This document is Amendment No. 0004 to a federal contract solicitation for the Hungry Horse Power Plant Turbine Runner Cavitation Repair project located in Montana's Columbia Pacific Northwest Interior Region 9, issued by the Bureau of Reclamation.

The solicitation establishes five price schedules (A through E) for repair work on four 105,000 HP Francis-type turbine runners (Units G1-G4) that have experienced cavitation damage. Schedule A includes G1 repairs with three line items: mobilization and preparatory work (lump sum), welding repair of turbine runner (250 pounds at unit price), finish grinding of hydraulic profile (20 square feet at unit price), and removal of turbine runner blade extensions (lump sum). Schedules B, C, and D follow identical structures for Units G2, G3, and G4 respectively, each priced per unit. Schedule E covers contract document management system services (lump sum, applicable to all units G1-G4). The amendment revises sections addressing submittals, contractor onsite safety personnel qualifications and responsibilities, metal fabrications welding procedures and standards, and turbine repair execution requirements. Key revisions include updated submittal forms (B-51 and B-52 for hydraulic profile grinding documentation), clarified material testing and weld procedure requirements per ASME BPVC Section IX and ASTM standards, and detailed specifications for repair procedures including crack remediation, surface finish tolerances (125 micro-inches, D/L ratio of 0.015 or less), and dye penetrant verification inspection by third-party inspectors. The contract requires comprehensive safety planning with onsite safety representatives and certified industrial hygienists, material chemical composition testing via spark atomic emission spectrometry, and submission of qualification records and inspection reports to a Contracting Officer Representative.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Signature Sheet / Certification of Technical Specifications

Project Title: Hungry Horse Power Plant Turbine Runner Cavitation Repair

Region: Columbia Pacific Northwest Interior Region 9

Technical Specifications Project Title: Hungry Horse Power Plant Turbine Runner Cavitation Repair

Digitally signed by STACEY

STACEY CARLSON CARLSON

Date: 2026.06.03 15:18:32 -06'00'

Digitally signed by DAVID DAVID CHRISTENSEN CHRISTENSEN

Date:

Technical Approval: Date: 2026.06.04 14:13:58 -06'00' Date:

1. The person signing the specifications package as “Prepared by” shall have developed or assembled the written specifications.

2. The person signing the specifications package for “Technical Approval” shall have been in responsible charge of the overall design including developing or assembling the specifications. This person will typically be the design team leader. In cases where the designs described by the specifications meet the criteria for preparation by a registered engineer or architect, this person shall be registered with the applicable professional designation after their signature, such as P.E. for professional engineer or R.A. for registered architect. By this signature, this person is certifying the written specifications convey the design intent as portrayed on the drawings included therein. For specifications package containing designs from multiple disciplines, it is the signing individual’s responsibility to ensure (using procedures defined by his/her organization) that the technical information prepared by other professions and disciplines and depicted in the document is compatible with the overall design intent and that the documents used to depict that information (e.g., drawings) include signatures with appropriate professional registration designations.

3. Revisions to designs after drawings and written specifications are originally signed will be reviewed by a design team representative (typically the design team leader). The review of written specifications revisions must be documented on a signature sheet included with the revised written specifications (see below).

AMD/MOD

No.

Technical Approval Signature:

Prepared By Signature:

Revised Sections:

Amend No 0004 00 00 50, 01 33 00, 01 35 30, 05 50 00, 48 13 13

Prepared by:

STACEY

CARLSON

Digitally signed by STACEY

CARLSON

Date: 2026.07.29 16:03:33 -06'00'

DAVID CHRISTENSEN Digitally signed by DAVID CHRISTENSEN Date: 2026.07.29 17:41:09 -06'00'

Hungry Horse Power Plant Turbine Runner Cavitation Repair Amendment No. 0004

Price Schedule – (Revised)

B - 1

CONTINUATION OF

SECTION B – SUPPLIES OR SERVICES AND COSTS

HUNGRY HORSE POWER PLANT

TURBINE RUNNER CAVITATION REPAIR

HUNGRY HORSE PROJECT, MONTANA

B.1 PRICE SCHEDULE

(a) Bids will be considered for award on the following Price Schedules, but no bid will be considered for award on only a part of a Price Schedule.

(b) Bids are subject to the terms and conditions of this solicitation.

(c) Quantities in the Price Schedule are estimated quantities for comparison of bids only.

Except as provided in the contract clause at Section H. Clause Title Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns.

(d) See the contract clause at WBR 1452.232-81 Alt III, Payment for Mobilization and Preparatory Work, for CLIN 1 of applicable Price Schedules.

(e) Definitions:

