This document is an amendment (Amendment 0004) to a solicitation (140R1024B0001) for a potable water conveyance system project. The amendment provides the following key details:
-
Partial responses to questions from the pre-bid site visit on 5/29/2024. Remaining questions 45 and 54 will be addressed in a future amendment.
-
Revisions to technical specifications for vertical turbine pumps (submersible), including updated drawings.
-
Additional technical drawings provided, including for the civil inspection gallery, elevator tower, power plant adit, and miscellaneous details.
-
The bid submission deadline has been extended from 7/24/2024 to 7/31/2024.
-
All solicitation amendments must be acknowledged by the contractor for their bid to be considered responsive.
The overall solicitation is for the HH Potable H20 Conveyance System project, issued by the Department of the Interior's Bureau of Reclamation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C06_01e_Amend__6_-_24B0001-0006_(RELEASED)_8-1-24_0006.pdf | ||
| Sol_140R1024B0001_Amd_0006.pdf | ||
| Sol_140R1024B0001_Amd_0005.pdf | ||
| C06_01_Amend_5_-_24B0001-0005_(RELEASED)_7-22-24_0005.pdf | ||
| C06_01_Amend__4_-_24B0001-0004_(RELEASED)_7-18-24_0004.pdf | ||
| C06_01_Amend__3_-_24B0001-0003_(RELEASED)_6-26-24_0003.pdf | ||
| Sol_140R1024B0001_Amd_0003.pdf | ||
| Sol_140R1024B0001_Amd_0002.pdf | ||
| C06_01_Amend__2_--_24B0001-0002_(Amend__2)_6-17-24_0002.pdf | ||
| Sol_140R1024B0001_Amd_0001.pdf | ||
| C06_01_--_140R1024B0001-00001_(Full_Amend__1)_6-5-24_0001.pdf | ||
| C05-03_--_140R1024B0001_-_CONFORMED_HH_Potable_H20_Convey_System.pdf | ||
| Sol_140R1024B0001.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R1024B0001 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Boise ID 83706-1234 1150 N. Curtis Road, Ste. 100
R10
Acquisition Management Division Regional Office Pacific Northwest Region Bureau of Reclamation
07/18/20240004
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/13/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment #4 (0004) is to provide the following information:
1. Provide a partially completed list of government responses to questions stemming from
5/29/2024 pre-bid site visit. (8 pages)
Note: Remaining questions 45 & 54 will be fully addressed upon future amendment issuance.
2. Provide the following technical specification revisions (5 pages):
-- Signature Sheet / Certification of Technical Specifications -- 43 24 26, Revised
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 20
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R1024B0001/0004 drawings: 60507, 60511, 60512, 60513 & added drawing 60546
-- Vertical Turbine Pumps
(Submersible)-(Revised) 43 24 26 - 4
-- Vertical Turbine Pumps
(Submersible)-(Revised) 43 24 26 - 4A
-- Vertical Turbine Pumps
(Submersible)-(Revised) 43 24 26 - 13
-- Vertical Turbine Pumps
(Submersible)-(Revised) 43 24 26 - 13A
3. Provide the following technical drawings (5 pages):
-- General Cover Sheet and Sheet Index -
Location, Map, Vicinity Map, and Aerial Photo
447-100-60507 - Sheet 1
-- Civil Inspection Gallery (2 of 2) Plan View and Details
447-100-60511 - Sheet 5
-- Civil Block 19 Elevator Tower Elevation
View and Details
447-100-60512 - Sheet 6
-- Civil Power Plant Adit and Floors 3 and 4
Plan View and Details
447-100-60513 - Sheet 7
-- Civil Details Guardrail and Wall/Floor
Penetration Details
447-100-60546 - Sheet 10
4. This bid opportunity is being EXTENDED:
-- FROM: Wed, 7/24/2024 at 2:00 PM MST.
-- TO: Wed, 7/31/2024 at 2:00 PM MST.
5. ALL SOLICITATION AMENDMENT(S) SHALL BE
ACKNOWLEDGED BY THE CONTRACTOR FOR THEIR
RESPECTIVE BID TO BE CONSIDERED RESPONSIVE.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .