JELA_325250_335621_-_RFI_Log_-_Amendment_002_0002.pdf

PDF 229 KB Posted

Attached to
JELA 325250 335621 - Rehabilitate Cemetery
Solicitation number
140PP027R0004
Issued by
Not on record

About this file

This document is a Consolidated RFI (Request for Information) Tracking Log for federal contract solicitation 140PP027R0004, issued by the National Park Service for the rehabilitation of Chalmette National Cemetery (JELA 325250 / 335621). The solicitation contains 145 tracked RFIs addressing specifications, drawings, permits, labor classifications, scheduling, and contract administration across two contract line items (CLINs): CLIN 1 for Cemetery Rehabilitation (LRF funding) and CLIN 2 for Stormwater improvements (DS-22 funding).

The project scope includes removal and replacement of approximately 3,549 grave markers, historic masonry wall repair and repointing, perimeter fencing restoration, concrete and brick curbing work, stormwater drainage system installation with an approximately 124 linear foot outfall, site grading and turf establishment, tree protection and arborist services, and interpretive signage installation. Key outstanding issues addressed include specification cross-reference conflicts, section cross-references, CLIN allocation clarification, spalled-brick allowances, permit responsibilities (Norfolk Southern Environmental Right of Entry, Southeast Louisiana Flood Protection Authority Levee Safety Permit, NPDES stormwater permit, USACE authorization MVN-2026-00072-ENP), archaeological monitoring procedures, drainage pipe quantities and materials specifications, replacement brick and mortar testing results, wage determination classifications (Building and Heavy Construction determinations LA20260038 and LA20260005), option exercise periods (90 calendar days after award), and baseline schedule requirements. The government responses clarify that the contractor is responsible for certain permits and construction-related approvals; that archae­ological monitoring will be government-furnished; that work must proceed sequentially by cemetery section with potential COR approval for concurrent work; that the site will be closed to the public during construction; and that government-furnished headstones will be coordinated with the contractor's approved phasing plan.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tracking No. Subject / Category Question / Request Drawing Reference Specification / Solicitation Reference Government Response

RFI-001 Specifications / Cross- References

Please clarify the following cross-reference conflicts: (a) G1.2 Concrete Roadway Notes 4 and 7 cite Sections 03 33 00 and 03 33 10, but the specification contains 03 30 00 and 03 33 10 and no 03 33 00 (Spec 03 33 10 also cites "03 00 10"). Please confirm 03 30 00 (cast-in-place) and 03 33 10 (exposed aggregate) govern. (b) The Table of Contents lists 33 34 00 Storm Drainage Piping and 10 75 16 Ground Set Flag Pole, but no 33 34 00 section is included and the flagpole section is numbered 10 75 00; Sections 01 14 13, 01 73 29 and 07 92 00 are in the book but not in the TOC. Which section governs storm piping (33 05 39, 33 30 00, 33 05 13)? (c) Various sections cite non-existent sections (32 91 00, 32 91 20, 31 20 00, 32 22 50, 01 60 00, 01 30 00, 08 71 00, 01 35 25, 03 31 00). Please identify the intended sections.

G1.2 (Concrete Roadway Notes 4, 7, 14); A6.0 Note D; C3.5

03 33 00; 03 30 00; 03 33 10; 03 00 10; 33 34 00; 10 75 00/10 75 16; 32 91 00; 32 91 20; 31 20 00;

32 22 50; 01 60 00; 01 30 00; 08 71 00; 01 35 25; 03 31 00

(a) Confirmed. Section 03 30 00 – Cast-in-Place Concrete and Section 03 33 10 – Exposed Aggregate Concrete govern, as applicable. (b) 33 34 00 – Storm Drainage Piping was inadvertently listed in the Table of Contents but was not included as a project specification section. For reinforced concrete storm drainage piping, Section 33 05 39 – Reinforced Concrete Pipe shall govern. Section 33 30 00 – Stormwater Utility Structures and Section 33 05 13 – Manholes shall govern the respective structures indicated on the Drawings. (c) 32 91 00 - 32 91 13 – Planting Soil shall govern, 32 91 20 - 32 91 19.20 – Landscape Grading shall govern, 31 20 00 - 31 23 00 – Earth Moving shall govern, 32 22 50 - 31 11 50 – Selective Turf Removal shall govern, 01 60 00 - 01 67 00 – Product Requirements shall govern 01 30 00 - 01 31 00 – Project Management & Coordination shall govern 08 71 00 - 08 11 74 - Sliding Metal Grilles shall govern, 01 35 25 - 01 35 23 – Safety Requirements shall govern, 03 31 00 - 03 33 10 - Exposed Aggregate Concrete shall govern

RFI-002 Bid Schedule / CLIN Allocation

Please provide a definitive allocation of work between CLIN 1 (Cemetery Rehabilitation, LRF funding) and CLIN 2 (Stormwater, DS-22 funding).

Specifically identify the CLIN for: roadway removal/replacement and historic brick curbing; grading and turf/sod restoration over drainage work;

dewatering; storm-related utility relocations; grave-marker removal/reset within ponding areas (01 27 00 para 3.1.B.2) vs. the general marker work;

the four historic nodes, new site features, parking, seating and interpretive elements named in Sec. C and Spec 01 11 00 but not in the 01 27 00 CLIN descriptions; the Maintenance Shed, flagpole and site furnishings; and the "no direct payment" items in G1.2 Notes 13, 15, 18 and 19. Please also confirm the percentage-complete payment basis for each CLIN.

L3.1-L3.6; A0-A1; C3.1-C3.8;

C4.1-C4.6

Sec. B; Spec 01 27 00 paras 1.1.B, 3.1.A-C; Sec. C

CLIN 1, Cemetery Rehabilitation / LRF: the general cemetery rehabilitation, preservation, landscape, monument, headstone/marker, site-feature, and visitor-amenity scope.

CLIN 2, Stormwater / DS-22:

Roadway removal/replacement and historic brick curbing.