(1) CLIN – Contract Line Item Number

B - 2

PRICE SCHEDULE A

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

A-1 WBR

1452.232 -81

G1 Mobilization and Preparatory Work

For the lump sum of $

A-2 48 13 13 G1 Welding Repair of Turbine Runner

250 pounds $ $

A-3 48 13 13 G1 Finish Grinding of Hydraulic Profile for Turbine Runner

20 square feet

A-4 48 13 13 G1 Removal of Turbine Runner Blade Extensions

For the lump sum of $

TOTAL FOR PRICE SCHEDULE A $__________________

B - 3

PRICE SCHEDULE B

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

B-1 WBR

1452.232 -81

G2 Mobilization and Preparatory Work

For the lump sum of $

B-2 48 13 13 G2 Welding Repair of Turbine Runner

250 pounds $ $

B-3 48 13 13 G2 Finish Grinding of Hydraulic Profile for Turbine Runner

20 square feet

TOTAL FOR PRICE SCHEDULE B $__________________

B - 4

PRICE SCHEDULE C

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

C-1 WBR

1452.232 -81

G3 Mobilization and Preparatory Work

For the lump sum of $

C-2 48 13 13 G3 Welding Repair of Turbine Runner

250 pounds $ $

C-3 48 13 13 G3 Finish Grinding of Hydraulic Profile for Turbine Runner

20 square feet

TOTAL FOR PRICE SCHEDULE C $__________________

B - 5

PRICE SCHEDULE D

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

D-1 WBR

1452.232 -81

G4 Mobilization and Preparatory Work

For the lump sum of $

D-2 48 13 13 G4 Welding Repair of Turbine Runner

250 pounds $ $

D-3 48 13 13 G4 Finish Grinding of Hydraulic Profile for Turbine Runner

20 square feet

TOTAL FOR PRICE SCHEDULE D $__________________

B - 6

PRICE SCHEDULE E

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

E-1 01 31 30 G1-G4 Contract Document Management System

For the lump sum of $

TOTAL FOR PRICE SCHEDULE E $__________________

END OF SUPPLIES OR SERVICES AND COSTS

Submittals – (Revised)

01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices bid in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1-12 Decimal-inch Drawing Sheet Size and

Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS-14 United States National CAD Standards, Version 6

1.03 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

C. Submittal Types, as listed in Table 01 33 00A - List of Submittals:

1. A - Approval:

a. Government will respond as to adequacy of submittal.

b. Approval Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction.

2. I - Informational:

a. Government will acknowledge receipt of Informational submittals.

b. Government may reject an Informational submittal when the submittal does not satisfy contract requirements. Correct mistakes or deficiencies in rejected Informational submittals and resubmit.

c. Informational Submittals: Considered “shop drawings” within terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by Government is not required.

01 33 00 - 2

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement Units: US Customary Units.

4. Provide a unique transmittal number for each submittal.

C. Government Forms:

1. Fill in all requested data on forms electronically or by hand.

2. Handwritten data on forms shall be neat and legible.

3. Forms with handwritten data shall be scanned to create high-resolution electronic files.

4. Retain all forms with handwritten data and submit complete set of hardcopies at the completion of each task order.

5. Submit complete set of electronic files on a USB flash drive at the completion of each task order.

D. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

c. Mark items to be furnished in a manner that will photocopy (no highlighter).

d. Strike through items that do not apply.

E. Certifications:

1. Certifications by a Registered Professional: Signed and sealed by registered professional.

2. Manufacturer’s Certifications: Signed by authorized representative of manufacturer.

1.05 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

01 33 00 - 3

B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes listed items for RSNs with multiple parts.

C. Submit sets specified in “Sets to be sent:” columns in Table 01 33 00A - List of Submittals.

1. Submittals identified with “CDMS” in the “Sets to be sent” column shall be submitted electronically in accordance with Section 01 31 30 - Contract Document Management System.

D. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for each attached submittal.

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 7 days after receiving the comments, unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

F. More than one RSN may be submitted under a transmittal letter, provided responsible code is same.

1.06 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.

B. Time in Excess of Specified:

1. CO may extend contract completion date to allow additional time for completing work affected by excess review time.

a. Time extension will be to extent that excess review time caused delay to contract completion date.

01 33 00 - 4

b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.

2. No time extension will be allowed if Contractor fails to make complete approval submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to the extent that:

a. Approval was required under the contract, and.

b. Requests for approval were properly and timely submitted and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of clause at FAR

52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as term is used in that clause.

C. Return of Submittals:

1. Return of submittals will be by CDMS response or hard copy, as applicable.

2. Approval Submittals: 1 set of submittals required for approval will be returned either approved, approved with comments or not approved.

a. Revise and resubmit submittals not approved.

b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.

3. Informational Submittals: Government will acknowledge Informational submittals.

a. Informational submittals will not be returned when they satisfy contract requirements.

b. Informational submittals that do not satisfy contract requirements may be returned for resubmittal, or additional information may be requested.

1.07 HARD COPY TRANSMITTALS

A. Addresses for codes listed in Table 01 33 00A - List of Submittals:

1. Contracting Officer (CO), Bureau of Reclamation, Attn: CPN-7300, 1150 N.

Curtis Rd, Boise, ID 83706-1234.

2. Construction Field Manager (COR), Bureau of Reclamation:

a. Request address after task order award.

B. Send original transmittal letter with appropriate number of sets to office listed in “Responsible Code” column in Table 01 33 00A - List of Submittals.

01 33 00 - 5

C. Send copy of transmittal letter with appropriate number of sets to offices that are not responsible code, but show “Sets to be sent” in Table 01 33 00A - List of Submittals.

D. When “Sets to be sent” is 0, send a copy of transmittal letter to that office.

E. Submittals required by specifications, but not listed in Table 01 33 00A - List of Submittals:

1. Submit in accordance with this section.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

01 33 00 - 6

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and CDMS indicates Contract Document Management System.

