Attachment_8_-_Task_Order_1_-_Price_Schedule_-_Revised_0002.pdf
PDF 160 KB Posted
- Attached to
- Civil Site Work - Mulitiple Award IDIQ Federal contract opportunity
- Solicitation number
- 140R3021R0029
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Supplemental_IDIQ_Clauses_-_TO_No__1_0003.pdf | ||
| Sol_140R3021R0029_Amd_0003.pdf | ||
| Sol_140R3021R0029_Amd_0002.pdf | ||
| 140R3021R0029_Sign_in_Sheet_0001.pdf | ||
| Attachment_9_-_Task_Order_1_-_Drawing_No__45-300-60126-RD-1_(revision1)_0001.pdf | ||
| Attachment_7_-_Task_Order_1_-_SOW_-_8-11-2021_0001.pdf | ||
| Sol_140R3021R0029_Amd_0001.pdf | ||
| _RFP_No__140R3021R0029_-_Civil_Site_Work_-_IDIQ_-_Revised_Pages_0001.pdf | ||
| Attachment_11_-_TO_1_-_Wage_Determination_No__NV20210024__Rev_7-02-21_0001.pdf | ||
| Questions_and_Answers_0001.pdf | ||
| Attachment_12_-_Staging_Area_Map_0001.pdf | ||
| _RFP_No__140R3021R0029_-_Civil_Site_Work_-_IDIQ.pdf | ||
| Sol_140R3021R0029.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 8 Task Order No. 1 – Revised Price Schedule - Lower Colorado Basin
Regional Campus, Reclamation Boulevard Parking, Boulder City, NV
This page left intentionally blank
Solicitation No. 140R3021R0029/0002 Project Name: Task Order No. 1 – Lower Colorado Basin Regional Campus, Reclamation Boulevard Parking, Boulder City, NV
B.1 PRICE SCHEDULE
a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
b) Offers are subject to the terms and conditions of this solicitation.
c) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 2.
d) Definitions:
(1) CLIN – Contract Line-Item Number
CLIN Section Supplies or Services Quantities Estimated Qty
Unit Unit Price Amount
Mobilization and Preparatory Work 1 LS $ $
011 Bonds 1 LS $ $
01 70 32 03 81 10 Demolition
012 Remove and dispose of curbing 350 LF $ $
Remove and dispose of valley gutter 20 SY $ $
31 11 00 31 23 02 31 23 39 31 23 70 Earthwork
Prepare subgrade and base for sidewalks, sidewalk ramps, and asphalt pavement (parking stalls) 1 LS $ $
Install two (2) 4-inch diameter schedule 40 PVC drainpipe under proposed sidewalk at north end of project.
Approximate length 20 ft each. 1 LS $ $
03 11 10 03 20 00 03 30 00 03 81 10 Concrete Work
016 Construct concrete sidewalks 399 SY $ $
Construct Architectural Barriers Act (ABA) compliant curb ramps 5 EA $ $
018 Construct type “A” curb 371 LF $ $ 019 Construct type “L” curb 93 LF $ $ 020 Construct valley gutter 81 SY $ $
Solicitation No. 140R3021R0029/0002 Project Name: Task Order No. 1 – Lower Colorado Basin Regional Campus, Reclamation Boulevard Parking, Boulder City, NV
021 Install concrete wheel stops 27 EA $ $
32 12 22 32 17 10 Asphalt Pavement
022 Construct parking stalls 27 EA $ $
32 17 20 Pavement Markings 023 Paint parking stall lines 24 EA $ $ 024 Paint crosswalk 1 EA $ $
01 14 10 3 84 00 Landscaping
025 Remove and dispose trees 3 EA $ $
Install irrigation and power conduit for future landscaping areas adjacent to proposed sidewalk 1 LS $ $
Maintain irrigation system to the four (4) trees that are to remain as indicated on the plans 1 LS $ $
12 93 00 Lighting
Install solar powered streetlights including light standards and concrete bases 4 EA $ $
Total $ $