01_33_00_and_01_57_20_Spec_Revisions_0004.pdf
PDF 331 KB Posted
- Attached to
- 140R1021B0015 Leavenworth NFH SWISP Phase II
- Solicitation number
- 140R1021B0015
About this file
This solicitation document is for a construction project to rehabilitate the pipeline at the Leavenworth National Fish Hatchery in Washington state. The solicitation requests bids for cured-in-place pipe lining, high density polyethylene pressure pipe, steel piping, valves and equipment, earthwork, erosion control, seeding and other construction activities. Responses are due by January 21, 2022. The award date is scheduled for March 2022. The contract will be administered by the Bureau of Reclamation and involve coordination with the National Fish Hatchery. The contractor must meet environmental, safety, quality control and other standards specified in the attachments.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Leavenworth National Fish Hatchery Surface Water Intake Fish Screens and Fish Passage Project Phase II Pipeline Rehabilitation Columbia Basin Project, WA Solicitation No. 140R1021R0002
Submittals
01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in Price Schedules for other items of work.
1.02 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittal Types, as listed in Table 01 33 00A - List of Submittals:
D. A - Action:
1. Government will respond as to adequacy of submittal.
2. Action Submittals: Considered “shop drawings” within the terms of the clause at
FAR 52.236-21, Specifications and Drawings for Construction.
E. I - Informational:
1. The Government will acknowledge receipt of Informational submittals.
2. The Government may reject an Informational submittal when the submittal does not comply with the contract. The Contractor shall correct mistakes or deficiencies in rejected Informational submittals and resubmit.
3. Informational Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by the Government is not required.
F. CDMS: Construction Document Management System.
1.03 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-12 Decimal Inch Drawing Sheet Size and
Format
B. National Institute of Building Sciences (NIBS)
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 2
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement Units: US Customary Units.
C. Drawings:
1. Minimum Identification in Title Block:
a. Contract number and title.
b. Contractor or supplier’s title and drawing number.
c. Date.
2. Reserve 3- by 3-inch space next to title block for review stamps.
3. Print Size: D size (22 inches by 34 inches).
4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.
a. Lettering shall be neat when drawing preparation with drafting equipment is allowed.
5. Final Drawings:
a. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
6. Final Electronic Drawings: When final electronic drawings are required;
a. Drawing format: AUTOCAD, Version 2010 or later, or as approved by the
COR.
b. Compile using ‘eTransmit’ utility in AutoCAD.
c. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
d. Electronic files: On CD or DVD discs.
e. Original plots: D size (22 inches by 34 inches).
f. Government will provide an electronic AutoCAD template.
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 3
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a Registered Professional: Signed and sealed by registered professional.
2. Manufacturer’s Certifications: Signed by authorized representative of manufacturer.
F. Photographs:
1. When requested.
2. Each COR requested view.
a. Include contract number, name of equipment and view title.
b. Format:
c. Digital Photographs on CD, DVD, or SDHC card in jpeg format. Four
Megapixels minimum. With accompanied prints if requested and of a size requested by the COR.
d. Prints only: Only if specifically requested.
e. Professional quality 8- by 10-inch color.
1) Identify with adhesive labels on back.
a) Do not type directly on back of photograph.
G. Samples Submittals:
1. Label with complete manufacturer's product identification.
2. Include type and quantity of materials specified in the referenced section in each
“set” of samples.
3. Samples: Representative of product to be installed.
4. Label each sample with contract number and title.
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 4
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
C. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
D. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 28 days after receiving the comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.
B. Time in Excess of Specified:
1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.
a. The time extension will be to the extent that excess review time caused delay to the contract completion date.
b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.
2. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the Contract completion date.
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 5
3. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.
4. Adjustment for delay will be made only to the extent that:
a. Approval was required under the contract, and,
b. Requests for approval were properly and timely submitted and were approved.
5. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at
FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Return of Submittals:
1. Action Submittals: One set of submittals required for action will be returned either approved, approved subject to identified changes, or not approved.
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of the CO after drawings, documentation, and technical data have been approved.
2. Informational Submittals: The Government will acknowledge Informational submittals.
a. Informational submittals will not be returned when they comply with the specifications.
b. Informational submittals that do not comply with the specifications may be returned for resubmittal or additional information may be requested.
D. Provide the CO with a copy of all correspondence and related documents, pertaining to this contract that it addresses to representatives of the Government. This does not pertain to the Submittal Requirements as they are outlined herein.
1.07 ELECTRONIC TRANSMITTALS
A. Except as noted, transmit electronically through Government supported CDMS Site.
Contact information will be provided to the Contractor after award.
B. CDMS submittal shall meet the requirements of Article 1.05 Submittal Procedures.
C. Only one complete set shall be submitted with each CDMS submittal.
D. Each submittal shall be submitted separately.
E. Electronic file size shall not exceed 40 Megabytes (MB). Electronic files in excess of 40 MB must be transmitted as hard copy transmittals on suitable storage medium, CD-ROM or other.
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 6
F. Submit data in required format; e.g., survey data ASCII, electronic drawings AutoCAD .dwg.
G. Where format is not specified, preferred format is searchable portable document format (.pdf).
H. The Government, at the discretion of the COR, may require the Contractor to resubmit as hardcopy any transmittals which appear unclear or illegible in their electronic format.
I. Time required for review of each submittal or resubmittal begins on the next business day after transmittal of a complete set and ends the day the response is transmitted.
J. CDMS submittals will be responded to through CDMS.
K. Submittals required by the specifications, but not listed in Table 01 33 00A - List of Submittals:
1. Submit in accordance with this section.
2. Submit to COR, unless otherwise specified.
1.08 HARD COPY TRANSMITTALS
A. Transmit hard copies of transmittals when required by Table 01 33 00A - List of Submittals or these specifications. If there is a conflict between these specifications and Table 01 33 00A - List of Submittals, Table 01 33 00A - List of Submittals shall govern.
B. Addresses for codes listed in Table 01 33 00A - List of Submittals:
1. Contracting Officer (CO), Bureau of Reclamation Contracting Officer, PN-7100, 1150 N. Curtis Road, Boise, ID 83706-1234.
2. Contracting Officer’s Representative (COR) Bureau of Reclamation, PN-3500, 1150 N. Curtis Road. Boise, ID 83706-1234.
3. Technical Service Center, Bureau of Reclamation, Attn: 86-68160, P.O.
Box 25007, Denver, CO 80225-0007; Express Mail: Sixth and Kipling, Building 67, Room 152.
C. Send original transmittal letter with appropriate number of sets to office listed in “Responsible Code” column in Table 01 33 00A - List of Submittals.
1. Send copy of transmittal letter with appropriate number of sets to offices that are not the responsible code but show “Sets to be sent” in Table 01 33 00A - List of Submittals. When “Sets to be sent” is 0, send a copy of transmittal letter to that office.
D. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 7
E. Post copy of transmittal letter to Government supported CDMS Site. Government will post copy of response to Government supported CDMS Site.
F. Hard copies of the following are required:
1. Original signed copies of bonds and insurance.
2. Paint samples or color chips.
3. Physical samples.
4. Release of Claims.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 8
Table 01 33 00A – List of Submittals
* Submittal Types: A – Approval, I – Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule – see Section 01 32 10 – Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates Technical Service Center
RSN
Clau se or Secti on Title required
Due date or
Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
I-01 Release of claims (1452.204-70)
Release of claims (DI-137) against United States
After completion of work and prior to final payment
A CO 1 0 0
I-02 Payroll and Basic Records (52.222-8)
Certified payrolls Weekly for each week any contract work is performed on site
I COR CDMS
I-03 Labor standards data (52.222-11)
(1) List of subcontractors
(2) Statement and Acknowledgment Form (SF-1413) for each subcontract
Within 14 days after award of contract, and within 14 days after award of any subcontract
I COR CDMS
I-04 Equal opportunity (52.222-26)
Information required by Executive Order
11246 (SF-100)
Within 30 days following award
I COR CDMS
I-05 Bonds (52.228- 15)
Performance and payment bonds
Within 10 calendar days after award
A CO 1 0 0
I-06 Estimate of Percentage of Recovered Material Content of
EPA-
Designated Items (52.223- 9)
Estimate the percentage of the total recovered material content for EPA designated item(s) delivered and/or used in contract performance
On completion of the contract (no later than with submittal of final voucher)
I COR CDMS
I-07 Security Requirements
(WBR
1452.237- 80)
Security Program Submitted and approved before mobilization
A Y COR CDMS
I-08 Security Requirements
(WBR
1452.237-
List of Onsite Employees
At least 7 days before employee arrival
I COR CDMS
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 9
80)
I-09 Liability Insurance
(WBR
1452.228-70)
Acceptable evidence showing that insurance has been obtained
Within 10 calendar days after award
A CO 1 0 0
01 14 10-1
Use of Site Land Use and Landscape Rehabilitation Plan
At least 28 days before use of Government land
A Y COR CDMS
01 14 10-2 Use of Site Other Land Use Coordination
At least 28 days before use of private land
A Y COR CDMS
01 14 30-1
Interruption of Services
Interruption of Electrical Services Request
At least 14 days before interruption is scheduled
A Y COR CDMS
01 31 19-1
Project Management and Coordination
Progress Review Meeting Agenda and Minutes
Weekly I COR CDMS
01 31 30-1
Contract Document Management System
Approval Data Within 10 days of
NTP
A COR Hardcopy
01 31 30-2
Contract Document Management System
Final Data At Closeout A COR CDMS
01 32 10-1
Construction Program
Representative Information
Within 10 days of Notice of Award
A COR CDMS
01 32 10-2 Construction Program
Baseline Schedule Within 21 days after receipt of Notice to Proceed
A COR CDMS
01 32 10-3 Construction Program
Updated Schedule Reports
Monthly
When invoice for progress payments will be submitted, submit at least 7 days before invoice
A COR CDMS
01 32 10-4 Construction Program
Time Impact Analysis
Within 28 days after the CO directs a contract change, or requests proposal for a future modification, A COR CDMS
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 10 with value engineering proposal, or request for equitable adjustment
01 35 10-1 Safety Data Sheets
Complete LHM and SDS
At least 14 days before jobsite delivery of hazardous material.
I COR CDMS
01 35 10-2 Safety Data Sheets
Updated LHM and SDS
At least 14 days before jobsite delivery of hazardous material not previously listed
I COR CDMS
01 35 20-1 Safety and Health
Safety and Health Program
At least 40 days before beginning onsite work
A COR
CDMS
01 35 20-2 Safety and Health
Monthly Accident Summary Report
At least 40 days before beginning onsite work
A COR
CDMS
01 35 20-3 Safety and Health
Respirator User Documentation
At least 40 days before beginning onsite work
A COR
CDMS
01 35 20-4 Safety and Health
Crane Operation Certificates
At least 40 days before beginning onsite work
A COR
CDMS
01 35 20-5 Safety and Health
Other Training Certificates
At least 40 days before beginning onsite work
I COR CDMS
01 35 20-6 Safety and Health COVID-19
Notification
Immediately upon Notification of Positive Results
I COR Encrypted
01 35 20-7 Safety and Health
Employee Return to Work Documentation
Immediately upon Notification of Clearance