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Type

CP

Respon-sible code

Sets to be sent: ***

CO COR

I-1 Release of Claims (1452.204-70)

Release of claims (DI-137) against the United States

Submitted after completion of work and prior to final payment

I CO

1 0

I-2 Payrolls and Basic Records (52.222-8)

Certified payrolls Submitted weekly for each week any contract work is performed

I COR CDMS

I-3 Subcontracts (Labor Standards) (52.222-11)

1) List of subcontractors

2) Statement and Acknowledgement Form (SF-1413) for each subcontract

Submitted within 14 days after task order award, and within 14 days after any subcontract award

I COR 1 0

I-4 Equal Opportunity (52.222-26)

Information required by Executive Order

11246 (SF-100)

Submitted within 28 days following task order award

I COR 1 0

I-5 Bonds (52.228-15)

Performance and payment bonds

Submitted and approved within 10 calendar days after task order award

A CO 1 0

I-6 Liability Insurance (1452.228-70)

Acceptable evidence showing that insurance has been obtained

Submitted and approved within 10 calendar days after task order award

A CO 1 0

I-7 Security Requirements

(WBR

1452.237-80)

Security Program Submitted and approved within 7 days after the task order work starts or another period approved by the Contracting Officer

A COR CDMS

I-8 Security Requirements

(WBR

1452.237-80)

List of onsite employees

Submitted within 7 days after the task order work starts or another period determined by the Contracting Officer

I COR CDMS

01 31 19-1 Project Management and Coordination

Pre-Work Meeting Agenda

Submitted and approved at least 35 days before each mobilization

A Y COR CDMS

01 31 19-2 Project Management and Coordination

Progress Review Meeting Agenda

Submitted at least 2 days before the meeting

I COR CDMS

01 33 00 - 7

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and CDMS indicates Contract Document Management System.

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Respon-sible code

Sets to be sent: ***

CO COR

01 31 19-3 Project Management and Coordination

Progress Review Meeting Minutes

Submitted within 24 hours after the meeting

I COR CDMS

01 31 30-1 Contract Document Management System

Approval Data Submitted and approved within 28 days after task order NTP

A COR 0 1

01 31 30-2 Contract Document Management System

Final Data Submitted and approved within 28 days of completion of work

A COR CDMS

01 32 10-1 Construction Program

Representative Information

Submitted and approved within 7 days after task order NTP

A COR 0 1

01 32 10-2 Construction Program

Baseline Schedule Submitted and approved within 28 days after task order NTP

A Y COR CDMS

01 32 10-3 Construction Program

Updated Schedule Reports

Submitted and approved monthly, with progress payments, and within 14 days after award of a task order

01 32 10-4 Construction Program

Time Impact Analysis

Submitted and approved within 28 days after the CO directs a contract change with schedule impacts

Or

With proposal for future modification, value engineering proposal, or request or claim for equitable adjustment to the contract when time is requested

A COR CDMS

01 35 20-1 Safety and Health

Safety Program Submitted and approved within 28 days after task order NTP

01 33 00 - 8

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and CDMS indicates Contract Document Management System.

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Respon-sible code

Sets to be sent: ***

CO COR

01 35 20-2 Safety and Health

Job Hazard Analysis List

Submitted and approved within 28 days after task order NTP

A COR CDMS

01 35 20-3 Safety and Health

Monthly Accident Summary Report

Submitted within 28 days of the start of onsite work and monthly thereafter

I COR CDMS

01 35 20-4 Safety and Health

Documentation and Records

Submitted at least 28 days before start of onsite work

I COR CDMS

01 35 30-1 Contractor’s Onsite Safety Personnel

Qualifications Submitted and approved at least 28 days before start of onsite work

A COR CDMS

01 35 30-2 Contractor’s Onsite Safety Personnel

Safety Inspection Reports

Submitted within 7 days after inspection

I COR CDMS

01 35 30-3 Contractor’s Onsite Safety Personnel

CIH Reports Submitted within 7 days after inspection

I COR CDMS

01 46 00-1 Quality Procedures

Contractor Quality Control Plan

Submitted and approved at least 28 days before start of onsite work

A COR CDMS

01 46 00-2 Quality Procedures

Contractor’s Daily Reports

Submitted within the following workday

I COR CDMS

01 54 20-1 Use of Government Crane

Use of Crane Request

Submitted and approved at least 4 days before crane is used

A COR CDMS

01 54 23-1 Temporary Scaffolding and Platforms

Scaffolding Approval Data

Submitted and approved at least 28 days before starting scaffolding erection

A Y COR CDMS

01 64 40-1 Government- Furnished Equipment

Shortage Report Submitted within 24 hours after joint inspection

A COR CDMS

01 64 40-2 Government- Furnished Equipment

Acceptance of Draft Tube Platform Installation

Submitted within 3 days after inspection

I COR CDMS

01 74 00-1 Cleaning and Waste Management

Waste Production and Disposal Plan

Submitted and approved at least 28 days before starting onsite work

01 33 00 - 9

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and CDMS indicates Contract Document Management System.

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Respon-sible code

Sets to be sent: ***

CO COR

01 74 00-2 Cleaning and Waste Management

Waste Production and Disposal Records

Submitted within 7 days of waste disposal

I COR CDMS

01 74 00-3 Cleaning and Waste Management

Environmental Consultant Resume

Submitted and approved at least 35 days before beginning site assessment

A COR CDMS

01 74 00-4 Cleaning and Waste Management

Final Inspection of Hungry Horse Cavitation Repair

Submitted within 3 days after inspection

A COR CDMS

05 50 00-1 Metal Fabrications

Weld Procedure Specifications

Submitted and approved at least 28 days before start of weld repairs

A Y COR CDMS

05 50 00-2 Metal Fabrications

Weld Material Certifications

Submitted and approved at least 28 days before start of weld repairs

A COR CDMS

05 50 00-3 Metal Fabrications

Qualification Records

Submitted and approved at least 28 days before start of weld repairs

A Y COR CDMS

05 50 00-4 Metal Fabrications

Material Test Reports

Submitted within 7 days of performing testing

I COR CDMS

48 13 13-1 Turbine Repair Secondary Assessment – Runner

Submitted within 24 hours after discovery of damage

A COR CDMS

48 13 13-2 Turbine Repair Verification Inspection Report

Submitted within 7 days after passing inspection

A COR CDMS

END OF SECTION

Contractor’s Onsite Safety Personnel – (Revised)

01 35 30 - 1

SECTION 01 35 30

CONTRACTOR’S ONSITE SAFETY PERSONNEL

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices bid in the Price Schedules for other items of work.

