This document contains the salient characteristics for a Towable 125kW 3-Phase 480V Diesel Generator required as part of a federal contract opportunity. The generator must have a prime power rating of 110 ekW, operate at 60 Hz, and provide 3-phase 480/277V and 1-phase 240/120V power. Key requirements include a 4-stroke turbocharged diesel engine, heavy-duty air cleaner, 50C ambient cooling capability, dual-wall 150-gallon fuel tank, Cat EMCP 4.2B control panel, 12V-100A charging alternator, and a towable trailer no larger than 177" x 78" x 86". Two complete service manuals and a 1-year warranty are also required. The related federal contract opportunity is Solicitation Number 140R3024Q0050 for a Towable Diesel Generator, issued by the Department of the Interior Bureau of Reclamation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C05_SOW_-_Attach_001.pdf | ||
| C05_140R3024Q0050_RFQ.pdf | ||
| Sol_140R3024Q0050.pdf | ||
| C05_Combined_Synopsis.pdf | ||
| C05_Clauses___Provisions.pdf | ||
| C05__XQ125_Tier_4_Spec_Sheet_-_Attach_003.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Towable 125kw 3phase 480V Diesel Generator
Required Salient Characteristics
POWER
1) Power Rating:
2) Prime Power Rating:
3) Frequency:
4) Voltage:
1) 125 KW
2) 110 ekW
3) 60 Hz
4) 3-Phase 480/277 Volt, & 208/120 Volt
a. 1-Phase 240/120 Volt
Excitation 1) Self-Excited
ENGINE SYSTEM 1) 4-Stroke-Cycle Diesel
2) Turbocharged with Aftercooler
3) Water Cooled
ENGINE AIR INLET 1) Heavy-duty air cleaner with dust cup and service indicator.
2) Turbocharger and air-to-air after cooler.
COOLING SYSTEM 1) Provide 50°C ambient capability @ full rating
2) Vertically mounted radiator with engine mounted cooling fan
3) 50/50 Extended Life Coolant
4) Coolant low-level shutdown switch
5) Coolant recovery system
6) Coolant drain line with valve
7) Block Heater
FUEL SYSTEM 1) Diesel Fuel
2) Dual wall fuel tank 150-gal
3) Fuel tank capable of running generator for 24 hours @ 75%
4) 3 way directional valve capable of external supply
5) Engine mounted primary fuel filter with integral water separator
6) Engine-mounted secondary fuel filter
CONTROL SYSTEM 1) Cat EMCP 4.2B Control Panel
a. Electronic control panel provides power metering, protective relaying, engine, and generator parameter viewing, and expanded AC metering.
b. Graphical display (3.8 in.) denotes text alarm/ event descriptions, set points, engine and generator monitoring, and is visible in all lighting conditions • Simple, user-friendly interface and navigation.
c. Automatic set-point adjustment integrated with voltage selection
ALTERNATOR SYSTEM
1) Charging alternator; 12V-100A, heavy duty with integral regulator and belt guards.
2) 10-Watt Solar maintainer for batteries.
POWER DISTRIBUTION
1) Twist lock receptables (X3)
2) STD connection group camlock
ENCLOSURE
1) Steel enclosure with hinged, lockable doors.
TRAILER
1) Trailer hitch Pintle, or 2-5/16” ball
2) Trailer brakes hydraulic
3) Trailer dimensions (L x W x H) no greater than 177” x 78” x 86”
4) Trailer weight 7500 lbs
OPERATING MANUAL
1) Two complete sets of service manuals
2) Operating instructions
3) Technician manuals
4) Maintenance procedures
5) Illustrated parts breakdown
WARRANTY
1) Standard 1-year warranty
SHIPPING, STORAGE, &
PROTECTION
1) Comply with manufacturer's installation instructions for rigging, unloading, and transporting units. Unit shall be stored and handled per manufacturer’s instructions.
2) Protect units from physical damage.
3) Shipped to:
a) Parker Dam
Highway 95 Parker Dam Field Division
Parker Dam, CA 92267.
OTHER REQUIRMENTS
File details come from the government source that posted it. Updated .