Attachment_7_-_Task_Order_1_-_SOW_-_8-11-2021_0001.pdf

PDF 235 KB Posted

Attached to
Civil Site Work - Mulitiple Award IDIQ Federal contract opportunity
Solicitation number
140R3021R0029
Issued by
Department of the Interior Bureau of Reclamation

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of the Interior August 2021 Bureau of Reclamation Engineering Services Office Boulder City, Nevada

Civil Site Work IDIQ – Task Order No. 1

Lower Colorado Basin Regional Campus, Reclamation Boulevard Parking, Boulder City, NV

Attachment 7 Task Order No. 1 – Statement of Work

TO No. 1 –LCB Regional Campus, Reclamation Boulevard Parking RFP No. 140R3021R0029/0001

SUMMARY OF WORK

1. Location

Work is located on Bureau of Reclamation’s Lower Colorado Basin Date Street Campus, located at 500 Date Street, Boulder City, Nevada 89005.

2. Scope

The Bureau of Reclamation, Interior Region 8: Lower Colorado Basin’s Date Street Campus is in Boulder City, Nevada. The campus is 19.25 acres, has 12 buildings and approximately 308 employees. The purpose of Task Oder 1 is to improve the campus by adding 27 additional parking spaces for employee and government vehicles and improve accessibility by adding sidewalks with Architectural Barriers Act Accessibility Standards (ABAAS) compliant ramps and crosswalks. Lighting and conduit/irrigation line for future landscaping are also included as part of this task order. The following is a list of the major tasks that are included as part of this Task Order.

1. Remove and dispose 350 linear feet of curbing,

2. Remove and dispose 20 square yards of valley gutter,

3. Prepare subgrade and base for sidewalks, sidewalk ramps, and asphalt pavement (parking stalls),

4. Construct 399 square yards of concrete sidewalks,

5. Construct five (5) Architectural Barriers Act (ABA) compliant curb ramps,

6. Construct 371 linear feet of type “A” curb,

7. Construct 93 linear feet of type “L” curb,

8. Construct 81 square yards of valley gutter,

9. Construct 27 parking stalls (approx. 5,434 square feet of asphalt pavement at 4-inch-thick over a 6-inch aggregate base),

10. Install 27 concrete wheel stops,

11. Paint 24 parking stall lines (approx. 600 linear feet),

12. Paint crosswalk (approx. 350 square feet),

13. Remove and dispose three (3) trees as indicated on plans,

14. Install irrigation and power conduit for future landscaping areas adjacent to proposed sidewalk. Installation of new irrigation and power conduit to be coordinated with the COR two (2) business days prior to the start of this task.

15. Maintain irrigation system to the four (4) trees that are to remain as indicated on the plans. Existing irrigation locations and new lines will need to be coordinated with the COR five (5) prior to the start of this task.

16. Install four (4) solar powered streetlights including light standards and concrete bases (similar in size, style, and intensity of existing streetlighting within the Date Street Campus). Location: Sta. 12+ 96, 35’ RT; Sta. 13+85, 26’ RT; Sta. 14+79, 37’ RT;

Sta. 15+47, 37’ Rt. Stationing and offsets are approximate. Locations to be verified with the COR five (5) days prior to the start of this task.

17. Install two (2) 4-inch diameter schedule 40 PVC drainpipe under proposed sidewalk at north end of project. Approximate length 20 ft each. See revised Drawing No. 45- 300-60126-RD-1 for additional information.

18. Salvage existing landscape rock and use to protect slope and disturbed area at the north end of project.

Quantities listed are estimated only and may differ from actual field conditions. It is the responsibility of the contractor to field verify all quantities prior to construction.

3. Requirements

Permits and licenses should not be priced separately, they are covered by the FAR the Contractor shall perform this in accordance with FAR Clause 52.236-7 Permits and Responsibilities (Nov 1991).

Until further notice, contractors will be responsible for updating site specific safety plans to address the risks presented by COVID-19. The safety plan must be submitted to both the contracting office and designated Contracting Officer's Representative (COR) for review and approval. The contractor must refer to the Center for Disease Control (CDC) and Occupational Safety and Health Administration (OSHA) information related to COVID-19.

Work shall conform to the Reclamation Safety and Health Standards (RSHS) and must take all necessary precautions to ensure the safety of the public.

Principle components of work include, but are not limited to, any or all the following tasks:

1. The contractor must conduct mobilization and demobilization, along with preparatory work.

2. The contractor must provide bonding and liability insurance.

3. Furnish and submit all permits, licenses, and regulatory approvals that may be required by, including but not limited to, Federal, state, city, and county agencies.