1.02 DEFINITIONS

A. ABIH: American Board of Industrial Hygiene.

1.03 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards, including revisions posted at https://www.usbr.gov/safety/rshs/index.html

B. Code of Federal Regulations (CFR)

1. 29 CFR Part 1926.32 Definitions

1.04 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 30-1, Qualifications:

1. Contractor’s Onsite Safety Representative.

2. Part-time Onsite Safety and Health Professional.

3. Certified Industrial Hygienist (CIH).

a. Copy of current ABIH certificate.

4. Competent Person.

5. Independent testing laboratory:

a. NLLAP laboratory accreditation number.

b. NVLAP laboratory accreditation number.

c. Name, address, and telephone number.

C. RSN 01 35 30-2, Safety Inspection Reports:

01 35 30 - 2

1. Prepare detailed weekly safety inspection reports listing noted deficiencies, digital photos, abatement dates and follow-up action for all jobsite activities.

2. Inspection report shall include findings of jobsite walk-through with Government representative.

D. 01 35 30-3, CIH Reports:

1. Detailed monthly summary report for coatings related activities:

a. Summary of exposure monitoring results and sampling activities and interpretation of the data to confirm that the work is being performed in accordance with the approved plans.

2. Detailed monthly summary report for any hazardous agents related to work activities.

a. Summary of exposure monitoring results and sampling activities and interpretation of the data to confirm the work is being performed in accordance with the submitted approval plans.

3. Include noted deficiencies, digital photos, abatement dates and follow-up action.

4. Submit written report to COR within 7 days of the inspection.

1.05 QUALIFICATIONS

A. Contractor’s Onsite Safety Representative:

1. Competent supervisory employee with current safety and health related training, experience and duties on at least three projects of similar nature, size, complexity, and work to be performed as the current project

2. OSHA Construction 30-Hour Training Course including applicable elective subjects, for example Confined Space Entry; Cranes, Derricks, Hoists, Elevators, and Conveyors; Ergonomics; Excavations; Fire Protection and Prevention;

Materials Handling, Storage, Use and Disposal; Rollover Protective Structures and Overhead Protection; and Signs; Signals and Barricades; Powered Industrial Vehicles; Safety and Health Programs; Scaffolds; Tools - Hand and Power;

Welding and Cutting. Current first aid CPR certification.

3. Include resume with current telephone numbers of references, description of safety representative responsibilities, and copies of training certifications.

B. Contractor’s Part-time Onsite Safety and Health Professional:

1. The Contractor shall identify a part-time Safety and Health Professional that is acceptable to Reclamation. The safety professional shall visit the site a minimum of one time per week.

2. Include resume with current telephone numbers of references, description of safety professional responsibilities on similar construction projects, and copies of training certifications and registration.

01 35 30 - 3

3. The individual shall be qualified by virtue of education, training, certification, and experience in which professional status in the construction safety field has been established.

4. Meeting the requirements training and experience requirements of Article 1.05A and:

a. Possessing at least a 4-year Bachelor’s Degree from an accredited college or university in:

1) Safety Engineering.

2) Safety and Occupational Health.

b. Knowledgeable of current safety trends, industry practices, and can exercise technical expertise.

C. Certified Industrial Hygienist (CIH):

1. The Contractor shall identify an individual meeting the following requirements:

a. Certified by the American Board of Industrial Hygiene.

b. Trained in recognizing complex safety, occupational health, and environmental issues.

c. Knowledgeable of current safety trends, industry practices, and can exercise technical expertise.

d. Demonstrates professional level knowledge of exposure hazards associated with the specific construction activities and can provide best practices on mitigation and/or controls.

2. Include resume, description of CIH responsibilities on similar construction projects and copies of training certifications of the individual proposed as the onsite CIH.

3. For hazardous Materials work, CIH shall be independent from the Contractor.

D. Competent Person:

1. As defined in 29 CFR 1926.32.

2. Authority to take prompt corrective measures to eliminate hazards.

3. Duties can be performed by CIH, if qualified.

1.06 APPLICATION

A. Designate an employee as the Contractor’s Onsite Safety Representative prior to start of construction, and employ Safety Professional for part-time on the job.

1. Safety Professional requirements may be met by retaining appropriate level of services of an acceptable safety consultant.

B. Contractor’s Onsite Safety Representative Authorities, Duties, and Responsibilities:

01 35 30 - 4

1. Responsible for effectively implementing the Contractor’s Safety Program.

2. The Safety Representative shall coordinate all emergency response activities.

3. Recommend controls for observed hazards or predicted hazards.

4. Full authorization to correct unsafe acts on the spot, including the authority to stop work to correct safety and health problems.

5. Lead weekly safety meetings at the jobsite.

6. Onsite, during any and all construction activities.

7. Assemble, review, and sign each Job Hazard Analysis (JHA).

a. Review of JHA with employees.

8. Verify the correct use of respiratory protection and personal protective equipment.

9. Conduct and prepare weekly safety inspections in conjunction with the onsite government representative listing noted deficiencies, their abatement dates, follow up action. The report shall be available for review onsite.

10. Provide direct oversight and assemble a detailed report of all incident reviews, near-misses, accidents, and emergency response or rescue actions.