All work related to Grading Area 01 and 02 including headstone/marker work, sodding, filling etc.

The complete stormwater system and all demolition, temporary work, protection, relocation, reconstruction, grading, and restoration made necessary by that stormwater work. Curb and roadway reconstruction.

The notes referenced are to ensure the contractor keeps the site in working order and relatively tidy condition protecting existing infrastructure at no extra cost to the owner.

Basis of payment will be percent complete of each CLIN.

RFI-003 Bid Schedule / Option

Spalled-brick allowances conflict: A0.1 Note C states approximately 30 spalled bricks per panel where 25% of the section is missing; A1.1 Note 3 base bid assumes 15 per panel at 50% loss or greater, and Bid Option #1 assumes 20 per panel at 25-49%; Spec 01 27 00 describes Option 1 as "25 to 49% loss or greater." Please (a) state which loss thresholds and per-panel counts govern the base bid and Option 1; (b) provide the total panel count and locations included; (c) confirm what Option 1 includes (removal, replacement brick, mortar, access, protection, repointing) and how it is measured; (d) state the treatment where loss exceeds 49%; and (e) address A1.1 Note M (bricks heavily bedded; extraction may require deconstructing surrounding brick). Also reconcile the option period: Sec. B states 180 days from award; Special Requirement 4 allows exercise within 90 days.

A0.1 General Note C; A1.1 Note 3 and Note M; A9.3

Sec. B (CLIN 3); Spec 01 27 00 Opt. 1; Special Req. 4; Spec 04 09 20

(A) Sheets A0.1-A0.6 do not indicate an allowance. Sheets are noted as for reference only describing existing conditions and do not direct any scope of work.

The threshold for performing base bid work is 50% loss or greater as shown on Sheets A1.1-A1.6 note 3 and for stated quantities.

Bid Option #1 captures 25-49% loss for stated quantity.

(B) Refer to A0 and A1 series for panel numbering.

(C) Bid option 1 requires brick removal and replacement.

(D) Replace brick where loss exceeds 49% as noted in Base Bid.

RFI-004 Permits / Regulatory Please identify every outstanding permit, license, consent and third-party approval the Contractor must obtain, who pays fees, and provide copies of all approvals already obtained. Spec 01 31 00 lists as "Government-furnished" a Section 401/404/408 permit marked "To be issued" and the Railroad Longitudinal Occupation License (RailPros/Norfolk Southern), but also lists the railroad license as a potential Contractor permit, and Spec 01 11 00 para 1.14.C assigns Norfolk Southern permits/agreements to the Contractor.

Please clarify the status of: USACE (MVN-2026-00072-ENP) and any Section 408 permission; LDCE coastal consistency/NDSI (required by the USACE letter); St. Bernard Parish (stormwater/MS4, dewatering, street closure, utility hookups); South Louisiana Flood Protection Authority levee safety permit/statement of no objection; Urban Forester permit (G1.2 Arboricultural Note 1); and approvals for River Road, Port and water-treatment-plant access.

G1.2 Arboricultural Requirements Note 1

FAR 52.236-7; Spec 01 31 00 (Government-furnished and potential permits); Spec 01 11 00 paras 1.14.C-E; Att. 5

Urban Forester Permit will not be required for this project. The Contractor will need to acquire a Norfolk Southern (NS) Environmental Right of Entry (EROE), see Norfolk Southern's website for requirements. The Prime Contractor to furnish agreements and the required insurances. Contractor responsible for Southeast Flood Protection Authority Levee Safety Permit and the NPDES National Pollution Discharge Elimination System storm water runoff permit/plan. Contractor responsible for relevant constructed related permits.

RFI-005 Permits / USACE Alignment

Att. 5 exhibits show a 0.42-acre limit of disturbance, a 1.57-acre equipment workspace, 15.7 acres of gravestone realignment with 32-inch maximum excavation depth, and an earlier 11-sheet stormwater set (e.g., stations 299+50-303+50 and "Option 2 Proposed Ditch") dated 5/4/2026 and marked "Not for Construction." The contract set contains 8 stormwater sheets (C3.1- C3.8) dated 9/22/2026. Please confirm that the final design and all contemplated activities (pipe trenching, wall below-grade excavation of 30 inches or more, staging areas on C2.1-C2.3, ground-protection mats, access routes) are fully covered by USACE authorization MVN-2026-00072-ENP. If a permit amendment is needed, who prepares it, and how are delay and cost treated? Please also provide the executed ENG Form 1721 / permit enclosures (the form in Att. 5 is blank).

C3.1-C3.8 vs. Att. 5 storm sheets (marked Sheet 6 of 11, Sheet 9 of 11; 5/4/2026 "Not for Construction"); C2.1-C2.3; L1.x

Att. 5 USACE letter 9/30/2026 and exhibits; Spec 01 11 00 para 1.14.E

No amendments to this permit are needed. Minor changes to the total acreage of potential wetland impact are within the scope of the furnished Nationwide permit.

RFI-006 Railroad / Third-Party Access

Please clarify (a) which party obtains the Railroad Longitudinal Occupation License / RailPros authorization and Norfolk Southern right-of-entry (Spec 01 31 00 lists it as Government-furnished and as a potential Contractor permit;

Spec 01 11 00 para 1.14.C assigns it to the Contractor); (b) required flagging, inspection/protective services, insurance, submittals, work windows and fees, and whether any are reimbursable; (c) where the "existing culvert on Norfolk Southern property" repair described in Spec 01 11 00 para 1.2.B is shown on the drawings (it was not located on the sheets reviewed); and (d) the status of access across Port property and the NPS easements shown on C3.6- C3.8.

C3.6-C3.8 (railroad property, NPS/Port easements at outfall)

Spec 01 11 00 paras 1.2.B, 1.14.C; Spec 01 31 00 (permits)

(c) Spec 01 11 00 para 1.2.B - (a) The Contractor will need to acquire a Norfolk Southern (NS) Environmental Right of Entry (EROE), see Norfolk Southern's website for requirements. The Prime Contractor to furnish agreements and the required insurances. (c) This work related to "the existing culvert" on Norfolk southern property is not in the scope but an Environmental Right of Access will still need to be obtained prior to construction for work related to road resurfacing and drainage improvements.

(b) and (d) -All areas between the gates and St Bernard Highway are owned by the Railroad and not the Port.

Solicitation No. 140PP027R0004 | Consolidated RFI Tracking Log JELA 325250 / 335621 – Rehabilitate Chalmette National Cemetery

RFI-007 Archaeology / Unknown Conditions

Please confirm (a) whether the Government furnishes and pays for the Archeological Monitor or the Contractor must hire one, and the staffing level, hours, mobilization time and response time bidders should assume; (b) the soil screening methods, production assumptions, staffing and allowable disposition of excavated soil; (c) whether stoppages (discovery, unmarked graves/human remains, 50-ft buffer, 24-hour notifications under the USACE special conditions) not caused by the Contractor receive an equitable adjustment for standby, remobilization, resequencing, extended overhead and time; (d) the schedule for Park Compliance Coordinator training required before ground disturbance; and (e) whether the historic well on C3.5 requires review before filling.

C1.1 Demolition Note 4; C3.5 (historic well fill); G1.2 Archeological Protection

Spec 01 35 13.22; Spec 01 11 00 para 1.10; Spec 02 41 92; 12 93 01/12 93 02; Att. 5 USACE special conditions

Monitor will be provided by the NPS. Screening of soil would not be required unless a discovery was made. The USACE permit was updated, and the archeology language was removed. The NPS just signed a Programmatic Agreement with the SHPO to streamline all work and possible discoveries at Chalmette. Programmatic Agreement and Updated Permit to be included in this amendment.

RFI-008 Drainage / Outfall and Option 2

C3.7 shows a +/-124 LF 44"x27" RCPA outfall at stations 200+00-203+49;

C3.8 shows +/-131 LF of 44"x27" RCPA at stations 299+50-303+50 with a different plan orientation, near active railroad tracks; Spec 01 27 00 states approximately 131 LF to a riprap-lined ditch "west of the cemetery." Several sheets are labeled "Option 2" (C3.7, C3.8, C9.2 "Drainage Option 2"; Spec 31 05 19 "Option 2 outfall if applicable"), but the bid schedule has only Option 1 (brick). Please clarify (a) what "Option 1" and "Option 2" mean for the outfall and which is in the base bid; (b) which length, alignment and station system govern; (c) the ditch/swale limits, grading, riprap extents and geotextile; (d) the limits, capacity, environmental restrictions and acceptance criteria for diverting stormwater to the North Woods; and (e) whether the Government has confirmed the discharge is permitted and hydraulically adequate.

C3.7, C3.8, C9.2, C10.1 detail 3;

C3.6

Spec 01 27 00 para 3.1.B.1; Spec 01 11 00 para 1.2.B; Spec 31 05 19 (Option 2 outfall); Spec 33 40 10; Spec 31 37 00

(a) There are no Option 1 or Option 2 alternatives for the outfall. Disregard all references to Outfall “Option 1” and “Option 2” in the Drawings and Specifications. (b) The outfall consists of approximately 124 LF of 44-inch x 27-inch RCPA. The alignment and stationing shown on Sheet C3.7 shall govern. (c) Construct the outfall ditch/swale, grading, riprap, and geotextile within the limits and to the elevations indicated on Sheet C3.7 and the referenced details. (d) Conduct construction activities in accordance with the applicable environmental protection and stormwater pollution prevention requirements of the Contract Documents. (e) The proposed North Woods outfall has been evaluated as part of the project drainage design and hydraulic analysis and is considered hydraulically adequate for the intended design conditions. Environmental and permitting requirements associated with the permanent discharge are the responsibility of the Government and have been addressed through the project design and compliance process. Drawings updated.

RFI-009 Drainage / Pipe Quantities

Spec 01 27 00 states approximately 718 LF of new concrete pipe. Call-outs on C3.5-C3.6 (e.g., +/-276 LF and +/-53 LF of 36"x23" RCPA, +/-260 LF of 30"x23" RCPA, and +/-9 to 11 LF 18" RCP connections) appear to total less than 718 LF before the outfall. Please provide a pipe and structure schedule (sizes, lengths, inverts, structures CB-06/07/08 and MH-06) and confirm the 718 LF basis. Please also confirm flow direction and the size transitions (36"x23" to 30"x23" to 44"x27"), and confirm that the 1-ft minimum cover in G1.2 Drainage Note 8 is met by 23-inch-rise arch pipe at the inverts and top-of-casting elevations shown. Are the existing pipes to be abandoned (+/-111 LF on C3.4 and +/-109 LF on C3.5) separate segments?

C3.5, C3.6, C3.4 Spec 01 27 00 para 3.1.B.1; Spec 33 05 39; 33 30 00; 33 05 13;

G1.2 Drainage Note 8

The quantities stated in Section 01 27 00 are incorrect. The approximately 718 LF of new concrete drainage pipe shall be corrected to approximately 654 LF of new drainage piping beneath the roadway. The approximately 131 LF of new stormwater drain line extending from the last proposed catch basin to the riprap-lined outfall ditch shall be corrected to approximately 124 LF.

The total length of new drainage piping is approximately 778 LF. Pipe sizes, alignments, lengths, inverts, structures, and flow directions shall be as indicated on the Contract Drawings. There is no transition from 36"x23" RCPA to 30"x23" RCPA. The applicable pipe size transition is from 36"x23" RCPA to 44"x27" RCPA, as indicated on the Contract Drawings. Specification updated.