4. The contractor shall provide qualified surveyors with all labor, equipment, and materials necessary to conduct preliminary, construction, and as-built surveys, this may include but not limited to setting control, staking, and record data for work indicated in this task order.

5. Provide all plans, labor, equipment, and materials necessary for traffic control of parking lots, public and office roads, and highways as designated.

6. Furnish all labor, equipment, and materials to pothole, locate and verify existing utilities.

7. Furnish all labor, equipment, and materials needed to place temporary fencing, barricades, lighting, and signage to secure work area.

8. Furnish all labor, equipment, and materials to demolish and remove existing foundations, utilities, and appurtenances.

9. Demolition, saw cut, remove, dispose, reuse, or stockpile of existing concrete slab, curbs and structures, and other identified materials.

10. Demolition, saw cut, remove dispose, reuse, or stockpile of existing asphalt paving, asphalt curbs and patching, and other identified materials.

11. Furnish all labor, equipment, and materials needed to install ABA/ADA compliant curb ramps and cross walk.

12. Furnish all labor, equipment, and materials needed to place slurry sealant or fog seal on existing asphalt pavement as indicated.

13. Furnish all labor, equipment, and materials to stockpile all recyclable materials as indicated on the drawings.

14. Furnish all labor, equipment, and materials required to perform earthwork for roadway and parking area subgrade.

15. Furnish and place subgrade material.

16. Furnish and place compacted aggregate base material, for new asphalt pavement or patching.

17. Furnish all labor, equipment, and materials for grading shoulders along roads and parking lot for drainage.

18. Furnish and install new asphalt concrete pavement.

19. Furnish and place aggregate base, Plantmix bituminous surface, concrete curb, gutter, and sidewalks.

20. Furnish and apply the parking lot striping and parking lot markings.

21. Conduct, and submit all asphalt, concrete, or other material testing to comply with specification.

22. Furnish all labor, materials, and equipment to install site landscaping and irrigation system.

23. Furnish all labor, materials, and equipment to install solar lighting, poles, and concrete bases.

24. Contractor to provide for all materials testing and quality control testing; including sampling and testing of existing soils to determine dry density and optimum moisture content (Proctor). Quality control sampling and testing to be performed by a certified material testing laboratory under the direction of a Civil Engineer licensed in the state of Nevada.

4. Site Access

Access to the gated area and work site will be given via a PIV card issued to the project Superintendent. The Superintendent is responsible for providing access and logging in all personnel, materials, and deliveries to the site.

5. Contractor Use Areas

The Contractor use areas are designated in Attachment No. 12. The use areas must be used for equipment loading/staging areas, the storage of equipment and materials, parking, and other work-related activities.

6. Work Hours

Work shall be scheduled between the hours of 6:00 AM to 4:30 PM, Monday through Friday.

Any request for weekend work, holiday work, or work outside of the specified work hours must be submitted to the Contracting Officer for approval at least two (2) days prior to the activity.

7. Period of Performance

The performance period for Task Order No. 1 is 120 calendar days from receipt of Notice to Proceed.

8. Submittals

List of Submittals

* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, PM indicates Project Manager.

RSN

Clause or Section

Title

Submittals required

Due date or delivery time

Type

Responsible Code

No. of sets to be sent to: **

CO COR PM

I-1 Schedules for Construction Contracts (52.236-15)

Practicable Schedule:

Blackline Prints

Within 14 days after Notice to Proceed but prior to Mobilization to the Jobsite

A CO 1 2 1

** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, PM indicates Project Manager.

RSN

Clause or Section

Title

Submittals required

Due date or delivery time

Type

Responsible Code

No. of sets to be sent to: **

CO COR PM

I-2 Schedules for Construction Contracts (52.236-15)

Updated schedule showing actual progress: Bar Chart and/or Timeline

As directed by the CO A CO 1 1 1

I-3 Schedules for Construction Contracts (52.236-15)

Supplementary Schedule or Schedules:

Blackline Prints

As deemed necessary by the CO.

A CO 1 1 1

I-4 Safety and Health

(WBR 1452.223-81)

Safety Program Submitted and accepted before commencing onsite work. See section 3 of RSHS

A CO 1 1 0

01 35 10-1 Safety Data Sheets Complete LHM and SDS

At least 14 days before jobsite delivery of hazardous material

I COR 1 1 1

01 35 10-2 Safety Data Sheets Updated LHM and

SDS

At least 14 days before jobsite delivery of hazardous material not previously listed