11. The Onsite Safety Representative may have other non-safety duties.

C. Contractor’s Part-time Onsite Safety and Health Professional Authorities, Duties, and Responsibilities

1. The Onsite Safety and Health Professional’s job shall be hazard recognition, control and accident prevention.

2. Shall NOT be supervised by the onsite superintendent, but shall report directly to the corporate manager/owner.

3. Provide guidance and oversite to Contractor’s Onsite Safety Representative.

4. Shall have full authorization to correct unsafe acts on the spot, including the authority to stop work to correct safety and health problems.

5. Shall visit the site weekly and inspect the site with a Government representative listing noted deficiencies, their abatement dates, and follow up action. The report shall be available for review onsite.

6. Shall participate in the planning and preparation of all activities including but not limited to:

a. Development and approval of JHA.

b. Review of equipment and materials.

c. Employee training.

d. Observing and reporting on activities.

7. Shall participate in the planning, preparation and execution of high exposure activities.

01 35 30 - 5

8. Duties include, but are not limited to the following:

a. Before start of construction, identify existing and predictable unsanitary, hazardous, or dangerous conditions.

b. Approve the site-specific Contractor safety and health plans and program prior to submission.

c. Coordinating all elements contained in the Contractor safety and health program and these specifications, including safety training.

d. May act as the qualified person for designing fall protection, excavation and scaffolding systems in accordance with the regulatory standards.

e. Assemble, review and sign each Job Hazard Analysis (JHA).

f. Review and finalize all incident reviews, near-misses and accident reports in accordance with RSHS.

g. Conduct, prepare, and submit weekly safety inspections in conjunction with the onsite government representative listing noted deficiencies, their abatement dates, and follow up action. The report shall be available for review onsite.

h. Attend the Safety Program Review Meeting and Conduct the monthly Joint Safety Policy Meetings in accordance with the RSHS Section 3.

D. Certified Industrial Hygienist (CIH) Duties:

1. CIH duties include, but are not limited to:

a. Establish work place exposure assessments in accordance with federal, state, and local regulations and standard industrial hygiene practices to ensure personnel exposures are below regulated levels.

b. Review and sign the Written Compliance Program for Worker Protection, Containment System Plan, Emissions Monitoring Plan, Waste Characterization, Handling, and Disposal Plan, Heavy Metal Exposure Certifications and Test Results, Working Level Test Results, Post- Construction Test Results, and Certificate of disposal.

c. Conduct and/or coordinate and review and sign all coatings background sampling, surface sampling, waste stream sampling, personal exposure monitoring, area air monitoring, peripheral air monitoring, and clean up monitoring.

d. Visit the site during start-up of coating removal activities, and thereafter when necessary, to evaluate the extent of coating removal required in areas adjacent to repairs where existing coatings may produce particulates from grinding, or emissions from the high heat of air carbon arc gouging and welding; and to confirm that the work is being performed in accordance with the submitted plans.

e. Conduct functional testing of engineering controls, critical barriers, containments and secondary containments.

01 35 30 - 6

f. Full authorization to correct unsafe acts, stop work, prevent exposures, control contamination, engineering controls and containment failures.

g. Exposure assessments to select or verify personal protective equipment or respiratory protection inside and outside containments.

h. Submit detailed monthly CIH inspection reports in accordance with RSN 01 35 30-3.

i. Attend the Safety Program Review Meeting in accordance with the RSHS Section 3.

j. Assist Onsite Supervisor in implementing Hazardous Materials safety and health requirements during the performance of the required work.

k. Available for emergencies.

l. MAP Contractor/ Supervisor training.

m. Direct air monitoring.

E. Competent Person:

1. Duties include, but are not limited to:

a. Control entry to and from the Regulated Area.

b. Ensure engineering controls in use are in proper operating condition and are functioning properly.

c. Assure employees wear appropriate PPE, are trained in the use of appropriate methods for exposure control, use proper hygiene methods and decontamination procedures.

d. Supervise employee exposure monitoring required by 29 CFR 1926.1101.

1.07 QUALITY ASSURANCE

A. Contractor’s Onsite Safety Representative:

1. The effectiveness of the Contractor’s Onsite Safety Representative in prosecuting the safety program will be subject to continued review and approval by the COR.

2. Should the Contractor’s onsite safety representative’s effort be deemed insufficient the Contractor may be required to provide the services of a qualified, full-time safety and health professional at no additional cost to the Government.

B. Contractor’s Part-time Onsite Safety and Health Professional:

1. The effectiveness of the Contractor’s Onsite Safety Professional in prosecuting the safety program will be subject to continued review and approval by the COR.

2. Should the Contractor’s part-time safety professional effort be deemed insufficient the Contractor may be required to provide the services of a qualified, full-time Safety and Health Professional at no additional cost to the Government.

01 35 30 - 7

C. Certified Industrial Hygienist (CIH):

1. The effectiveness of the Contractor’s Onsite CIH in prosecuting the coatings related activities will be subject to continued review and approval by the COR.

2. Should the Contractor’s CIH effort be deemed insufficient the Contractor may be required to provide the services of a qualified, full-time CIH during coatings related activities at no additional cost to the Government.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Metal Fabrications – (Revised)

05 50 00 - 1

SECTION 05 50 00

METAL FABRICATIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include cost in applicable prices bid in the Price Schedules for which welding is required.

1.02 ACRONYMS

A. Carbon equivalent: empirical value used to predict the weldability of a steel based on its chemical composition. Calculated as:

B.A. Carbon equivalent: empirical value used to predict the weldability of a steel based on its chemical composition. Calculated as:

C.B. WPS – Weld Procedure Specification.

D.C. NDE – Non-Destructive Examination, also referred to as NDT – Non-Destructive Testing.

