Amendment_0001_Merged_Documents_0001.pdf
PDF 2 MB Posted
- Attached to
- Kachess Dam Modification Phase 3 Yakima Project Federal contract opportunity
- Solicitation number
- 140R1024R0002
About this file
This document is an amendment to the solicitation for the Kachess Dam Modification Phase 3 project in Yakima, Washington.
The amendment provides responses to contractor questions, revises submittal requirements and timelines, and updates specifications. Key details include that the project remains a total small business set-aside. Submittals for items such as safety, quality control, environmental protection, and construction plans are due at least 28 days prior to mobilization. Construction will require diversion of reservoir releases, cofferdam installation, excavation and reconstruction of the outlet works channel. The Bureau of Reclamation is the contracting agency. Products and services encompass concrete, earthwork, drainage, instrumentation, and HVAC work needed to modify the dam.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C06-01_Amendment_0003_Attachments_0003.pdf | ||
| Sol_140R1024R0002_Amd_0003.pdf | ||
| Sol_140R1024R0002_Amd_0002.pdf | ||
| Sol_140R1024R0002_Amd_0001.pdf | ||
| Sol_140R1024R0002.pdf | ||
| J_5_Bid_Bond.pdf | ||
| J_4_Geology_Drawings_Combined_-353_Pages.pdf | ||
| J_2a_Drawings_-_Pages_111-229.pdf | ||
| 140R1024R0002_Solicitation.pdf | ||
| J_2_Drawings_-_Pages_1-110.pdf | ||
| J_3_Permits-743_pages.pdf | ||
| J_6_Past_Performance_Questionnaire.pdf | ||
| J_1_Wage_Determination_WA20230049.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
# Offeror Question Government Answer Answered in Amendment
Is there another set of drawings for this project? We have the ones provided from today but were hoping additional ones might be available
No, there is not another set of drawings. The ones posted to SAM.gov in the intial solicitation are current and complete.
The Kackhess Dam Modifications -Phase 3 project is solicited as a total small business set-aside project. Can we bid it as a subcontractor to a small business general contractor even thou we are not a small business?
The Prime contractor must be compliant with the clause at Section I 52.219-14 Limitations on Subcontracting (Oct 2022).
Question in regards to Notice ID - 140R1024R0002 Kachess Dam Modification Phase 3. We noticed Government Furnished Products included 413lf of Steel Pipe. Is this part of the bid or bid as a separate project?
Government Furnished Products including 413lf of Steel Pipe will be furnished by the government and provided to the contractor. The contract to procure government furnished material has been awarded.
4 Is there a possibility USBR would open this project up for all to bid?
No, at this time the government will not change the small business set-aside to an unrestricted competition.
140R1024R0002 Kachess 3 SOD Dam Q&A Log
QUESTIONS AND ANSWERS
TECHNICAL SERVICE CENTER
WRITTEN SPECIFICATIONS SIGNATURE SHEET
Specifications Title:
Project Title:
Region:
Prepared: P.E.
Technical Approval: P.E.
Certified: P.E.
Kachess Dam Modification Phase 3 Yakima Project, Washington Amendment No. 0001
Submittals (Revised)
01 33 00 - 9
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
10 Security Requirements
(WBR 1452.237-
80)
Security Program Submitted and approved before mobilization
A COR CDMS
01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan
Submitted and approved at least 28 days before mobilization
A COR CDMS
01 14 10-2 Use of Site Site Security Plan Submitted and approved at least 28 days before mobilization
A COR CDMS
01 14 10-3 Use of Site Finished Grading Plan
Submitted and approved at least 28 days before mobilization
A COR CDMS
01 14 12-1 Work Restriction and Limitations
Construction Sequencing Plan
Submitted and approved at least 28 days before mobilization
A COR CDMS
01 31 19-1 Project Management and Coordination
Weekly Coordination Meeting Documentation
Submitted at least 24 hours before meeting
I COR CDMS
01 31 30-1 Contract Document Management System
Approval Data Within 10 calendar days after award
A COR CDMS
01 31 30-2 Contract Document Management System
Final Data Within 14 days after completing work.
A COR CDMS
01 32 10-1 Construction Program
Representative Information
Within 10 days of
NTP
A COR CDMS
01 32 10-2 Construction Program
Baseline Schedule Within 10 days of
NTP
A COR CDMS
01 32 10-3 Construction Program
Updated Schedule Reports
Submitted Monthly A COR CDMS
01 32 10-4 Construction Program
Time Impact Analysis
With appropriate changes or as requested by the
CO
A COR CDMS
01 33 00 - 10
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
01 35 10-1 Safety Data Sheets
Complete LHM and SDS
Submitted and approved at least 28 days before mobilization
A COR CDMS
01 35 10-2 Safety Data Sheets
Updated LHM and
SDS
At least 28 days before jobsite delivery of hazardous material not previously listed
A COR CDMS
01 35 20-1 Safety and Health
Safety and Health Program.
Within 30 days or NTP and at least 28 days before mobilization
A COR CDMS
01 35 20-2 Safety and Health
Monthly Accident Summary Report
At least 28 days before the start of the specified construction activities
A COR CDMS
01 35 20-3 Safety and Health
Respirator User Documentation
At least 28 days before the start of the specified construction activities
A COR CDMS
01 35 20-4 Safety and Health
Crane Operation Certificates
At least 28 days before the start of the specified construction activities
A COR CDMS
01 35 20-5 Safety and Health
Other Training Certificates
At least 28 days before the start of the specified construction activities
A COR CDMS
01 35 30-1 Contractor’s On-site Safety Personnel
Qualifications Submitted and accepted at least 28 days prior to mobilization
A COR CDMS
01 35 30-2 Contractor’s On-site Safety Personnel
Safety Inspection Reports
Monthly I COR CDMS
01 33 00 - 11
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
01 46 00-1 Quality Procedures
Contractor Quality Control Plan (QC)
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 46 00-2 Quality Procedures
Contractor’s Daily Report
Weekly I COR CDMS
01 46 00-3 Quality Procedures
Quality Control Supervisor (QCS) Resume
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 46 00-4 Quality Procedures
Contractor’s Quality Testing Plan
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 46 00-5 Quality Procedures
Summary of Monthly Test Results
Monthly I COR CDMS
01 46 20-1 Testing agency Services
Testing Agency Services Plan
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 51 00-1 Temporary Utilities
Temporary Water Access Plan
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 51 00-2 Temporary Utilities
Temporary Electrical Power Plan
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 55 00-1 Vehicular Access and Parking
Initial Digital Photographic Record
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 55 00-2 Vehicular Access and Parking
Post Construction Digital Photographic Record
At least 2 days before demobilization
I COR CDMS
01 55 00-3 Vehicular Access and Parking
Post Repair Digital Photographic Record
Within 14 days of making repairs
01 33 00 - 12
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
01 55 00-4 Vehicular Access and Parking
Use of Dam Crest for Hauling Operations
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 55 00-5 Vehicular Access and Parking
Use of Outlet Works Conduit Crossing for Hauling Operations
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 55 20-1 Traffic Control Traffic Control Plan
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 56 12-1 Protection of Existing Infrastructure
Plan for Protecting Existing Infrastructure
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 57 20-1 Environmental Controls
Copy of Applicable Air Quality Permit
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 57 20-2 Environmental Controls
Noise Monitoring Plan
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 57 20-3 Environmental Controls
Noise Monitoring Reports
Submit daily and week batches
A COR CDMS
01 57 30-1 Water Pollution Control
Pollution Prevention Plan
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 57 30-2 Water Pollution Control
Water Quality Monitoring Plan
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 57 30-3 Water Pollution Control
Spill Prevention, Control, and Countermeasure (SPCC) Plan
Submitted and approved at least 28 days before delivery or storage of oil
A COR CDMS
01 57 30-4 Water Pollution Control
Sedimentation Control Plan
Submitted and approved at least 28 days prior to mobilization
A
COR CDMS
01 33 00 - 13
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
01 57 30-5 Water Pollution Control
Water Quality Monitoring Reports
Submit daily and weekly summary results
01 57 30-6 Water Pollution Control
Straw Wattle Certification
Submitted and approved at least 28 days prior to
01 57 50-1 Tree and Plant Protection
Protection Plan Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 57 90-1 Preservation of Historical and Archaeological Data
Request for Additional Areas of Disturbance
At least 45 days before the start of any additional disturbance activities proposed
A COR CDMS
01 64 40-1 Government Furnished Products
Shortage Report At least 28 days before starting onsite work
A COR CDMS
01 71 20-1 Surveying Surveying Plan At least 28 days before beginning survey work
A COR CDMS
01 71 20-2 Surveying Resumes At least 28 days before beginning survey work; At least 28 days before personnel change
A COR CDMS
01 71 20-3 Surveying Accuracy Check Results
At least 14 days before beginning survey work
A COR CDMS
01 71 20-4 Surveying Completed and Reduced Survey Notes
Within 2 days of completing each set of survey notes
I COR CDMS
01 71 20-5 Surveying Quantity Survey Notes and Computations
Submitted and approved for progress payments
A COR CDMS
01 74 00-1 Cleaning and Waste Management
Hazardous Waste Management Plan
Submitted and approved at least 28 days prior to
01 33 00 - 14
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Plan
Submitted and approved at least 28 days prior to mobilization
A COR CDMS
01 74 00-3 Cleaning and Waste Management
Waste Production and Disposal Records
Within 7 days of waste disposal
I COR CDMS
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment and Environmental Consultant Resume
At least 28 days before beginning environmental assessment
A COR CDMS
01 78 30-1 Project Record Documents
Final As-built Drawings
Within 28 days of completion of work
A COR CDMS
01 78 30-2 Project Record Documents
AutoCAD Set of Final As-built Drawings
Within 28 days of completion of work
A COR CDMS
02 41 07-1 Removal and Disposal of Existing Features
Removal of Existing Features Plan
At least 28 days before starting onsite work
A COR CDMS
03 11 10-1 Concrete Forming
Formwork Design and Drawings
At least 28 days before starting onsite work
A COR CDMS
03 15 12-1 PVC Waterstops Purchase Orders At least 28 days before starting onsite work
A COR CDMS
03 15 12-2 PVC Waterstops Samples At least 28 days before starting onsite work
A COR CDMS
03 15 12-3 PVC Waterstops Certificates At least 28 days before starting onsite work
A COR CDMS
03 15 12-4 PVC Waterstops Drawings At least 28 days before starting onsite work
A COR CDMS
03 15 12-5 PVC Waterstops Instructions At least 28 days before starting onsite work
A COR CDMS
03 20 00-1 Concrete Reinforcing
Reinforcement Diagrams and Lists
At least 28 days before starting onsite work
01 33 00 - 15
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
03 30 00-1 Cast-in Place Concrete
Approval Data At least 28 days before starting onsite work
A COR CDMS
03 30 00-2 Cast-in Place Concrete
Concrete Placement Drawings
At least 28 days before starting onsite work
A COR CDMS
03 30 00-3 Cast-in Place Concrete
Concrete Placement Schedule
At least 28 days before starting onsite work
A COR CDMS
03 30 00-4 Cast-in Place Concrete
RSMC
Temperature Control Plan
At least 28 days before starting onsite work
A COR CDMS
03 30 00-5 Cast-in Place Concrete
Certifications At least 28 days before starting onsite work
A COR CDMS
03 30 00-6 Cast-in Place Concrete
Test Reports Within 7 days after test
I COR CDMS
03 60 10-1 Backfill Grouting Approval Data At least 28 days before starting onsite work
A COR CDMS
03 60 10-2 Backfill Grouting Grouting Plan At least 28 days before starting onsite work
A COR CDMS
03 60 10-3 Backfill Grouting Test Reports Within 7 days after test
I COR CDMS
03 60 10-4 Backfill Grouting Resume At least 28 days before starting onsite work
A COR CDMS
03 81 10-1 Concrete Removal
Concrete Removal Plan
At least 28 days before starting onsite work
A COR CDMS
07 21 50-1 Sprayed-applied Polyurethane Foam Insulation
Approval Data At least 28 days before starting onsite work
A COR CDMS
07 92 00-1 Joint Sealants Approval Data At least 28 days before starting onsite work
A COR CDMS
07 92 00-2 Joint Sealants Certifications At least 28 days before starting
01 33 00 - 16
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
07 92 00-3 Joint Sealants Instructions At least 28 days before starting onsite work
A COR CDMS
07 92 00-4 Joint Sealants Contractors Field Quality Verification Report
Within 7 days after completing work
I COR CDMS
08 31 20-1 Floor Access Hatches
Product Data At least 28 days before starting onsite work
A COR CDMS
09 96 20-1 Coatings Approval Data At least 28 days before starting onsite work
A COR CDMS
09 96 20-2 Coatings Final Approval Data
Within 14 days after completing work
I COR CDMS
09 96 20-3 Coatings Paint Chip Samples
At least 28 days before starting onsite work
A COR CDMS
09 96 20-4 Coatings Qualifications At least 28 days before starting onsite work
A COR CDMS
09 96 20-5 Coatings Quality Control Plan
At least 28 days before starting onsite work
A COR CDMS
09 96 20-6 Coatings Contractor Quality Testing Final Report
Within 7 days after test
I COR CDMS
22 09 23-1 Flowmeter System
Approval Data At least 28 days before starting onsite work
A COR CDMS
22 09 23-2 Flowmeter System
Final Data At least 14 days after completing onsite work
A COR CDMS
22 14 30-1 Sump Pumping Systems
Approval Data At least 28 days before fabricating or procuring sump pumping systems
A COR CDMS
22 14 30-2 Sump Pumping Systems
Test Plan At least 28 days before starting
01 33 00 - 17
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
22 14 30-3 Sump Pumping Systems
Final Data Within 14 days after test
I COR CDMS
23 00 00-1 Heating, Ventilating, and Air-Conditioning (HVAC) Systems
Approval Drawings
At least 28 days before beginning installation of heating, ventilating, and air-conditioning (HVAC) system components
A COR CDMS
23 00 00-2 Heating, Ventilating, and Air-Conditioning (HVAC) Systems
Final Drawings Within 14 days after completing installation of heating, ventilating, and air conditioning (HVAC) system components
A COR CDMS
23 31 00-1 HVAC Ducts and Castings
Approval Data At least 28 days before fabricating or procuring ducts –
HVAC
A COR CDMS
23 33 00-1 Air Duct Accessories
Approval Data At least 28 days before fabricating or procuring air duct accessories
A COR CDMS
23 33 00-2 Air Duct Accessories
Final Data Within 14 days after installation of air duct accessories
A COR CDMS
23 34 00-1 HVAC Fans Approval Data At least 28 days before fabricating or procuring fans -
HVAC
A COR CDMS
23 34 00-2 HVAC Fans Final Data Within 14 days after installation of fans - HVAC
I COR CDMS
23 37 00-1 Air Inlets and Outlets
Approval Data At least 28 days before fabricating or procuring air inlets and outlets
A COR CDMS
23 54 13-1 Electrical Resistance Duct Heater
Approval Data, Drawings, and Test Plan
At least 28 days before fabricating or procuring air inlets and outlets
01 33 00 - 18
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
23 54 13-2 Electrical Resistance Duct Heater
Final Drawings and Data
Within 14 days after completing installation of heating, ventilating, and air conditioning (HVAC) system components
A COR CDMS
23 82 39-1 Electrical Heat Units
Approval Drawings and Data
