C06_01_Amendment_No_P00005_Spec_Changes_0005.pdf
PDF 486 KB Posted
- Solicitation number
- 140R1026B0004
About this file
This is Amendment No. P00005 to a federal solicitation for turbine repair services at the Nathaniel "Nat" Washington Power Plant, located in the Columbia Pacific Northwest Interior Region 9.
The solicitation covers comprehensive turbine repair work for six hydroelectric generating units (G19-G24) operated by the Bureau of Reclamation. Services include welding repair of turbine runners and stay vanes, finish grinding of hydraulic profiles, draft tube platform installation and removal, coating of turbine components, asbestos survey and removal, abrasive blasting, load testing, and contract document management. The work is structured across multiple price schedules (A through M) with varying quantities for different units and work activities. Measurement and payment are based on weight of weld metal (pounds) for welding repairs and area (square feet) for grinding work. The contract is divided into six units with scheduled maintenance outages extending from August 2026 through March 2032, with turbines available for repair during 90-day periods at each unit's scheduled outage. Work is restricted to Monday through Thursday, 6:00 AM to 5:00 PM, with limited pre-outage access for material sampling. The solicitation references comprehensive technical standards including ASME codes, AWS standards, and ASTM specifications for welding, material testing, and quality control. Contractor responsibilities include secondary damage assessment, verification inspection by third-party inspectors, non-destructive examination of repairs, and detailed documentation using government-provided forms. The amendment revises sections on price schedules, work by government, work restrictions, submittals, metal fabrications, and turbine repair procedures.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DAVID CHRISTENSEN CHRISTENSEN
Digitally signed by DAVID
Date: 2026.06.04 14:55:04 -06'00'
Signature Sheet / Certification of Technical Specifications
Project Title: Nathaniel “Nat’ Washington Power Plant Turbine Repair
Region: Columbia Pacific Northwest Interior Region 9
Technical Specifications Project Title: Nathaniel “Nat’ Washington Power Plant Turbine Repair
Prepared by:
STACEY CARLSON
Digitally signed by STACEY
CARLSON
Date: 2026.06.03 09:44:19 -06'00' Date:
Technical Approval: Date:
1. The person signing the specifications package as “Prepared by” shall have developed or assembled the written specifications.
2. The person signing the specifications package for “Technical Approval” shall have been in responsible charge of the overall design including developing or assembling the specifications. This person will typically be the design team leader. In cases where the designs described by the specifications meet the criteria for preparation by a registered engineer or architect, this person shall be registered with the applicable professional designation after their signature, such as P.E. for professional engineer or R.A. for registered architect. By this signature, this person is certifying the written specifications convey the design intent as portrayed on the drawings included therein. For specifications package containing designs from multiple disciplines, it is the signing individual’s responsibility to ensure (using procedures defined by his/her organization) that the technical information prepared by other professions and disciplines and depicted in the document is compatible with the overall design intent and that the documents used to depict that information (e.g., drawings) include signatures with appropriate professional registration designations.
3. Revisions to designs after drawings and written specifications are originally signed will be reviewed by a design team representative (typically the design team leader). The review of written specifications revisions must be documented on a signature sheet included with the revised written specifications (see below).
AMD/MOD
No.
Technical Approval Signature:
Prepared By Signature:
Revised Sections & Binders:
Amd No. P00005 00 00 50, 01 11 16, 01 14 00, 01 33 00, 05 50 00, & 48 13 13.
Amended: Forms Binder Section J, and GCPO Health Program Binder Section J.
STACE
Y
CARLS
ON
Digitally signed by
STACEY
CARLSON
Date:
2026.07.20 15:00:51 -06'00'
DAVID
CHRISTENSEN
Digitally signed by DAVID
CHRISTENSEN
Date: 2026.07.21 15:59:59 -06'00'
Nathaniel ‘Nat’ Washington Power Plant Turbine Repair Amendment No. P00005
Price Schedule – (Revised)
B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND COSTS
NATHANIEL ‘NAT’ WASHINGTON POWER PLANT
TURBINE REPAIR
COLUMBIA BASIN PROJECT, WASHINGTON
B.1 PRICE SCHEDULE
(a) Bids will be considered for award on the following Price Schedules, but no bid will be considered for award on only a part of a Price Schedule.
(b) Bids are subject to the terms and conditions of this solicitation.
(c) Quantities in the Price Schedule are estimated quantities for comparison of bids only.
Except as provided in the contract clause at Section H. Clause Title Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns.
(d) See the contract clause at WBR 1452.232-81 Alt III, Payment for Mobilization and Preparatory Work, for CLIN 1 of applicable Price Schedules.
(e) Definitions:
(1) CLIN – Contract Line Item Number
B - 2
PRICE SCHEDULE A
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
A-1 WBR
1452.232 -81
G19 Mobilization and Preparatory Work
For the lump sum of $
A-2 48 13 13 G19 Welding Repair of Turbine Runner pounds
A-3 48 13 13 G19 Finish Grinding of Hydraulic Profile for Turbine Runner
300 square feet
TOTAL FOR PRICE SCHEDULE A $__________________
B - 3
PRICE SCHEDULE B
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
B-1 01 64 41 G19 Installation of Draft Tube Platform
For the lump sum of $
B-2 09 96 20 G19 Coating of Turbine Runner square feet
B-3 02 82 10 G19 Asbestos Survey For the lump sum of $
B-4 02 82 20 G19 Removal and Disposal of Asbestos Containing Materials
825 square feet
B-5 09 96 20 G19 Abrasive Blasting of Turbine Stay Vanes for Examination
825 square feet
B-6 48 13 13 G19 Welding Repair of Turbine Stay Vanes pounds
B-7 48 13 13 G19 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes
150 square feet
B-8 09 96 20 G19 Coating of Turbine Stay Vanes
825 square feet
B-9 01 64 41 G19 Removal of Draft Tube Platform
For the lump sum of
TOTAL FOR PRICE SCHEDULE B $__________________
B - 4
PRICE SCHEDULE C
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
C-1 WBR
1452.232 -81
G20 Mobilization and Preparatory Work
For the lump sum of $
C-2 48 13 13 G20 Welding Repair of Turbine Runner pounds
C-3 48 13 13 G20 Finish Grinding of Hydraulic Profile for Turbine Runner
300 square feet
TOTAL FOR PRICE SCHEDULE C $__________________
B - 5
PRICE SCHEDULE D
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
D-1 01 64 41 G20 Installation of Draft Tube Platform
For the lump sum of $
D-2 09 96 20 G20 Coating of Turbine Runner square feet
D-3 02 82 10 G20 Asbestos Survey For the lump sum of $
D-4 02 82 20 G20 Removal and Disposal of Asbestos Containing Materials
825 square feet
D-5 09 96 20 G20 Abrasive Blasting of Turbine Stay Vanes for Examination
825 square feet
D-6 48 13 13 G20 Welding Repair of Turbine Stay Vanes pounds
D-7 48 13 13 G20 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes
150 square feet
D-8 09 96 20 G20 Coating of Turbine Stay Vanes
825 square feet
D-9 01 64 41 G20 Removal of Draft Tube
TOTAL FOR PRICE SCHEDULE D $__________________
B - 6
PRICE SCHEDULE E
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
E-1 WBR
1452.232 -81
G21 Mobilization and Preparatory Work
For the lump sum of $
E-2 48 13 13 G21 Welding Repair of Turbine Runner pounds
E-3 48 13 13 G21 Finish Grinding of Hydraulic Profile for Turbine Runner
300 square feet
TOTAL FOR PRICE SCHEDULE E $__________________
B - 7
PRICE SCHEDULE F
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
F-1 01 64 41 G21 Installation of Draft Tube Platform
For the lump sum of $
F-2 09 96 20 G21 Coating of Turbine Runner square feet
F-3 02 82 10 G21 Asbestos Survey For the lump sum of $
F-4 02 82 20 G21 Removal and Disposal of Asbestos Containing Materials
825 square feet
F-5 09 96 20 G21 Abrasive Blasting of Turbine Stay Vanes for Examination
825 square feet
F-6 48 13 13 G21 Welding Repair of Turbine Stay Vanes pounds
F-7 48 13 13 G21 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes
150 square feet
F-8 09 96 20 G21 Coating of Turbine Stay Vanes
825 square feet
F-9 01 64 41 G21 Removal of Draft Tube
TOTAL FOR PRICE SCHEDULE F $__________________
B - 8
PRICE SCHEDULE G
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
G-1 WBR
1452.232 -81
G22 Mobilization and Preparatory Work
For the lump sum of $
G-2 48 13 13 G22 Welding Repair of Turbine Runner pounds
G-3 48 13 13 G22 Finish Grinding of Hydraulic Profile for Turbine Runner
325 square feet
TOTAL FOR PRICE SCHEDULE G $__________________
B - 9
PRICE SCHEDULE H
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
H-1 01 64 41 G22 Installation of Draft Tube Platform
For the lump sum of $
H-2 09 96 20 G22 Coating of Turbine Runner square feet
H-3 02 82 10 G22 Asbestos Survey For the lump sum of $
H-4 02 82 20
G22 Removal and Disposal of Asbestos Containing Materials
475 square feet
H-5 09 96 20 G22 Abrasive Blasting of Turbine Stay Vanes for Examination
475 square feet
H-6 48 13 13 G22 Welding Repair of Turbine Stay Vanes pounds
H-7 48 13 13 G22 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes
100 square feet
H-8 09 96 20 G22 Coating of Turbine Stay Vanes
475 square feet
H-9 01 64 41 G22 Removal of Draft Tube
TOTAL FOR PRICE SCHEDULE H $__________________
B - 10
PRICE SCHEDULE I
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
I-1 WBR
1452.232 -81
G23 Mobilization and Preparatory Work
For the lump sum of $
I-2 48 13 13 G23 Welding Repair of Turbine Runner pounds
I-3 48 13 13 G23 Finish Grinding of Hydraulic Profile for Turbine Runner
325 square feet
TOTAL FOR PRICE SCHEDULE I $__________________
B - 11
PRICE SCHEDULE J
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
J-1 01 64 41 G23 Installation of Draft Tube Platform
For the lump sum of $
J-2 09 96 20 G23 Coating of Turbine Runner square feet
J-3 02 82 10 G23 Asbestos Survey For the lump sum of $
J-4 02 82 20
G23 Removal and Disposal
Materials
475 square feet
J-5 09 96 20 G23 Abrasive Blasting of Turbine Stay Vanes for Examination
475 square feet
J-6 48 13 13 G23 Welding Repair of Turbine Stay Vanes pounds
J-7 48 13 13 G23 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes
100 square feet
J-8 09 96 20 G23 Coating of Turbine Stay Vanes
475 square feet
J-9 01 64 41 G23 Removal of Draft Tube
TOTAL FOR PRICE SCHEDULE J $__________________
B - 12
PRICE SCHEDULE K
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
K-1 WBR
1452.232 -81
G24 Mobilization and Preparatory Work
For the lump sum of $
K-2 48 13 13 G24 Welding Repair of Turbine Runner pounds
K-3 48 13 13 G24 Finish Grinding of Hydraulic Profile for Turbine Runner
325 square feet
TOTAL FOR PRICE SCHEDULE K $__________________
B - 13
PRICE SCHEDULE L
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
L-1 01 64 41 G24 Installation of Draft Tube Platform
For the lump sum of $
L-2 09 96 20 G24 Coating of Turbine Runner square feet
L-3 02 82 10 G24 Asbestos Survey For the lump sum of $
L-4 02 82 20
G24 Removal and Disposal
Materials
475 square feet
L-5 09 96 20 G24 Abrasive Blasting of Turbine Stay Vanes for Examination
475 square feet
L-6 48 13 13 G24 Welding Repair of Turbine Stay Vanes pounds
L-7 48 13 13 G24 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes
100 square feet
L-8 09 96 20 G24 Coating of Turbine Stay Vanes
475 square feet
L-9 01 64 41 G24 Removal of Draft Tube
TOTAL FOR PRICE SCHEDULE L $__________________
B - 14
PRICE SCHEDULE M
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
M-1 01 64 41 Load Testing of G19-G21 Draft Tube Platform
For the lump sum of $
M-2 01 64 41 Load Testing of G22-G24 Draft Tube Platform
For the lump sum of $
M-3 01 31 30 G19-G24 Contract Document Management System
For the lump sum of $
TOTAL FOR PRICE SCHEDULE M $__________________
END OF SUPPLIES OR SERVICES AND COSTS
Work by Government – (Revised)
01 11 16 - 1
SECTION 01 11 16
WORK BY GOVERNMENT
PART 1 GENERAL
1.01 GENERAL
A. The Government shall perform customary tasks to assist the Contractor with gaining access for the work. The Government makes no guarantee as to the condition of completed tasks. Contractor shall accept the conditions “as-is” and improve conditions as required to complete the work.
B. Prior to the start of work, Government will:
1. Drain and open unit waterway.
2. Install vane axial fans.
3. Install wire rope around runner blades’ leading edges.
4. Install wire rope around stay vanes’ leading edges.
5. Install string of lights around the periphery of the stay ring.
C. During installation of draft tube platform, Government may:
1. Maintain water level in draft tube waterway from 4 feet to 8 feet below the invert of the draft tube access door:
a. This has been a customary practice for additional fall protection during draft tube platform installation. Government makes no guarantee that this practice will continue.
a.b. Contractor may request draining of the draft tube to avoid working over water.
D. After installation of draft tube platform, Government will:
1. Install lighting around the periphery of the draft tube.
2. Drain the draft tube waterway.
E. Upon completion of the work, Government will:
1. Remove and store vane axial fans.
2. Remove and store wire rope around runner blades’ leading edges.
3. Remove and store wire rope around stay vanes’ leading edges.
4. Remove and store string of lights around the periphery of the stay ring.
5. Remove and store lighting around the periphery of the draft tube.
6. Close and fill waterway in preparation for the unit to return to service.
Work by Government – (Revised)
01 11 16 - 2
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Work Restrictions – (Revised)
01 14 00 - 1
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.01 WORK RESTRICTIONS
A. Perform work during Government’s scheduled maintenance outages:
1. The Government makes no guarantee as to the number of units scheduled for maintenance within a 12-month period:
a. Unit to be repaired will be issued at the Task Order Level.
b. For information only, this outage schedule is subject to change:
2. Turbines will be available for repair for a 90-day period during the scheduled outage:
a. 90-day period will be scheduled at the Task Order Level.
b. Limited access is available 30 days prior to the 90-day duration for sampling the stay vane material and coating only:
1) Access is only available through the drained and opened spiral case.
2.2) Provide equipment for accessing the stay vanes from the spiral case door.
B. Allowable working hours:
1. Monday through Thursday, 6:00AM to 5:00PM.
C. Allowable delivery hours:
1. Monday through Thursday, 7:00AM to 3:00PM.
Unit Megawatt Rating
Start Date End Date Purpose
23 805 8/30/2026 4/2/2027 Sexennial Maintenance and stator bar repair
24 805 8/29/2027 3/31/2028 Sexennial Maintenance
21 690 9/3/2028 3/30/2029 Sexennial Maintenance
19 690 9/2/2029 3/29/2030 Sexennial Maintenance
20 690 9/1/2030 3/28/2031 Sexennial Maintenance
22 805 8/24/2031 3/26/2032 Sexennial Maintenance
01 14 00 - 2
D. Schedule time for access by the Government to perform turbine runner and discharge ring initial assessment and final inspection:
1. After draft tube platform installation: 7 days:
a. Includes all appurtenances for complete access to all work surfaces.
b. Submit written notification 7 days in advance of the start of scheduled time for access in accordance with Section 01 31 19 – Project Management and Coordination.
2. After completion of repair work and prior to removal of draft tube platform: 7 days:
a. Includes all appurtenances for complete access to all work surfaces.
b. Submit written notification 7 days in advance of the start of scheduled time for access in accordance with Section 01 31 19 – Project Management and Coordination.
E. Schedule time for access by the Government to perform turbine stay vane initial assessment and final inspection:
1. After stay vane coating removal: 7 days:
a. Includes all appurtenances for complete access to all work surfaces.
b. Submit written notification 7 days in advance of the start of scheduled time for access in accordance with Section 01 31 19 – Project Management and Coordination.
2. After completion of repair work and prior to removal of scaffolding: 7 days:
a. Includes all appurtenances for complete access to all work surfaces.
b. Submit written notification 7 days in advance of the start of scheduled time for access in accordance with Section 01 31 19 – Project Management and Coordination.
F. Do not exceed the safe working capacity of the elevator.
1. When necessary to move components in excess of the safe working capacity of the elevator, Government-owned crane will be available to move components between floors using existing hatches. Provide all necessary labor and equipment to move the component to and from the existing floor hatches. Comply with requirements of Section 01 54 20 – Use of Government Crane.
PART 2 PRODUCTS
01 14 00 - 3
PART 3 EXECUTION
01 14 00 - 4
This page intentionally left blank.
Submittals – (Revised)
01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices bid in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-12 Decimal-inch Drawing Sheet Size and
Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittal Types, as listed in Table 01 33 00A - List of Submittals:
1. A - Approval:
a. Government will respond as to adequacy of submittal.
b. Approval Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction.
2. I - Informational:
a. Government will acknowledge receipt of Informational submittals.
b. Government may reject an Informational submittal when the submittal does not satisfy contract requirements. Correct mistakes or deficiencies in rejected Informational submittals and resubmit.
c. Informational Submittals: Considered “shop drawings” within terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by Government is not required.
01 33 00 - 2
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement Units: US Customary Units.
4. Provide a unique transmittal number for each submittal.
C. Government Forms:
1. Fill in all requested data on forms electronically or by hand.
2. Handwritten data on forms shall be neat and legible.
3. Forms with handwritten data shall be scanned to create high-resolution electronic files.
4. Retain all forms with handwritten data and submit complete set of hardcopies at the completion of each task order.
5. Submit complete set of electronic files on a USB flash drive at the completion of each task order.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a Registered Professional: Signed and sealed by registered professional.
2. Manufacturer’s Certifications: Signed by authorized representative of manufacturer.
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
01 33 00 - 3
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes listed items for RSNs with multiple parts.
C. Submit sets specified in “Sets to be sent:” columns in Table 01 33 00A - List of Submittals.
1. Submittals identified with “CDMS” in the “Sets to be sent” column shall be submitted electronically in accordance with Section 01 31 30 - Contract Document Management System.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 7 days after receiving the comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
F. More than one RSN may be submitted under a transmittal letter, provided responsible code is same.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. CO may extend contract completion date to allow additional time for completing work affected by excess review time.
a. Time extension will be to extent that excess review time caused delay to contract completion date.
01 33 00 - 4
b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.
2. No time extension will be allowed if Contractor fails to make complete approval submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to the extent that:
a. Approval was required under the contract, and.
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of clause at FAR
52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as term is used in that clause.
C. Return of Submittals:
1. Return of submittals will be by CDMS response or hard copy, as applicable.
2. Approval Submittals: 1 set of submittals required for approval will be returned either approved, approved with comments or not approved.
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.
3. Informational Submittals: Government will acknowledge Informational submittals.
a. Informational submittals will not be returned when they satisfy contract requirements.
b. Informational submittals that do not satisfy contract requirements may be returned for resubmittal, or additional information may be requested.
1.07 HARD COPY TRANSMITTALS
A. Addresses for codes listed in Table 01 33 00A - List of Submittals:
1. Contracting Officer (CO), Bureau of Reclamation, Attn: CPN-7300, 1150 N.
Curtis Rd, Boise, ID 83706-1234.
2. Construction Field Manager (COR), Bureau of Reclamation:
a. Request address after task order award.
B. Send original transmittal letter with appropriate number of sets to office listed in “Responsible Code” column in Table 01 33 00A - List of Submittals.
01 33 00 - 5
C. Send copy of transmittal letter with appropriate number of sets to offices that are not responsible code, but show “Sets to be sent” in Table 01 33 00A - List of Submittals.