D. PQR – Procedure Qualification Record.

E. WPQ/WPQR – Welder Performance Qualification Record.

1.03 DEFINITIONS

A. Miscellaneous metalwork: Where specified elsewhere in these specifications or this Section, “miscellaneous metalwork” means metal fabrications and metal repair as used in this Section.

B. Verification Inspector: This inspector is the duly designated person who acts for, and in behalf of, the Owner on all inspection and quality matters within the scope of the contract

05 50 00 - 2 documents. This is a 3rd party inspector hired by the Contractor to provide independent inspection.

C. Contractor’s Inspector: This inspector is the duly designated person who acts for, and in behalf of, the Contractor on all inspection and quality matters within the scope of the contract documents.

1.04 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1.041. ASME BPVC Section IX 2025 Boiler and Pressure Vessel Code –

Section IX. Qualification Standard for Welding, Brazing, and Fusing Procedures;

Welders; Brazers; and Welding, Brazing, and Fusing Operators

B. American Welding Society, Inc. (AWS) A.1. AWS QC1 AWS Certification of Welding Inspectors

1.2. Deleted

2.3. Deleted

C. ASTM International (ASTM)

1. ASTM A216/216M-26 Steel Casting, Carbon, Suitable for Fusion

Welding, for High-Temperature Service

2. ASTM A488/A488M-24 Steel Castings, Welding, Qualifications of

Procedures and Personnel

3. ASTM A751-25 Chemical Analysis of Steel Products B.4. ASTM E415-21 Analysis of Carbon and Low-Alloy Steel by

Spark Atomic Emission Spectrometry

1.05 SUBMITTALS

A. RSN 05 50 00 – 1, Weld Procedure Specifications, including:

1. WPSs for each type of weld.

A.2. PQRs.

B. RSN 05 50 00 – 2, Weld Material Certifications.

C. RSN 05 50 00 – 3, Qualification Records:

1. Welder performing repairs:

a. Name.

05 50 00 - 3

b. WPQ/WPQRs, including active continuity logs demonstrating that each proposed welder is certified for the specific process, position, thickness, and filler metal classification required by the subject WPSs.

2. Weld inspectors performing inspections:

a. Verification Inspector:

1) Name.

2) Company name.

3) Certifications.

b. Contractor’s Inspector:

1) Name.

2) Certification.

D. RSN 05 50 00 – 4, Material Test Reports, including:

1. Test reports for all materials tested.

2)2. Percentages of carbon, manganese, and other metals sufficient to calculate the carbon equivalent.

1.06 QUALIFICATIONS

A. Verification Inspector:

1. Current certification as an AWS Certified Welding Inspector in conformance with the requirements of AWS QC1, Standard for AWS Certification of Welding Inspectors.

2. NDT Level II.

B. Contractor’s Inspector:

1. Holds, or has held within the past 5 years, current certification as an AWS

Certified Welding Inspector in conformance with the requirements of AWS

QC1.

1.07 DELIVERY, STORAGE, AND HANDLING

A. Protect from corrosion, deformation, and other types of damage.

B. Store items in an enclosed area free from contact with soil and weather.

C. Remove and replace damaged items with new items.

1.08 EXISTING BASE METALS

A. Units G1-G4:

05 50 00 - 4

C.1. Runner assembly: cast steel, per Federal Specification QQ-S-681b, Class 2 Medium, Annealed.

PART 2 PRODUCTS

2.01 MATERIALS

A. All welding filler metals, electrodes, flux, and shielding gases shall comply with the applicable welding code specified in Part 3 for the respective weld type and base metal combination.

2.01B. Use filler metal with a minimum tensile strength meeting or exceeding the minimum tensile strength of the base metal.

PART 3 EXECUTION

3.01 MATERIAL TESTING

A. On each runner assembly, prior to performing welding, take at least 1 specimen of base metal and perform chemical composition testing.

B. Chemical Composition Testing:

1. Perform quantitative chemical analysis in accordance with ASTM A751.

2. Utilize Spark Atomic Emission Spectrometry per ASTM E415. The size and characteristics of the test specimen shall be per E415. The testing shall be sufficient to calculate the carbon equivalent.

C. Test Specimen Extraction:

1. The physical location on the turbine from which test specimens will be extracted shall be subject to the approval of the COR.

2. Extract specimens from low-stress, non-critical areas of the component.

3. Avoid zones of existing cavitation damage or heat-affected zones from prior repair.

PART 34. Repair extraction areas in accordance with Section 48 13 13 – Turbine

Repair.

3.013.02 REMOVING METAL

A. Only in areas authorized for repair.

B. Acceptable metal excavation methods:

1. Air carbon arc gouging followed by power-tool grinding to sound, bright metal.

2. Grinding to sound, bright metal.

05 50 00 - 5

3. Follow procedures outlined in 48 13 13 – Turbine Repair.

3.023.03 WELDING

A. Only in areas authorized for repair.

B. Deleted

C. All weld metal shall be deposited using Flux-Core Arc Weld (FCAW) wire feed welding machines.

D. Shielded Metal Arc Weld (SMAW, or stick-electrode welding) shall not be used.

E. Keep distortion to a minimum:

1. Verify with measurements.

2. Utilize bracing where needed.

F. Follow procedures outlined in 48 13 13 – Turbine Repair.

3.04 WELD PROCEDURE REQUIREMENTS

A. Perform all welding in accordance with the codes specified below.

B. Base metal of the existing runner assembly shall be considered equivalent to ASTM A216, Grade WCC.

C. Runner assembly cast steel build-up:

1. Governing standards: ASTM A488 and ASME BPVC Section IX.

2. Qualification: Qualify WPS in accordance with ASME BPVC Section IX.

D. Stainless steel cladding over runner assembly:

1. Governing standard: ASME Section IX.

2. Qualification: Qualify WPS in accordance with ASME Section IX, Paragraph

QW-214 (Corrosion-Resistant Weld Metal Overlay)

3.05 WELDER PERFORMANCE QUALIFICATIONS

F.A. Qualify welders in accordance with the governing code for their respective scope of work using procedures, materials, and equipment of the type required for the work.