RFI-010 Drainage / Trench Backfill Materials

G1.2 Drainage Note 2 requires pumped river sand in trenches within street rights-of-way, while the specifications provide separate bedding, backfill and geotextile requirements and C8.1 shows geotextile wrap with Type A/B backfill. Please clarify the required bedding, haunching, backfill and stabilization materials for trenches in roadway, turf and culvert areas;

whether Military Cemetery Road is considered "street right-of-way"; where geotextile and geogrid are required (31 05 19); and where the sheet-pile/retaining structure shown on C8.1 detail 3 is required.

C8.1 (details 1-3, general notes);

G1.2 Drainage Notes 1-7

Spec 31 23 33; 31 12 19; 31 05 16; 31 05 19; 31 23 00; 33 05 39

Military Cemetery Road shall be considered a roadway area for trench backfill, compaction, and pavement restoration requirements. Drainage Note 2 on Sheet G1.2 requiring pumped river sand within street rights-of-way shall be disregarded.

Bedding, haunching, backfill, and trench stabilization shall comply with the applicable trenching, reinforced concrete pipe, and geosynthetics specifications. Sheet updated.

For RCPA installations, provide a minimum 6-inch bedding layer of AASHTO No. 57 or No. 67 aggregate beneath the pipe.

Provide the same aggregate for haunching and Type “A” initial backfill, carefully placed beneath and along the sides of the arch pipe to provide continuous support and eliminate voids. In roadway areas with shallow pipe cover, extend Type “A” aggregate backfill around the pipe to the bottom of the pavement section. The requirement for initial backfill to extend 12 to 18 inches above the pipe does not apply where the pipe elevation and pavement section do not provide sufficient depth.

Type “B” backfill shall consist of suitable excavated material or approved borrow and shall be used above the Type “A” backfill in turf and other non-pavement locations, as applicable. Type “B” backfill is not required above shallow RCPA where the pavement section immediately overlies the Type “A” aggregate backfill.

Provide separation geotextile beneath the bedding and around the aggregate trench section as indicated on Detail 2/C8.1. Provide geogrid where required for stabilization of unsuitable, soft, saturated, or pumping subgrade conditions.

The sheet-pile/retaining structure shown on Detail 3/C8.1 is a typical excavation-support detail intended to limit the extent of excavation and minimize disturbance where trenching is in close proximity to grave sites and other sensitive cemetery features.

Provide temporary excavation support as required to maintain the excavation limits and protect adjacent grave sites and improvements.

RFI-011 Masonry / Replacement Brick and Mortar Testing

New brick must match the compressive strength and absorption of existing brick, but only the May 2026 brick-extraction request is provided; no test results are included, and the Mortar Testing Report (Masonry Guide Appendix D) is not included. Please provide the brick and mortar test results, approved brick/mortar sources or performance criteria, and expected procurement lead times, and confirm who bears risk if available brick does not meet the stated properties.

A9.3; Att. 4 (brick extraction letter 5/21/2026; Masonry Best Practice Guide App. D)

Spec 04 09 20; Spec 04 01 20;

Spec 01 40 00

Mortar testing and brick testing is attached. Specifications on exact products have been incorporated into the specification or in response to this RFI. Refer to Masonry Repair and Repointing specification 04 0920, paragraph 2.2.B for mortar specification.

The brick testing report was received after the bid documents were distributed. It can now be provided. Based on the brick test results, we have determined the following bricks will be suitable for use: St. Joe's and Old Carolina Brick Company. Specific brick lines will be confirmed through in situ mock-ups. Both St. Joe and Old Carolina bricks will be required to provide the range of brick colors incorporated in the walls. For bidding purposes, assume Old Carolina Post Office brick and St, Joe's jumbo brick in assorted colors.

RFI-012 GAR Monument / Cannon Monuments

Spec 04 03 10 requires the Monument Conservator to assess the GAR Monument to establish the full scope of repair, while A6.0 lists specific repairs (e.g., repoint 100% of vertical face, replace 100% of sky-facing joints, coat all cast iron tubes) and states that bronze components are "removed from the scope" (Note 2). Please confirm (a) whether scope is defined by the drawings or by the conservator's assessment; (b) the scope limits for CM1- CM5 cannon monuments; (c) which coating system (09 96 00 vs. 09 97 25) applies; (d) the treatment for bronze components; (e) scaffolding/lift constraints in the fenced plots and sole-source product approvals; and (f) delete or correct the "NOT USED" notes (6 and 12).

A6.0-A6.3 (sheets 108-111); A6.1

CM1-CM5

Spec 04 03 10; 05 03 00; 04 01 20; 09 96 00; 09 97 25

(A) The Monument Conservator will assess and define the scope. The drawings and specification set a standard for quality conservation materials, practices and exclusions (bronze components), but an experienced conservator can develop their own conservation plan for review and approval.

(B) Refer to sheet specific notes. Question is unclear.

(C) 099600 specifies coatings for metals & wood. 099725 specifies a mineral silicate coatings for concrete piers at gate and at cannon bases.

(D) Bronze work excluded from project.

(E) Scaffolding and lift constraints will be coordinated via submission of construction phasing and access plans. There is not a fenced plot in the vicinity of the GAR or cannon monuments.

(F) To be revised in addendum.

RFI-013 Gates / Fencing / Ironwork

Please clarify the gate and fence scope: whether "make operable" includes operators, hardware, access control or electrical; fence removal/storage/reinstallation limits with new concrete footings (A1.1 Note 4, S1.1); the location(s) of Section 08 11 74 Sliding Metal Grilles on the drawings; which coating system applies to iron vs. other metals; and the Maintenance Shed work on A4.1.

A1.1 Notes 1 and 4; A2.1-A2.3;

S1.1; A0.1 (security gate); A4.1

Spec 05 03 00; 32 31 19; 08 11 74; 09 96 00; 09 97 25; 03 30 00

"Make Operable" does not require electrical or mechanically assisted operators. Level of operability shall be by manual means as is currently, a manually operated entry gate. The gate will require temporary removal and storage to be coordinated by the contractor. Fencing at north entrance to be cast iron painted black. The sliding metal grilles are specified for the Maintenance Shed and not associated with the gates or fencing. These can be a fabricated item constructed of aluminum with a premium fluoropolymer coating.

RFI-014 Grave Markers / Quantity Reconciliation

Spec 02 41 92 states approximately 3,594 block markers are to be removed, transported, crushed and disposed of. Spec 12 93 02 identifies 3,549 Government-supplied replacements (UH 2,394, XC 1,093, XA 28, U1 19, XE 15), and the L2.1 legend states 3,549 remove-and-replace, 1,015 remove-protect-reinstall, 21 small and 4 medium private markers, 1 raise-and-realign private marker, 14 buried lifts, 162 section markers and 9,692 markers reset and realigned. Please reconcile the 45-marker difference and its disposition;

confirm L2.1 totals are project-wide; and provide totals by section and marker type for each treatment: raise/realign, reset only, clean only, remove and replace, protect in place, return to NPS rather than crush, and buried/missing markers to be probed (02 41 92 para E).

L2.1-L2.6 (L2.1 legend and notes); L3.x

Spec 02 41 92 (removal paragraphs); Spec 12 93 01;

Spec 12 93 02

Clerical error on Spec 02 41 92 -Total number of markers to be removed, crushed and disposed = 3,549. Confirmation L2 series totals are project wide. Cleaning - All markers not being government furnished are to be cleaned. Specification has been updated.

RFI-015 Government-Furnished Markers / Logistics

Please clarify (a) from what event the 45-day production notice runs and the schedule relief if Government deliveries are late, damaged, mis-inscribed, short or inconsistent with the approved phasing; (b) the fabrication/delivery schedule and shipment sizes; (c) that the Contractor is not responsible for replacement cost or time for pre-existing defects, shipping damage, inscription errors or shortages when inspection/notification procedures are followed; (d) the secure storage location and capacity (Maintenance Shed vs.

other), and where on-site storage is "as shown"; and (e) when the NPS digital headstone database will be provided.

L2.1 Note 2; C2.x Spec 12 93 02 paras 1.3-1.4;

Spec 01 11 00 paras 1.4, 1.5.B-C

(a) The 45-day notice runs from the Contractor's submission to the CO of the required headstone production/order information for the applicable approved phase. The Contractor shall coordinate this notice with the approved phasing plan and accepted construction schedule. The Government will arrange and pay for delivery of Government-furnished materials in accordance with the Contractor's construction schedule and will arrange replacement of Government-furnished items that are damaged, defective, or missing. If a Government-furnished delivery, replacement, shortage, damage, or inscription error affects the critical path through no fault of the Contractor, the Contractor may request an equitable time adjustment in accordance with the contract's scheduling/change provisions. The schedule specification requires a Time Impact Analysis and provides that an extension is based on the demonstrated critical-path impact after available float is considered.

(b) Fabrication/delivery schedule and shipment sizes: There is not a predetermined fixed shipment schedule or lot size. NCA/NPS will coordinate the delivery sequence with the Contractor after award so deliveries correspond to the Contractor's approved phasing and construction schedule.

(c) Responsibility for defects, damage, errors and shortages: Correct. The Contractor is responsible for receiving and promptly inspecting shipments, verifying quantities and inscriptions, documenting damage or errors, notifying the CO, and protecting the stones after receipt. The Contractor bears replacement and installation costs only when the CO determines the Contractor is responsible for the damage. The broader Government-furnished-material provision also states that the Government will arrange replacement when Government-furnished items are damaged, defective, or missing; the Contractor becomes responsible for repair/replacement when damage results from the Contractor's operations.

(d) The selected contractor is responsible for providing adequate secure staging areas. The Cage is offered as an option but might not fully fulfill storage needs.

(e) NPS will provide the available electronic headstone database/NCA Order List and associated CAD/GIS/excel files after award and early enough to support preparation of the Contractor's phasing plan, survey/layout activities, and required 45-day production notification.

RFI-016 Work Sequencing / Hours / Interments

Spec 12 93 01 limits work to one cemetery section at a time unless approved. May offerors assume approval to work concurrently in multiple non-adjacent sections, or must proposals assume one active section? Spec 01 11 00 states the site is closed to the public yet allows case-by-case visitor access; G1.2 Note 17 requires pausing for interment ceremonies. Please state the permitted workdays/hours (including start/end times), weekend/holiday blackout dates, noise/vibration limits, the typical annual number of funerals, interments and ceremonies, the minimum notice to be given, and whether repeated suspensions support time or cost relief.

G1.2 Note 17; C2.1 Site Control Notes

Spec 12 93 01 para 1.06.A; Spec 01 11 00 paras 1.3, 1.8, 1.11.C, 1.13.A

All work is to be accomplished in a sequential manner, with work limited to no more than one section at any given time. Requests to work on more sections at one time or move to another section before finishing the previous section may be submitted to the COR for approval. Approval/disapproval will be based on the impact on the cemetery operations and the progress and workmanship of the contractor, as determined by the COR. Work cannot begin in subsequent sections until such time that work has been completed in prior areas. While the cemetery is an inactive cemetery and spousal burials are permitted. The last burial was in 2021. It is possible that we will have an internment the park is not aware of an expected spousal plan at this time, and if there is an interment, the contractor will be given advanced notice and any delays to the critical path will be evaluated per the specifications. The site will be closed to the public; the contractor is not responsible for maintaining public access during construction. No limitations on the workday start and end times. Weekends and holidays will require approval by the CO.

RFI-017 Quality / Mockups / Testing

Please provide objective acceptance criteria for cleaned markers (Spec 12 93 01 leaves the determination to the COR) and confirm whether the approved cleaning mockup becomes the contractual benchmark. Please list required mockups, samples and testing with sizes/quantities, approval sequence, whether accepted mockups may remain in the work, and which testing and special inspections are Government-furnished vs. Contractor-furnished.

L2.x; L3.x; L5.x Spec 01 40 00; Spec 12 93 01 (marker cleaning); Spec 32 14 10 (4 ft x 4 ft mockup); Spec 04 09 20; 03 33 10

Accepted mockups may remain as part of the work per determination by COR as per specification - D/2 is the Parks preferred method of cleaning stones as outlined in -https://www.nps.gov/subjects/policy/upload/RM-61_11-4-2011.pdf Section E - Headstone Cleaning provides guidance on the cleaning criteria - The cleaning regimen will be based on environmental considerations such as humidity, biological growth rates, tree cover and vegetation, precipitation and other factors.

The natural surface of headstones and markers will be retained. Headstones and markers should be cleaned to remove objectionable accumulations, such as bird droppings, mud, tire or hose markings, grass stains, residue from trees, fungus, and so forth. The toning or patina of the stone should not be purposefully removed. In cases where spot or partial cleaning may change the patina or tone of the headstone or marker, the headstone or marker should be cleaned in its entirety so as to present a uniform appearance.

RFI-018 Trees / Arborist / Root Protection

Please provide the list of trees approved for removal, pruning and root cutting; clarify arborist attendance requirements (qualified/licensed arborist on site for all work in tree protection zones), air-spading/root investigation extents, fencing and ground-protection limits, and responsibility and cost of the Urban Forester permit. The Att. 4 tree inventory (approximately 159 trees) recommends maintenance pruning, 2-4 inch mulch and deep-root soil injections near construction, and notes headstones engulfed by roots with no removal method that avoids harming the tree. Please state whether these recommendations are in scope and how root-locked markers are to be handled.

G1.2 Arboricultural Requirements 1-3; L0.1-L0.2; L1.1-L1.6 (Notes 1-7); C1.1 Note 3; L6.1 (sheet 87)

Spec 01 56 39; 31 13 13; 31 13 16; 32 96 00; Att. 4 tree inventory (Trinity, 9/29/2025)

Trees approved for removal and pruning are listed on L0.1-L1.6. All work within the tree protection zone will need to be conducted under the guidance of a qualified licensed arborist. For example, during construction for the new drainage work and reconstruction of the roadway from STA:20+57.74, there is the potential to come across roots requiring root investigation/air spading to ensure the best practices are taken according to the arborist.

RFI-019 Grading / Fill / Survey Proposed grading is shown for Grading Areas 01 and 02 only (the key map lists C4 sheets under those areas); L1.1 refers to C4.1 and C4.2 for "proposed grading areas"; C1.1 calls for imported fill without a volume; C2.1 shows a "limit of depression fill area"; and the USACE exhibit describes a 15.7-acre realignment area with a 32-inch maximum excavation depth.

Please confirm whether regrading is required outside Areas 01-02, provide fill volumes, source and quality requirements, and define the depression-fill limits. The survey on Sheet 6 was performed 2/27-3/2/2023; please confirm it remains valid for grading and fill quantities.

C4.1-C4.2 (Grading Area 01 and 02 only); C4.3-C4.6; L1.1; C1.1;

C2.1

Spec 31 22 00; 31 23 23; 32 91 13; 32 91 19.10; 32 91 19.20;

Sheet 6 survey notes; Att. 5 exhibits

Grading Areas 01 and 02 are areas that currently pond during rainfall events and the intent is to raise these areas to better drain.

As shown in cross sections and stated in the specs, all other areas are to receive localized infilling with appropriate planting soil to infill low spots in the existing turf areas.

RFI-020 Schedule / Weather / Liquidated Damages

Please state the baseline number of anticipated adverse-weather days by month and the standard for time extensions for extraordinary rainfall, tropical storms, hurricanes, flooding and saturated ground. Please define the milestone that stops liquidated damages (substantial completion, beneficial occupancy, completion of all base work, or final acceptance including punch list, closeout and turf establishment), given Special Requirement 1 requires work "ready for use" including final cleanup.

— Sec. F (FAR 52.211-12, $1,120/day); Spec. Req. 1; Sec. L Factor 4

If the company does not have their own method of estimating weather days for a baseline schedule, we generally advise the contractor to use the USACE Regulation No. 415-1-15 for Estimating Construction Time Extensions for Weather. The contractor should also factor in historical data for Mississippi River flood stage and potential permit time restrictions.

The milestone that stops Liquidated Damages is Substantial Completion.

RFI-021 Site Furnishings / Government-Furnished Items / Buy American

A1.1 states "install replicated cast stone urns, refer to landscape sheets," but no urn specification or quantity is provided. Please identify who furnishes the urns, Bivouac of the Dead tablets, wayside signage and interpretive sign bases, and provide quantities and specifications. Spec 12 93 00 names basis-of-design products from Reliance Foundry (Canada) and Kenneth Lynch & Sons; please confirm Buy American (FAR 52.225-11) treatment and acceptable equivalents.

A1.1 legend (cast stone urns);

L3.1 legend (urn, bench, bollard, wayside signage, Bivouac of the Dead)

Spec 12 93 00; Spec 01 11 00 para 1.4; FAR 52.225-11

Cast stone urns are not in the project scope. Bivouac of the Dead Tablets will be provided by the government to the contractor for installation. Wayside signage will be provided by the government to the Contractor for installation.

Acceptable substitution for Reliance Foundry include Bollards USA JR Hoe - 150 Century - Twist and lock removable bollard or equal. Kenneth Lynch meets Buy American standards.

RFI-022 Contract / Self- Performance

Section H requires the Contractor to perform at least 15 percent of the work on site with its own organization, while Section I includes FAR 52.219-14.

Please confirm the calculation method: whether materials are excluded;

whether similarly situated entities count; whether it applies to total contract value or construction cost; treatment of option work; and treatment of joint-venture member performance.

— Special Req. 3; FAR 52.219-14 Section H – 15% On-Site Performance: The Contractor must perform at least 15% of the total amount of work to be performed under the contract on site and with its own organization.

