Amendment_0001_Merged_Documents_0001.pdf

PDF 2 MB Posted

Attached to
Kachess Dam Modification Phase 3 Yakima Project Federal contract opportunity
Solicitation number
140R1024R0002
Issued by
Department of the Interior Bureau of Reclamation

About this file

This document is an amendment to the solicitation for the Kachess Dam Modification Phase 3 project in Yakima, Washington.

The amendment provides responses to contractor questions, revises submittal requirements and timelines, and updates specifications. Key details include that the project remains a total small business set-aside. Submittals for items such as safety, quality control, environmental protection, and construction plans are due at least 28 days prior to mobilization. Construction will require diversion of reservoir releases, cofferdam installation, excavation and reconstruction of the outlet works channel. The Bureau of Reclamation is the contracting agency. Products and services encompass concrete, earthwork, drainage, instrumentation, and HVAC work needed to modify the dam.

View the file

Other files for this federal contract opportunity

Other files attached to Kachess Dam Modification Phase 3 Yakima Project, newest first.
File Type Posted
C06-01_Amendment_0003_Attachments_0003.pdf PDF
Sol_140R1024R0002_Amd_0003.pdf PDF
Sol_140R1024R0002_Amd_0002.pdf PDF
Sol_140R1024R0002_Amd_0001.pdf PDF
Sol_140R1024R0002.pdf PDF
J_5_Bid_Bond.pdf PDF
J_4_Geology_Drawings_Combined_-353_Pages.pdf PDF
J_2a_Drawings_-_Pages_111-229.pdf PDF
140R1024R0002_Solicitation.pdf PDF
J_2_Drawings_-_Pages_1-110.pdf PDF
J_3_Permits-743_pages.pdf PDF
J_6_Past_Performance_Questionnaire.pdf PDF
J_1_Wage_Determination_WA20230049.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

# Offeror Question Government Answer Answered in Amendment

Is there another set of drawings for this project? We have the ones provided from today but were hoping additional ones might be available

No, there is not another set of drawings. The ones posted to SAM.gov in the intial solicitation are current and complete.

The Kackhess Dam Modifications -Phase 3 project is solicited as a total small business set-aside project. Can we bid it as a subcontractor to a small business general contractor even thou we are not a small business?

The Prime contractor must be compliant with the clause at Section I 52.219-14 Limitations on Subcontracting (Oct 2022).

Question in regards to Notice ID - 140R1024R0002 Kachess Dam Modification Phase 3. We noticed Government Furnished Products included 413lf of Steel Pipe. Is this part of the bid or bid as a separate project?

Government Furnished Products including 413lf of Steel Pipe will be furnished by the government and provided to the contractor. The contract to procure government furnished material has been awarded.

4 Is there a possibility USBR would open this project up for all to bid?

No, at this time the government will not change the small business set-aside to an unrestricted competition.

140R1024R0002 Kachess 3 SOD Dam Q&A Log

QUESTIONS AND ANSWERS

TECHNICAL SERVICE CENTER

WRITTEN SPECIFICATIONS SIGNATURE SHEET

Specifications Title:

Project Title:

Region:

Prepared: P.E.

Technical Approval: P.E.

Certified: P.E.

Kachess Dam Modification Phase 3 Yakima Project, Washington Amendment No. 0001

Submittals (Revised)

01 33 00 - 9

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

10 Security Requirements

(WBR 1452.237-

80)

Security Program Submitted and approved before mobilization

A COR CDMS

01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan

Submitted and approved at least 28 days before mobilization

A COR CDMS

01 14 10-2 Use of Site Site Security Plan Submitted and approved at least 28 days before mobilization

A COR CDMS

01 14 10-3 Use of Site Finished Grading Plan

Submitted and approved at least 28 days before mobilization

A COR CDMS

01 14 12-1 Work Restriction and Limitations

Construction Sequencing Plan

Submitted and approved at least 28 days before mobilization

A COR CDMS

01 31 19-1 Project Management and Coordination

Weekly Coordination Meeting Documentation

Submitted at least 24 hours before meeting

I COR CDMS

01 31 30-1 Contract Document Management System

Approval Data Within 10 calendar days after award

A COR CDMS

01 31 30-2 Contract Document Management System

Final Data Within 14 days after completing work.

A COR CDMS

01 32 10-1 Construction Program

Representative Information

Within 10 days of

NTP

A COR CDMS

01 32 10-2 Construction Program

Baseline Schedule Within 10 days of

NTP

A COR CDMS

01 32 10-3 Construction Program

Updated Schedule Reports

Submitted Monthly A COR CDMS

01 32 10-4 Construction Program

Time Impact Analysis

With appropriate changes or as requested by the

CO

A COR CDMS

01 33 00 - 10

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

01 35 10-1 Safety Data Sheets

Complete LHM and SDS

Submitted and approved at least 28 days before mobilization

A COR CDMS

01 35 10-2 Safety Data Sheets

Updated LHM and

SDS

At least 28 days before jobsite delivery of hazardous material not previously listed

A COR CDMS

01 35 20-1 Safety and Health

Safety and Health Program.

Within 30 days or NTP and at least 28 days before mobilization

A COR CDMS

01 35 20-2 Safety and Health

Monthly Accident Summary Report

At least 28 days before the start of the specified construction activities

A COR CDMS

01 35 20-3 Safety and Health

Respirator User Documentation

At least 28 days before the start of the specified construction activities

A COR CDMS

01 35 20-4 Safety and Health

Crane Operation Certificates

At least 28 days before the start of the specified construction activities

A COR CDMS

01 35 20-5 Safety and Health

Other Training Certificates

At least 28 days before the start of the specified construction activities

A COR CDMS

01 35 30-1 Contractor’s On-site Safety Personnel

Qualifications Submitted and accepted at least 28 days prior to mobilization

A COR CDMS

01 35 30-2 Contractor’s On-site Safety Personnel

Safety Inspection Reports

Monthly I COR CDMS

01 33 00 - 11

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

01 46 00-1 Quality Procedures

Contractor Quality Control Plan (QC)

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 46 00-2 Quality Procedures

Contractor’s Daily Report

Weekly I COR CDMS

01 46 00-3 Quality Procedures

Quality Control Supervisor (QCS) Resume

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 46 00-4 Quality Procedures

Contractor’s Quality Testing Plan

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 46 00-5 Quality Procedures

Summary of Monthly Test Results

Monthly I COR CDMS

01 46 20-1 Testing agency Services

Testing Agency Services Plan

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 51 00-1 Temporary Utilities

Temporary Water Access Plan

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 51 00-2 Temporary Utilities

Temporary Electrical Power Plan

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 55 00-1 Vehicular Access and Parking

Initial Digital Photographic Record

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 55 00-2 Vehicular Access and Parking

Post Construction Digital Photographic Record

At least 2 days before demobilization

I COR CDMS

01 55 00-3 Vehicular Access and Parking

Post Repair Digital Photographic Record

Within 14 days of making repairs

01 33 00 - 12

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

01 55 00-4 Vehicular Access and Parking

Use of Dam Crest for Hauling Operations

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 55 00-5 Vehicular Access and Parking

Use of Outlet Works Conduit Crossing for Hauling Operations

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 55 20-1 Traffic Control Traffic Control Plan

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 56 12-1 Protection of Existing Infrastructure

Plan for Protecting Existing Infrastructure

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 57 20-1 Environmental Controls

Copy of Applicable Air Quality Permit

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 57 20-2 Environmental Controls

Noise Monitoring Plan

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 57 20-3 Environmental Controls

Noise Monitoring Reports

Submit daily and week batches

A COR CDMS

01 57 30-1 Water Pollution Control

Pollution Prevention Plan

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 57 30-2 Water Pollution Control

Water Quality Monitoring Plan

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 57 30-3 Water Pollution Control

Spill Prevention, Control, and Countermeasure (SPCC) Plan

Submitted and approved at least 28 days before delivery or storage of oil

A COR CDMS

01 57 30-4 Water Pollution Control

Sedimentation Control Plan

Submitted and approved at least 28 days prior to mobilization

A

COR CDMS

01 33 00 - 13

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

01 57 30-5 Water Pollution Control

Water Quality Monitoring Reports

Submit daily and weekly summary results

01 57 30-6 Water Pollution Control

Straw Wattle Certification

Submitted and approved at least 28 days prior to

01 57 50-1 Tree and Plant Protection

Protection Plan Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 57 90-1 Preservation of Historical and Archaeological Data

Request for Additional Areas of Disturbance

At least 45 days before the start of any additional disturbance activities proposed

A COR CDMS

01 64 40-1 Government Furnished Products

Shortage Report At least 28 days before starting onsite work

A COR CDMS

01 71 20-1 Surveying Surveying Plan At least 28 days before beginning survey work

A COR CDMS

01 71 20-2 Surveying Resumes At least 28 days before beginning survey work; At least 28 days before personnel change

A COR CDMS

01 71 20-3 Surveying Accuracy Check Results

At least 14 days before beginning survey work

A COR CDMS

01 71 20-4 Surveying Completed and Reduced Survey Notes

Within 2 days of completing each set of survey notes

I COR CDMS

01 71 20-5 Surveying Quantity Survey Notes and Computations

Submitted and approved for progress payments

A COR CDMS

01 74 00-1 Cleaning and Waste Management

Hazardous Waste Management Plan

Submitted and approved at least 28 days prior to

01 33 00 - 14

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

01 74 00-2 Cleaning and Waste Management

Waste Production and Disposal Plan

Submitted and approved at least 28 days prior to mobilization

A COR CDMS

01 74 00-3 Cleaning and Waste Management

Waste Production and Disposal Records

Within 7 days of waste disposal

I COR CDMS

01 74 00-4 Cleaning and Waste Management

Environmental Site Assessment and Environmental Consultant Resume

At least 28 days before beginning environmental assessment

A COR CDMS

01 78 30-1 Project Record Documents

Final As-built Drawings

Within 28 days of completion of work

A COR CDMS

01 78 30-2 Project Record Documents

AutoCAD Set of Final As-built Drawings

Within 28 days of completion of work

A COR CDMS

02 41 07-1 Removal and Disposal of Existing Features

Removal of Existing Features Plan

At least 28 days before starting onsite work

A COR CDMS

03 11 10-1 Concrete Forming

Formwork Design and Drawings

At least 28 days before starting onsite work

A COR CDMS

03 15 12-1 PVC Waterstops Purchase Orders At least 28 days before starting onsite work

A COR CDMS

03 15 12-2 PVC Waterstops Samples At least 28 days before starting onsite work

A COR CDMS

03 15 12-3 PVC Waterstops Certificates At least 28 days before starting onsite work

A COR CDMS

03 15 12-4 PVC Waterstops Drawings At least 28 days before starting onsite work

A COR CDMS

03 15 12-5 PVC Waterstops Instructions At least 28 days before starting onsite work

A COR CDMS

03 20 00-1 Concrete Reinforcing

Reinforcement Diagrams and Lists

At least 28 days before starting onsite work

01 33 00 - 15

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

03 30 00-1 Cast-in Place Concrete

Approval Data At least 28 days before starting onsite work

A COR CDMS

03 30 00-2 Cast-in Place Concrete

Concrete Placement Drawings

At least 28 days before starting onsite work

A COR CDMS

03 30 00-3 Cast-in Place Concrete

Concrete Placement Schedule

At least 28 days before starting onsite work

A COR CDMS

03 30 00-4 Cast-in Place Concrete

RSMC

Temperature Control Plan

At least 28 days before starting onsite work

A COR CDMS

03 30 00-5 Cast-in Place Concrete

Certifications At least 28 days before starting onsite work

A COR CDMS

03 30 00-6 Cast-in Place Concrete

Test Reports Within 7 days after test

I COR CDMS

03 60 10-1 Backfill Grouting Approval Data At least 28 days before starting onsite work

A COR CDMS

03 60 10-2 Backfill Grouting Grouting Plan At least 28 days before starting onsite work

A COR CDMS

03 60 10-3 Backfill Grouting Test Reports Within 7 days after test

I COR CDMS

03 60 10-4 Backfill Grouting Resume At least 28 days before starting onsite work

A COR CDMS

03 81 10-1 Concrete Removal

Concrete Removal Plan

At least 28 days before starting onsite work

A COR CDMS

07 21 50-1 Sprayed-applied Polyurethane Foam Insulation

Approval Data At least 28 days before starting onsite work

A COR CDMS

07 92 00-1 Joint Sealants Approval Data At least 28 days before starting onsite work

A COR CDMS

07 92 00-2 Joint Sealants Certifications At least 28 days before starting

01 33 00 - 16

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

07 92 00-3 Joint Sealants Instructions At least 28 days before starting onsite work

A COR CDMS

07 92 00-4 Joint Sealants Contractors Field Quality Verification Report

Within 7 days after completing work

I COR CDMS

08 31 20-1 Floor Access Hatches

Product Data At least 28 days before starting onsite work

A COR CDMS

09 96 20-1 Coatings Approval Data At least 28 days before starting onsite work

A COR CDMS

09 96 20-2 Coatings Final Approval Data

Within 14 days after completing work

I COR CDMS

09 96 20-3 Coatings Paint Chip Samples

At least 28 days before starting onsite work

A COR CDMS

09 96 20-4 Coatings Qualifications At least 28 days before starting onsite work

A COR CDMS

09 96 20-5 Coatings Quality Control Plan

At least 28 days before starting onsite work

A COR CDMS

09 96 20-6 Coatings Contractor Quality Testing Final Report

Within 7 days after test

I COR CDMS

22 09 23-1 Flowmeter System

Approval Data At least 28 days before starting onsite work

A COR CDMS

22 09 23-2 Flowmeter System

Final Data At least 14 days after completing onsite work

A COR CDMS

22 14 30-1 Sump Pumping Systems

Approval Data At least 28 days before fabricating or procuring sump pumping systems

A COR CDMS

22 14 30-2 Sump Pumping Systems

Test Plan At least 28 days before starting

01 33 00 - 17

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

22 14 30-3 Sump Pumping Systems

Final Data Within 14 days after test

I COR CDMS

23 00 00-1 Heating, Ventilating, and Air-Conditioning (HVAC) Systems

Approval Drawings

At least 28 days before beginning installation of heating, ventilating, and air-conditioning (HVAC) system components

A COR CDMS

23 00 00-2 Heating, Ventilating, and Air-Conditioning (HVAC) Systems

Final Drawings Within 14 days after completing installation of heating, ventilating, and air conditioning (HVAC) system components

A COR CDMS

23 31 00-1 HVAC Ducts and Castings

Approval Data At least 28 days before fabricating or procuring ducts –

HVAC

A COR CDMS

23 33 00-1 Air Duct Accessories

Approval Data At least 28 days before fabricating or procuring air duct accessories

A COR CDMS

23 33 00-2 Air Duct Accessories

Final Data Within 14 days after installation of air duct accessories

A COR CDMS

23 34 00-1 HVAC Fans Approval Data At least 28 days before fabricating or procuring fans -

HVAC

A COR CDMS

23 34 00-2 HVAC Fans Final Data Within 14 days after installation of fans - HVAC

I COR CDMS

23 37 00-1 Air Inlets and Outlets

Approval Data At least 28 days before fabricating or procuring air inlets and outlets

A COR CDMS

23 54 13-1 Electrical Resistance Duct Heater

Approval Data, Drawings, and Test Plan

At least 28 days before fabricating or procuring air inlets and outlets

01 33 00 - 18

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

23 54 13-2 Electrical Resistance Duct Heater

Final Drawings and Data

Within 14 days after completing installation of heating, ventilating, and air conditioning (HVAC) system components

A COR CDMS

23 82 39-1 Electrical Heat Units

Approval Drawings and Data

At least 28 days before beginning installation of heating, ventilating, and air-conditioning (HVAC) system components

A COR CDMS

23 82 39-2 Electrical Heat Units

Final Drawings and Data

Within 14 days after completing installation of heating, ventilating, and air-conditioning (HVAC) system components