D. When “Sets to be sent” is 0, send a copy of transmittal letter to that office.
E. Submittals required by specifications, but not listed in Table 01 33 00A - List of Submittals:
1. Submit in accordance with this section.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
01 33 00 - 6
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
CP
Respon-sible code
Sets to be sent: ***
CO COR
I-1 Release of Claims (1452.204-70)
Release of claims (DI-137) against the United States
Submitted after completion of work and prior to final payment
I CO
1 0
I-2 Payrolls and Basic Records (52.222-8)
Certified payrolls Submitted weekly for each week any contract work is performed
I COR CDMS
I-3 Subcontracts (Labor Standards) (52.222-11)
1) List of subcontractors
2) Statement and Acknowledgement Form (SF-1413) for each subcontract
Submitted within 14 days after task order award, and within 14 days after any subcontract award
I COR 1 0
I-4 Equal Opportunity (52.222-26)
Information required by Executive Order
11246 (SF-100)
Submitted within 28 days following task order award
I COR 1 0
I-5 Bonds (52.228-15)
Performance and payment bonds
Submitted and approved within 10 calendar days after task order award
A CO 1 0
I-6 Liability Insurance (1452.228-70)
Acceptable evidence showing that insurance has been obtained
Submitted and approved within 10 calendar days after task order award
A CO 1 0
I-7 Security Requirements
(WBR
1452.237-80)
Security Program Submitted and approved within 7 days after the task order work starts or another period approved by the Contracting Officer
A COR CDMS
I-8 Security Requirements
(WBR
1452.237-80)
List of onsite employees
Submitted within 7 days after the task order work starts or another period determined by the Contracting Officer
I COR CDMS
01 31 19-1 Project Management and Coordination
Pre-Work Meeting Agenda
Submitted and approved at least 35 days before each mobilization
A Y COR CDMS
01 31 19-2 Project Management and Coordination
Pre-Load Test of Draft Tube Platform Meeting Agenda
Submitted and approved at least 21 days before start of assembly for load testing
A Y COR CDMS
01 33 00 - 7
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Respon-sible code
Sets to be sent: ***
CO COR
01 31 19-3 Project Management and Coordination
Pre-Installation of Draft Tube Platform Meeting Notification
Submitted and approved at least 21 days before start of installation
A Y COR CDMS
01 31 19-4 Project Management and Coordination
Notification of Scheduled Time for Access for Initial Assessment of Turbine Runner and Discharge Ring
Submitted and approved at least 7 days before start of scheduled time for access
A Y COR CDMS
01 31 19-5 Project Management and Coordination
Notification of Scheduled Time for Access for Final Inspection of Turbine Runner and Discharge Ring
Submitted and approved at least 7 days before start of scheduled time for access
A Y COR CDMS
01 31 19-6 Project Management and Coordination
Notification of Scheduled Time for Access for Initial Assessment of Turbine Stay Vanes
Submitted and approved at least 7 days before start of scheduled time for access
A Y COR CDMS
01 31 19-7 Project Management and Coordination
Notification of Scheduled Time for Access for Final Inspection of Turbine Stay Vanes
Submitted and approved at least 7 days before start of scheduled time for access
A Y COR CDMS
01 31 19-8 Project Management and Coordination
Progress Review Meeting Agenda
Submitted at least 2 days before the meeting
I COR CDMS
01 31 19-9 Project Management and Coordination
Progress Review Meeting Minutes
Submitted within 24 hours after the meeting
I COR CDMS
01 31 30-1 Contract Document Management System
Approval Data Submitted and approved within 28 days after task order NTP
A COR 0
01 31 30-2 Contract Document Management System
Final Data Submitted and approved within 28 days of completion of work
A COR CDMS
01 33 00 - 8
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Respon-sible code
Sets to be sent: ***
CO COR
01 32 10-1 Construction Program
Representative Information
Submitted and approved within 7 days after task order NTP
A COR 0 1
01 32 10-2 Construction Program
Baseline Schedule Submitted and approved within 28 days after task order NTP
A Y COR CDMS 1
01 32 10-3 Construction Program
Updated Schedule Reports
Submitted and approved monthly, with progress payments, and within 14 days after award of a task order
A Y COR CDMS
01 32 10-4 Construction Program
Time Impact Analysis
Submitted and approved within 28 days after the CO directs a contract change with schedule impacts
Or
With proposal for future modification, value engineering proposal, or request or claim for equitable adjustment to the contract when time is requested
01 35 20-1 Safety and Health
Safety Program Submitted and approved within 28 days after task order NTP
A Y COR CDMS
01 35 20-2 Safety and Health
Job Hazard Analysis List
Submitted and approved within 28 days after task order NTP
A COR CDMS
01 35 20-3 Safety and Health
Asbestos Personnel Protection Plan
Submitted and approved within 28 days after task order NTP
A COR CDMS
01 35 20-4 Safety and Health
Regulated Metals in Coatings Personnel Protection Plan
Submitted and approved within 28 days after task order NTP
A COR CDMS
01 35 20-5 Safety and Health
Asbestos Working Level Test Results
Submitted within 7 days of testing
I COR CDMS
01 35 20-6 Safety and Health
Asbestos Post- Construction Test Results
Submitted within 7 days of testing
I COR CDMS
01 33 00 - 9
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Respon-sible code
Sets to be sent: ***
CO COR
01 35 20-7 Safety and Health
Regulated Carcinogenic Coatings Personnel Protection Plan
Submitted and approved within 28 days after task order NTP
A COR CDMS
01 35 20-8 Safety and Health
Monthly Accident Summary Report
Submitted within 28 days of the start of on-site work and monthly thereafter
I COR CDMS
01 35 20-9 Safety and Health
Documentation and Records
Submitted at least 28 days before start of on-site work
I COR CDMS
01 35 30-1 Contractor’s Onsite Safety Personnel
Qualifications Submitted and approved at least 28 days before start of on-site work
A COR CDMS
01 35 30-2 Contractor’s Onsite Safety Personnel
Safety Inspection Reports