I COR 1 1 1

01 35 30-1 Contractor‘s Onsite Safety Personnel

Qualifications Prior to employment I COR 1 1 1

01 35 30-2 Contractor’s Onsite Safety Personnel

Detailed Safety Inspection Report

At least biweekly I COR 0 1 0

01 46 20-1 Testing Agency Services

Testing Agency Services Plan

Within 14 days after Notice to Proceed but prior to Mobilization to the Jobsite

I COR 0 1 1

01 46 20-2 Testing Agency Services

Contractor Quality testing results

Within seven (7) days after testing

I COR 0 1 1

01 55 00-1 Vehicular Access and Parking

Initial Digital Recording

At least 21 days before beginning on-site work or as directed by CO

A COR 0 1 0

** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, PM indicates Project Manager.

RSN

Clause or Section

Title

Submittals required

Due date or delivery time

Type

Responsible Code

No. of sets to be sent to: **

CO COR PM

01 55 00-2 Vehicular Access and Parking

Post Construction Digital Recording

At least 21 days before leaving site or as directed by CO.

A COR 0 1 0

01 55 00-3 Vehicular Access and Parking

Post Repair Digital Recording

Within 14 days of making repairs.

A COR 0 1 0

01 55 20-1 Traffic Control Traffic Control Plan

At least 15 days before affecting public traffic.

A COR 0 1 0

01 57 30-1 Water Pollution Control

Water Management Plan

At least 28 days before commencing construction activities]

A COR 0 1 1

01 57 30-1 Water Pollution Control

Pollution Prevention Plan

At least 28 days before start of onsite construction work

A COR 0 1 1

01 57 30-2 Water Pollution Control

Spill Prevention Control and Countermeasure Plan (SPCC)

At least 28 days before delivery or storage of oil

A COR 0 1 0

01 57 50-1 Tree and Plant Protection

Protection Plan At least 28 days before start of onsite construction work

A COR 0 1 0

01 71 20-1 Surveying Surveying Plan At least 28 days before beginning survey work

A COR 0 1 1

01 71 20-2 Surveying Resume At least 28 days before beginning survey work;

At least 28 days before personnel change

I COR 0 1 0

01 71 20-3 Surveying Accuracy Check Results

At least 14 days before beginning survey work

I COR 0 1 1

01 71 20-4 Surveying Completed and Reduced Survey Notes

Within two (2) days of completing and reducing notes

I COR 0 1 1

01 71 20-5 Surveying Quantity Survey Notes and Computations

Accompanying progress payment requests

I COR 0 1 1

** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, PM indicates Project Manager.

RSN

Clause or Section

Title

Submittals required

Due date or delivery time

Type

Responsible Code

No. of sets to be sent to: **

CO COR PM

01 71 20-6 Surveying Workday's Survey Notes

At conclusion of workday when requested by Government

I COR 0 1 0

01 74 00-1 Cleaning and Waste Management

Waste Production and Disposal Plan

At least 28 days before starting onsite work

I COR 0 1 0

01 74 00-2 Cleaning and Waste Management

Waste Production and Disposal Records

Within seven (7) days of waste disposal

I COR 0 1 0

01 74 00-4 Cleaning and Waste Management

Environmental Site Assessment

Within 14 days of completion of work

I COR 0 1 0

01 78 30-2 Project Record Documents

Progress As-built Drawings

Within 14 days after construction of a particular structure or work is completed

I COR 0 1 0

03 20 00-1 Concrete Reinforcing Reinforcement diagrams and lists

Within 14 days prior to construction

I COR 0 1 1

03 30 00-1 Cast in Place Concrete

Mix design for each concrete mix within 14 days of notice to proceed

A COR 0 1 1

03 30 00-7 Cast in Place Concrete

Test reports Within 24 hours for failing test results, seven (7) days after final break of specimen.

A COR 0 1 1

03 81 10-1 Concrete Removal Concrete removal plan

Within 14 days of notice to proceed

A COR 0 1 1

31 23 02-1 Compacting Earth Materials

Contractor materials testing requirements and frequency

Within 24 hours with COR’s approval to proceed.

A COR 1 1

31 23 70-1 Controlled Low Strength Material

(CLSM)

Approval data As requested by COR A COR 0 1 1

31 23 70-2 Controlled Low Strength Material

(CLSM)

Contractor field quality testing results

As requested by COR A COR 0 1 1

** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, PM indicates Project Manager.

RSN

Clause or Section

Title

Submittals required

Due date or delivery time

Type

Responsible Code

No. of sets to be sent to: **

CO COR PM

32 12 22-1 Asphalt Concrete Pavement

Job mix formula Within 14 days of notice to proceed

A COR 5 1 1

This page left intentionally blank

1. Location
3. Requirements
5. Contractor Use Areas
6. Work Hours
7. Period of Performance
The performance period for Task Order No. 1 is 120 calendar days from receipt of Notice to Proceed.
8. Submittals