3.033.06 GRINDING

A. Only in areas authorized for repair.

B. Use separate grinding wheels for carbon steel and stainless steel to prevent metal contamination.

05 50 00 - 6

C. In accordance with tolerances outlined in 48 13 13 – Turbine Repair.

3.043.07 NON-DESTRUCTIVE EXAMINATION

A. Perform NDE in accordance with applicable standards. Deleted

B. Follow procedures outlined in 48 13 13 – Turbine Repair.

Turbine Repair – (Revised)

48 13 13 - 1

SECTION 48 13 13

TURBINE REPAIR

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. G1 Welding Repair of Turbine Runner:

1. Measurement: weight of weld metal used.

2. Payment: price per pound bid in the Price Schedule A.

B. G1 Finish Grinding of Hydraulic Profile for Turbine Runner:

1. Measurement: square feet of grinding.

2. Payment: price per square foot bid in the Price Schedule A.

C. G1 Removal of Turbine Runner Blade Extensions:

1. Payment: lump sum price bid in the Price Schedule A.

D. G2 Welding Repair of Turbine Runner:

1. Measurement: weight of weld metal used.

2. Payment: price per pound bid in the Price Schedule B.

E. G2 Finish Grinding of Hydraulic Profile for Turbine Runner:

1. Measurement: square feet of grinding.

2. Payment: price per square foot bid in the Price Schedule B.

F. G3 Welding Repair of Turbine Runner:

1. Measurement: weight of weld metal used.

2. Payment: price per pound bid in the Price Schedule C.

G. G3 Finish Grinding of Hydraulic Profile for Turbine Runner:

1. Measurement: square feet of grinding.

2. Payment: price per square foot bid in the Price Schedule C.

H. G4 Welding Repair of Turbine Runner:

1. Measurement: weight of weld metal used.

2. Payment: price per pound bid in the Price Schedule D.

I. G4 Finish Grinding of Hydraulic Profile for Turbine Runner:

48 13 13 - 2

1. Measurement: square foot of grinding.

2. Payment: price per square foot bid in the Price Schedule D.

1.02 ACRONYMS

A. HH – Hungry Horse dam and power plant.

B. NDE – Non-Destructive Examination, also referred to as NDT – Non-Destructive Testing.

C. PT – Dye penetrate testing.

1.03 DEFINITIONS

A. Base metal – primary carbon steel metal used in construction of the turbine runner.

B. Cladding metal – a layer of stainless steel metal over the base metal which enhances properties such as corrosion resistance and wear resistance, also referred to as overlay.

C. Hydraulic turbine or turbine – mechanical device that converts the potential energy of flowing water into mechanical energy, includes both stationary and rotating components.

D. Turbine runner or runner – rotating component of the hydraulic turbine that is a welded assembly consisting of a crown, band, blades, and cone.

E. Initial assessment – documentation of zones requiring repair, prepared by Government.

F. Secondary assessment – documentation of zones requiring repair, prepared by Contractor.

1.04 REFERENCE STANDARDS

A. United States Bureau of Reclamation (USBR, Reclamation):

1. RSHS Reclamation Safety and Health Standards http://www.usbr.gov/safety/rshs/index.html

2. FIST Vol. 1-1 Facilities Instructions, Standards, and Techniques:

Volume 1-1 Hazardous Energy Control Program http://www.usbr.gov/power//data/fist/fist1_1/FIST_ 1-1.pdf

3. FIST Vol. 2-5 Facilities Instructions, Standards, and Techniques:

Volume 2-5 Turbine Repair http://www.usbr.gov/power/data/fist/fist2_5/vol2- 5.pdf

B. Hungry Horse Field Office (HHFO):

1. F-HECP Facility Hazardous Energy Control Program

(Onsite copy provided by Government)

48 13 13 - 3

1.05 SUBMITTALS

A. RSN 48 13 13 – 1, Secondary Assessment – Runner:

1. Submitted according to an on-going basis when damage is discovered.

2. Use Form B-1 to summarize all runner damage.

3. Use Form B-2 to document runner damage.

4. Use Form B-51 to summarize all runner hydraulic profile grinding.

4.5. Use Form B-52 to document runner hydraulic profile grinding.

B. RSN 48 13 13 – 2, Verification Inspection Report.

1.06 EXISTING CONDITIONS

A. There are four hydro-electric generating units in the HH Power Plant, called G1 through G4.

B. Turbine Runner:

1. Units G1 through G4 are equipped with 105,000 HP Francis-type turbine runners, designed and manufactured by Allis-Chalmers, Milwaukee, WI. The runner throat diameter is 126 inches.

2. Each runner contains 15 blades, also referred to as “buckets” or “vanes”.

3. The runners have been in service since 1950, and each runner has had cavitation damage repaired on multiple contracts. Each contract has had different work crews and time-limited scope of work resulting in different conditions for each runner.

4. Most of the runner is carbon steel, but a significant amount of stainless steel exists from previous repair areas:

a. Base metal of the runner assembly is cast steel conforming to Federal

Specifications QQ-S-681b, Class 2 Medium, Annealed. Copy of historical specification is made a part of Section L – Attachments.

5. Runner material will be tested in accordance with 05 50 00 – Metal Fabrications for each unit to verify material type for information.

6. Previously applied protective coatings on runners may contain regulated metals.

Other contaminants may be present.

7. On units G1 through G4, runner damage is mostly observed as cavitation-enhanced corrosion in the crown area and on the face of the blades. This corrosion has been characterized as severe surface pitting with a porous appearance reminiscent of some kinds of cheese. The leading edge of most of the blades exhibit corrosion erosion. Although these units are not known for having cracks in the blades, some cracks have been previously found. Several of the units have already been clad with stainless steel in the most troublesome areas.

48 13 13 - 4

8. On unit G1 a trailing edge extension was added to each of the 15 blades in a trial attempt to mitigate cavitation damage. See section 51 00 00 – Information Available to Bidders.

9. The work area of the turbine runner is accessible through two large doors in the draft tube:

a. Draft tube doors are accessed from Floor 1 at El. 3070.50.

b. Access opening dimensions:

1) Door opening dimensions are 23.5 inches wide by 29.5 inches high.

2) After installation of the draft tube work platform, the access opening dimensions are 23.5 inches wide by 20 inches high.

10. Main access to the power plant is from ground level Floor 4 at El. 3113.50.

1.07 AMBIENT CONDITIONS

A. Each of the subject units consisting of the generator and turbine is entirely indoors, where the ambient temperature ranges from 60 degrees Fahrenheit to 80 degrees Fahrenheit.

1.08 COORDINATION

A. Coordinate with COR to finalize scope of repairs based on Government’s initial assessment and Contractor’s secondary assessments.

1.09 SEQUENCING

A. Work will follow the following sequence:

1. Government physically marks zones to receive repairs, and issues initial assessment form designating zones requiring repair, including:

a. High and Low priority designations.

b. Defect Group Number:

1) Defect Group numbered 1 shall be repaired first, followed sequentially by other defect groups.

2. Contractor reviews markings and initial assessment report.

3. Contractor holds a pre-work coordination meeting with the COR, to facilitate understanding between Contractor and Government of overall condition of runner. Contractor describes the anticipated effort associated with repairing high-and low-priority zones, and potential problems.

4. COR authorizes work on specific zones.

5. If, during surface preparation and repair activities, additional repair is identified, prepare a secondary assessment form documenting the needed repair.

48 13 13 - 5

6. Prior to performing repair work on newly identified zones, hold an additional pre-work coordination meeting with the COR to describe the newly needed repair and anticipated effort to repair.

7. Depending on the nature of needed repair and current activities, the Government may authorize additional work after designating high and low priority, and assigning a Defect Group Number.

8. Contractor performs repairs on authorized additional work.

1.10 PRE-WORK COORDINATION MEETINGS

A. Prior to performing turbine repair, meet with Government Representative.

B. Coordinate time and place of meeting with Government Representative at least 2 days before meeting.

C. Contractor attendees shall be at least the following:

1. Contractor onsite supervisor.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 EXAMINATION

A. Review the damaged repair zones which the Government physically outlined with paint-stick, marker, chalk or other means. Cease work and notify COR if outlines or markings are unclear.

B. Review the Government’s initial assessment form. Cease work and notify COR if information provided in the Government’s initial assessment form is unclear or does not match visible conditions.

C. Continuously inspect surfaces for additional needed repair which may become visible during all stages of repair work. Needed repair includes defects such as:

1. Indications.

2. Cracks.

3. Porosity.

4. Lamination.

5. Centerline shrinkage.

6. Other apparent discontinuities.

48 13 13 - 6

3.02 SECONDARY ASSESSMENTS

A. When additional needed repair is observed, prepare a secondary assessment form which documents the observed needed repair:

1. For “other” describe defect type in the field provided on the form.

B. Use Government forms:

1. Forms listed below are made a part of Section J - Attachments:

a. B-1, Unit Summary of Runner Damage Records.

b. B-2, Runner Damage Record.

c. B-51, Unit Summary of Runner Hydraulic Profile Grinding Records.

c.d. B-52, Runner Hydraulic Profile Grinding Record.

3.03 TURBINE REPAIR

A. Restore all areas, which have been authorized for repair, to like new condition.

3.04 GEOMETRY OF REPAIRED AREAS

A. When original component dimensional data is available, match original dimensions.

B. When original component profile templates are available, match original profiles.

C. Make repairs smooth and continuous through the repaired area, so that repaired areas match existing hydraulic profile and contour.

1. Confirm that repairs do not violate hydraulic contour from its initial condition by utilizing a flexible spline as described in FIST 2-5 and as depicted in Figure 4-12 of FIST 2-5.

2. Confirm that repairs do not create sharp features and leading edges that do not match the original design.

D. Do not alter a blade shape to make it substantively different from the other blades in the runner.

3.05 REPAIRS IN BASE METAL

A. Only in areas authorized for repair.

B. Remove metal and weld in accordance with Section 05 50 00 – Metal Fabrications.

C. Runner:

1. Metal removal procedure:

a. Remove metal to a consistent depth for each Defect Group Number.

48 13 13 - 7

b. Remove metal to a depth of 1/16 inch beyond the deepest damage for each Damage Area Number.

c. Remove metal to create a definite 90-degree edge recess at the boundary line. This feature will prevent grinding newly deposited stainless steel to a “feather” edge at a boundary line.

d. Remove metal with a minimum radius of 1/16 inch at the bottom of the recess. This feature will reduce potential stress concentrations in the corner of the recess.

e. Check the bottom of excavations for the presence of stainless steel metal:

1) Use copper sulfate to check.

2) Remove stainless steel metal.

2. Metal build-up procedure:

a. Depositing carbon steel filler metal over stainless steel is not permitted.

Recheck the…