Submitted within 7 days after inspection
I COR CDMS
01 32 30-3 Contractor’s Onsite Safety Personnel
CIH Reports Submitted within 7 days after inspection
I COR CDMS
01 46 00-1 Quality Procedures
Contractor Quality Control Plan
Submitted and approved at least 28 days before start of on-site work
A COR CDMS
01 46 00-2 Quality Procedures
Contractor’s Daily Reports
Submitted within the following workday
I COR CDMS
01 54 20-1 Use of Government Crane
Use of Crane Request
Submitted and approved at least 4 days before crane is used
A COR CDMS
01 54 23-1 Temporary Scaffolding and Platforms
Scaffolding Approval Data
Submitted and approved at least 28 days before starting scaffolding erection
A Y COR CDMS
01 54 23-2 Temporary Scaffolding and Platforms
Scaffolding Plan Submitted and approved at least 28 days before start of on-site work
A COR CDMS
01 64 40-1 Government- Furnished Equipment
Shortage Report Submitted within 24 hours after joint inspection
A COR CDMS
01 64 41-1 Government- Furnished Draft Tube Platforms
Shortage Report Submitted within 24 hours after joint inspection
01 33 00 - 10
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Respon-sible code
Sets to be sent: ***
CO COR
01 64 41-2 Government- Furnished Draft Tube Platforms
Load Test Certificate
Submitted within 24 hours after successful completion of draft tube platform load test
I COR CDMS
01 64 41-3 Government- Furnished Draft Tube Platforms
Installation Certificate
Submitted within 24 hours after successful service ready installation of the draft tube platform
I COR CDMS
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
Submitted and approved at least 28 days before starting onsite work
A Y COR CDMS
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
Submitted within 7 days of waste disposal
I COR CDMS
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
Submitted and approved at least 35 days before beginning site assessment
A COR CDMS
02 82 10-1 Asbestos Containing Materials Survey
Qualifications Submitted and approved at least 35 days before start of asbestos removal work
A COR CDMS
02 82 10-2 Asbestos Containing Materials Survey
Asbestos Survey Report
Submitted within 7 days of completed survey
I COR CDMS
02 82 20-1 Removal and Disposal of Asbestos Containing Materials
Resumes, Certificates, and Qualifications
Submitted and approved at least 35 days before start of asbestos removal work
A COR CDMS
02 82 20-2 Removal and Disposal of Asbestos Containing Materials
Asbestos Hazard Abatement Plan
Submitted and approved at least 35 days before start of asbestos removal work
A COR CDMS
02 82 20-3 Removal and Disposal of Asbestos Containing Materials
Certificate of Disposal
Submitted within 14 days of disposal
I COR CDMS
01 33 00 - 11
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Respon-sible code
Sets to be sent: ***
CO COR
05 50 00-1 Metal Fabrications
Material Test Reports for Known Base Metals
Submitted within 7 days of testing.
I COR CDMS
05 50 00-2 Metal Fabrications
Approval Data for Welding on Known Base Metals
Submitted and approved at least 28 days before the start of welding on known base metals.
A Y COR CDMS
05 50 00-3 Metal Fabrications
Weld Material Certifications
Submitted and approved at least 28 days before the start of weld repairs
A COR CDMS
05 50 00-4 Metal Fabrications
Inspector Approval Data
Submitted and approved at least 28 days before the start of weld repairs
A Y COR CDMS
05 50 00-5 Metal Fabrications
Approval Data for Welding on Discharge Ring
Submitted and approved at least 28 days before the start of welding on discharge ring.
A COR CDMS
05 50 00-6 Metal Fabrications
Approval Data for Welding on Stay Vane
Submitted and approved at least 28 days before the start of welding on stay vanes.
A COR CDMS
09 96 20-1 Coatings Approval Data Submitted and approved at least 28 days before start of coating section work
A COR CDMS
09 96 20-2 Coatings Final Approval Data
Submitted and approved at least 28 days before start of coating section work
A COR CDMS
09 96 20-3 Coatings Qualifications Submitted and approved at least 28 days before start of coating section work
A COR CDMS
09 96 20-4 Coatings Quality Control Plan
Submitted and approved at least 28 days before start of coating section work
A COR CDMS
09 96 20-5 Coatings Contractor Quality Testing Report
Submitted within 24 hours after a day of coating work
01 33 00 - 12
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Respon-sible code
Sets to be sent: ***
CO COR
48 13 13-1 Turbine Repair Secondary Assessment – Runner
Submitted within 24 hours after discovery of damage
A COR CDMS
48 13 13-2 Turbine Repair Secondary Assessment – Discharge Ring
Submitted within 24 hours after discovery of damage
A COR CDMS
48 13 13-3 Turbine Repair Secondary Assessment – Stay Vanes
Submitted within 24 hours after discovery of damage
A COR CDMS
48 13 13-4 Turbine Repair Verification Inspection Report
Submitted within 7 days after passing inspection
Metal Fabrications – (Revised)
05 50 00 - 1
SECTION 05 50 00
METAL FABRICATIONS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include cost in applicable prices bid in the Price Schedules for which welding is required.
1.02 ACRONYMS
A. WPS – Weld Procedure Specification.
B. NDE – Non-Destructive Examination, also referred to as NDT – Non-Destructive Testing.
C. PQR – Procedure Qualification Record.
C.D. WPQ/WPQR – Welder Performance Qualification Record.
1.03 DEFINITIONS
A. Carbon equivalent: empirical value used to predict the weldability of a steel based on its chemical composition. Calculated as:
B. Miscellaneous metalwork: Where specified elsewhere in these specifications or this Section, “miscellaneous metalwork” means metal fabrications and metal repair as used in this Section.
C. Verification Inspector: This inspector is the duly designated person who acts for, and in behalf of, the Owner on all inspection and quality matters within the scope of the contract documents. This is a 3rd party inspector hired by the Contractor to provide independent inspection.
05 50 00 - 2
D. Contractor’s Inspector: This inspector is the duly designated person who acts for, and in behalf of, the Contractor on all inspection and quality matters within the scope of the contract documents.
