Sol_140R3026R0016_Amd_0001.pdf

PDF 204 KB Posted

Attached to
Hydraulic Turbine Runner for Units A2 and N7 for H
Solicitation number
140R3026R0016
Issued by

About this file

This is Amendment 0001 to a federal solicitation issued by the Bureau of Reclamation, Lower Colorado Region for the purchase of a turbine runner for Unit A2 and N7. The solicitation number is 140R3026R0016, dated June 10, 2026, with an effective amendment date of June 25, 2026.

The amendment updates the solicitation to revise the Foreword regarding the date for receipt of questions, correct the Table of Contents and Section I numbering, add Clause 1452.246-81 (Failure to Meet Performance Warranties) to Section I Paragraph I.17, revise Section L Paragraph L.9 to correct the Award Form and update Subcontracting Small Business Goals for Small Business and ISBEE, revise multiple items throughout the Statement of Work, and incorporate new drawings. All revisions are identified with vertical lines in the left margin. The proposal receipt date remains August 10, 2026, at 5:00 p.m. local time, with submission location unchanged. The period of performance is December 15, 2026, through May 18, 2029. This is a construction contract. Offerors must acknowledge receipt of this amendment by one of three methods: completing items 8 and 15 and returning the form, acknowledging receipt on each copy of the offer submitted, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers. Failure to acknowledge receipt at the designated location prior to the specified hour and date may result in offer rejection.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Luis Gallardo

See continuation page

Bureau of Reclamation Lower Colorado Region Regional Office 500 Fir Street Boulder City NV 89005

R30

140R3026R0016

06/25/2026

06/10/2026

1 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140R3026R0016/0001

Project Title: Purchase of Turbine Runner for

Unit A2 and N7

Purpose of Amendment: This amendment is issued to update the solicitation, transmit an updated

Statement of Work, and update and incorporate drawings.

Description of changes:

1. Solicitation - Foreword is revised to change the date for receipt of questions.

2. Solicitation - The Table of Contents is revised, and the numbering in Section I has been corrected.

2. Section I - Paragraph I.17 is added to incorporate Clause 1452.246-81 - Failure to

Meet Performance Warranties

3. Section L - Paragraph L.9 is revised to correct the Award Form and revise the

Subcontracting Small Business Goals for Small

Business and ISBEE

4. Revise Statement of Work - Multiple items have been revised throughout the sections.

5. Incorporate new drawings

All revisions are identified with a vertical line in the left margin.

Receipt of Proposal: The date for receipt of proposal remains August 10, 2026, at 5:00 p.m., local time; and the location for submission of proposal remains unchanged.

Acknowledgement: Refer to Block 11 above regarding how to acknowledge this amendment.

The acknowledgement must be received at the place designated for receipt of offers

CONSTRUCTION CONTRACT (see block 8 of the

"Solicitation, Offer, and Award," Standard Form

1442).

Period of Performance: 12/15/2026 to

05/18/2029

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .