B08_Attachment_8_-_Baseline_Schedule_Review_Checklist_Form_0002.pdf
PDF 133 KB Posted
- Attached to
- JELA 325250 335621 - Rehabilitate Cemetery
- Solicitation number
- 140PP027R0004
- Issued by
- Not on record
About this file
This document is the Baseline Schedule Review Checklist Form used by the National Park Service Denver Service Center to evaluate contractor-submitted project schedules for construction contracts.
The checklist establishes mandatory basic requirements for initial schedules, including verification that key contract dates (Award, Notice to Proceed, Substantial Completion, and Project Completion) align with contract terms, and that the completion date reflects the actual contract deadline rather than an earlier date. Schedules must incorporate all procurement and construction activities, including mobilization, submittals, and fabrication and delivery of long-lead items, with activities sequenced logically and showing interdependence. Each activity requires at least one predecessor and successor (except Notice to Proceed and Project Completion), a concise description limited to 48 characters, and realistic duration in whole working days with a 15-work day maximum, though exceptions exist for mobilization, shop drawings, fabrication, delivery, and concrete curing. Schedules must include a critical path, start activities only on workdays, incorporate contract constraints such as seasonal shutdowns and holidays, account for normal bad weather using historical data rather than estimates, and allocate at least 10 days for start-up and testing activities. The schedule must coordinate with the Schedule of Values to enable straightforward progress tracking and billing correlation aligned with contract line item numbers, and must avoid frontloading unreasonably high costs unrelated to long-lead items that could indicate inappropriate early-stage funding attempts.
Optional requirements depending on project complexity, duration, cost, and phasing include numerically identifying activities in 10-digit increments, limiting activities to single trades, resource-loading by labor category and equipment type, accounting for special circumstances like traffic control, and including milestones identified in specifications or by the Project Manager and Contracting Officer Representative.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NPS DSC Baseline Schedule Review Checklist Form page 1 of 2
Baseline Schedule Review Checklist Form National Park Service (NPS) - Denver Service Center (DSC)
General
☐ Draft Baseline Schedule submitted before Pre-Construction Conference.
Initial Schedule - Basic Requirements
☐ Check dates of Award, Notice to Proceed, Substantial Completion(s-if there are multiple beneficial occupancies), and Project Completion with contract. Completion Date is the contract completion date, not an earlier date.
☐ Include in Project Schedule: Procurement and Construction activities including mobilization; submittals; and fabrication and delivery of key and long-lead procurement items.
☐ Schedules containing items of work currently underway or design progress and milestones shall be up to date and correct. Check milestones against contract.
☐ Activities shall have at least one predecessor and one successor except Notice to Proceed and Project Completion.
☐ Include a Critical Path.
☐ Include concise description of work represented by activity (48-character maximum).
☐ Activity duration shall be in whole working days, 15-work day maximum. (Exceptions include mobilization, shop drawings and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing times).
☐ Include and coordinate work by Contractor and Subcontractor.
☐ Show sequence and interdependence of activities for complete performance of work.
☐ Show a coordinated work plan with logical sequence.
☐ Assign realistic duration to each activity, considering scope and resource loading.
☐ Start activities on a work day, not a holiday or weekend.
☐ Incorporate contract constraints into schedule such as seasonal shutdown, blackout non-work dates, holidays, and breaks in schedule where work is not performed.
☐ Compare to Schedule of Values to ensure that progress and monthly billings can be tracked with relative ease. Consider what will happen if there is delay or work done out of sequence? Can progress still be followed without a degree in scheduling? Does presented schedule work with CLINs (contract line item numbers)?
☐ Account for “normal” bad weather in schedule. Normal bad weather information is available, so this number should not be a swag.
☐ Start-up and testing shall have a duration of at least 10 days, depending on what is being tested.
NPS DSC Baseline Schedule Review Checklist Form page 2 of 2
☐ Activities can include Mobilization but not General Conditions and Overhead Profit. There may be multiple mobilizations.
☐ Review schedule for frontloaded or unreasonably scheduled high cost items to allow for higher billing during early stages of project. A schedule is a work plan and if the plan makes sense, costs will follow. But at the beginning of the job, if there is a particularly high cost not associated with long lead items, it could indicate an attempt to obtain a lot of money up front to fund a job and this can lead to problems later.
Initial Schedule - Optional Requirements Depending on Complexity, Duration, Cost and/or Phasing
☐ Identify activities numerically (5-digit maximum) in 10-digit increments.
☐ Limit one activity to one work trade.
☐ Resource load each activity by labor category and equipment type.
☐ If applicable, account for special circumstances in the Schedule-Traffic Control and/or Coordination activities and avoid double-charging. Include in schedule if critical to project.
☐ Include milestones. At a minimum, include Notice to Proceed, Substantial Completion, and milestones identified in Division 01 Specifications and by Project Manager (PM) and/or Contracting Officer Representative (COR).
| Draft Baseline Schedule submitted before PreConstruction Conference: Off |
| Check dates of Award Notice to Proceed Substantial Completionsif there are multiple beneficial: Off |
| Include in Project Schedule Procurement and Construction activities including mobilization submittals and: Off |
| Schedules containing items of work currently underway or design progress and milestones shall be up to: Off |
| Activities shall have at least one predecessor and one successor except Notice to Proceed and Project: Off |
| Include a Critical Path: Off |
| Include concise description of work represented by activity 48character maximum: Off |
| Activity duration shall be in whole working days 15work day maximum Exceptions include mobilization: Off |
| Include and coordinate work by Contractor and Subcontractor: Off |
| Show sequence and interdependence of activities for complete performance of work: Off |
| Show a coordinated work plan with logical sequence: Off |
| Assign realistic duration to each activity considering scope and resource loading: Off |
| Start activities on a work day not a holiday or weekend: Off |
| Incorporate contract constraints into schedule such as seasonal shutdown blackout nonwork dates: Off |
| Compare to Schedule of Values to ensure that progress and monthly billings can be tracked with relative: Off |
| Account for normal bad weather in schedule Normal bad weather information is available so this number: Off |
| Startup and testing shall have a duration of at least 10 days depending on what is being tested: Off |
| Activities can include Mobilization but not General Conditions and Overhead Profit There may be multiple: Off |
| Review schedule for frontloaded or unreasonably scheduled high cost items to allow for higher billing: Off |
| Identify activities numerically 5digit maximum in 10digit increments: Off |
| Limit one activity to one work trade: Off |
| Resource load each activity by labor category and equipment type: Off |
| If applicable account for special circumstances in the ScheduleTraffic Control andor Coordination: Off |
| Include milestones At a minimum include Notice to Proceed Substantial Completion and milestones: Off |