Section I – FAR 52.219-14, Limitations on Subcontracting: For general construction, the Contractor may not pay more than 85% of the amount paid by the Government for contract performance, excluding materials, to subcontractors that are not similarly situated entities. Qualifying similarly situated first-tier subcontractors are treated in accordance with FAR 52.219-14, including the requirement that they perform the work with their own employees.

Compliance is generally measured at the end of the base period and each subsequent option period. For joint ventures, the aggregate performance of the joint-venture participants counts toward meeting the applicable limitation, subject to FAR 52.219- 14(g).

The Contractor is responsible for complying with both requirements independently.

RFI-023 Contract / Key Trades and Personnel Must all five key trades (civil, headstone work, landscape, masonry and concrete) be identified at proposal submission? If a firm changes after award, what approval standard applies, and must the replacement have equal or better qualifications?

— Special Req. 5-6; Sec. L Factor 2 In accordance with Special Requirement 6, the Contractor shall identify all five Key Trades (Civil, Headstone Work, Landscape, Masonry, and Concrete) and the firms assigned to perform each trade. If a trade will be self-performed, the Contractor shall identify it as such.

Key Trade assignments are permanent for the duration of the contract. Any proposed substitution requires prior written approval from the Contracting Officer. Requests must be submitted at least 15 calendar days before the proposed substitution and include an explanation of the circumstances necessitating the change and complete qualifications of the proposed replacement.

Replacement firms must have qualifications comparable to the firm being replaced. The Contracting Officer will approve or deny the request within 15 calendar days after receiving all required information. Approved substitutions will be incorporated into the contract through a modification.

RFI-024 Proposal / Evaluation Please confirm the number of projects permitted under Factor 1 and the completion look-back period; whether a mentor, joint-venture member and key-trade subcontractor may each submit projects; how an SBA-approved mentor-protege joint venture will be evaluated (credit for each member and proposed key subcontractors); and whether subcontractor experience for key trades (headstone, masonry, drainage, landscape, concrete) receives equal consideration to prime experience.

— Sec. K; Sec. L Factors 1-2; Sec.

M; Att. 6

Number of project can be 5 or less (note the section page limit is 5 pages), the projects must have been completed in the last 10 years.

For offerors submitting as a joint venture, the Government will consider relevant project experience performed by the joint venture and its individual members. Each joint venture member should identify its respective role, responsibilities, and contributions to the submitted projects. For SBA-approved mentor-protégé joint ventures, the Government will evaluate the experience and qualifications of each member consistent with applicable SBA regulations.

Offerors may also submit relevant project experience for proposed key-trade subcontractors responsible for specialized portions of the work, including headstone resetting and realignment, historic masonry restoration, drainage, landscape improvements, and concrete work. The offeror must identify the proposed subcontractor, the specific work it will perform, and its role in the submitted project.

The offeror must clearly distinguish between projects performed directly by the prime contractor, joint venture members, and proposed subcontractors. Submission of project experience by a joint venture member or subcontractor does not, by itself, demonstrate the prime contractor's direct experience performing that work.

The Government will consider subcontractor experience in relation to the specific work the subcontractor is proposed to perform and will separately evaluate the offeror's demonstrated ability to manage, coordinate, and successfully integrate specialized subcontracted work into the overall project.

Offerors must identify the proposed project team and explain how the experience and capabilities demonstrated through the submitted projects will be applied to this contract.

RFI-025 Bonding / Options FAR 52.228-1(c) sets the proposal guarantee at 20% or $3,000,000, whichever is less, while SF 1442 Item 13.b does not clearly mark whether an offer guarantee is required; please confirm the requirement. Please also confirm whether initial performance and payment bonds must cover the base award only or base plus the unexercised option, and whether the penal sums will be increased when the option is exercised.

SF 1442 Item 13.b; Sec. B FAR 52.228-1; FAR 52.228-15 An offer guarantee is required, as indicated in SF 1442, Item 13.b, in accordance with FAR 52.228-1. The required amount is 20% of the total bid price or $3,000,000, whichever is less. The guarantee will be calculated using the Contractor's submitted bid price.

The initial performance and payment bonds shall each be 100% of the base contract award price. Unexercised options are excluded from the initial bond calculations. Upon exercise of an option, the Contractor shall increase the penal sums of the performance and payment bonds to cover the revised contract price, in accordance with FAR 52.228-15.

RFI-026 Labor / Wage Determination

Wage Determination LA20260005 is for Heavy construction and does not list classifications for historic masonry/bricklayers, ironworkers, headstone setters/cleaners, arborists or monument-conservation specialists (it lists mason tender, common/landscape laborer, pipelayer, fence laborer and cement mason). Please confirm the applicable determination for each type of work (building vs. heavy) and the anticipated classifications, and whether conformance requests will be accepted before award or only after award.

— Att. 3 (WD LA20260005, Heavy construction)

The Government will incorporate DOL Wage Determination LA20260038 into the solicitation by amendment. Both the Heavy Construction and Building wage determinations will apply to the contract, as appropriate to the work being performed.

RFI-027 Restoration RFI 01 Our team will be utilizing 2-3 UTV’s for moving stone, soil, etc. to active work areas. Will we be permitted to park these vehicles near the equipment shed during off hours and weekends during the construction period along with misc. small equipment such as gantry cranes?

As stated in the specification - Existing pavement surfaces within the Cemetery and along Military Cemetery Road can be utilized, provided that emergency, Park staff, and construction vehicle access is maintained for days, nights, weekends and holidays.

There is approximately 4-6 spaces available north of the main entrance and approximately 6 spaces in the existing parking lot by the Maintenance Shed. Contractor shall provide temporary parking with ground protection matting for staff as shown on the drawings and maintain existing parking for Park maintenance equipment. The Contractor shall utilize a portion of the existing parking lot for Field offices for the Contracting Officer and a separate structure for the contractor.

RFI-028 Restoration RFI 02 May we use the widened area of the main drive for our use during working areas only?