1.04 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1.04 ASME BPVC Section IX 2025 Boiler and Pressure Vessel Code –
Section IX. Qualification Standard for Welding, Brazing, and Fusing Procedures;
Welders; Brazers; and Welding, Brazing, and Fusing Operators
A.B. American Welding Society, Inc. (AWS)
1. AWS D1.1/D1.1M:2025 Structural Welding Code - Steel
2. Deleted
C. ASTM International (ASTM)
1. ASTM A488/A488M-24 Steel Castings, Welding, Qualifications of
Procedures and Personnel
2. ASTM A751-25 Chemical Analysis of Steel Products
3. ASTM E8/E8M-25 Tension Testing of Metallic Materials
4. ASTM E415-21 Analysis of Carbon and Low-Alloy Steel by
Spark Atomic Emission Spectrometry
1.05 SUBMITTALS
A. RSN 05 50 00 – 1, Material Test Reports for Known Base Metals, including:
1. Test reports for all materials tested except discharge ring and stay vane material.
2. Carbon equivalent for each material tested.
B. RSN 05 50 00 – 2, Approval Data for Welding on Known Base Metals, including:
1. WPSs for welding on known base metals.
2. PQRs for each non-prequalified WPS.
1.3. WPQ/WPQRs, including active continuity logs demonstrating that each proposed welder is certified for the specific process, position, thickness, and filler metal classification required by the subject WPSs.
B.C. RSN 05 50 00 – 3, Weld Material Certifications
05 50 00 - 3
D. RSN 05 50 00 – 4, Inspector Approval Data, including:
1. Verification inspector:
a. Name.
b. Company name.
c. Certifications.
2. Contractor’s Inspector:
a. Name.
b. Certifications.
E. RSN 05 50 00-5, Approval Data for Welding on Discharge Ring, including:
1. Chemical and mechanical testing results, from discharge ring specimen.
2. Classification of material to an ASTM standard and grade.
3. Carbon equivalent for discharge ring material.
4. WPS for welding on discharge ring.
5. PQRs for each non-prequalified WPS.
6. WPQ/WPQRs, including active continuity logs demonstrating that each proposed welder is certified for the specific process, position, thickness, and filler metal classification required by the subject WPSs.
F. RSN 05 50 00-6, Approval Data for Welding on Stay Vane, including:
1. Chemical and mechanical testing results, from stay vane specimen.
2. Classification of material to an ASTM standard and grade.
3. Carbon equivalent for stay vane material.
4. WPS for welding on the stay vane.
5. PQRs for each non-prequalified WPS.
1.6. WPQ/WPQRs, including active continuity logs demonstrating that each proposed welder is certified for the specific process, position, thickness, and filler metal classification required by the subject WPSs.
1.06 QUALIFICATIONS
A. Verification Inspector:
1. Current certification as an AWS Certified Welding Inspector in conformance with the requirements of AWS QC1, Standard for AWS Certification of Welding Inspectors.
2. NDT Level II.
B. Contractor’s Inspector:
05 50 00 - 4
1. Qualification in accordance with AWS D1.1.
1.07 DELIVERY, STORAGE, AND HANDLING
A. Protect from corrosion, deformation, and other types of damage.
B. Store items in an enclosed area free from contact with soil and weather.
C. Remove and replace damaged items with new items.
1.08 EXISTING BASE METALS
A. Units G19 through G21:
1. Runner assembly: cast steel, per ASTM A216, Grade WCB
2. Original stainless steel overlay: Alloy 308L
B. Units G22 through G24:
1. Runner crown and blades: cast steel, per ASTM A216, Grade WCC.
2. Runner band: steel, per ASTM A516, Grade 70.
C. Discharge ring: steel of unknown composition.
1.08D. Turbine stay vanes: steel of unknown composition
PART 2 PRODUCTS
2.01 MATERIALS
2.01A. All welding filler metals, electrodes, flux, and shielding gases shall comply with the applicable welding code (ASME Section IX, ASTM A488, or AWS D1.1) specified in Part 3 for the respective weld type and base metal combination.
A.B. Deleted.
B.C. Deleted.
PART 3 EXECUTION
3.01 BASE MATERIAL TESTING AND IDENTIFICATION
A. Applicability: Table 05 50 00A summarizes test requirements by components.
05 50 00 - 5
Table 05 50 00A Component Test
Required Minimum # of tests:
Material test reports required prior to preparing WPSs?
Runner crown Chemical 1 per unit No Runner blade Chemical 1 per unit No Runner band Chemical 1 per unit No Runner cone Chemical 1 per unit No Discharge ring
Chemical and mechanical
1 per unit Yes
Stay vane Chemical and mechanical
1 per unit Yes
B. Chemical Composition Testing:
1. Perform quantitative chemical analysis in accordance with ASTM A751.
2. For Carbon and Low-Alloy Steels (including ASTM A216 and A516): Utilize
Spark Atomic Emission Spectrometry per ASTM E415. The size and characteristics of the test specimen shall be per E415. The testing shall be sufficient to calculate the carbon equivalent.
C. Mechanical Testing:
1. Perform tension testing in accordance with ASTM E8 to determine yield strength, ultimate strength, and elongation. The size and characteristics of the test specimen shall be per E8.
D. Test Specimen Extraction:
1. The physical location on the turbine from which test specimens will be extracted shall be subject to the approval of the COR.
2. Extract specimens from low-stress, non-critical areas of the component.
3. Avoid zones of existing cavitation damage or heat-affected zones from prior repair.
4. Repair extraction areas in accordance with Section 48 13 13 – Turbine Repair.
E. Classification of Steel of Unknown Composition:
1. Use chemical and mechanical test results to classify existing material as an
ASTM standard grade.
3.02 PREPARATION
A. Where locations and dimensions of miscellaneous metalwork are dependent upon existing equipment and/or equipment furnished, confirm locations and dimensions prior to fabrication of miscellaneous metalwork.