I COR Encrypted
01 35 22-1 First Aid Medical Facilities Plan
At least 28 days before start of construction or on- site activities
I COR CDMS
01 35 30-1 Contractor’s Onsite Safety and Health Personnel
Qualifications At least 56 days before start of construction or on-site activities
A COR CDMS
01 35 30-2 Contractor’s Onsite Safety and Health Personnel
Safety Inspection Reports
Weekly I COR CDMS
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 11
01 46 00-1 Quality Procedures
Contractor’s Daily Reports
Weekly I COR CDMS
01 46 00-2 Quality Procedures
Quality Control Manager Resume
At least 28 days before start of construction or on- site activities
A COR CDMS
01 46 00-3 Quality Procedures
Contractor’s Quality Testing Plan
At least 28 days before start of construction or on-site activities
A COR CDMS
01 46 00-4 Quality Procedures
Summary Monthly Test Results
Monthly I COR CDMS
01 46 20-1 Testing Agency Services
Testing Agency Services Plan
At least 28 days before start of construction activities
A COR CDMS
01 55 00-1 Vehicular Access and Parking
Preconstruction Video
Within 2 days of completing video
I COR DVD
01 55 20-1 Traffic Control Traffic Control Plan
At least 28 days before start of construction activities
A COR CDMS
01 56 10-1 Protection of Existing Utilities and Installations
Plan for Protecting Existing Utilities and Installations
At least 28 days before start of construction activities
A COR CDMS
01 57 20-1 Environmental Controls
Copy of Applicable Air Quality Permit
At least 28 days before start of construction activities
I COR CDMS
01 57 20-2 Environmental Controls
Dust Abatement Plan
At least 28 days before start of construction activities
A COR CDMS
01 57 20-3 Environmental Controls
Noise Reduction Draft Plan
At least 84 days before start of construction activities
A COR CDMS
01 57 20-4 Environmental Controls
Noise Reduction Final Plan
At least 28 days before start of construction activities
A COR CDMS
01 57 20-5 Environmental Controls
Noise Reduction Monitoring
Daily I COR CDMS
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 12
01 57 30-1 Water Pollution Control
Pollution Prevention Plan
At least 28 days before start of onsite work
A Y COR CDMS
01 57 30-2 Water Pollution Control
Spill Prevention, Control, and Countermeasure (SPCC) Plan
At least 28 days before delivery or storage of oil
A COR CDMS
01 57 50-1 Tree and Plant Protection
Protection Plan At least 28 days before start of onsite work
A COR CDMS
01 57 70-1 Fire Protection and Prevention
Approved Fire Protection and Prevention Plan
At least 28 days before start of onsite work
A COR CDMS
01 57 90-1 Preservation of Historical and Archeological Data
Proposed Use, Borrow, and Spoil/Waste Areas
At least 56 days before start of onsite work
A COR CDMS
01 71 20-1 Surveying Surveying Plan At least 28 days before beginning survey work
A COR CDMS
01 71 20-2 Surveying Resume At least 28 days before beginning survey work;
At least 28 days before personnel change
I COR CDMS
01 71 20-3 Surveying Accuracy Check Results
At least 14 days before beginning survey work
I COR CDMS
01 71 20-4 Surveying Electronic Survey Data Files and Printouts
Within 2 days of completing each set of survey notes
I COR CDMS
01 71 20-5 Surveying Quantity Survey Notes and Computations
Accompanying progress payment requests
A COR CDMS
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
Monthly and within 14 days of completion of work
A COR CDMS
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
Within 7 days of waste disposal
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 13
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
At least 28 days before beginning environmental assessment
I COR CDMS
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
At least 28 days before beginning environmental assessment
I COR CDMS
01 78 30-1 Project Record Documents
Draft As-built Drawings
Updated Weekly A COR 0 1 1
01 78 30-2 Project Record Documents
Final As-built Drawings
Within 28 days of completion of onsite work
A COR 0 1 1
02 41 10-1 Selective Site Demolition
Demolition Plan At least 28 days before start of onsite work
A COR
CDMS
02 80 10-1 General Requirements for Hazardous Materials
Qualifications At least 28 days before starting abatement
A COR
CDMS
02 80 10-2 General Requirements for Hazardous Materials
Worker Protection Plan
At least 28 days before starting abatement
A COR
CDMS
02 80 10-3 General Requirements for Hazardous Materials
Background Test Results
Within 7 days of testing.
A COR
CDMS
02 80 10-4 General Requirements for Hazardous Materials
Working Level Test Results:
Within 1 day of testing A COR
CDMS
02 80 10-5 General Requirements for Hazardous Materials
Post-construction Test Results
Within 7 days of testing
A COR
CDMS
02 80 10-6 General Requirements for Hazardous Materials
Asbestos Clearance Test Results
Within 1 day of testing A COR
CDMS
02 82 20-1 Removal and Disposal of Asbestos Containing Materials
Certificates At least 28 days before starting abatement
I COR
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 14
02 82 20-2 Removal and Disposal of Asbestos Containing Materials
Asbestos Inspection
Within 14 days of completing inspection
I COR
CDMS
02 82 20-3 Removal and Disposal of Asbestos Containing Materials
Asbestos Contractor History
At least 28 days before starting abatement
I COR
CDMS
02 82 20-4 Removal and Disposal of Asbestos Containing Materials
Certificates At least 28 days before starting abatement
I COR
CDMS
02 82 20-5 Removal and Disposal of Asbestos Containing Materials
Asbestos Notification of Demolition and Renovation
At least 14 days before starting abatement
I COR
CDMS
02 82 20-6 Removal and Disposal of Asbestos Containing Materials
Certificate of Disposal
Within 28 days of disposal.
I COR
CDMS
03 11 10-1 Concrete Forming
Formwork Design and Drawings
At least 28 days before start of onsite work
A COR
03 20 00-1 Concrete Reinforcing
Reinforcement Diagrams and Lists
At least 28 days before start of onsite work
A COR CDMS
03 30 00-1 Cast-in-Place Concrete
Approval Data At least 28 days before start of onsite work
A COR
03 30 00-2 Cast-in-Place Concrete
Concrete Placement Drawings
At least 28 days before start of onsite work
I COR
03 30 00-3 Cast-in-Place
Concrete Placement Schedule
At least 28 days before start of onsite
03 30 00-4 Cast-in-Place
Certifications At least 28 days before
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 15
03 30 00-5 Cast-in-Place Concrete
Pre-Placement Inspection Placement Cards
At least 2 days before start concrete placement
03 30 00-6 Cast-in-Place Concrete
Test Reports Within 1 day of test completion
03 30 00-7 Cast-in-Place
Control Valve Vault Calculations and Shop Drawings
At least 28 days before start of onsite
03 30 00-8 Cast-in-Place
Control Valve Vault Installation Plan
At least 56 days before start of onsite
03 48 00-1 Precast
Structures
Certificates, Product Data and Test Reports
At least 90 days before fabrication
I Y COR
03 48 00-2 Precast
Structures
Shop Drawings At least 90 days before fabrication
A Y COR
03 48 00-3 Precast
Structures
Approval Data At least 90 days before fabrication
A Y COR
03 48 00-4 Precast
Structures
Dry-Fit Test At Factory, prior to shipping to site
I COR
03 62 20-1 Nonshrink Grout for Equipment and Metalwork
Packaged Nonshrink Grout Data
At least 28 days before
03 81 10-1 Concrete Removal and Disposal
Concrete Removal and Disposal Plan
At least 28 days before start of onsite work
I COR CDMS
08 31 20-1 Floor Access Hatches
Product Data At least 28 days before installation
A COR
09 96 20-1 Coatings Approval Data At least 42 days before start of onsite work
A COR
09 96 20-2 Coatings Final Approval Data
At least 28 days before start of onsite work
A COR
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 16
09 96 20-3 Coatings Paint Chip Samples
At least 28 days before start of onsite work
A COR 0 1 1
09 96 20-4 Coatings Qualifications At least 28 days before start of onsite work
A COR
09 96 20-5 Coatings Quality Control Plan
At least 28 days before start of onsite work
A COR
09 96 20-6 Coatings Contractor Quality Testing Report
Within 3 days of Testing
A COR
26 05 10-1 Conductors and Cables
Approval Data At least 56 days before start of onsite work
A COR
26 05 10-2 Conductors and Cables
Construction Documentation
Within 14 Days of Completion
A COR
26 05 26-1 Grounding and Bonding
Approval Data At least 56 days before start of onsite work
A COR
26 05 26-2 Grounding and
As-Built Drawings
Within 14 Days of Completion
A COR
26 05 26-3 Grounding and
Test Reports Within 14 Days of Completion
A COR
26 05 33-1 Raceways and Boxes
Approval Drawings and Data
At least 56 days before start of onsite work
A COR
26 05 33-2 Raceways and Boxes
As-Built Drawings and Data
Within 14 Days of Completion
A COR
26 05 80-1 Wiring Checkout and Tests
Test Reports Within 7 days of Test Completion
A COR
26 24 20-1 Control Boards
Approval Drawings and Data
At least 56 days before start of onsite work
A COR
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 17
26 24 20-2 Control Boards
Check Prints At least 35 days before start of onsite work
A COR
26 24 20-3 Control
Factory Test Report
At least 28 days before start of onsite work
A COR
26 24 20-4 Control
Final Drawings Within 14 days of Completion
A COR
26 24 20-5 Control
Operation and Maintenance Instruction Book
Within 28 days of completion of onsite work
A COR
31 03 10-1 Diversion and Care of Water During Construction
Plan for Temporary Pumping
At least 84 days before start of onsite work
A COR
31 03 33-1 Removal and Control of Water
Removal and Control of Water Plan
At least 28 days before start of onsite work
A COR
31 23 02-1 Compacting Earth Materials
Test Results Within in 1 day of test
31 23 02-2 Compacting Earth Materials
Method Specification Verification
At least 28 days before start of onsite work
A COR CDMS
31 23 11-1 Earthwork for Pipe and Structures
Excavation and Backfill Plan for Control Valve Structure
At least 28 days before start of onsite work
A COR
31 23 11-2 Earthwork for Pipe and Structures
Excavation and Backfill Plan for Pipeline Trench
At least 28 days before start of onsite work
A COR
31 23 70-1 Controlled Low Strength Material
Approval Data At least 56 days before start of onsite work
A COR
31 23 70-2 Controlled Low Strength Material
Contractor Field Quality Testing Results
Within in 1 day of test completion
A COR
31 25 10-1 Erosion Control
Silt Fence Certifications
At least 28 days before
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 18
31 25 10-2 Erosion Control
Straw Certification
At least 28 days before start of onsite work
A COR CDMS
32 12 00-1 Asphaltic Concrete Repairs
Asphaltic Concrete Repair Plan
At least 28 days before start of onsite work
A COR
32 15 10-1 Gravel Surfacing
Certification and Laboratory Test Results
At least 28 days before start of onsite work
A COR CDMS
32 92 20-1 Seeding and Soil Supplements
Seeding Plan At least 28 days before start of onsite work
A COR
32 92 20-2 Seeding and Soil Supplements
Certifications At least 28 days before start of onsite work
A COR
33 05 30-1 Control Valve Vault
Construction Schedule and Installation Plan
At least 56 days before start of onsite work
A COR
33 05 30-2 Control Valve
Approval Drawings
At least 35 days before start of onsite work
A COR
33 05 30-3 Control Valve
Calculations At least 35 days before start of onsite work
A COR
33 11 10-1 Cured in Place Pipe
CIPP Lining Manufacturer Resume
At least 84 days before start of onsite work