As stated in the specification - Existing pavement surfaces within the Cemetery and along Military Cemetery Road can be utilized, provided that emergency, Park staff, and construction vehicle access is maintained for days, nights, weekends and holidays.

There is approximately 4-6 spaces available north of the main entrance and approximately 6 spaces in the existing parking lot by the Maintenance Shed. Contractor shall provide temporary parking with ground protection matting for staff as shown on the drawings and maintain existing parking for Park maintenance equipment. The Contractor shall utilize a portion of the existing parking lot for Field offices for the Contracting Officer and a separate structure for the contractor.

RFI-029 Restoration RFI 03 When concrete flatwork is being poured in the Superintendents Lodge area will the cemetery staff be responsible for making other arrangements for staff parking?

Contractor shall provide temporary parking with ground protection matting for staff as shown on the drawings and maintain existing parking for Park maintenance equipment. The Contractor shall utilize a portion of the existing parking lot for Field offices for the Contracting Officer and a separate structure for the contractor. See C2.3 for general staff parking.

RFI-030 Restoration RFI 04 Once we commence work activities will the cemetery staff be sending alerts to the public/visitors advising that there will be a construction project for the noted duration of the project?

Information will be posted to the park website.

RFI-031 Restoration RFI 05 Should stumps and dead trees noted on our site visit be addressed from a cost standpoint by the contractor to be totally removed below grade and sod installed as a finished activity?

Yes - it is the intent to remove any stumps or dead trees as part of this project. Drawings capture stumps and dead trees known at the time of submission.

RFI-032 Restoration RFI 06 When the brick curbing is being worked on along the roadway edge may we block this area off while still allowing for visitor passage with the contractor providing necessary traffic control along with directional and safety signage for safe passage in the areas being worked?

The site will be closed to visitors for the duration of the project. Refer to 01 11 00 regarding government, emergency and delivery access during construction. The contractor will need to coordinate access and restrictions during the construction period.

RFI-033 Restoration RFI 07 If the contractor feels the need to work extended hours and possibly weekends, with advanced notice in writing, will this be permissible?

The NPS team will work with the contractor, spec section 01 11 00 does not limit the Monday-Friday workday. CO approval will be needed for holidays and weekends. The government will work with the contractor to accommodate reasonable requests for weekend and holiday work. this may limit the activities the contractor can perform on those days if the CMR cannot be present.

RFI-034 Restoration RFI 08 When the Government inspection team enters an active work area may it be understood that they follow EM 385-1 PPE requirements?

Yes, all visitors must check in first with the contractor and comply with the contractor safety requirements.

RFI-035 Restoration RFI 09 May the contractor be permitted or required to have portable toilet stations and hand wash stations with the placement of these units being discussed upon NTP?

The contractor is to provide portable toilet facilities, location can be shown on the Site Access Plan for NPS review.

RFI-036 Restoration RFI 10 Has the Government planned for any alternate means of entry and exit from the cemetery grounds during times (which will be noted in our CPM schedule) for visitors and staff?

Staff will use the road connecting to the battlefield running north from the lodge complex. The project site will be closed to visitors during construction.

RFI-037 Restoration RFI 11 Will the headstone inventory be provided in Excel/spreadsheet format as well as AutoCAD and GIS?

The headstone database can be provided in multiple formats including, Xcel and GIS and AutoCAD.

RFI-038 Restoration RFI 12 Regarding Section 12 93 01, “Work cannot begin until such time that work has been completed in prior sections,” does the understanding of completed work include the return of crushed marble to the site?

Crushed material shall be disposed of offsite in compliance with 02 41 92. The crushing of the headstones offsite does not need to be complete prior to the work on the next section.

RFI-039 Restoration RFI 13 We believe that a Bobcat or Skid steer may cause more damage to the grounds as we move forward in the process, would a walk behind “Dingo” be acceptable in lieu of the equipment suggested as being the recommended equipment? Our staff is more used to using a gantry crane and this would be our tool of choice; would this be acceptable?

Other means and methods are acceptable to avoid damage while maintaining schedule. The awarded contractor will be required to submit a Site Access Plan outlining proposed methods, materials and schedule.

RFI-040 Restoration RFI 14 During the site visit, permits were discussed. We understand the Government has applied for and acquired most of all the permits. Are there any additional permits that the contractor will be responsible for procuring?

The Contractor will be responsible for acquiring a Norfolk Southern (NS) Environmental Right of Entry (EROE), see Norfolk Southern's website for requirements. The Prime Contractor to furnish agreements and the required insurances. Contractor responsible for Southeast Flood Protection Authority Levee Safety Permit and the NPDES National Pollution Discharge Elimination System storm water runoff permit/plan. Contractor responsible for relevant constructed related permits.

RFI-041 Restoration RFI 15 Headstone work is limited to one section at a time and must be coordinated with turf establishment. Please define the completion milestone required before commencing work in another section. May the contractor advance after marker acceptance and sod installation while the establishment and maintenance continue in the preceding section?

All work is to be accomplished in a sequential manner, with work limited to no more than one section at any given time. Requests to work on more sections at one time or move to another section before finishing the previous section may be submitted to the COR for approval. Approval/disapproval will be based on the impact on the cemetery operations and the progress and workmanship of the contractor, as determined by the COR. Work cannot begin in subsequent sections until such time that work has been completed in prior areas. The contractor may advance to another section while the establishment and maintenance continue until final acceptance.

RFI-042 Restoration RFI 16 The lighting specification references a 12-volt system with an internal driver and also a 110/120- volt “output”. Please clarify the required supply voltage and driver arrangement. Identify the approved power connection point circuit requirements, controls and conduit-routing requirements.

Contractor to provide schematics as part of the submittal process. Install flag pole lighting per manufacturers requirements.

RFI-043 Restoration RFI 17 Please identify which project activities and work areas are subject to suspension at the stated Carrollton Gauge thresholds. Confirm any existing waivers and the contract procedure for addressing schedule impacts from agency-directed river stage shutdowns.

Refer to the Southeast Louisiana Flood…