05 50 00 - 6
3.03 REMOVING METAL
A. Only in areas authorized for repair.
B. Acceptable metal excavation methods:
1. Air carbon arc gouging followed by power-tool grinding to sound, bright metal.
2. Grinding to sound, bright metal.
3. Follow procedures outlined in 48 13 13 – Turbine Repair.
3.04 WELDING
A. Only in areas authorized for repair.
B. Deleted.
C. All weld metal shall be deposited using Flux-Core Arc Weld (FCAW) wire feed welding machines.
D. Shielded Metal Arc Weld (SMAW, or stick-electrode welding) shall not be used.
E. Keep distortion to a minimum:
1. Verify with measurements.
2. Utilize bracing where needed.
F. Follow procedures outlined in 48 13 13 – Turbine Repair.
3.05 WELD PROCEDURE REQUIREMENTS
A. Perform all welding in accordance with the codes specified below. Prequalified welding procedures are prohibited unless otherwise stated in this section.
B. ASTM A216 cast steel build-up:
1. Governing standards: ASTM A488 and ASME BPVC Section IX.
2. Qualification: Qualify WPS in accordance with ASME BPVC Section IX.
3. Per ASME BPVC Section IX Paragraph QW-424, it is permissible to use a readily available steel plate (not a casting) within the same P-number as the base metal to qualify the procedure.
C. ASTM A516 steel build-up:
1. Governing standards: AWS D1.1 or ASME BPVC Section IX.
2. Qualification: Prequalified WPSs are permitted for this scope.
D. Stainless steel cladding over A216:
1. Governing standard: ASME Section IX.
05 50 00 - 7
2. Qualification: Qualify WPS in accordance with ASME Section IX, Paragraph QW-214 (Corrosion-Resistant Weld Metal Overlay)
E. Stainless steel cladding over existing stainless steel cladding:
1. Governing standard: ASME Section IX.
2. Qualification: Qualify WPS in accordance with ASME Section IX, Paragraph
QW-214 (Corrosion-Resistant Weld Metal Overlay)
F. Discharge ring and stay vane repair:
1. Governing standard: AWS D1.1 or ASME BPVC Section IX, depending on material identification.
2. Qualification: if the base metal identified is a prequalified base metal per AWS
D1.1, a prequalified WPS per AWS D1.1 will be permitted for this scope, otherwise, qualification shall be in accordance with ASME BPVC Section IX.
3.06 WELDER PERFORMANCE QUALIFICATIONS
3.05A. Qualify welders in accordance with the governing code for their respective scope of work using procedures, materials, and equipment of the type required for the work.
3.063.07 GRINDING
A. Only in areas authorized for repair.
B. Use separate grinding wheels for mild steel and stainless steel to prevent metal contamination.
C. In accordance with tolerances outlined in 48 13 13 – Turbine Repair.
3.073.08 NON-DESTRUCTIVE EXAMINATION
A. Deleted.
B. Follow procedures outlined in 48 13 13 – Turbine Repair.
05 50 00 - 8
This page intentionally left blank.
Turbine Repair – (Revised)
48 13 13 - 1
SECTION 48 13 13
TURBINE REPAIR
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. G19 Welding Repair of Turbine Runner:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule A.
B. G19 Finish Grinding of Hydraulic Profile for Turbine Runner:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule A.
C. G19 Welding Repair of Turbine Stay Vanes:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule B.
D. G19 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule B.
E. G20 Welding Repair of Turbine Runner:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule C.
F. G20 Finish Grinding of Hydraulic Profile for Turbine Runner:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule C.
G. G20 Welding Repair of Turbine Stay Vanes:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule D.
H. G20 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule D.
48 13 13 - 2
I. G21 Welding Repair of Turbine Runner:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule E.
J. G21 Finish Grinding of Hydraulic Profile for Turbine Runner:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule E.
K. G21 Welding Repair of Turbine Stay Vanes:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule F.
L. G21 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule F.
M. G22 Welding Repair of Turbine Runner:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule G.
N. G22 Finish Grinding of Hydraulic Profile for Turbine Runner:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule G.
O. G22 Welding Repair of Turbine Stay Vanes:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule H.
P. G22 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule H.
Q. G23 Welding Repair of Turbine Runner:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule I.
R. G23 Finish Grinding of Hydraulic Profile for Turbine Runner:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule I.
48 13 13 - 3
S. G23 Welding Repair of Turbine Stay Vanes:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule J.
T. G23 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes J:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule.
U. G24 Welding Repair of Turbine Runner:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule K.
V. G24 Finish Grinding of Hydraulic Profile for Turbine Runner:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule K.
W. G24 Welding Repair of Turbine Stay Vanes:
1. Measurement: weight of weld metal used.
2. Payment: price per pound bid in the Price Schedule L.
X. G24 Finish Grinding of Hydraulic Profile for Turbine Stay Vanes:
1. Measurement: square feet of grinding.
2. Payment: price per square foot bid in the Price Schedule L.
1.02 ACRONYMS
A. WPP – Grand Coulee Nathaniel ‘Nat’ Washington Power Plant, Washington Power Plant:
1. Formerly referred to as the Grand Coulee Third Power Plant, Third Power Plant.
B. CJP – Complete Joint Penetration
C. NDE – Non-Destructive Examination, also referred to as NDT – Non-Destructive Testing.
D. PT – Dye penetrate testing.
1.03 DEFINITIONS
A. Base metal – primary carbon steel metal used in construction of the turbine runner, discharge ring, and stay vanes.
48 13 13 - 4
B. Cladding metal – a layer of stainless steel metal over the base metal which enhances properties such as corrosion…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .