This document is a Solicitation for a firm-fixed-price construction contract to renew and reconfigure the Stinson Beach Maintenance Building and install a new lifeguard locker room trailer at the Golden Gate National Recreation Area in Marin County, California.
The National Park Service has a requirement to repurpose the existing maintenance building into offices and a gym for the Stinson Beach Lifeguards, and install a new mobile shower/restroom trailer to serve as a locker room facility. The project is estimated to be between $250,000 and $500,000. This is a Total Small Business Set-Aside under NAICS code 236210. Proposals are due by the date and time specified in the solicitation. The period of performance is 120 days after the notice to proceed, from August 1, 2024 to November 29, 2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8624R0011_Amd_0002.pdf | ||
| B08_Attachment_9_Maintenance_Building_Dimensions_0002.pdf | ||
| Sol_140P8624R0011_Amd_0001.pdf | ||
| B08_Attachment_4_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| B08_Attachment_1_Specifications_Stinson_Beach_.pdf | ||
| B08_Attachment_3_Davis-Bacon_Wage_Rates_CA20240007.pdf | ||
| B08_Attachment_5_Past_Performance_Questionnaire.docx | DOCX document | |
| B08_Attachment_6_General_References.docx | DOCX document | |
| B08_Attachment_7_Relevant_Experience_Questionnaire.pdf | ||
| B08_Attachment_8__VIOLATION_OF_ARMS_CONTROL_TREATIES_OR_AGREEMENTS-CERTIFICATION.pdf | ||
| B08_Attachment_2_Bid_Schedule-_Stinson_Beach.xls | XLS spreadsheet |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040648713
NPS, PWR - GOGA MABO
Building 201, Fort Mason
San Francisco CA 94123
PPG
Robert Barnes 0000000000
1x 06/13/2024
140P8624R0011
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
The National Park Service, Golden Gate National Recreation Area, at Stinson Beach in
Marin County, CA has a requirement to Renew and Reconfigure Stinson Beach
Maintenance Building and Install Locker Room Trailer.
Renew and Reconfigure Maintenance Building includes:
The maintenance building in the Stinson beach corporate yard is to be repurposed into offices and a gym for the Stinson Beach Lifeguards. A mobile shower/restroom trailer is to be moved into the corporate yard to serve as a locker room facility while the lifeguard tower is under construction.
The maintenance building is to become the primary contact station for the lifeguards for Stinson Beach National Recreation area while the lifeguard tower is under construction. Upgrades to the interior are needed to repurpose the existing structure into a gym and offices, due to the age of the building and its previous use as a maintenance shed.
Install Locker Room Trailer includes:
NPS is Installing a new shower trailer and upgrading the interior of the Stinson
Beach Maintenance Building. The scope of this project includes demolition and installation of utility sink, new shelving and demolition and installation epoxy
Continued ...
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 120 calendar days and complete it within ________________ ________________ calendar days after receiving
FAR 52.11-10
07/15/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
NPS, PWR - GOGA MABO
Building 201, Fort Mason
San Francisco CA 94123
PPG
Liset Gomez
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 39
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P8624R0011 primer and epoxy floor over plywood; cove base to match existing. Infill the wall in the office to the safe room, add glass block window to safe room. and match finish surfaces; Add interior solid core pre-hung door into safe room, Paint door, remove existing lumber rack; install ½-inch gypsum board and ½-inch cork sound panels to cage wall south and move cage door to corner of west wall; Move fuel and hazardous storage.
The Government contemplates award of a firm-fixed price contract resulting from this solicitation.
This acquisition is a Total Small Business
Set-Aside. Offers received from concerns that are not small business concerns shall be considered non-responsive and will be rejected.
The North American Industry Classification System
(NAICS) Code for this requirement is 236210, with a corresponding size standard of $45.0 million in annual gross receipts for the past three years.
Per FAR 36.204 the project range is estimated to be between $250,000 and $500,000.00.
A SITE VISIT is scheduled on Wednesday, June
26,2024, at 9:00 AM PDT.
Submit questions in accordance with the instructions in Section L.
Proposals must be received in their entirety no later than the date and time specified in Block
13 of the SF1442.
