Attachment_3_-_Section_7_and_Agnes_Wilson_Price_Schedule_0003.pdf

PDF 98 KB Posted

Attached to
YAO - Quarry & Mining at Agnes Wilson Quarry and S
Solicitation number
140R3022Q0064
Issued by

About this file

This document contains two price schedules for quarry and mining services at the Section 7 and Agnes Wilson Quarries. The schedules list estimated quantities and unit pricing for services including crushing material to gravel size, loading, hauling, and stockpiling gravel, and establishing or reestablishing access roads. The total estimated quantity of gravel to be delivered from Section 7 Quarry is 7,400 tons to two stockpile sites by December 2022. The total estimated quantity from Agnes Wilson Quarry is 7,500 tons to two stockpile sites between March 2023 and May 2023. The related federal contract opportunity is solicitation number 140R3022Q0064 from the Department of the Interior Bureau of Reclamation for quarry and mining services at the specified quarries. Pricing and delivery details are provided for required products and services.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140R3022Q0064/0003 – Attachment 3 Price Schedule

Section 7 and Agnes Wilson Quarries Price Schedule

Section 7 Quarry

Item

No.

Service

Estimated

Quantity

Unit

Unit Price

Total Cost

1-1

Standard move-in to designated quarry.

job

1-2

Crush 1- to 4-inch material to gravel size

7,400 tons

1-3 Load, weigh, haul, & stockpile gravel 111,000

66,600 ton-miles

1-4

Establishing or reestablishing access roads, and haul roads, that are heavily damaged that need excavation, material, blading, and watering. (Per miles)

3.2 mi.

1-5 Establishing or reestablishing roads inside the quarry that need routine blading and water. (Per miles)

2 mi.

1-6 Prepare, submit and implement Storm water Pollution Prevention Plan (SWPPP)

1 Ea.

1-7 Prepare and Submit NOI to EPA 1 Ea.

1-8 Provide qualified Biologist as project monitor for designated quarries

Del.

Order

Total of Cost

Contractor will deliver the gravel as indicated in CLNN’s 1-3 to stockpile site C253.8 and C248.7.

Performance shall be completed 90 Days After Award.

Stockpile site C253.8 will have a total of 3,700 ton delivered to it and Stockpile site C248.7 will have a total of 3,700 ton delivered to it.

Total tons of gravel delivered will be 7,400 tons out of the Section 7 Quarry.

140R3022Q0064/0003 – Attachment 3 Price Schedule

Agnes Wilson Quarry

Item

No.

Service

Estimated

Quantity

Unit

Unit Price

2-1

Standard move-in to designated quarry.

job

2-2 Crush 1- to 4-inch material to gravel size 7,500 tons

2-3

Load, weigh, haul, & stockpile gravel

157,500

70,500 ton-miles

2-4

Establishing or reestablishing access roads, and haul roads, that are heavily damaged that need excavation, material, blading, and watering. (Per miles)

1.5 mi.

2-5 Establishing or reestablishing roads inside the quarry that need routine blading and water. (Per miles)

1.5 mi.

2-6 Prepare, submit and implement Storm water Pollution Prevention Plan (SWPPP)

1 Ea.

2-7 Prepare and Submit NOI to EPA 1 Ea.

2-8 Provide qualified Biologist as project monitor for designated quarries

Del.

Order

Contractor will deliver the gravel as indicated in CLNN’s 2-3 to stockpile site A174.3 and A162.5.

Performance will commence on March 1, 2023 and be completed by May 30, 2023.

Stockpile site A174.3 will have a total of 2,640 3,000 ton delivered to it and Stockpile site A252.6 A162.5 will have a total of 3,960 4,500 ton delivered to it.

Total tons of gravel delivered will be 6,600 7,500 tons out of the Agnes Wilson Quarry.