A COR
33 11 10-2 Cured in Place
CIPP Installer Resume
At least 84 days before start of onsite work
A COR
33 11 10-3 Cured in Place
Existing Pipeline Video Inspection
At least 56 days before start of onsite work
A Y COR
33 11 10-4 Cured in Place
Existing Pipeline Survey
At least 56 days before start of onsite work
A Y COR
33 11 10-5 Cured in Place
CIPP
Manufacturer’s Certification
At least 56 days before start of onsite work
A COR
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 19
33 11 10-6 Cured in Place Pipe
CIPP Installer’s Certification
At least 56 days before start of onsite work
A COR
33 11 10-7 Cured in Place
CIPP Design Calculations
At least 84 days before start of onsite work
A Y COR
33 11 10-8 Cured in Place
Product Information
At least 84 days before start of onsite work
A COR
33 11 10-9 Cured in Place
Product Samples At least 56 days before start of onsite work
A COR 0 1 1
33 11 10-10 Cured in Place Pipe
Site Use Plan At least 84 days before start of onsite work
A COR
33 11 10-11 Cured in Place
Installation and Curing Plan
At least 84 days before start of onsite work
A COR
33 11 10-12 Cured in Place
Testing Plan At least 84 days before start of onsite work
A COR
33 11 10-13 Cured in Place
Site Restoration Plan
At least 56 days before start of onsite work
A COR
33 11 18-1 HDPE
Pressure Pipe
Qualifications At least 56 days before start of onsite work
A COR
CDMS
33 11 18-2 HDPE
Pressure Pipe
Pipe Laying Diagrams
At least 56 days before start of onsite work
A COR
CDMS
33 11 18-3 HDPE
Pressure Pipe
Shop Drawings At least 56 days before start of onsite work
A COR
33 11 18-4 HDPE
Certification At least 56 days before start of onsite work
A COR
33 11 18-5 HDPE
Fusion Procedures At least 56 days before start of onsite work
A COR
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 20
33 11 18-6 HDPE
Pressure Pipe
Pipe Deflection Measurements
Within 1 day of test completion
A COR
33 11 18-7 HDPE
Heat Fusion Joint Operator Qualifications
At least 56 days before start of onsite work
A COR
CDMS
33 11 18-8 HDPE
Pressure Pipe
Filling and Testing Plan
At least 56 days before start of onsite work
A COR
CDMS
33 11 18-9 HDPE
Pressure Pipe
Floatation Prevention Plan
At least 56 days before start of onsite work
A COR
CDMS
35 21 95-1 Steel Piping Shop Drawings At least 28 days before start of onsite work
A COR
35 21 95-2 Steel Piping Commercial Products Data
At least 28 days before start of onsite work
A COR
35 21 95-3 Steel Piping Pipe Installation Procedure
At least 28 days before start of onsite work
A COR
35 21 95-4 Steel Piping Field Weld Test Results
Within 1 day of test completion
A COR
35 21 95-5 Steel Piping Final Drawings Within 14 days of
I COR
35 22 14-1 Valves and Equipment
Commercial Product Data
At least 28 days before start of onsite work
A COR
35 22 14-2 Valves and
Check Prints At least 28 days before start of onsite work
I COR
35 22 14-3 Valves and
Shop Testing Certifications and Report
At least 28 days before start of onsite work
A COR
35 22 14-4 Valves and
Service Manuals Within 14 days of completion
A COR
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 21
END OF SECTION
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 33 00 - 22
This page intentionally left blank.
Columbia Basin Project, WA Solicitation No. 140R1021R0002
Environmental Controls
01 57 20 - 1
SECTION 01 57 20
ENVIRONMENTAL CONTROLS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in Price Schedules for other items of work, except as specified.
2. Costs for damages and work stoppage are the Contractor's responsibility.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (Reclamation)
1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/safety/rshs/index.html
B. Reclamation Project Website
1. Surface Water Intake Fish Environmental Impact Statement and Screens and Fish Passage Resource Reports posted at 1.
https://www.usbr.Gov/pn/programs/ Leavenworth/swisp/index/html
1.03 SUBMITTALS
A. Submit in accordance with Section 01 33 00 - Submittals.
B. RSN 01 57 20-1, Copy of Applicable Air Quality Permit:
C.1. Air Quality Permits are required for certain construction-related activities including, but not limited to, earthmoving, sandblasting, aggregate processing, welding, spray-coating operations, or other processes which discharge pollutants into the open air.
D.C. RSN 01 57 20-2, Dust Abatement Plan:
1. Submit Dust Abatement Plan.
a. Include the following:
1) See Article 1.05, Dust Control.
2) Maintain copy of plan onsite.
http://www.usbr.gov/safety/rshs/index.html
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 57 20 - 2
D. RSN 01 57 20-3, Noise Reduction Draft Plan:
1. Noise reduction measures to minimize construction noise.
a. Includes, but not limited to the following:
1) Noise from pumps, generators and motors.
2) Equipment noise and motors.
3) General construction activities.
E. RSN 01 57 20-4, Noise Reduction Final Plan:
1. Noise reduction measures to minimize construction noise.
a. Includes, but not limited to the following:
1) Comments from review of RSN 01 57 20-3, Noise Reduction Draft
Plan.
a) Includes comments from:
i. Icicle River RV Resort.
ii. Icicle Creek Center of the Arts.
iii. Sleeping Lady Mountain Resort.
F. RSN 01 57 20-5, Noise Reduction Monitoring:
1. Includes the following:
a. Perform continuous monitoring of noise at, or in the vicinity, of the following locations, as determined by the COR:
1) Icicle River RV Resort.
2) Icicle Creek Center of the Arts.
3) Sleeping Lady Mountain Resort.
2)b. Submit monitoring results to the COR daily.
1.04 REGULATORY REQUIREMENTS
A. Comply with Federal, State, and local laws and regulations.
B. Comply with RSHS.
C. Reference the Reclamation Project Website for additional information regarding the Environment Impact Statement and Resource Reports. See Article 1.02 B.
C.D. Conform to most stringent requirement in cases of conflict between specifications, regulatory requirements, and RSHS.
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 57 20 - 3
D.E. Contractor shall be responsible for damages resulting from dust originating from Contractor operations in accordance with clause at FAR 52.236-7, Permits and Responsibilities.
E.F. The CO may stop construction activity in violation of Federal, State, or local laws and additional expenses resulting from work stoppage will be responsibility of Contractor.
1.05 DUST CONTROL
A. Provide dust control and abatement during performance of work.
1. Water for dust control to be obtained as determined by COR.
a. See Section 01 51 00 – Temporary Utilities, Article 1.04.
B. Prevent, control, and abate dust pollution on rights-of-way provided by Government or elsewhere during performance of work.
C. Provide labor, equipment, and materials, and use efficient methods wherever and whenever required to prevent dust nuisance or damage to persons, property, or recreational activities.
D. Provide means for eliminating atmospheric discharges of dust during mixing, handling, and storing of cement, pozzolan, and concrete aggregate.
1.06 AIR POLLUTION CONTROL
A. Use reasonably available methods and devices to prevent, control, and otherwise minimize atmospheric emissions or discharges of air contaminants.
B. Do not operate equipment and vehicles that show excessive exhaust gas emissions until corrective repairs or adjustments reduce such emissions to acceptable levels.
1.07 NOISE CONTROL
A. Only construction activities approved by CO will be allowed during hours of 7 P.M. to 7 A.M.
1. After hours construction activities need to be approved by the CO.
B. Daytime Noise Levels:
1. Government will determine the baseline noise levels based on daytime measurements during construction.
PART 2 PRODUCTS
Columbia Basin Project, WA Solicitation No. 140R1021R0002
01 57 20 - 4
PART 3 EXECUTION
END OF SECTION
| 01 33 00 - Submittals_Rev_002 |
| 01 57 20 - Environmental Controls_Rev_002 |