevation (feet)
Tailwater Minimum 630
Normal Range 639 – 656
Headwater Minimum for generation 1000
Maximum for generation 1229
Casing Centerline 637
3.03 UNIT STRESSES AND FATIGUE ANALYSIS
A. Ensure that the turbine runner and associated components provided under this solicitation adhere to the same safety factors used for units A1, N5, N6, and N8.
B. Provide the COR, upon request, a copy of each mill or shop order for material purchased by the
Contractor for use in the fabrication of turbine components.
1. The copies of the orders shall state the place at which the material is to be manufactured.
2. All such mill or shop orders shall quote the requirements of the special conditions and drawings for articles, materials, and supplies to be furnished.
C. Perform fatigue analysis on units A2 and N7 using the following conditions:
1. The units rotate at 180 rpm, clockwise, viewed from above.
2. Unit runaway speed: 340 rpm.
3. Unit Cycles:
a. Number of starts/stops per year: 400.
b. Runaway: 1 time per year.
c. Load rejection: 1 time per year.
d. Unit is under Automatic Generation Control and experiences continuous load adjustments when online.
e. Load changes; 40 load changes per day from SNL to 100% wicket gate opening is typical.
f. The unit operates in condense for a maximum of 500 hours a month, 67% of the year.
4. Ensure that fatigue analysis shows the turbine runners are capable of a lifespan of 50 years or more.
D. As per RSN 002 perform CFD/FEA as needed to provide the following guaranteed points:
1. The guaranteed points below will be used for performance testing after runners are installed.
a. Peak efficiency at 400 feet net head.
b. Full gate efficiency at 400 feet net head.
c. Full gate power at net head of 400 feet net head.
2. The characteristics from this section will be considered warrantied characteristics and covered under FAR clause WBR 1452.246-81, Failure to Meet Performance Warranties.
E. In the hill charts for A2 and N7 provided as per RSN 002 detail cavitation-free zones and rough zone magnitudes at various heads.
3.04 DESIGN AND PERFORMANCE REQUIREMENTS
A. Manufacture and deliver two turbine runners using the design provided to the Hoover Dam for units
A1, N5, N6, and N8.
B. The first runner, for Unit A2, shall use the counterclockwise design from A1. The second runner, for Unit N7, shall use the clockwise design from N5, N6, and N8.
3.05 NON-DESTRUCTIVE TESTING AND INSPECTIONS
A. Inspection Plan:
1. As per RSN 002, provide a plan for inspections including the following:
a. Examination type to be used for each given situation.
b. Equipment to be used for examinations and inspections that meets standards for each method being used. For dimensional checks, describe measurement equipment and accuracy of instrumentation to be used.
c. Details and qualifications of inspection personnel for each examination type to be used.
d. Procedure of inspections and reference standard to be used by the contractor
e. Procedure and details of weld repairs.
i. Include details such as the filler material to be used for certain components and the pre-post heat procedure within the plan.
f. Procedure of component locational adjustment in the case of a failed dimensional check.
B. Personnel Qualifications:
1. Qualified in accordance with the relevant reference standard for the examination type.
2. The minimum qualification level of all NDT personnel shall be Level II for the specific examination type being used.
a. Personnel must have at least 5 years of experience as a Level II.
b. For UT and RT, inspection reports shall be reviewed and signed by someone of
Qualification Level III for UT and/or RT respectively.
C. Equipment Requirements:
1. Provide the necessary equipment and tools to perform adequate NDT on the runner and associated equipment.
a. Equipment must meet standards as applicable for each inspection method.
2. Provide templates and other means, such as 5-axis measuring machinery or templates, to compare dimensions of the runner to drawings to check dimensions.
D. VT, MT, and PT Requirements:
1. VT in accordance with CCH 70-4 and ASTM A802.
a. VT on cast components in accordance with ASTM A802.
b. Unless otherwise stated, VT alone will not be sufficient for an inspection and must be performed in addition to another examination method.
2. MT in accordance with ASTM E709.
a. MT on cast components in accordance with both ASTM E709 and A903.
3. PT performed in accordance with ASTM E165.
a. PT on cast components in accordance with both ASTM E165 and A903.
E. RT Requirements:
1. Perform RT in accordance with Section V of the ASME BPVC and the following ASTM standards for cast components:
a. ASTM E446 for all castings up to 2 inches in thickness.
b. ASTM E186 for all castings 2 to 4.5 inches in thickness.
c. ASTM E280 for all castings 4.5 to 12 inches in thickness.
i. Components that are 4.5 inches in thickness shall be inspected in accordance with ASTM E280.
2. RT on welds performed in accordance with ASTM E390.
3. For all other components, RT performed in accordance with ASTM E1742.
4. Contractor may use any radiation source listed in the relevant ASTM standard, so long as they specify in the inspection plan what source will be used.