Delivery: 120 Days After Notice to Proceed
Delivery Location Code: 0009060573
NPS, GOLDEN GATE NRA
Bldg. 201, Fort Mason
San Francisco CA 94123-1307 US
Period of Performance: 08/01/2024 to 11/29/2024
00010 Renew & Reconfigure Stinson Beach Mainte
Product/Service Code: Z2AZ
Product/Service Description: REPAIR OR ALTERATION
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
4 39
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P8624R0011
OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE
BUILDINGS
00020 Install Stinson Beach Lifeguard Locker Room
Product/Service Code: Z2AZ
Product/Service Description: REPAIR OR ALTERATION
OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE
BUILDINGS
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Solicitation 06/13/2024
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
TABLE OF CONTENTS
PART I – THE SCHEDULE
SECTION A – SOLICITATION / CONTRACT FORM
SECTION C – SPECIFICATIONS / DRAWINGS
SECTION D – PACKAGING AND MARKING
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
SECTION F – DELIVERIES OR PERFORMANCE
CLAUSES INCORPORATED BY REFERENCE
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
52.242-14 SUSPENSION OF WORK (APR 1984)
SECTION G – CONTRACT ADMINISTRATION DATA
CONTRACT ADMINISTRATION
CORRESPONDENCE
APPOINTMENT OF CONTRACTOR REPRESENTATIVE/SUPERINTENDENT
1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)
1452.204-70 RELEASE OF CLAIMS—DEPARTMENT OF THE INTERIOR (Jul 1996)
CONSTRUCTION CONTRACT ADMINISTRATION
NOTICE TO CONTRACTORS – CONTRACTOR PERFORMANCE ASSESSMENT REPORTING
SYSTEM (DEC 2015)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM
(APR 2013)
SECTION H – SPECIAL CONTRACT REQUIREMENTS
WAGE RATES
WORKERS COMPENSATION
SITE SPECIFIC SAFETY AND HEALTH PLAN
ARCHEOLOGICAL FINDINGS
CONDUCT OF OPERATIONS
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
CLAUSES INCORPORATED BY REFERENCE
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
1452.203-70 RESTRICTIONS ON ENDORSEMENTS (JUL 1996)
52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)
1452.228-70 LIABILITY INSURANCE (JUL 1996)
1452.236-70 PROHIBITION AGAINST USE OF LEAD-BASED PAINT (JUL 1996)
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
PART III – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J – LIST OF ATTACHMENTS
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)
52.204-24 REPRESENTATIONS REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES AND EQUIPMENT (NOV 2021)
52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES-REPRESENTATION
(OCT 2020)
52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS-CERTIFICATION (NOV
2021)
PROVISIONS INCORPORATED BY REFERENCE
1452.215-71 USE AND DISCLOSURE OF PROPOSAL INFORMATION—DEPARTMENT OF THE
INTERIOR (APR 1984)
52.216-1 TYPE OF CONTRACT (APR 1984)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT – CONSTRUCTION MATERIALS (MAY 2014)
52.228-1 BID GUARANTEE (SEP 1996)
52.233-2 SERVICE OF PROTEST DEPARTMENT OF THE INTERIOR (JUL 1996) (DEVIATION)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)–ALTERNATE I (FEB 1995)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER INFORMATION – COMPETITIVE
SOURCE SELECTION
RESPONSIBILITY DETERMINATION
SECTION M – EVALUATION FACTORS FOR AWARD
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
PART I – THE SCHEDULE
SECTION A – SOLICITATION / CONTRACT FORM
Solicitation, Offer, and Award (SF 1442) - pages 1- 4 of this package.
SECTION C – SPECIFICATIONS / DRAWINGS
Specifications are attached and incorporated herein by reference. Refer to section J.
SECTION D – PACKAGING AND MARKING
No clauses included.
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not—
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may—
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of clause)
SECTION F – DELIVERIES OR PERFORMANCE
CLAUSES INCORPORATED BY REFERENCE
The following contract clauses pertinent to this section are incorporated by reference (by Citation Number, Title, and Date) per the clause at FAR “52.252-2 CLAUSES INCORPORATED BY REFERENCE” in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to a clause’s full text.
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within ____10____ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than ______120______ calendar days after the date the Contractor receives the notice to proceed.
The time stated for completion shall include final cleanup of the premises.
(End of clause)
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
52.242-14 SUSPENSION OF WORK (APR 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
(End of clause)
SECTION G – CONTRACT ADMINISTRATION DATA
CONTRACT ADMINISTRATION
The Contracting Officer's Representative (COR) for this contract will be:
Name: Jennifer Hardin Title: Contracting Officer Representative Park/Office: Golden Gate National Recreation Area jen_hardin@nps.gov
The Contract Specialist (CS) responsible for administering this contract will be:
Name: Robert Barnes Contract Specialist Robert_j_barnes@nps.gov
The Contracting Officer (CO) with overall responsibility for this contract will be:
Name: Liset Gomez Contracting Officer Liset_Gomez@nps.gov
(End of Clause)
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
CORRESPONDENCE
Copies of all correspondence and written notices between the Contracting Officer’s Representative and the Contractor shall be sent to the cognizant Contract Specialist at the email address below. All correspondence shall state the contract number in the subject line of the email.
Name: Robert Barnes Contract Specialist Robert_j_barnes@nps.gov (End of Clause)
APPOINTMENT OF CONTRACTOR REPRESENTATIVE/SUPERINTENDENT
Prior to commencement of work on this contract, the contractor shall provide to the Contracting Officer, the name and telephone number of at least one responsible individual who will serve to respond to operational problems and/or emergencies on a daily basis. The contractor agrees that notice to the designated representative shall constitute notice to the contractor and agrees to be bound by any commitments or representations made by the representative.
(End of Clause)
1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer’s Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor’s performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
€ The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor’s right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR’s appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph € prior to receipt of the Contracting Officer’s response issued under paragraph € of this clause.
€ The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause.
A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor’s risk.
(End of clause)
1452.204-70 RELEASE OF CLAIMS—DEPARTMENT OF THE INTERIOR (Jul 1996)
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
(End of clause)
CONSTRUCTION CONTRACT ADMINISTRATION
Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract.
(End of clause)
NOTICE TO CONTRACTORS – CONTRACTOR PERFORMANCE ASSESSMENT REPORTING
SYSTEM (DEC 2015)
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We may request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
https://www.doi.gov/pam/acquisition/policy/constructioncontract https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.cpars.gov/ https://www.cpars.csd.disa.mil/ https://www.cpars.gov/
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
a. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
b. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
c. All information provided should be reviewed for accuracy prior to submission.
d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of Notice)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING
PLATFORM (APR 2013)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract. The IPP website address is: https://www.ipp.gov.
The Contractor shall submit a draft Invoice Package, including copies of the following documents, to the National Park Service’s (NPS) Contracting Officer’s Representative (COR), with a copy to the Contract Specialist, a minimum of 5 working days prior to submittal of the formal Invoice through IPP. Within 5 working days of receipt, the COR shall provide an acceptability recommendation to both the NPS Contract Specialist and the Contractor. If the COR recommends acceptance, the Contractor shall submit a copy of the final version of the COR’s checklist and the Invoice Package to the NPS through IPP.
https://www.ipp.gov/
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
1. Completed copy of the Invoice Payment Request (including signed certification of subcontractor payments as required by contract clause 52.232-5)
2. Certified copies of Payroll Reports per Contract clause 52.222-8 Payrolls and Basic Records.
3. Completed copy of the Payroll Report PII Certification sheet
4. Information required by contract clause 52.232-27, Prompt Payment for Construction Contracts
5. A copy of the current construction schedule.
6. A copy of the current Schedule of Values.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal.
(End of Clause)
SECTION H – SPECIAL CONTRACT REQUIREMENTS
WAGE RATES
Davis-Bacon Wage Rates apply for this project and are attached to this solicitation (See Section J). The project is located in Marin County, California.
(End of Clause)
WORKERS COMPENSATION
The Contractor is required to be insured against liability for workmen's compensation or to undertake self-insurance in accordance with the provisions of the Section 3700 of the Labor Code of the State of California. Evidence of coverage is required before commencement of project work.
(End of Clause)
SITE SPECIFIC SAFETY AND HEALTH PLAN
A site specific safety and health plan shall be prepared covering on-site work to be performed by the contractor and all subcontractors. The prime contractor shall be responsible for development, implementation, and oversight of the site specific plan. The site specific safety and health plan shall establish in detail, the protocols necessary for recognition, evaluation, and control of hazards associated with each task performed. The plan shall address site specific safety and health requirements and procedures based upon site specific conditions. The level of detail provided in the site specific safety and health plan shall be tailored to the type of work, complexity of operations to be performed, and hazards anticipated. The site specific safety and health plan shall address, in as much detail as possible, anticipated tasks, their related hazards, and anticipated control measures.
mailto:ippgroup@bos.frb.org
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
As work proceeds, the site specific safety and health plan shall be adapted to new situations and new conditions.
Changes and modifications to the accepted site specific safety and health plan shall be made with the knowledge and concurrence of the safety office, site superintendent, and contracting office. Should any unforeseen hazard become evident during the performance of work, the contractor shall bring such hazard to the attention of the safety office and COR, both verbally and in writing for resolution as soon as possible. In the interim, necessary action shall be taken to re-establish and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public, and the environment.
Prior to submittal to the COR, the site specific safety and health plan shall be signed and dated by the prime contractor's safety and health manager and site superintendent. The site specific safety and health plan shall be part of the contractor's safety and Health program. The contractor shall submit to the COR the contractor's site specific safety and health plan for review and approval by the safety office.
Work performed under this contract shall comply with applicable federal, state, and local safety and occupational health laws and regulations. This includes, but is not limited to, Occupational Safety and Health Administration (OSHA) standards, 29 CFR, Part 1910 and Part 1926. Where the requirements of applicable laws, criteria, ordinances, regulations, and referenced documents vary the most stringent requirements shall apply.
(End of Clause)
ARCHEOLOGICAL FINDINGS
(a) Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed only by the Government. Should Contractor's operations uncover or his employees find any archeological remains, Contractor shall suspend operations at the site of discovery; notify Contracting Officer immediately of the findings; and continue operations in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for Contractor, he will be compensated by an equitable adjustment under the General Provisions of the Contract.
(End of Clause)
CONDUCT OF OPERATIONS
At all times the Contractor shall conduct his organization in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and with such appropriate regulations as the Superintendent may prescribe. Work on Saturdays, Sundays, Federal holidays or at night may be performed only with the prior consent of the Contracting Officer. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park except with approval of the Contracting Officer.
(End of Clause)
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
CLAUSES INCORPORATED BY REFERENCE
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
The following contract clauses pertinent to this section are incorporated by reference (by Citation Number, Title, and Date) per the clause at FAR “52.252-2 CLAUSES INCORPORATED BY REFERENCE” in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to a clause’s full text.
52.202-1 DEFINITIONS (JUN 2020)
52.203-3 GRATUITIES (APR 1984)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (JUN 2020)
52.203-7 ANTI-KICKBACK PROCEDURES (JUN 2020)
52.203-8 CANCELLATION, RECESSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY
(MAY 2014)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (JUN 2020) 52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM EMPLOYEES
OF WHISTLEBLOWER RIGHTS (JUN 2020)
52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR
STATEMENTS (JAN 2017)
52.204-4 PRINTED OR COPIED DOUBLE SIDED ON POSTCONSUMER FIBER CONTENT PAPER (MAY 2011) 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS (JUN 2020)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018)
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (AUG 2020)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR
PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021)
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
52.209-6 PROTECTING THE GOVERNMENT’S INTEREST WHEN SUBCONTRACTING WITH CONTRACTOR’S
DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (NOV 2021)
52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015)
52.215-2 AUDIT AND RECORDS-NEGOTIATIONS (JUN 2020)
52.215-8 ORDER OF PRECEDENCE - UNIFORM CONTRACT FORMAT (OCT 1997)
52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2021)
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (OCT 2018)
52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)
52.219-28 POST AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021)
52.222-3 CONVICT LABOR (JUN 2003)
52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS-OVERTIME COMPENSATION (MAY 2018)
52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (AUG 2018)
52.222-7 WITHHOLDING OF FUNDS (MAY 2014)
52.222-8 PAYROLLS AND BASIC RECORDS (JUL 2021)
52.222-9 APPRENTICES AND TRAINEES (JUL 2005)
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)
52.222-12 CONTRACT TERMINATION - DEBARMENT (MAY 2014)
52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIRMENTS AND RELATED REGULATIONS
(MAY 2014)
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)
52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)
52.222-26 EQUAL OPPORTUNITY (SEP 2016)
52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APR 2015)
52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)
52.222-37 EMPLOYMENT REPORTS ON VETERANS (JUN 2020)
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)
52.222-50 COMBATING TRAFFICKING IN PERSONS (NOV 2021)
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (MAY 2022)
52.222-55 MINIMUM WAGES FOR CONTRACTOR WORKERS UNDER EXECUTIVE ORDER 14026 (JAN 2022)
52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JAN 2022)
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)
52.223-6 DRUG-FREE WORKPLACE (MAY 2001)
52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING (JUN 2020)
52.223-21 FOAMS (JUN 2016)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (FEB 2021)
52.227-1 AUTHORIZATION AND CONSENT (JUN 2020)
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT (JUN 2020)
52.227-4 PATENT INDEMNITY—CONSTRUCTION CONTRACTS (DEC 2007)
52.227-17 RIGHTS IN DATA – SPECIAL WORKS (DEC 2007)
52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)
52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-11 INDIVIDUAL SURETY—PLEDGES OF ASSETS (FEB 2021)
52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (DEC 2022)
52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)
52.228-15 PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION (JUN 2020)
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
52.232-17 INTEREST (MAY 2014)
52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER – SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (MAR 2023)
52.233-1 DISPUTES (MAY 2014)–ALTERNATE I (DEC 1991)
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.236-2 DIFFERING SITE CONDITIONS (APR 1984)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)
52.236-8 OTHER CONTRACTS (APR 1984)
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (APR 1984)
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)
52.236-12 CLEANING UP (APR 1984)
52.236-13 ACCIDENT PREVENTION (NOV 1991)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
52.242-13 BANKRUPTCY (JUL 1995)
52.243-4 CHANGES (JUN 2007)
52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS AND COMMERCIAL SERVICES (JUN 2023)
52.248-3 VALUE ENGINEERING – CONSTRUCTION (OCT 2020)
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012)-ALTERNATE I
(SEP 1996)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.253-1 COMPUTER GENERATED FORMS (JAN 1991)
(End of clause)
1452.203-70 RESTRICTIONS ON ENDORSEMENTS (JUL 1996)
The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205–1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.
(End of clause)
52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of the threshold specified in Federal Acquisition Regulation (FAR) 22.1408(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of clause) https://www.acquisition.gov/far/part-22#FAR_22_1408
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
1452.228-70 LIABILITY INSURANCE (JUL 1996)
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer.
The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
$1,000,000 each person $1,000,000 each occurrence $1,000,000 property damage
(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
(End of clause)
1452.236-70 PROHIBITION AGAINST USE OF LEAD-BASED PAINT (JUL 1996)
Paint containing more than .06 percent by weight of lead in paint, or the equivalent measure of lead in the dried film of paint already applied, shall not be used in the construction or rehabilitation of residential structures under this contract or any resulting subcontracts.
(End of clause)
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/diar
(End of clause)
PART III – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J – LIST OF ATTACHMENTS
TITLE DATE NO. OF PAGES
ATTACHMENT 1 Attachment 1 Specifications Stinson Beach 05/23/2024 8 ATTACHMENT 2 Bid Schedule- Stinson Beach 05/23/2024 1 ATTACHMENT 3 Davis-Bacon Wage Rates CA20240007 04/12/2024 44 ATTACHMENT 4 Limitations on Subcontracting Report 05/23/2024 1 ATTACHMENT 5 Past Performance Questionnaire 05/23/2024 3 https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/diar
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
ATTACHMENT 6 General References 05/23/2024 1 ATTACHMENT 7 Relevant Experience Questionnaire 09/13/2022 5
ATTACHMENT 8 VIOLATION OF ARMS CONTROL TREATIES OR
AGREEMENTS-CERTIFICATION 11/2021 2
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS
OF OFFERORS
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)
(a)
(1) The North American Industry Classification System (NAICS) code for this acquisition is 236210
(2) The small business size standard is $45.0 Million
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519 if the acquisition—
(i)Is set aside for small business and has a value above the simplified acquisition threshold;
(ii)Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii)Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b)
(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the
Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph
(d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation.
The Offeror shall indicate which option applies by checking one of the following boxes:
(i) [_] Paragraph (d) applies.
(ii) [_] Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
https://www.acquisition.gov/far/part-52#FAR_52_204_7 https://www.acquisition.gov/far/part-52#FAR_52_204_7
Document No.
140P8624R0011
Document Title NPS Golden Gate – Stinson Beach Lifeguard Shower Trailer and Maintenance Building Reconfigure
(c)
(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless–
(A) The acquisition is to be made under the simplified acquisition procedures in part 13;