This is Amendment 0005 to Solicitation 140R1026B0003, issued by the Bureau of Reclamation, Pacific Northwest Region on August 6, 2026, with an effective date of July 1, 2026. The amendment incorporates two substantive changes to the original solicitation requirements.

The primary change includes the full text incorporation of FAR clause 52.228-1, Bid Guarantee, which requires bidders to submit a bid guarantee in the form of a firm commitment such as a bid bond, certified check, cashier's check, irrevocable letter of credit, or other acceptable instruments. The bid guarantee amount must equal 20 percent of the bid price or $3 million, whichever is less. The clause specifies that unsuccessful bidders will receive their bid guarantees returned promptly after bid opening, while the successful bidder's guarantee will be returned upon execution of contractual documents and required bonds. The clause further establishes that failure to execute contractual documents within 10 days of receipt may result in contract termination for default, with the bidder liable for any costs exceeding the bid amount, and the bid guarantee available to offset such differences. The secondary change notifies bidders that the bid opening date and time was previously changed in Amendment 0003 to August 13, 2026, at 0900 MDT. All other terms and conditions of the solicitation remain unchanged. Offerors must acknowledge receipt of this amendment prior to the bid opening date and time through completion of SF 30 items 8 and 15, or by separate letter or electronic communication referencing the solicitation and amendment numbers.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Lance Fleming

See continuation page

Bureau of Reclamation Pacific Northwest Region Regional Office Acquisition Management Division 1150 N. Curtis Road, Ste. 100 Boise ID 83706-1234

R10

140R1026B0003

08/06/2026

07/01/2026

1 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140R1026B0003/0005

The purpose of this amendment is for the following.

A. Due to surety inquiry, the Government is incorporating L.18. 52.228-1 Bid Guarantee in full text as follows:

Bid Guarantee (Sept 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under

Treasury Department regulations, certain bonds or notes of the United States. The Contracting

Officer will return bid guarantees, other than bid bonds-

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3 million, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of

Continued...

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140R1026B0003/0005 acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of clause)

B. Reminder that the Bid Opening date and time was changed in amendment 0003 to August 13, 2026, at 0900 MDT.

All other solicitation terms and conditions remain unchanged.

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .