Sol_140P9725Q0016_Amd_0001.pdf

PDF 95 KB Posted

Attached to
GAAR HEATING SYSTEM REPLACEMENT BETTLES VISITOR CE Federal contract opportunity
Solicitation number
140P9725Q0016
Issued by
Department of the Interior National Park Service Alaska Region

About this file

This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for the Bettles Visitor Center Heating System Replacement project. The amendment, issued by the National Park Service Alaska Regional Office, provides detailed answers to six vendor questions regarding project specifications. Key clarifications include: all control valves will be replaced, contractor work hours are 7 am to 7 pm Monday through Saturday, 17 existing thermostats must be replaced with programmable units (preferably wi-fi enabled), Pro-Press fittings are not allowed, and waste disposal will be through the Evansville Tribal Council landfill.

The amendment also confirms NPS housing is available at $43.38/day for a three-bedroom unit, with billing occurring post-use. The project's period of performance is scheduled from 07/01/2025 to 10/31/2025, and will be executed as a firm fixed-price contract. Contractors must submit requests for extended working hours at least two weeks in advance, with final approval contingent on visitor center usage and NPS staff availability for building access.

View the file

Other files for this federal contract opportunity

Other files attached to GAAR HEATING SYSTEM REPLACEMENT BETTLES VISITOR CE, newest first.
File Type Posted
Sol_140P9725Q0016_Amd_0002.pdf PDF
B08_Attach_7_Original_2007_Construction_Drawings___Mechanical_and_Electrical_Sheets.pdf PDF
B08_Attach_3_Hot_Work_Permit.pdf PDF
B08_Attach_2_Photo_logs.pdf PDF
B08_Attach_4_Wage_Determination_AK20250001_3_14_25.pdf PDF
B08_Attach_5_CM-16_Submittal_Form.pdf PDF
B08_Attach_1_SOW.pdf PDF
B08_Attach_6_Bid_Schedule_(price).xlsx XLSX spreadsheet
Sol_140P9725Q0016.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P9725Q0016 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PAK

Anchorage AK 99501-2327 240 W. 5th Ave, Room 114 NPS, ARO - Alaska Regional Office

04/09/20250001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

04/09/2025

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

BETTLES VISITOR CENTER HEATING SYSTEM REPLACEMENT

THE PURPOSE OF THIS AMENDMENT IS TO POST ANSWERS TO VENDOR QUESTIONS:

1.Are all control valves to be replaced on this project?

ANSWER: Yes, all control valves will be replaced as part of this project.

2.The RFQ states work hours to be 8-5 Monday thru Friday. Will contractors be allowed to work 7days a week, as well as a longer work day?

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Janet Milson

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P9725Q0016/0001

ANSWER: Contractor work hours are clarified as 7 am to 7 pm Monday through Saturday. After the initial project schedule is developed and the project kickoff meeting is conducted, the

Contractor may submit a request to the CO for longer working hours or additional working days.

The request must be submitted no less than two weeks (14 days) ahead of the desired dates and reference specific work to be performed during the extended hours/days. The CO will approve or reject the request based on usage of the visitor center and availability of NPS staff to provide building access during the requested times.

3.Please clarify intent regarding a "new electronic system controller/thermostat".

ANSWER: There are currently 17 thermostats in the

Bettles Visitor Center (ref sheets M2.0 & M2.1 on provided drawings). Contractors shall replace existing thermostats. New thermostats must, at a minimum, be programmable on a 5-2 schedule. It is preferred that the new thermostats be compatible with a wi-fi network and be capable of issuing an alert to the Bettles maintenance worker if dropping below a selected temperature.

4. Will Pro-Press fittings be allowed?

ANSWER: Pro-Press fittings are not allowable for this project as Park maintenance staff does not have Pro-Press tooling for future repair work.

5.Is there a transfer site available to dispose of material and equipment to be removed?

ANSWER: The Evansville Tribal Council operates a landfill accepting waste from Evansville and

Bettles. Contractors are responsible for confirming the landfill will accept waste generated from this project by contacting the owners at 907-692-5005 or evansvillealaska@gmail.com. ADEC maintains a record of this landfill and contact information on the Solid Waste Information Management System

(SWIMS).

6. Will there be a nightly rate at the mentioned

NPS units near site?

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P9725Q0016/0001

ANSWER: Yes, the rate for NPS housing is

$43.38/day for a full three-bedroom, one-bathroom unit with kitchen. Contractors will be billed post-use.

Period of Performance: 07/01/2025 to 10/31/2025

FIRM FIXED PRICE