F. UT Requirements:
1. UT on welds shall be in accordance with ASTM E164.
2. UT on other components in accordance with ASTM A609.
3. Note that UT may be used on cast components to determine if a defect has been totally removed during excavation but cannot be used as the primary defect inspection method.
G. Dimensional Checks:
1. Provide dimensional measurements of the turbine runner and compare them to the dimensions in the design drawings.
H. Inspection Reporting:
1. Report all defects with clear defect mapping that indicates the location, size, and depth of all defects.
2. Provide photos of defects and include images in inspection reports.
a. Photos to the requirements described within section 2.02.F.
b. Photos to include a scale for relative size of defect and location of defect.
3. For dimensional checks, contractor shall provide annotated drawings showing the as found measurements taken during the inspection and a copy of the design drawings with dimensions and tolerances that were compared.
a. If adjustments were required to pass the dimensional check, include in the report indications of which components needed to be adjusted and dimensions before and after said adjustments.
I. Acceptance Criteria:
1. Refer to Table 3A for runner blades, band, crown, band, and welds acceptance criteria.
2. Refer to Table 3B for all other components (bolts, seal rings, etc.) acceptance criteria.
a. For Table 3A and 3B, critical locations shall refer to the following areas:
i. Welds joining the runner blade to the curb/band and crown, including the area within 2 inches beyond the weld of all surfaces.
ii. Leading and trailing edges of the runner blades.
iii. Any location that experiences more than 1/3 of the material yield strength during regular operation as determined by FEA.
3. Dimensional check Criteria:
a. To pass the dimensional check, all measurements must be accurate to the contractor drawings with all the dimensions within design tolerances.
4. Base acceptance criteria on whatever measurement/value is the smallest.
J. Table 3A – Acceptance Criteria for Runner Blades, Band, Crown, Band, And Welds.
Method Critical Locations All Other Locations
VT
As per ASTM A802, cast surface discontinuities shall have an Acceptance Level of A1, B1, C2, D1, E3, F1, G1, H1, and J1. For non-cast components any cracks or cavities exceeding 10 percent of the material thickness or 0.5 inches will not be accepted.
As per ASTM A802, discontinuities of cast surfaces shall have an Acceptance Level of A2, B2, C1, D1, E3, F1, G2, H3, and J2. For non-cast components any cracks or cavities exceeding 15 percent of the material thickness or 0.75 inches will not be accepted.
PT
As per ASTM A903, cast components shall be inspected to Acceptance Level 1. For non-cast components any cracks or cavities exceeding 10 percent of the material thickness or 0.5 inches will not be accepted.
As per ASTM A903, cast components shall be inspected to Acceptance Level 2. For non-cast components any cracks or cavities exceeding 15 percent of the material thickness or 0.75 inches will not be accepted.
MT
As per ASTM A903, cast components shall be inspected to Acceptance Level 1. For non-cast components any cracks or cavities exceeding 10 percent of the material thickness or 0.5 inches will not be accepted.
As per ASTM A903, cast components shall be inspected to Acceptance Level 2. For non-cast components any cracks or cavities exceeding 15 percent of the material thickness or 0.75 inches will not be accepted.
UT
Cavities or voids shall be held to an acceptance of
CCH70-4 quality level 1 for their given thickness. .
Cavities or voids shall be held to an acceptance of
CCH70-4 quality level 2 for their given thickness.
RT
Using the appropriate ASTM standard, cast surfaces with any discontinuity above severity level 1 will not be accepted.
Using the appropriate ASTM standard, cast surfaces with any discontinuity above severity level 2 will not be accepted.
K. Table 3B – Acceptance Criteria for All Other Components
Method Critical Locations All Other Locations
VT
As per ASTM A802, discontinuities of cast surfaces shall have an Acceptance Level of A2, B2, C1, D1, E3, F1, G2, H3, and J2. For non-cast components any cracks or cavities exceeding 15 percent of the material thickness or 0.75 inches will not be accepted.
As per ASTM A802, discontinuities of cast surfaces shall have an Acceptance Level of A3, B4, C3, D2, E3, F1, G3, H4, and J3. For non-cast components, any cracks or cavities exceeding 20 percent of the material thickness or 1 inch will not be accepted.
PT
As per ASTM A903, cast surfaces shall be inspected to Acceptance Level 2. For non-cast components any cracks or cavities exceeding 15 percent of the material thickness or 0.75 inches will not be accepted.
As per ASTM A903, cast surfaces shall be inspected to Acceptance Level 3. For non-cast components, any cracks or cavities exceeding 20 percent of the material thickness or 1 inch will not be accepted.
MT
As per ASTM A903, cast surfaces shall be inspected to Acceptance Level 2. For non-cast components any cracks or cavities exceeding 15 percent of the material thickness or 0.75 inches will not be accepted.
As per ASTM A903, cast surfaces shall be inspected to Acceptance Level 3. For non-cast components, any cracks or cavities exceeding 20 percent of the material thickness or 1 inch will not be accepted.
UT
Cavities or voids shall be held to an acceptance of
CCH70-4 quality level 1 for their given thickness. .
Cavities or voids shall be held to an acceptance of
CCH70-4 quality level 2 for their given thickness.
RT
Using the appropriate ASTM standard, cast surfaces with any discontinuity above severity level 2 will not be accepted.
Using the appropriate ASTM standard, cast surfaces with any discontinuity above severity level 3 will not be accepted.
L. Government Witness Inspections
1. Conduct final NDT and dimensional check inspection of the runner with the COR present at a location that is approved for travel by the Department of State (www.travel.state.gov) without additional protective services or safety requirements.
a. If the runner fabrication and inspection location does not meet these requirements, relocate the runner to a machine within the United States, for final inspection.
b. Perform both the final NDT and dimensional check inspections within the same time period to be witnessed and examined by the Government during one visit. A report of inspections results as part of RSN 009 is still required.
2. Provide 30-days notice for domestic witness inspections and 60-days notice for international witness inspections.
3.06 PERFORMANCE TESTING
A. Performance testing will be performed on both units. The government will be responsible for data collection and evaluation. The contractor shall provide an engineer to witness testing.
1. Performance testing must be performed no later than 2 years of the runner being put into service.
B. Per ASME PTC 18. Testing to be conducted within two years of when the units are placed into service.
C. Performance will be evaluated using the final hill chart from the most recent turbine runner the new units are based upon.
1. To pass performance testing each tested unit must meet the efficiency as defined within the hill chart in accordance with ASME PTC 18.
2. Test uncertainty of +/- 0.75 percent.
3. Test head within +/-4 percent of a net head of 400 feet.
D. If the tested unit(s) do not produce the efficiency as guaranteed the contract price will be adjusted in accordance with the clause at WBR 1452.246-81, Failure to Meet Performance Warranties.
SECTION 4 - RUNNER MANUFACTURING
Turbine Runner (ref. Dwg. No. 42335, 42343, 42344, 42345, 42390, 42393)
4.01 MATERIAL REQUIREMENTS
A. Turbine runner components materials:
1. Runner: ASTM A743 grade CF-3 cast components including supplemental requirements S3 through S7 and S12.
2. Nose cone: ASTM A240 UNS S30403/304L stainless steel plate.
3. Integral Seal Rings: Same material as used for the turbine runner crown and band.
B. Unless otherwise specified, materials used in the manufacturing of the equipment shall conform to applicable specifications of ASTM, SAE, or ANSI.
C. Submit to the COR, per RSN 003, fabrication logistics including the following:
1. Casting, plate, forging, and fabrication locations.
2. Transportation information.
D. Submit to the COR, per RSN 004, material certifications for all materials including the following:
1. Chemical composition of materials determined by ladle analysis.
2. Mill Test Report detailing the physical properties of the material:
a. Ultimate Tensile Strength in KSI.
b. 0.2% Yield in KSI.
c. Percent elongation in 2 inches.
d. Brinell hardness.
e. Records of method used to determine physical properties.
3. Heat treatment records.
E. Show the chemical composition of components in their respective drawings.
F. Procure the specified materials. If the specified materials are unavailable, substitute materials shall only be permitted with written approval from the Government.
1. Any substitution shall be equal to or better than the material specified. The contractor shall prove that the proposed substitute material is equal to or better than the material specified.
2. Substitute materials will be reviewed by the COR and CO prior to approval, and the CO may accept or reject any proposed material substitution at their discretion.
4.02 CASTING
A. Furnish to the COR certificates showing the results of the ladle analysis and material properties as per ASTM A751. See RSN 004 in Table 1 – List of Submittals.
1. The COR will compare the material composition results from the ladle analysis to the material standard for ASTM A743 Grade CF-3. If any element in the material composition is outside of acceptable range for A743 Grade CF-3 the material will be rejected.
B. Heat-treating procedure as recommended by the contractor in accordance with ASTM A743 and approved by the COR. See RSN 002 in Table 1 – List of Submittals.
C. Perform NDT on all cast components prior to assembly in accordance with section 3.05.
1. Any defect or discontinuity found that does not meet the acceptance criteria defined in section 3.05.I and Tables 3A and 3B must be repaired by the contractor.
a. If any casting has more than 5 defects that fail acceptance the entire casting shall be rejected, and contractor must furnish a new casting.
i. The new casting shall be subject to the same inspection criteria.
b. Contractor must first notify the COR and await approval to begin any repairs.
i. Include in the correspondence the extent of defect excavation prior to repair welding.
c. If excavation is required to properly repair a defect, contractor must use PT or MT in accordance with section 3.05.E to ensure the defect is entirely removed.
d. Ensure repairs do not reduce the base metal below the design thickness.
e. After repairing the defect contractor shall refinish repaired regions to meet the requirements in section 4.07.
f. After repairs are complete, contractor must repeat NDT on component to ensure all defects have been repaired and no new defects are present.
2. As per RSN 005, contractor shall provide a report of results from the NDT in accordance with section 3.05.H.
3. All inspections and repairs shall be done at the expense of the contractor.
4.03 RUNNER BLADE TEMPLATES
A. As per RSN 010, fabricate and furnish four templates to fit the profile of the runner blade, spaced evenly across the discharge edge, and three templates to fit the profile of the runner blade, spaced evenly across the inlet edge, to aid in runner repair per IEC 60193.
1. Use templates to validate final hydraulic profile.
2. Design all templates for use in the field.
B. Laser-cut to match profile in designated locations, considering allowable tolerances.
C. Stamp to identify relative locations to leading and trailing edges, pressure or suction side and template elevation.
D. Deliver templates along with the turbine runner, coupling nuts, or seal rings to the government.
E. Contractor shall provide a rigid storage case with lockable latches and foam interior with cut-outs to secure templates.
1. Clearly label case with project name, unit, contents, and weight.
4.04 INTEGRAL SEAL RINGS
A. Provide turbine runner with integral upper and lower rotating seal rings as per the design used for
A1, N5, N6, and N8.
1. Machine and finish the turbine runner’s integrated rotating seal rings.
a. Refer to section 4.07.A.3 for requirements on seal ring surface finish.
2. Ensure the seal rings have sufficient base material to allow for seal rehabilitation in the future.
3. Measure the rotating seal diameters of the turbine runner which interfaces with the stationary surfaces.
B. Determine target diameters for each surface and submit the targets to the COR for review before any material is removed.
4.05 ASSEMBLY
A. Assemble runner of major components welded together.
1. The band, crown, and blades are considered major components.
2. Details on welding requirements are provided in Section 4.06.
B. Cast the crown, band, and buckets or fabricate using stainless steel plate.
C. Perform shaping of the buckets prior to welding between the crown and band by machining using a numerically controlled 5-axis milling machine or by stamping plate material.
D. Perform dimensional check inspections on the turbine runner in accordance with Section 3.05.H.
1. Any dimensions found during a dimensional check inspection that does not meet the acceptance criteria defined in Section 3.05.I.3. must be adjusted by the contractor.
2. Contractor must first notify the COR and await approval to begin any adjustments.
a. After making necessary adjustments contractor shall reperform dimensional check inspections to ensure dimensions are in tolerance.
b. Regions where tack welds had to be removed and reapplied for adjustments shall have NDT performed to ensure no defects formed during the process.
i. Refer to Section 4.06.G for weld inspection guidelines.
3. Dimensional check inspections shall be performed at the following intervals:
a. Initial dimensional check: Perform inspection with all components positioned in trial assembly and tack welded together.
b. Final dimensional check: Perform inspection after assembly, machining, and balancing of the runner is complete and RSN 001 through 008 are submitted and approved.
i. Final dimensional check inspection shall be performed with a government witness. Refer to Section 3.05.J for more details.
4. As per RSN 006, provide a report of results from the initial dimensional check inspection in accordance with Section 3.05.H.
5. As per RSN 009, provide a report of results from the final dimensional check inspection in accordance with Section 3.05.H.
6. All inspections and adjustments shall be made at the expense of the contractor.
E. Perform final NDT in accordance with Section 3.05 on the turbine runner after assembly, machining, and balancing of the runner is complete and RSN 001 through 008 are submitted and approved.
1. This inspection shall be conducted with a government witness. Refer to Section 3.05.J for more details.
2. Any defect or discontinuity found that does not meet the acceptance criteria defined in
Section 3.05.I and Tables 3A and 3B must be repaired by the contractor.
a. Contractor must first notify the COR and await approval to begin any repairs.
i. Include in the correspondence the extent of defect excavation prior to repair welding.
b. If excavation is required to properly repair a defect, contractor must use PT or MT in accordance with Section 3.05.F to ensure the defect is entirely removed.
c. Ensure repairs do not reduce the base metal below the design thickness.
d. After repairing the defect contractor shall refinish repaired regions to meet the requirements in Section 4.07.
e. After repairs are complete, contractor…