At least 28 days before beginning installation of heating, ventilating, and air-conditioning (HVAC) system components
A COR CDMS
23 82 39-2 Electrical Heat Units
Final Drawings and Data
Within 14 days after completing installation of heating, ventilating, and air-conditioning (HVAC) system components
A COR CDMS
26 05 10-1 Conductors and Cables
Approval Data At least 28 days before starting onsite work
A COR CDMS
26 05 10-2 Conductors and Cables
Field Test Reports Within 14 days after test
I COR CDMS
26 05 20-1 Grounding and Bonding
Approval Data At least 28 days before starting onsite work
A COR CDMS
26 05 20-2 Grounding and Bonding
As-built Drawings Within 14 days after completing work
A COR CDMS
26 05 20-3 Grounding and Bonding
Test Reports Within 14 days after test
I COR CDMS
26 05 33-1 Raceways and Boxes
As-built Drawings Within 14 days after completing work
A COR CDMS
26 22 16-1 Transformer Load Center
Approval Data At least 28 days before starting onsite work
A COR CDMS
26 22 16-2 Transformer Load Center
Approval Drawings
At least 28 days before starting
01 33 00 - 19
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
26 22 16-3 Transformer Load Center
Operation and Maintenance Instruction Book
Within 14 days after completing work
A COR CDMS
26 24 24-1 Distribution Panelboards
Approval Data At least 28 days before starting onsite work
A COR CDMS
26 24 24-2 Distribution Panelboards
Factory Test Reports
Within 14 days after test
I COR CDMS
26 24 24-3 Distribution Panelboards
Operation and Maintenance Instruction Book
Within 14 days after completing work
A COR CDMS
26 24 24-4 Distribution Panelboards
Final Drawings and Data
Within 14 days after completing work
A COR CDMS
26 24 24-5 Distribution Panelboards
Field Test Reports Within 7 days after test
I COR CDMS
26 27 30-1 Wiring Devices Approval Data At least 28 days before starting onsite work
A COR CDMS
26 51 10-1 Interior Luminaires
Approval Data At least 28 days before starting onsite work
A COR CDMS
31 02 10-1 Water for Dust Abatement
Dust Abatement Plan
At least 28 days before starting onsite work
A COR CDMS
31 03 10-1 Diversion and Care of Reservoir Releases During Construction
Qualifications At least 28 days before starting onsite work
A COR CDMS
31 03 10-2 Diversion and Care of Reservoir Releases During Construction
Diversion Plan At least 28 days before starting onsite work
A COR CDMS
31 03 20-1 Cofferdam Construction
Cofferdam Design At least 28 days before starting onsite work
A COR CDMS
31 03 20-2 Cofferdam Construction
Cofferdam Construction Plan
At least 28 days before starting
01 33 00 - 20
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
31 03 20-3 Cofferdam Construction
Certification and Quality Assurance Documentation
At least 28 days before starting onsite work
A COR CDMS
31 03 33-1 Removal and Control of Water
Unwatering Plan At least 28 days before starting onsite work
A COR CDMS
31 03 33-2 Removal and Control of Water
Qualifications At least 28 days before starting onsite work
A COR CDMS
31 03 33-3 Removal and Control of Water
Unwatering Reports
Submit weekly reports
A COR CDMS
31 03 33-4 Removal and Control of Water
Primary and Standby Power for Unwatering Systems
At least 28 days before starting onsite work
A COR CDMS
31 03 33-5 Removal and Control of Water
Abandonment Plan
At least 28 days before starting onsite work
A COR CDMS
31 09 10-1 Abandoning and Removing Existing Instrumentation
Abandoning and Removing Existing Instrumentation Plan
At least 28 days before starting onsite work
A COR CDMS
31 09 10-2 Abandoning and Removing Existing Instrumentation
Instrument Abandonment Closeout
Within 14 days after completing work
A COR CDMS
31 09 20-1 Inspection Well Instrumentation
Approval Data At least 28 days before starting onsite work
A COR CDMS
31 09 20-2 Inspection Well Instrumentation
Final Data Within 14 days after completing work
A COR CDMS
31 09 22-1 Protecting Existing Instrumentation
Protecting Existing Instrumentation Plan
At least 28 days before starting onsite work
A COR CDMS
31 09 22-2 Protecting Existing Instrumentation
Post-Modification Inspection
At least 28 days before starting
01 33 00 - 21
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
31 09 25-1 Vibrating Wire and Fiber Optic Piezometers
Installation Plan At least 28 days before starting onsite work
A COR CDMS
31 09 25-2 Vibrating Wire and Fiber Optic Piezometers
As-built Reports and Drawings
Within 14 days after completing work
A COR CDMS
31 09 25-3 Vibrating Wire and Fiber Optic Piezometers
Fiber Optic Splicing Method and Personnel
At least 28 days before starting onsite work
A COR CDMS
31 23 02-1 Compacting Earth Materials
Test Results Within 7 days after test
I COR CDMS
31 23 16-1 Existing Embankment and Foundation Excavation
Excavation of Existing Dam Embankment and Foundation Plan
At least 28 days before starting onsite work
A COR CDMS
31 23 16-2 Existing Embankment and Foundation Excavation
Temporary Slope Protection/Erosion Control Plan
At least 28 days before starting onsite work
A COR CDMS
31 23 16-3 Existing Embankment and Foundation Excavation
Temporary Dam Crest Measurement Points and Monitoring
At least 28 days before starting onsite work
A COR CDMS
31 23 16-4 Existing Embankment and Foundation Excavation
Excavation for New Auxiliary Drain Plan
At least 28 days before starting onsite work
A COR CDMS
31 24 10-1 Embankment Construction
Embankment Construction Plan
At least 28 days before starting onsite work
A COR CDMS
31 24 12-1 Zone 3 - Sand Filter Material
Certification and Laboratory Test Results
At least 28 days before starting onsite work
A COR CDMS
31 24 13-1 Zone 4 - Gravel Drain Material
Certification and Laboratory Test Results
At least 28 days before starting onsite work
A COR CDMS
31 24 15-1 Zone 3A - 50/50 Sand Filter Material/Gravel Drain Material Mix
Material Processing Plan
At least 28 days before starting
01 33 00 - 22
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
31 24 15-2 Zone 3A - 50/50 Sand Filter Material/Gravel Drain Material Mix
Certification and Laboratory Test Results
Within 7 days after completing work
A COR CDMS
31 25 10-1 Erosion Control Erosion Control Plan
At least 28 days before starting onsite work
A COR CDMS
31 25 10-2 Erosion Control Straw Certifications
At least 28 days before starting onsite work
A COR CDMS
31 32 32-1 Geotextile Manufacturer's Certification
At least 28 days before starting onsite work
A COR CDMS
31 32 32-2 Geotextile Protection Method At least 28 days before starting onsite work
A COR CDMS
31 37 00-1 Outlet Works Channel Reconstruction
Outlet Works Channel Reconstruction Plan
At least 28 days before starting onsite work
A COR CDMS
32 15 10-1 Gravel Surfacing Certification and Laboratory Test Results
At least 28 days before starting onsite work
A COR CDMS
32 91 60-1 Topsoil Erosion Control Matting
Manufacturer’s Information
At least 28 days before starting onsite work
A COR CDMS
32 91 60-2 Topsoil Erosion Control Matting
Installation Plan At least 28 days before starting onsite work
A COR CDMS
32 92 20-1 Seeding Seeding Plan At least 28 days before starting onsite work
A COR CDMS
32 92 20-1 Seeding Statement of Qualifications
At least 28 days before starting onsite work
A COR CDMS
33 09 12-1 Inspection Wells Certifications At least 28 days before starting onsite work
A COR CDMS
33 09 12-2 Inspection Wells Shop Drawings At least 28 days before starting
01 33 00 - 23
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
33 09 12-3 Inspection Wells Product Data and Test Reports
At least 28 days before starting onsite work
A COR CDMS
33 42 50-1 Reinforced Concrete Pipe Culvert
Approval Data At least 28 days before starting onsite work
A COR CDMS
33 46 36-1 HDPE Drain Pipe
Approval Data At least 28 days before starting onsite work
A COR CDMS
33 46 36-2 HDPE Drain Pipe
Certifications At least 28 days before starting onsite work
A COR CDMS
33 46 36-3 HDPE Drain Pipe
Final Inspection Video
Within 14 days after completing work
A COR CDMS
33 46 40-1 Parshall Flume Flume Installation Plan
At least 28 days before starting onsite work
A COR CDMS
34 71 10-1 W-Beam Guardrail
Certifications At least 28 days before starting onsite work
A COR CDMS
35 21 94-1 Steel Transition and Steel Deflector Plates
Shop Drawings At least 42 days prior to beginning fabrication
A COR CDMS
35 21 94-2 Steel Transition and Steel Deflector Plates
Certification and Requirements for Steel Transition and Steel Deflector Plates
At least 28 days prior to beginning fabrication
A COR CDMS
35 21 94-3 Steel Transition and Steel Deflector Plates
Instructions for Transporting, and Handling
At least 28 days before transporting
A COR CDMS
35 21 94-4 Steel Transition and Steel Deflector Plates
Shipping Inspection Reports
Within 14 days after arrival onsite
A COR CDMS
35 21 95-1 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe
Certifications and Requirements for Installation and Inspection of Government Furnished Pipe
At least 28 days before starting
01 33 00 - 24
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
35 21 95-2 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe
Government Furnished Pipe Inspection Reports
Within 14 days after arrival on site
A COR CDMS
35 21 95-3 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe
Grating Shop Drawings
At least 28 days prior to beginning fabrication
A COR CDMS
35 21 95-4 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe
Installation Plan and Calculations
At least 56 days before starting onsite work
A COR CDMS
35 21 95-5 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe
Field Test Plan At least 28 days before testing
A COR CDMS
35 21 95-6 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe
Final Drawings and Data
Within 14 days after completing work
A COR CDMS
35 22 15-1 Installation of Government Furnished Plunger Valve
Government Furnished Plunger Valve Assembly Inspection Report
Within 14 days after arrival onsite of Government Furnished Plunger Valve
A COR CDMS
35 22 15-2 Installation of Government Furnished Plunger Valve
Butterfly Valve Assembly Removal and Plunger Valve Assembly Installation Plan
At least 28 days before starting
01 33 00 - 25
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
35 22 15-3 Installation of Government Furnished Plunger Valve
Plunger Valve Field Test Plan
At least 28 days before testing
A COR CDMS
35 22 15-4 Installation of Government Furnished Plunger Valve
Final Drawings and Data
Within 14 days after completing work
END OF SECTION
Flowmeter Systems (Revised)
22 09 23 - 2
2. Detailed installation instructions and drawings showing installation details, detail dimensions, and locations of conduit connections. Include manufacturer’s instructions for attaching flowmeter to the pipe and cabling to the flowmeter display indicator/transmitter.
3. Schematic and wiring diagrams including those showing connections to external equipment in accordance with Division 26 – Electrical.
C. RSN 22 09 23-2, Final Data:
1. Service Manuals:
a. Bound service manual containing:
1) Installation, maintenance, and operating instructions,
2) Identifying parts list,
3) Schematic and wiring diagrams,
4) Recommended parts list.
2. Simulated test reports.
D. Deleted
1.04 SYSTEM DESCRIPTION
A. Electromagnetic insertion flow meter based on Faraday’s Law.
B. Dedicated indicator/transmitter microprocessor-based processing unit.
C. Provides an electronic output signal proportional to the flow of the liquid in a closed pipe system.
D. Capable of operating up to 100-feet between flowmeter sensor and remote indicator/transmitter.
E. System Pipe Parameters:
1. Pipe Sizes, Nominal: 4-inch
2. Pipe Material: PVC.
3. Flow Range: 20-500 GPM
4. Pipe Operating Pressure: 20 psi
PART 2 PRODUCTS
2.01 FLOWMETER SYSTEMS
A. Insertion Electromagnetic Flowmeter
| 140R1024R0002 QA Log.pdf |
| Government Answers |