A COR CDMS

26 05 10-1 Conductors and Cables

Approval Data At least 28 days before starting onsite work

A COR CDMS

26 05 10-2 Conductors and Cables

Field Test Reports Within 14 days after test

I COR CDMS

26 05 20-1 Grounding and Bonding

Approval Data At least 28 days before starting onsite work

A COR CDMS

26 05 20-2 Grounding and Bonding

As-built Drawings Within 14 days after completing work

A COR CDMS

26 05 20-3 Grounding and Bonding

Test Reports Within 14 days after test

I COR CDMS

26 05 33-1 Raceways and Boxes

As-built Drawings Within 14 days after completing work

A COR CDMS

26 22 16-1 Transformer Load Center

Approval Data At least 28 days before starting onsite work

A COR CDMS

26 22 16-2 Transformer Load Center

Approval Drawings

At least 28 days before starting

01 33 00 - 19

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

26 22 16-3 Transformer Load Center

Operation and Maintenance Instruction Book

Within 14 days after completing work

A COR CDMS

26 24 24-1 Distribution Panelboards

Approval Data At least 28 days before starting onsite work

A COR CDMS

26 24 24-2 Distribution Panelboards

Factory Test Reports

Within 14 days after test

I COR CDMS

26 24 24-3 Distribution Panelboards

Operation and Maintenance Instruction Book

Within 14 days after completing work

A COR CDMS

26 24 24-4 Distribution Panelboards

Final Drawings and Data

Within 14 days after completing work

A COR CDMS

26 24 24-5 Distribution Panelboards

Field Test Reports Within 7 days after test

I COR CDMS

26 27 30-1 Wiring Devices Approval Data At least 28 days before starting onsite work

A COR CDMS

26 51 10-1 Interior Luminaires

Approval Data At least 28 days before starting onsite work

A COR CDMS

31 02 10-1 Water for Dust Abatement

Dust Abatement Plan

At least 28 days before starting onsite work

A COR CDMS

31 03 10-1 Diversion and Care of Reservoir Releases During Construction

Qualifications At least 28 days before starting onsite work

A COR CDMS

31 03 10-2 Diversion and Care of Reservoir Releases During Construction

Diversion Plan At least 28 days before starting onsite work

A COR CDMS

31 03 20-1 Cofferdam Construction

Cofferdam Design At least 28 days before starting onsite work

A COR CDMS

31 03 20-2 Cofferdam Construction

Cofferdam Construction Plan

At least 28 days before starting

01 33 00 - 20

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

31 03 20-3 Cofferdam Construction

Certification and Quality Assurance Documentation

At least 28 days before starting onsite work

A COR CDMS

31 03 33-1 Removal and Control of Water

Unwatering Plan At least 28 days before starting onsite work

A COR CDMS

31 03 33-2 Removal and Control of Water

Qualifications At least 28 days before starting onsite work

A COR CDMS

31 03 33-3 Removal and Control of Water

Unwatering Reports

Submit weekly reports

A COR CDMS

31 03 33-4 Removal and Control of Water

Primary and Standby Power for Unwatering Systems

At least 28 days before starting onsite work

A COR CDMS

31 03 33-5 Removal and Control of Water

Abandonment Plan

At least 28 days before starting onsite work

A COR CDMS

31 09 10-1 Abandoning and Removing Existing Instrumentation

Abandoning and Removing Existing Instrumentation Plan

At least 28 days before starting onsite work

A COR CDMS

31 09 10-2 Abandoning and Removing Existing Instrumentation

Instrument Abandonment Closeout

Within 14 days after completing work

A COR CDMS

31 09 20-1 Inspection Well Instrumentation

Approval Data At least 28 days before starting onsite work

A COR CDMS

31 09 20-2 Inspection Well Instrumentation

Final Data Within 14 days after completing work

A COR CDMS

31 09 22-1 Protecting Existing Instrumentation

Protecting Existing Instrumentation Plan

At least 28 days before starting onsite work

A COR CDMS

31 09 22-2 Protecting Existing Instrumentation

Post-Modification Inspection

At least 28 days before starting

01 33 00 - 21

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

31 09 25-1 Vibrating Wire and Fiber Optic Piezometers

Installation Plan At least 28 days before starting onsite work

A COR CDMS

31 09 25-2 Vibrating Wire and Fiber Optic Piezometers

As-built Reports and Drawings

Within 14 days after completing work

A COR CDMS

31 09 25-3 Vibrating Wire and Fiber Optic Piezometers

Fiber Optic Splicing Method and Personnel

At least 28 days before starting onsite work

A COR CDMS

31 23 02-1 Compacting Earth Materials

Test Results Within 7 days after test

I COR CDMS

31 23 16-1 Existing Embankment and Foundation Excavation

Excavation of Existing Dam Embankment and Foundation Plan

At least 28 days before starting onsite work

A COR CDMS

31 23 16-2 Existing Embankment and Foundation Excavation

Temporary Slope Protection/Erosion Control Plan

At least 28 days before starting onsite work

A COR CDMS

31 23 16-3 Existing Embankment and Foundation Excavation

Temporary Dam Crest Measurement Points and Monitoring

At least 28 days before starting onsite work

A COR CDMS

31 23 16-4 Existing Embankment and Foundation Excavation

Excavation for New Auxiliary Drain Plan

At least 28 days before starting onsite work

A COR CDMS

31 24 10-1 Embankment Construction

Embankment Construction Plan

At least 28 days before starting onsite work

A COR CDMS

31 24 12-1 Zone 3 - Sand Filter Material

Certification and Laboratory Test Results

At least 28 days before starting onsite work

A COR CDMS

31 24 13-1 Zone 4 - Gravel Drain Material

Certification and Laboratory Test Results

At least 28 days before starting onsite work

A COR CDMS

31 24 15-1 Zone 3A - 50/50 Sand Filter Material/Gravel Drain Material Mix

Material Processing Plan

At least 28 days before starting

01 33 00 - 22

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

31 24 15-2 Zone 3A - 50/50 Sand Filter Material/Gravel Drain Material Mix

Certification and Laboratory Test Results

Within 7 days after completing work

A COR CDMS

31 25 10-1 Erosion Control Erosion Control Plan

At least 28 days before starting onsite work

A COR CDMS

31 25 10-2 Erosion Control Straw Certifications

At least 28 days before starting onsite work

A COR CDMS

31 32 32-1 Geotextile Manufacturer's Certification

At least 28 days before starting onsite work

A COR CDMS

31 32 32-2 Geotextile Protection Method At least 28 days before starting onsite work

A COR CDMS

31 37 00-1 Outlet Works Channel Reconstruction

Outlet Works Channel Reconstruction Plan

At least 28 days before starting onsite work

A COR CDMS

32 15 10-1 Gravel Surfacing Certification and Laboratory Test Results

At least 28 days before starting onsite work

A COR CDMS

32 91 60-1 Topsoil Erosion Control Matting

Manufacturer’s Information

At least 28 days before starting onsite work

A COR CDMS

32 91 60-2 Topsoil Erosion Control Matting

Installation Plan At least 28 days before starting onsite work

A COR CDMS

32 92 20-1 Seeding Seeding Plan At least 28 days before starting onsite work

A COR CDMS

32 92 20-1 Seeding Statement of Qualifications

At least 28 days before starting onsite work

A COR CDMS

33 09 12-1 Inspection Wells Certifications At least 28 days before starting onsite work

A COR CDMS

33 09 12-2 Inspection Wells Shop Drawings At least 28 days before starting

01 33 00 - 23

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

33 09 12-3 Inspection Wells Product Data and Test Reports

At least 28 days before starting onsite work

A COR CDMS

33 42 50-1 Reinforced Concrete Pipe Culvert

Approval Data At least 28 days before starting onsite work

A COR CDMS

33 46 36-1 HDPE Drain Pipe

Approval Data At least 28 days before starting onsite work

A COR CDMS

33 46 36-2 HDPE Drain Pipe

Certifications At least 28 days before starting onsite work

A COR CDMS

33 46 36-3 HDPE Drain Pipe

Final Inspection Video

Within 14 days after completing work

A COR CDMS

33 46 40-1 Parshall Flume Flume Installation Plan

At least 28 days before starting onsite work

A COR CDMS

34 71 10-1 W-Beam Guardrail

Certifications At least 28 days before starting onsite work

A COR CDMS

35 21 94-1 Steel Transition and Steel Deflector Plates

Shop Drawings At least 42 days prior to beginning fabrication

A COR CDMS

35 21 94-2 Steel Transition and Steel Deflector Plates

Certification and Requirements for Steel Transition and Steel Deflector Plates

At least 28 days prior to beginning fabrication

A COR CDMS

35 21 94-3 Steel Transition and Steel Deflector Plates

Instructions for Transporting, and Handling

At least 28 days before transporting

A COR CDMS

35 21 94-4 Steel Transition and Steel Deflector Plates

Shipping Inspection Reports

Within 14 days after arrival onsite

A COR CDMS

35 21 95-1 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe

Certifications and Requirements for Installation and Inspection of Government Furnished Pipe

At least 28 days before starting

01 33 00 - 24

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

35 21 95-2 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe

Government Furnished Pipe Inspection Reports

Within 14 days after arrival on site

A COR CDMS

35 21 95-3 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe

Grating Shop Drawings

At least 28 days prior to beginning fabrication

A COR CDMS

35 21 95-4 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe

Installation Plan and Calculations

At least 56 days before starting onsite work

A COR CDMS

35 21 95-5 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe

Field Test Plan At least 28 days before testing

A COR CDMS

35 21 95-6 Installation of Steel Transition, Steel Deflector Plates, and Government Furnished Pipe

Final Drawings and Data

Within 14 days after completing work

A COR CDMS

35 22 15-1 Installation of Government Furnished Plunger Valve

Government Furnished Plunger Valve Assembly Inspection Report

Within 14 days after arrival onsite of Government Furnished Plunger Valve

A COR CDMS

35 22 15-2 Installation of Government Furnished Plunger Valve

Butterfly Valve Assembly Removal and Plunger Valve Assembly Installation Plan

At least 28 days before starting

01 33 00 - 25

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** CP -Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

35 22 15-3 Installation of Government Furnished Plunger Valve

Plunger Valve Field Test Plan

At least 28 days before testing

A COR CDMS

35 22 15-4 Installation of Government Furnished Plunger Valve

Final Drawings and Data

Within 14 days after completing work

END OF SECTION

Flowmeter Systems (Revised)

22 09 23 - 2

2. Detailed installation instructions and drawings showing installation details, detail dimensions, and locations of conduit connections. Include manufacturer’s instructions for attaching flowmeter to the pipe and cabling to the flowmeter display indicator/transmitter.

3. Schematic and wiring diagrams including those showing connections to external equipment in accordance with Division 26 – Electrical.

C. RSN 22 09 23-2, Final Data:

1. Service Manuals:

a. Bound service manual containing:

1) Installation, maintenance, and operating instructions,

2) Identifying parts list,

3) Schematic and wiring diagrams,

4) Recommended parts list.

2. Simulated test reports.

D. Deleted

1.04 SYSTEM DESCRIPTION

A. Electromagnetic insertion flow meter based on Faraday’s Law.

B. Dedicated indicator/transmitter microprocessor-based processing unit.

C. Provides an electronic output signal proportional to the flow of the liquid in a closed pipe system.

D. Capable of operating up to 100-feet between flowmeter sensor and remote indicator/transmitter.

E. System Pipe Parameters:

1. Pipe Sizes, Nominal: 4-inch

2. Pipe Material: PVC.

3. Flow Range: 20-500 GPM

4. Pipe Operating Pressure: 20 psi

PART 2 PRODUCTS

2.01 FLOWMETER SYSTEMS

A. Insertion Electromagnetic Flowmeter

140R1024R0002 QA Log.pdf
Government Answers
Text1: Kachess Dam Modification Phase 3
Text2: Update 1-22-24