01_14_30_Interruption_of_Service_0002.pdf
PDF 244 KB Posted
- Attached to
- Upper Snake River Field Office HVAC Renovation Pro Federal contract opportunity
- Solicitation number
- 140R1024R0009
About this file
This document is an Interruption of Service request related to the Upper Snake River Field Office HVAC Renovation Project, Solicitation No. 140R1024R0009.
The key details are:
- The contractor must coordinate and schedule any interruption of services with the Contracting Officer's Representative (COR). The COR must have reasonable assurance that required materials and equipment will be onsite, and the contractor must be prepared to perform the work during the requested interruption period.
- Allowable interruption of service periods are constrained - heating systems must be operational from November 1 to March 31, and cooling systems from May 15 to September 20. Temporary heating or cooling is required if an HVAC system is offline outside these dates.
- The contractor must submit an Interruption of Service Request detailing the work area, procedures, safety precautions, timing, personnel, and equipment. Interruptions over 4 hours must be included in the construction schedule.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R1024R0009_Amd_0002.pdf | ||
| Contractor_Questions_Responses_0002.pdf | ||
| Site_Visit_Sign-In_sheet_Redacted_0001.pdf | ||
| Sol_140R1024R0009_Amd_0001.pdf | ||
| Sol_140R1024R0009.pdf | ||
| Attachment_3_-_SF24-Bid_Bond.pdf | ||
| Attachment_2_-_Past_Performance_Questionnaire.pdf | ||
| Drawings_10-27-2023.pdf | ||
| 140R1024R0009_Conformed_Solicitation_Final.pdf | ||
| Attachment_1_-_WD_ID20240017_dtd_01-05-2024.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Upper Snake Field Office HVAC Renovation Project, Idaho Solicitation No. 140R1024R0009
Interruption of Service
01 14 30 - 1
SECTION 01 14 30
INTERRUPTION OF SERVICE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost: Include in prices offered in the Price Schedule for other items of work.
1.02 SUBMITTALS
A. In accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 30-1, Interruption of Service Request:
1. Area where work will be done (by number or other description).
2. Outline procedures for accomplishing work including:
a. Specific safety precautions to be taken.
b. Type and location of barricades.
c. Warning signs.
d. Protective grounds and devices to be used.
3. Commencement time of work.
4. Duration of work.
5. Number of personnel and their classification.
6. Description of equipment to be used.
7. Information indicating that required materials are onsite or data indicating shipping dates of materials not onsite.
1.03 PROJECT CONDITIONS
A. Coordinate and schedule interruption of services with COR:
1. Coordinate work with Government operations.
2. No specific interruption of service request will be considered unless:
a. COR has reasonable assurance that materials and equipment required for work will be onsite.
b. Contractor will be prepared to perform work on date and during period of time requested for specific interruption of service.
3. Allowable time and available interruption of service periods will govern interruption of service requests, work scheduling, onsite delivery of materials, and required drawings and data submittals.
Upper Snake Field Office HVAC Renovation Project, Idaho Amendment No. P0002
Interruption of Service (Revised)
01 14 30 - 2
4. Interruption of service window available to Contractor: Government will accommodate Contractor-requested and approved interruption of service only given the following constraints:
a. Heating systems shall be online from November 1 to March 31.
b. Cooling systems shall be online from May 15 to September 20.
c. Temporary heating or cooling shall be required if an HVAC system is offline outside the dates listed above. The Contractor shall ensure building temperatures are within occupancy standards when an HVAC system is offline.
B. When work cannot be performed during an approved interruption of service period, notify COR that interruption of service is not required.
C. Show construction interruption of services greater than 4 hours in construction schedule, refer to Section 01 32 10 - Construction Program.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION